Skip to main content Skip to footer

Finding the Leak

September 11, 2025

WITH THE INCREASING complexity of modern
building techniques, it is important for all
members of the project team to understand
how the various materials and systems
being utilized are to be incorporated into
the completed building. This was illustrated
with a new-construction project in downtown
Seattle, Washington, where an apparent
roof leak developed while construction was
underway. After the building was occupied,
the leak recurred at irregular intervals for
several years. Identifying and resolving the leak
required an extended series of investigative
techniques involving the use of water testing,
infrared thermography, and electronic leak
detection (ELD). The source of the roof leak was
unexpected as it was associated with the side
laps of the field roofing membrane, but once it
was identified, there was some logic behind its
occurrence.
BUILDING PROJECT
BACKGROUND
The building, where the long-recurring roof leak
happened, was constructed to be a corporate
headquarters. As such, the building was
viewed by the developer and building owner
as a long-term asset, and team members were
selected on the basis of expertise rather than
cost. This was true not only on the design side
but also on the construction side.
The building has seven full stories with a
partial eighth, or penthouse, story that was
originally intended to house amenity spaces
for the building’s occupants. The structure is
reinforced concrete, while the cladding is brick
veneer with unitized curtainwall glazing. The
roof slab has a two-way slope directed to the
center of the slab, although the roof drains are
located midway down the slope, resulting in
the need for a tapered roof insulation layout
to direct rainwater to the drains. The main
roof at the eighth-floor level was designed
as an extension of the amenity spaces in the
penthouse. Precast concrete pavers were laid
to create patio areas. Pavers were also placed
around the perimeters of the penthouse and
the roof parapet (Fig. 1), and these paths were
used for walking and jogging by employees.
The remaining roof areas were covered with
vegetation. During occupancy of the building,
the south recreational lounge of the penthouse
was repurposed as the corporate boardroom
Finding the Leak
Feature
By David A. Rash, RRC (Fig. 2), reinforcing the importance and
desirability of the garden roof, which was visible
from the boardroom.
For reference, the installed roofing assembly
is, from the roof deck upward:
• Primer on concrete deck
• Styrene-butylene-styrene (SBS)-modified
membrane as an air/vapor barrier and
temporary roofing membrane, torch applied
• Tapered polyisocyanurate roof insulation to
achieve R-38, adhered
• Gypsum-based coverboard, adhered
• Two-ply SBS-modified roofing membrane with
granular cap sheet, torch applied
At the patio deck areas, the overburden was
specified (from roofing membrane upward):
• Asphaltic protection board, loose laid
• Adjustable pedestals
• Hydraulically pressed precast concrete pavers,
typically 24 in. (610 mm) square in size
At the vegetated areas, the overburden was
specified (from roofing membrane upward):
• Drainage composite, loose laid
• Extruded polystyrene (XPS) insulation,
loose laid
• Growing medium and plants
A RECURRING LEAK
As the building approached completion and
occupancy in 2016, the building experienced
roof leaks. The first involved poorly detailed
conduit penetrations, which were quickly
resolved. More troublesome was a leak that
became evident at the ceiling level of the
seventh-story office space at the south end
of the building, in the general proximity of
the centerline of the roof slab. At the time,
the roofing contractor found some minor
deficiencies in the roofing membrane under the
precast concrete paver area at the south end of
the main roof, which were repaired. In addition,
Interface articles may cite trade, brand,
or product names to specify or describe
adequately materials, experimental
procedures, and/or equipment. In no
case does such identification imply
recommendation or endorsement by the
International Institute of Building Enclosure
Consultants (IIBEC).
©2025 International Institute of Building Enclosure 10 • IIBEC Interface Consultants (IIBEC) September 2025
the investigation team performed tests on both
the inside and outside face of the south parapet
using a calibrated spray wand (Fig. 3), based
on the American Architectural Manufacturers
Association’s AAMA 501.2 testing standard.1 The
water tests did not replicate the leak, and the
initial repairs made by the roofing contractor
appeared to address the leak issue.
Over the following 3 years, the initial roof
leak recurred with sufficient frequency that
the roofing contractor installed four inspection
ports near the roof drains and the centerline of
the main roof slab in 2017. Although the leak
recurred with some frequency, there did not
appear to be a consistent correlation between
weather events and the roof leak. A limited
number of exploratory openings were made,
which indicated that water was collecting at
the level of the air/vapor barrier (Fig. 4), but no
breaches were discovered in the air/vapor barrier.
The inspection ports (Fig. 5) were an attempt
to monitor water volume during rain events to
see if there was some correlation between water
volume and recurrence of the leak, but they
were ultimately not useful in understanding the
source(s) of the roof leak.
Due to the expense of removing sufficient
portions of the vegetated roof assembly to access
the roofing membrane underneath, as well as
the potential harm that this would cause the
plants, no leak investigation occurred in any of
the vegetated roof areas during this time. Also,
there was no direct evidence that pointed to
the vegetated areas as being the source of the
recurring leak. For the first several years, there
was no direct evidence of where the leak was
located other than the existence of water stains
and other damage on the ceiling below the roof
deck and on the floor finishes at the approximate
center of the south end of the building.
THE HUNT FOR THE LEAK
From approximately September 2018 to
September 2019, the building experienced
no apparent leaks, which gave hope that the
previous attempts to resolve the leaks had been
successful. Even when a severe thunderstorm
had occurred on September 7, 2019, with 0.59 in.
Figure 1. Southern view from company boardroom with paved patio
area and vegetative roof areas (2/17/2019).
Figure 2. View of eighth-floor green roof with pavers and south
end of penthouse structure with glazed wall of company boardroom
(2/17/2019).
Figure 3. Eighth-floor parapet water tested with a calibrated spray
wand shortly after the building was occupied with metal panel cladding
removed to identify potential leak path(s) (2/11/2016).
Figure 4. Exploratory opening revealing water at the level of the roof
air/vapor barrier, but no breaches (2/02/2017).
September 2025 IIBEC Interface • 11
The first component of the leak investigation
was an infrared thermographic survey of the
underside of the concrete roof deck, which was
performed on March 2, 2020. Some minor
thermal anomalies were identified; however,
none were indicative of significant water
absorption into the concrete deck (Fig. 6).
The second component was an ELD test
performed on the base flashing membrane
at the south end of the level 8 penthouse.
No breaches were found in the base flashing
membrane, although several anomalies
suggestive of potential breaches were identified
(Fig. 7); these were mainly small portions of side
lap edge conditions that did not appear to be
fully sealed.
The third component was a water test of the
three vegetated roof areas at the south end
of the building, which involved running the
irrigation system continuously without blocking
the roof drains (Fig. 8), eventually saturating
the vegetated assembly. Prior to initiating the
water test, the roofing contractor reinstalled one
of the inspection ports to determine whether
water from the testing was infiltrating down to
the vapor barrier and collecting in the roofing
assembly in conjunction with the roof leak; the
inspection port was located near the central
valley line of the roof deck. The inspection port
was a short piece of polyvinyl chloride piping
that extended several inches above the roofing
assembly and down to the vapor barrier; it
allowed the investigation team to confirm
whether water was infiltrating down to the vapor
barrier, but it did not allow one to ascertain
through which layers of the assembly that the
water might be percolating. This water test
replicated the leak for the first time, although
Figure 5. Inspection port installed under pavers on pedestals at south patio area of eighth-floor
green roof (2/17/2019).
(15 mm) of rainfall during roughly an hour and
sustained winds of 12 mph (19 km/h), the leak
had not recurred. When the leak returned, it
was after 3 consecutive days with precipitation:
rainfall was 0.49 in. (12.5 mm) on September 17,
2019, 0.26 in. (6.5 mm) on September 18, 2019,
and 0.03 in. (1 mm) on September 19, 2019.
Since the leak had not occurred when the
roof had recently experienced more severe
weather, the possibility existed that the leak
of September 19, 2019, was a new leak even
though it appeared to be a replication of the
prior leaks. Because the building had gone
for nearly a year without a recurrence of the
leak, the roofing contractor had removed the
inspection ports on September 19, 2019, and
when the leak recurred within a month, concern
was expressed that the repair patches at the
inspection port locations might be at fault for
the leak’s recurrence, even though the patching
material was polymethyl methacrylate (PMMA)
flashing membrane. Adhesion issues were
discovered with the PMMA patches, and new,
larger patches were installed; however, this did
not resolve the issue.
Still, the building owner wanted a resolution to
the problem and requested that an investigation
plan be developed to find the leak.
In developing the investigation plan, the client
requested that all potential sources for the leak
be investigated even if previous testing of some
locations was repeated. For the south end of the
main roof, this would include
• the south roof parapet,
• the south end of the penthouse structure,
including the base flashing transition from the
field membrane onto the roof curb supporting
the exterior walls, and
• the south end of the main roofing assemblies.
Testing techniques would ultimately include
infrared thermography, ELD, calibrated spray
wand water testing, continuous water flow
testing, and a limited flood test.
Although a flood test of the affected roof area
was initially considered, the roofing materials
manufacturer indicated that this test would
invalidate the extended roofing warranty.1 The
manufacturer reminded the testing team that
the roofing system was not intended to be
subjected to the hydrostatic pressure that would
result if approximately 5½ in. (140 mm) of water
was allowed to stand on the roof for the 24 hours
that the test would normally be expected to last.
This objection eliminated the need to have the
structural engineer of record determine if the
building structure was capable of supporting the
weight of a flood test.
Figure 6. Interior thermographic survey confirmed no excessive moisture accumulation in
concrete deck, while also identifying minor thermal bridging from fall-arrest anchors attached to
the deck (3/02/2020).
12 • IIBEC Interface September 2025
it did not identify which roof area might be
the source of the leak or if all three areas were
contributory; water was also observed in the
inspection port.
The fourth component was a water test of
only the southeast vegetated roof area (Fig. 9).
This water test replicated the leak for the
second time; replication took less time to occur
than during the prior (third) component of the
investigation.
The fifth component was a water test of
the southwest vegetated roof area (Fig. 10),
running water continuously so that the vegetated
assembly became saturated. This water test did
not replicate the leak, nor was further water
observed in the inspection port.
During the testing of the southwest vegetated
roof area, a review of the perimeters of the
vegetated areas found that the southeast
vegetated assembly was installed with expanded
polystyrene (EPS) insulation directly over the
roofing membrane (Fig. 11), while the southwest
vegetated area had EPS insulation installed
above the drainage composite. The change from
XPS insulation to EPS insulation was presumably
a cost-saving measure during construction.
At this point in the investigation, the
roofing installer elected to repair some of
the roofing anomalies by applying PMMA
flashing membrane over the anomalies,
primarily seams where the laps did not appear
to be fully sealed adjacent to the southeast
vegetated roof area, expressing the concern
that standing water around the vegetated roof
area might be the source of the leak. After the
repairs were completed, the southeast roof
area was retested (Fig. 12). Although it took
longer, the leak was replicated for a third time,
suggesting that the PMMA repairs may have
resolved contributing breaches in the roofing
membrane, but the primary cause of the leak
was still unresolved.
Figure 7. Electronic leak detection was used to confirm no breaches
in base flashing membrane along the base the penthouse structure
(3/02/2020).
Figure 8. The three vegetative roof areas at the southern end of the
eighth-floor roof were saturated with water from the irrigation system,
which replicated the leak for the first time (3/16/2020).
Figure 9. The southeast-corner vegetative roof was saturated with
water, replicating the leak for the second time (3/17/2020).
Figure 10. Saturating the southwest vegetative roof separately did not
replicate the leak (3/18/2020).
September 2025 IIBEC Interface • 13
The sixth component was a water test of the
glazing assembly of the south elevation of the
penthouse (Fig. 13). For this test, a spray rack
was utilized without a pressurized chamber on
the interior side of the glazing, as the test was to
determine whether water penetration was at the
interface between the glazing assembly and the
base flashing membrane at the concrete support
curb at the perimeter of the penthouse structure.
The roof leak was not replicated, nor was water
observed in the inspection port.
In late March 2020, the state of Washington
imposed a moratorium on nonessential
construction activities due to the COVID-19
pandemic, which was not lifted until mid-May
2020. Once the moratorium was lifted, the
seventh component of the investigation was
instigated. This included testing of the inside
face of the south parapet at its base, midsection
(cladding), and coping. Water was directed
at the various levels of the parapet using a
calibrated spray wand in general conformance
with the AAMA 501.2 testing standard,1 testing
5 ft (1.5 m) sections of the parapet laterally
for a period of 5 minutes. This was performed
initially at the base flashing membrane at the
bottom of the parapet, then the lower half of the
metal siding, followed by the upper half of the
metal siding, and finally the metal plate coping
(Fig. 14). At no point during this testing was the
roof leak replicated, nor was water observed in
the inspection port.
The eighth component was a water test of
the outside face of the south building parapet
(Fig. 15). For this test, a spray rack was utilized
to apply water to the metal plate coping and
the brick facing above the uppermost window
heads. Each section of the parapet was tested
for 15 minutes, with the middle third of the
Figure 11. Southeast vegetative roof area was discovered to have
expanded polystyrene (EPS) insulation resting directly on the roofing
membrane, with the drainage composite installed over the EPS
insulation (3/18/2020).
Figure 12. Minor deficiencies patched with polymethyl methacrylate
membrane, after which the southeast vegetative area was separately
tested, resulting in a third replication of the leak (3/19/2020).
Figure 13. A spray rack was used to determine if the interface between
the glazing assembly of the penthouse and the base flashing membrane
of the roofing system contributed to the roof leak (3/23/2020).
Figure 14. The south building parapet was tested using a calibrated
spray wand at the base of the parapet, the metal cladding of its interior
face, and the coping, in sequence from bottom to top (5/19/2020).
14 • IIBEC Interface September 2025
Figure 15. Spray rack was used to water test the exterior face of the
south building parapet (5/20/2020).
Figure 16. South-central vegetative area was also water tested
separately, but it did not replicate the leak despite having expanded
polystyrene insulation resting directly on the roofing membrane
(5/22/2020).
Figure 17. Vegetative assembly removed from the southeast corner of the main roof. Minor root
growth was discovered to have penetrated the root barrier but without evident damage to the
roofing membrane (7/14/2020).
south elevation being tested (centered at
the interior leak location). The roof leak was
not replicated.
The ninth component was a water test of the
small south-central vegetated roof area (Fig. 16),
running water continuously so that the vegetated
assembly became saturated. Even though the
installed vegetated assembly of this roof area
was similar to the southeast vegetated roof area
in that there was EPS insulation directly on the
roofing membrane with the drainage composite
above the EPS insulation, there was significantly
less growing medium due to its location
straddling the peak in the tapered roof insulation
of the roofing assembly. This water test did not
replicate the leak, nor was water observed in the
inspection port.
At this point, the preliminary leak
investigation was complete insofar as testing
to identify the likely location of where the leak
was entering the building. Since water testing
had replicated the leak at only the southeast
vegetated roof area, the general contractor
agreed to have the vegetated assembly removed
at this location. This allowed the roofing
membrane to be visually reviewed, after which
time decisions could be made about further
investigation of the roof leak.
After the vegetated assembly had been
removed, the exposed roofing membrane
was reviewed in company with the roofing
contractor (Fig. 17). Some minor roofing
anomalies were observed, such as minor
loss of granules from the cap sheet and lack
of bitumen bleed-out along portions of the
side laps, but none appeared to be obvious
breaches in the membrane that might allow
water intrusion. Plant roots were also evident
on the surface of the roofing membrane, but
these were sufficiently small as to be considered
inconsequential for possible water intrusion, as
none had breached the cap sheet.
After discussion with the project team, a
water test of the exposed roofing membrane
was conducted. The irrigation system for the
southeast roof area was allowed to run for
more than 6 hours, which had previously been
September 2025 IIBEC Interface • 15
sufficient time for the roof leak to become
manifest when the vegetated assembly was in
place. Without the vegetated assembly, the roof
leak was not replicated.
In hope of better understanding how
water might be infiltrating the southeast roof
area, an infrared thermographic survey was
performed (Fig. 18). Some minor thermal
anomalies were identified that did not appear
to be large enough to indicate that they were
part of the water path but were marked on
the cap sheet of the roofing membrane. Six
exploratory openings were performed by the
roofing contractor at locations chosen by the
investigation team and the chief building
engineer. At four locations south of the roof
drain, the top facer of the roof insulation was
wet, but the polyisocyanurate core was dry.
At two locations north of the roof drain, the
roofing assembly was dry.
Despite the infrared thermographic survey
and exploratory openings, no obvious sources
of water entry were evident from a review of the
exposed roofing membrane. After an inspection
of the roofing membrane, a T-lap approximately
12 ft (3.7 m) inboard of the south building
parapet was selected for a targeted flood test. A
temporary box dam, approximately 2 ft (0.6 m)
square in size, was constructed and sealed to
the cap sheet (Fig. 19). Approximately 5 in. to
6 in. (12.7 cm to 15.2 cm) of water was allowed
to accumulate inside the dammed area. After
approximately 1.5 hours, water was observed
seeping out of two other adjacent cap sheet
T-laps, as well as at the cap sheet edge of one
exploratory opening (Fig. 20–22). All locations
were upslope from the flood test location and
more than 20 ft (6.1 m) from the roof drain.
Once the water test was removed, water
migration ended.
Based on these observations, it was
concluded that the roof seams were allowing
water ingress when under hydrostatic pressure,
as occurs when the vegetated assembly
becomes fully saturated and becomes
increasingly heavy and exerting pressure on the
cap sheet similar to what would occur during
a flood test. This allowed water to migrate
laterally through the roofing assembly until
a penetration, like a fall-protection anchor,
allowed the water to migrate vertically to the
roof deck and subsequently to the south edge of
the roof deck and materialize on the interior of
the south exterior wall.
LEAK RESOLUTION
In discussing repair options with the roofing
contractor, one option was to simply have the
Figure 18. Infrared thermographic survey identified a few thermal anomalies, but none proved
to be the “smoking gun” for the roof leak (7/20/2020).
Figure 19. Flood test performed at a T-lap location suspected of being compromised (7/29/2020).
Figure 20. General view of roofing membrane upslope of flood test location with water visibly
seeping out of the T-lap seam (yellow circle) (7/29/2020).
16 • IIBEC Interface September 2025
vegetated assembly reinstalled as originally
specified, which was the responsibility of
a separate contractor, after the necessary
repairs to the exploratory openings were
completed. Considering that the roof leak had
been occurring for approximately 4 years, the
possibility existed that the roof seams might
have been compromised. Compromised seams
might allow the leak to recur if the vegetated
assembly became sufficiently saturated and
hydrostatic pressure developed, such as during
a severe weather event. Thus, despite the
presence of the drainage composite directly
above the roofing membrane, leaks could
still recur. There was also the consideration
of the expense of removal and reinstallation
of the vegetated assembly should there
be any future need to access the roofing
membrane should a leak reoccur. Even though
the building was then unoccupied due to
the COVID-19 pandemic, a recurrence of the
leak after the building was again occupied
would be impactful for the occupants and
building owner.
Ultimately, the roofing contractor chose to
apply a PMMA reinforced flashing membrane
at all the roofing membrane seams of the
southeast vegetated roof area. This was likely
the most conservative corrective action that
could be taken, but it was also the option that
minimized the potential for a recurrence of
the leak. A 4 in. (100 mm) wide strip of PMMA
membrane was installed, centered over
the leading edge of the roofing membrane
seams (Fig. 23). When the seam stripping
was approximately two-thirds complete, an
adhesion pull test of the PMMA membrane
Figure 23. Polymethyl methacrylate flashing membrane being applied to all roofing seams in
the southeast vegetative roof area (8/05/2020).
Figure 21. Close-up view of water seeping out of the roofing seam
(7/29/2020).
Figure 22. Additional water seepage from the roofing seam subsequent
to the time recorded by Figure 20 (7/29/2020).
was conducted, which indicated that good
adhesion was being achieved. In addition,
a technical representative of the roofing
materials manufacturer also reviewed the
corrective work prior to the reinstallation of the
vegetated assembly.
After the vegetated assembly was
reinstalled, a water test utilizing the irrigation
system was performed at the southeast roof
area. Since all previous tests that replicated
the leak lasted less than 6 hours, the
confirmation water test was run for slightly
more than 6 hours, during which time the leak
(fortunately) was not replicated. The roof is now
approaching some 5 years without a replication
of the leak.
September 2025 IIBEC Interface • 17
Please address reader comments to
chamaker@iibec.org, including
“Letter to Editor” in the subject line, or
IIBEC, IIBEC Interface Journal,
434 Fayetteville St., Suite 2400,
Raleigh, NC 27601
LESSONS LEARNED
Although there was a requirement for the
roofing contractor and a representative from
the roofing materials manufacturer to attend
the preinstallation meeting for the vegetated
assembly, the installation of the vegetated
assembly was essentially treated as separate
tasks. To a degree this was true, as there
was one installer for the roofing assembly
and a separate installer for the vegetated
assembly, and the only interface between
the two assemblies was the top surface
plane of the roofing membrane. Installation
review of the vegetated assemblies was not
part of the scope of work for the building
envelope consultant,i nor was attendance at
the preinstallation meeting for the vegetated
assembly. Presumably, if review of the
vegetated assembly had been part of the
building envelope consultant’s scope, the
inadvertent error of installing EPS insulation
below the drainage composite and in direct
contact with the roofing membrane would
have been caught and corrected during
original construction.
More generally, the roof leak and its cause
raise the question of how prudent it might be
to install a roofing membrane, as opposed to a
waterproofing membrane, at locations where
access to the membrane intended to keep
water at bay is difficult once construction is
complete. For this project, having a continuous
membrane to manage rainfall drainage was
highly beneficial, as it allowed for refinements
in the layout of paved areas and the vegetated
assemblies as construction was in progress. It
would have been possible to install a two-ply
SBS waterproofing membrane in lieu of the
two-ply SBS roofing membrane, but at a higher
cost. In retrospect, for this project, the higher
cost would have been justified, as a membrane
capable of being subjected to hydrostatic
pressure would have been in place and the leak
would not have occurred.
REFERENCE
1. American Architectural Manufacturers Association
(AAMA). 2009. Quality Assurance and Diagnostic Water
Leakage Field Check of Installed Storefronts, Curtain
Walls, and Sloped Glazing Systems. AAMA 501.2.
Schaumburg, IL: Fenestration & Glazing Industry
Alliance (FGIA).
ABOUT THE AUTHOR
David A. Rash, RRC,
is a senior building
science consultant
with Stantec, and he
has been a member
of the Seattle office
since 2015. He is a
consultant member of
IIBEC, having joined
the institute in 2000,
and currently serves
on the editorial board
of the Interface technical journal; he previously
served on the Registered Roof Consultant
Examination Development Subcommittee and
the Documents Competition Committee. The
leak investigation was conducted prior to the
merger of Morrison Hershfield with Stantec.
DAVID A. RASH, RRC
800.992.7663 | www.versico.com
BUI LDING V ALUE
DuraFaceR®
Polyiso
DEXcell FA VSH™ SecurShield® HD
Composite
DensDeck® StormX™
Prime Roof Board
Versico continues to shape the evolution of the commercial
roofing industry by offering system solutions that achieve
Factory Mutual’s Very Severe Hail (VSH) rating. Versico now
offers four coverboard solutions, including SecurShield HD
Composite, that are VSH approved. CHECK OUT OUR VSH
SYSTEMS SELL SHEET
TO LEARN MORE
Very Severe Hail (VSH) requirements
now include parts of 14 states as
designated by Factory Mutual.
If you live in one of these areas, your building may
require a roofing system solution that is VSH approved.
Hail Zones
15yr. mean recurrence interval
Moderate [Hail size < 1.75in. (44mm)] Very Severe [Hail size ≥ 2in. (51mm)] No Data
Severe [Hail size ≥ 1.75in. (44mm) and < 2in. (51mm)] Pacific
Ocean
CALIFORNIA
NEVADA
OREGON IDAHO
WASHINGTON
MONTANA
WYOMING
SOUTH DAKOTA
NORTH DAKOTA
MINNESOTA
WISCONSIN
MICHIGAN
INDIANA
ILLINOIS
NEBRASKA
KANSAS
NEW MEXICO
OKLAHOMA
LOUISIANA
TEXAS
MISSISSIPPI ALABAMA
TENNESSEE
KENTUCKY VIRGINIA
MARYLAND
DELAWARE
MASSACHUSETTS
NEW YORK
MAINE
WEST
VIRGINIA
PENNSYLVANIA
MISSOURI
IOWA
OHIO
GEORGIA
ARKANSAS
UTAH
ARIZONA
FLORIDA
NEW JERSEY
RHODE ISLAND
CONNECTICUT
NEW HAMPSHIRE
Helena
Billings
Casper
Havre
Jeffery City
Cody
Miles City Bismarck
Minot
Fargo
Minneapolis
Des Moines
Springfield
Hot Springs
Dallas
Austin
El Paso
Albuquerque
Colorado Springs
Roswell
Santa Fe
Denver
Cheyenne
Breckenridge
Grand Junction
San Antonio
New Orleans
Boothville
Houston
Cedar Rapids
Iowa City
Columbia Indianapolis
Cincinnati
Charlotte
Columbia
Raleigh
Roanoke
Fort Wayne
Milwaukee
NORTH CAROLINA
SOUTH
CAROLINA
Augusta
Valdosta
Tallahassee
Brownsville
COLORADO
VERMONT
116313850 _ •Ed i toIIriBalE.inCdd I n 1terface 8/26/2025 2:22:49 PM September 2025