Skip to main content Skip to footer

A Modern Makeover – A Failed, Tired Masonry Façade Gets a New High-Performance Look

April 25, 2021

BACKGROUND
Occasionally, building renovation projects present an opportunity to renovate
old, tired, worn out, or outdated features and totally transform the facility
into something completely new or different. Such is the case with the transformation
of a circa-1980s office building and research facility into a modern, more
energy-efficient, transformed structure (Figures 1, 2, and 3).
The facility, located in the Mid-Atlantic region in climate zone 4, was originally
constructed in two phases: phase one in the early 1980s and phase two
very shortly thereafter. Construction was similar in both phases. Recently, the
facility was undergoing an extensive interior renovation, including mechanical,
electrical, industrial process, and build-out of high-tech manufacturing space.
Prior to this recent renovation, the exterior brick cladding was showing
some signs of distress. Aesthetically, the building’s architecture was dated, and
repairs to the cladding systems were warranted. The exterior
had already undergone some prior exterior renovation a decade
earlier where the ribbon-style windows had been replaced
18 • IIBEC Interface April 2021
This paper was originally presented at the 2020 IIBEC Virtual Building Enclosure Symposium+. The session is also available at iibec.learnupon.com.
Figures 1, 2, and 3. Elevation views of
brick façade prior to project commencement.
and a new single-ply roofing system
had been installed. These building
elements were in satisfactory and
functional condition and were not in
need of renovation or replacement.
Therefore, replacement of the roof
and windows was not part of an
exterior repair plan.
The design team discovered a
significant number of horizontal
and vertical hairline cracks in the
exterior brick cladding, particularly
at locations where steel relief angles
were expected to be located. Initially,
the design team chose to design and
detail extensive exterior masonry
repairs to the cladding system. This
effort also called for replacing steel
relief angles, although their condition
was undetermined at the time,
as they were concealed. These initial
design decisions were made without
the benefit of a full forensic evaluation
and a determination as to
the cause of the observed masonry
deficiencies. A forensic study would
have provided critical as-built information
and a review of the long-term
performance of the various building
enclosure elements.
FORENSIC STUDY
Prior to the exterior work taking place, it
was determined that the project team might
benefit from a forensic study of the exterior
to better understand some of the defects that
had been discovered, identify their root cause,
and review various options for restoration or
repair. A forensic study would also allow for a
more in-depth evaluation to better understand
why cracks had occurred in the exterior brick
cladding and to provide recommendations for
restoration, repair, or even the possibility of
recladding the building.
The forensic study included a review of
the original drawings to the extent that only
a limited number of drawings were available.
This offered critical insight pertaining to how
the masonry cladding was supported, the locations
of a number of the steel relief angles, and
the details associated with their construction.
The study included two days of field work,
as well as a certain amount of deconstruction.
Observations included a closer visual survey
from the grade level up of the condition
of the exterior masonry, identifying areas of
weathered or damaged masonry (particularly
mortar); as well as the location of various horizontal,
vertical, and step cracks in the brick
April 2021 IIBEC Interface • 19
Figure 4. Inspection location at a window head corner revealing the condition of the loosely placed rigid
foam board sheathing and poorly installed PVC flashing.
Durability,
Sustainability,
Energy Effi ciency
Your GUARD Against Energy Loss
Insulated Concrete Solutions
for Wall Assemblies
ProGUARD® DP Insulated Concrete Board
A unique wall sheathing that provides
Continuous Insulation value consisting of
Util-A-Crete® Concrete Backerboard
laminated to rigid insulation with
specially designed drainage planes to
allow moisture to escape.
– Meets or Exceeds Energy Codes
– NFPA 285 Approved Wall Assembly
– ASTM E119 1-Hour Fire Approved Assembly
– Signifi cant Labor Savings Achieved
– Durable, Ready-to-Finish Substrate
WallGUARD® Concrete Faced
Insulated Perimeter Wall Panels
A “one step” Continuous Insulation panel
that protects foundations, slab edges,
rim joists and parapet walls by
combining rigid insulation laminated to
a latex-modifi ed c oncrete facing.
– Reduces Energy Loss
– Long-term High Insulation Value
– Above and Below Grade Approved
– Durable, Impact Resistant Substrate
800.544.7398 tclear.com
tclear_ad.indd 1 3/9/2021 10:15:04 AM
cladding system; and verification of the embedded
steel elements. Crack maps for each elevation
were generated by overlaying field-observed
deficiencies onto elevation drawings
or doing the same over photographs
of each elevation to create
a picture of the distress that
was observed. Photographs can
be stitched together to create
panoramic views of an overall
big picture of the building,
allowing for the overlay of crack
and deficiency locations. In
addition to creating crack maps
of each elevation and reviewing
the existing drawings, the team
created observation openings in
the brick cladding in several key
locations, as well as openings in
interior finishes at critical locations,
in order to see how the
building was constructed and
to determine the condition of
concealed elements inside the
cavity wall, including the general
condition of the steel supporting
members. Bricks were
removed at a window head condition
(Figure 4), a base-of-wall
through-wall flashing condition,
and a steel relief angle condition.
In several locations, interior finishes
were also removed to allow
for the inspection of the back
side of the brick cladding, sheathing, and construction
of the entire wall assembly (Figure 5).
The findings of the forensic study changed
a few significant assumptions regarding the
condition of several of the building
cladding, structural, cavity,
and wall assembly elements.
It became apparent that the asconstructed
condition of the brick
did not provide for any masonry
control joints. Masonry control
joints were not shown on the
original plans. There were no
vertical control joints near corners,
at openings, or at the ends
of the brick panels supported by
steel relief angles. There were no
soft joints (backer rod and sealant
joints) in any of the masonry
cladding systems. The lack of soft
joints at critical areas to allow for
a certain amount of stress relief in
the masonry cladding, for differential
movement between brick cladding
that is footing supported, and
brick cladding that is buildingframe
supported, was determined
to be the primary cause
of the horizontal and vertical
cracks on the building. Horizontal cracks in
mortar joints occurred at every relief angle
location, and vertical cracks occurred close to
building corners, as might be expected in the
20 • IIBEC Interface April 2021
Figure 5. Forensic study image where the brick cladding was inspected from the inside of the building by
removing interior finishes and sheathing. Note through-wall flashing at bottom of photo.
Figure 6. Forensic image of one of the methods used, fastening brick cladding anchors to the steel studs where
the anchors were field-welded in place; note large hole melted in the foam sheathing.
building where vertical control joints are normally
expected. Industry associations generally
recommend control joint placement at changes
in wall height; at changes in wall thickness,
such as at pipe and duct chases and pilasters;
at movement joints in foundations and
floors; at movement joints in roofs and floors
that bear on the wall; near one or both sides
of door and window openings; and adjacent
to corners of walls or intersections within a
distance equal to half the typical control joint
spacing. The study also found a limited number
of step cracks at window head corners—primarily
due to distress caused by the different
load-bearing conditions (steel vs. footingsupported
masonry).
At the locations where brick extraction
allowed for the inspection of the embedded
structural steel relief angles, it was found that
the steel members were in much better condition
than assumed and anticipated.
One critical finding was that the exterior
wall assemblies were originally constructed
with numerous deficiencies. The building
was constructed at a time when sensitivity to
energy conservation was a significant factor.
Construction occurred in the early 1980s after
several worldwide energy crises, which had
an impact on building design. The building
is constructed with a steel frame with exterior
walls composed of interior painted gypsum
and light-gauge metal-framed stud walls with 6
in. of kraft-faced fiberglass batt insulation. For
exterior sheathing, the assembly includes ¾ in.
of rigid extruded polystyrene insulation board
(no gypsum sheathing) with a masonry cavity
and brick masonry exterior cladding. The use of
an extruded polystyrene for exterior sheathing
is somewhat unique for the time period and,
to a certain extent, has made a comeback more
recently with the need for continuous insulation
(CI) in modern buildings. However, at the
time of construction, there appeared to be little
consideration for air- or weathersealing the
foam board sheathing.
Findings also included some unique features
where the brick masonry ties were welded
to interior studs or welded to steel washers,
which were welded or screw-fastened to the
interior studs (Figure 6).
This technique must have required pushing
the masonry anchors through the exterior
extruded insulation board to allow the anchor
to be welded to the studs. This construction
technique created thousands of holes in the
exterior sheathing, as well as burn marks and
melted insulation due to the welding activities.
In addition, it was determined that the
exterior foam board sheathing was installed
loosely with screws and washers
with no efforts made to seal
joints or provide any sort of
weather or air barrier. In
most instances, masonry
cavities were found to
be bridged with excessive
mortar.
Through-wa l l
flashings were found
to be composed of
a plastic PVC membrane
sheet, which
was loosely fastened
to the foam board
insulation or run up
behind it where gaps
occurred between
adjacent insulation
boards. The plastic
flashing had long since
lost its flexibility and was
brittle and easily damaged.
The forensic investigation
was completed during the cooling
season. When openings were
made in the brick, at each location a
large volume of cold air from the interior
conditioned spaces was felt rushing out (exfiltrating)
from the masonry cavity.
Overall, the exterior wall assemblies
appeared to be of stout construction consisting
of steel-stud metal framing generally 8 in. deep
and, in some cases, composed of double studs,
presumably in an effort to reduce thermal
shorts through the wall assembly. Wall studs
were welded to top and bottom tracks without
the benefit of slip tracks with the inability to
accommodate floor-to-floor or roof deflection.
This is not a good practice, although it was
determined that this condition did not appear
to impact building performance.
The brick units themselves were found to
be in remarkably good condition with little
indication of weathering. Some weathering was
observed in patchy areas in the mortar joints at
a few locations.
REPAIR OPTIONS
Given the findings, it was clear that simply
repointing or restoring the exterior brick cladding
would not solve many of the issues discovered
during the forensic study. One of the
positive findings of the forensic study was that
the supporting steel relief angles were in much
better condition than anticipated and therefore
could remain in place without the need for any
rework or repairs. These angles were supported
by steel channels that were hung from the floor
and roof beams above.
Due to the discovery of the lack of a proper
weather or air barrier, the large volume of exfiltrating
air that was observed inside the masonry
cavity, the poor installation techniques of the
PVC through-wall flashing products, and the
poor placement and installation of the extruded
foam board sheathing, the new challenge
became addressing the in-the-wall deficiencies
without tearing the building apart.
Some of the repair options that were considered
include:
• Only repointing and repairing the brick
cladding system. This approach would
have required an extensive amount
of saw cutting to provide relief joints
(both vertical and horizontal, at every
relief angle). In addition, a challenge to
this approach would be matching the
existing brick and mortar to provide a
seamless repair. This option would also
ignore the significant issues with the
building’s air and weather barriers.
• Sealing the exterior brick cladding
with a vapor-permeable silicatebased
paint coating. This would have
been applied over the existing cladding
system, completely sealing it from
April 2021 IIBEC Interface • 21
One critical finding
was that the exterior wall
assemblies were originally
constructed with numerous
deficiencies. The building
was constructed at a
time when sensitivity to
energy conservation was
a significant factor.
water penetration. Such an approach would still require
extensive rework of the brick cladding system to provide
relief in the form of control joints to prevent movement
of the brick cladding system from damaging the applied
coating. This approach also would not address the issues
inside the wall.
• Sealing the existing brick cladding system by using
it as a substrate for a vapor-permeable air/weather
barrier and an applied lightweight recladding system
such as prefinished metal panels or EIFS. Although more
costly, a recladding approach would provide the architect
an opportunity to transform the exterior of the building,
keeping it more in line with the owner’s corporate image,
and allow for installing an air/weather barrier using the
existing brick cladding system as a substrate, and to add
more insulation to the wall assembly. This approach
would also greatly reduce the amount of rework on the
brick cladding system, as vertical relief could easily be
added without the need for matching final architectural
22 • IIBEC Interface April 2021
Figures 7 and 8. Ongoing installation of the liquid-applied
vapor-permeable air and weather barrier being applied to
exterior gypsum sheathing and brick cladding.
Figure 9. Base-of-wall condition where through-wall flashing is
secured to the primed air-barrier membrane to flash out water
before the base-of-wall insulated concrete panels below.
Figure 10. Ongoing work where the liquid-installed air barrier
is visible, as well as horizontal Z tracks and thermal insulation
prior to installation of metal wall panels.
appearances. The
applied weather
barrier system
could tolerate a
certain number
of hairline cracks
in the substrate,
eliminating the
need to install
horizontal soft
joints at each of the
steel relief angles.
Hairline cracks
in the air barrier
would need to be
pretreated prior
to the application
of the system. A
lightweight metal
cladding system
could easily
accommodate a
small amount of
substrate movement.
Ultimately, installation of a lightweight metal cladding system was
selected.
DESIGN
During the design phase, a certain amount of effort was required to
verify that the existing selected substrate—the brick cladding system—
could be used as an acceptable substrate for the new air/weather barrier
and support the new cladding system. This effort included an engineering
evaluation of the adequacy of the existing masonry ties and the
ability to fasten a new cladding system to the existing brick. Therefore,
a certain amount of structural analysis was required as well as fastener
pullout resistance testing at the existing brick cladding to ensure that the
additional assembly could be adequately supported. Fastener spacing of
April 2021 IIBEC Interface • 23
Figure 12. Finished metal cladding system depicting custom
colors and variation of panel types and details.
Figure 11. The installed cladding system was tested using ASTM spray nozzle techniques.
Figure 13. Completed wall depicting various
metal panel types as well as insulated concrete-coated
rigid insulation panels at base of wall.
the new cladding system
was also a consideration
to ensure that
none of the existing
masonry ties became
overloaded.
As part of the
design effort, vertical
control joints were
saw-cut into the building
elevations at critical
locations. These
new control joints
were addressed with
the application of new
backer rod and sealant.
On either side and
adjacent to the new
vertical control joints,
new stainless steel and brass masonry repair
anchors were installed to properly support
the cladding at these areas. The new design
included the selection of a prefinished metal
cladding system, including both vertical and
horizontal panel selections with a custom layout
and custom accent colors. The new assembly
included a vapor-permeable liquid-applied air
barrier installed over the existing brick (Figure
7), horizontal or vertical light-gauge Z members
(Figure 8), and an additional layer of mineral
wool insulation (Figures 9 and 10).
As with any recladding effort, the architect
created new elevations, paying particular attention
to the numerous openings and penetrations
in the exterior façade, including simple items such
as hose bibs; electrical boxes; surface-mounted
conduits; lighting fixtures; openings for doors,
windows, and entrances; security cameras; and
a myriad of other building-mounted equipment.
There were numerous site visits and detailed
discussions about each of these details with the
general contractor and installer to ensure the
final fit finish and appearance met the architect’s
expectations. The new design included tying in
the new metal cladding system to the roof with a
matching prefinished manufactured fascia metal
system with an extruded aluminum closure.
The architect also elected to provide additional
thermal insulation at the base-of-wall
condition, tying the new metal cladding system
to an insulated concrete panel system using
extruded insulation that extended to below grade
(Figure 9). At some locations, a new below-grade
bentonite-based waterproofing system was also
installed. The architect went to great lengths
to detail as many of the as-built conditions as
possible and tie the new system into the existing
building elements. Finally, water-hose nozzle
testing was used to field-verify weathertightness
of the new installation (Figure 11).
The end result is a dramatic transformation
of a dated building façade into a modern facility
that is more energy efficient and far more airtight
and weathertight than the original building
(Figures 12, 13, 14, and 15).
24 • IIBEC Interface April 2021
Timothy Mills
graduated with
a BS in engineering
from Brooklyn
Polytechnic Institute
of New York in 1983.
Prior to forming
TAM Consultants in
2002, Mills worked
at a number of multidiscipline
design
and inspection firms.
He has published
numerous articles,
presented at conferences and symposia, and
completed nearly 1,500 residential home and
commercial building inspections and 300 energy
audits. He is an instructor for ABAA training
courses that educate and certify contractors in
the proper installation of air barriers and is a certified
ABAA Auditor for their quality assurance
program, as well as a Certified Level II Infrared
Thermographer.
Timothy A. Mills,
PE, LEED AP, CIT II
Figure 14. Completed end wall with
custom colors and variation of
metal building wall panels.
Figure 15. Another view of the completed
end wall with custom colors and
variation of metal building wall panels.