Skip to main content Skip to footer

The Cavity Wall Balancing Act: Designing for Watertightness, Airtightness, Thermal Efficiency, and NFPA 285 Code Compliance

May 15, 2018

8 • RC I I n t e r f a c e Oc t o b e r 2 0 1 8
Figure 1 – The Dancing House, designed
by Vlado Milunic and Frank O. Gehry,
in Prague, Czech Republic. Photo
©Vladimir Sazonov/Shutterstock.com.
ABSTRACT
The use of open-joint rainscreens, coupled with unconventional wall orientations, can be appealing, but can be a dangerous combination when abating water ingress and compliance with building codes, including combustibility. Balancing the need to keep the building dry, airtight, thermally efficient, and code-compliant can create a cavity wall conundrum. This piece looks at rainscreen design and standards for managing water in the context of the code requiring continuous insulation (ci), air barriers, and water-resistive barriers (WRBs), as well as life safety issues related to combustibility.
Designing exterior walls to be watertight, airtight, thermally efficient, and code-compliant can be quite a balancing act. This is particularly true with modern structures that combine open-joint rainscreens with unconventional wall orientations, such as those that are backward-sloping. In such cases, design teams need to prevent water ingress, but they also must comply with the latest building codes. Staying compliant with recent fire-related aspects of codes, however, can increase potential fire risks.
The American Society of Heating, Refrigerating, and Air-Conditioning Engineers’ ASHRAE 90.1 2010 and the 2012 International Energy Conservation Code (IECC), for example, require the use of ci, which in some cases is combustible. The 2012 International Building Code (IBC) requires that buildings in Climate Zones 4 to 7 have a continuous air barrier, which in most cases is also the WRB. All air and water barriers (AWBs), as well as some ci, are combustible, and therefore part of the compliance path (IBC 2012 and later) for National Fire Protection Association (NFPA) 285, Standard Fire Test Method for Evaluation of Fire Propagation Characteristics of Exterior Non-Loadbearing Wall Assemblies Containing Combustible Components.
In other words, today’s design teams are supposed to be designing building envelopes that are watertight, airtight, thermally efficient, and NFPA 285-compliant. Solving this cavity wall conundrum is possible, but it requires familiarity with competing design challenges and different industry standards and codes. Most cavity wall assemblies have either a metal studs with exterior sheathing or a concrete masonry unit (CMU) backup. All cavity walls share an air space to effectively drain the cavity.
KEEPING THE WATER OUT
According to John Straube, PhD, principal for RDH Building Science Inc., managing water with building enclosures involves the Three Ds: deflection, drainage, and drying. For water to penetrate the surface of a building enclosure, it must first be present on the wall surface. That surface must have an opening through which water can pass, and there must be a force to drive the water inward through the opening. To quote Dr. Straube, “All leaks occur at holes, but not all holes are leaks.” Open-joint rainscreen systems offer an increasingly popular means to achieve the Three Ds.
While the term “rainscreen” is becoming something of a generic phrase, it is important to know there are two main types of rainscreen systems: pressure-equalized (Figure 2), and drained and back-ventilated (DBV) (Figure 3). Both types must control the forces that will carry rain to the inside of the structure, including gravity, surface tension, capillary action, kinetic energy, and pressure differences. The majority of open-joint rainscreens being employed in today’s buildings are DBV.
October 2018 RCI Interface • 9
Behind open-joint rainscreens, AWBs provide the last line of defense against water ingress. There are a number of industry standards to help designers evaluate the water holdout capabilities of an AWB, but not all AWB manufacturers test all their products to each standard. AWB standards include:
•International Code Council EvaluationService (ICC-ES) Acceptance Criteria(AC) 38, Acceptance Criteria for Water-resistive Barriers (Sheet Membranes),which includes:
— American Association of Tex-tile Chemists and Colorists (AATCC) 127, Water Resistance: Hydrostatic Pressure Test
— ASTM D779, Standard Test Method for Determining the Water Vapor Resistance of Sheet Materials in Contact with Liquid Water by the Dry Indicator Method
— ICC-ES AC 212, Acceptance Criteria for Water-resistive Coatings Used as Water-resistive Barriers on Exterior Sheathing
An additional ASTM standard to evaluate the durability of fluid-applied air barriers (ASTM WK41724, Standard Practice for Assessing the Durability of Fluid-applied Air and Water-resistive Barriers) is under development. The task force working on this new standard has been challenged to provide common ground on which the industry can evaluate fluid-applied air barriers, including the water resistance of such barriers.
Once an AWB is installed, there are two other standards building envelope consultants can use to further evaluate the AWB’s water resistivity:
•ASTM E331-00 (2016), StandardTest Method for Water Penetration ofExterior Windows, Skylights, Doors,and Curtain Walls by Uniform StaticAir Pressure Difference
•American Architectural Manu-facturers Association (AAMA) 501.2,Quality Assurance and DiagnosticWater Leakage Field Check ofInstalled Storefronts, Curtain Walls,and Sloped Glazing Systems
ASTM E331 is a 15-minute lab test (the field test version is ASTM E1105, Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, and Curtain Walls, by Uniform or Cyclic Static Air Pressure Difference). The testing consists of using a calibrated spray nozzle that replicates wind-driven rain moving at 3.4L/m2/minute (5 gal/sf/hour), equivalent to 200 mm (8 in.) per hour.
In AAMA 501.2, handheld spray nozzle testing is set at 205 to 240 kPa (30 to 35 psi); there is a distance from the surface of the fenestration of 305 mm (12 in.) for five minutes for each 1.5 m (5 ft.) of joint. This test is best suited for surface-sealed assemblies of nonoperable fenestration.
To evaluate the performance of rainscreens, AAMA has also established AAMA 508, Voluntary Test Method and Specification for Pressure-equalized Rainscreen Wall Cladding Systems, and AAMA 509, Voluntary Test and Classification Method of Drained and Back-ventilated Rainscreen Wall Cladding Systems.
For these AAMA standards, designers should pay special attention to the amount of water allowed to get into these rainscreen systems while still being considered “passing.” Under AAMA 508, if the area of the water mist or droplets is greater than five percent of the AWB surface, it is considered a failing system. Under AAMA 509, water is expected to reach the WRB, so the pass/fail measure is whether the system is capable of venting and drying over time. Again, the AWB is the last line of defense for water getting into the building. As such, this system needs to be a robust, fully adhered, and properly designed, detailed, and constructed system.
Designers should also consider the cladding attachment system and its location relative to the ci, as this influences the choice and thickness of the AWB. When the cladding attachment system is outboard of the ci, the fasteners that hold the cladding support brackets will penetrate the ci and the AWB without compressing the AWB. In such cases, an AWB that is an adhesive-
backed sheet membrane offers a robust solution, as the adhesive clings to the fastener shank, helping seal the penetration.
If the cladding support system is fastened directly through the AWB and then into the exterior sheathing before going into the structural support, either an adhesive-backed sheet membrane or a full-
bodied, fluid-applied material performs well.
10 • RCI Interface October 2018
Figure 2 – Pressure-equalized rainscreen systems.
•Open joinery to air, but not water
•Drainable compartmentalization, limiting water pressure disequilibrium
•Complex design, which allows static and dynamic pressure equalization
•Minimizes or eliminates leakage through joints
•Developed in Canada
MAKING IT AIRTIGHT
Air barriers have been part of the National Building Code of Canada (NBC) since 1985. In the United States, air barriers were first adopted in the State of Massachusetts Building Code in 2000. For many other states, air barriers began to gain recognition with designers when the code of record became the 2012 IBC, which requires a continuous air barrier inclusive of the roof. Considerations for evaluating and specifying air barrier systems include vapor permeance and airtightness.
VAPOR PERMEANCE
Proper vapor permeance is determined by several parameters, including climate zone, interior relative humidity (RH), and the mechanical system (and whether it is designed to provide a positive or negative pressure).
If you find yourself still scratching your head, you can always perform a hygrothermal analysis using WUFI software or other similar programs. Analysis with WUFI can provide a calculation of the transient hygrothermal behavior of multi-layer building components exposed to a local natural climate condition.
Determining the proper vapor permeance can be a bit of a conundrum, and ASTM does not simplify matters. For example, ASTM E96, Standard Test Methods for Water Vapor Transmission of Materials, has multiple test procedure options. The two test procedures primarily used in our industry are Procedure A – Desiccant Method, and Procedure B – Water Method. Essentially, both procedures use the same test apparatus, temperature, and RH, but Procedure A utilizes a cup with a desiccant in it and is weighed once equilibrium is reached (water vapor entering the cup). Conversely, Procedure B utilizes a cup with water in it, and once equilibrium is reached (water vapor leaving the cup), the remaining water is weighed. The two procedures can yield significantly different results.
The International Code Council (ICC) recognizes Procedure A. When the Air Barrier Association of America (ABAA) evaluates air barriers, they perform and publish the results for both Procedure A and Procedure B.There is an ASTM specification guideunder development (WK51917, SpecifyingWater Vapor Transmission Properties of Water-Resistive Barriers and Air Barriers). This group contends that given the position in the wall assembly (beneath the cladding, protected from direct sun and wind-
driven rain), the AWB is exposed to environmental conditions similar to the exterior environment, and unless the project is in the arid desert, Procedure B is more relevant.
AIRTIGHTNESS
There are a few different ways to evaluate an air barrier, and these are also the same compliance paths in IBC and IECC. To be compliant with both codes, an air barrier needs to pass one of the following evaluation methods, listed in order of magnitude.
Material Testing
ASTM E2178, Standard Test Method for Air Permeance of Building Materials, is a pass/fail test at the threshold of 0.02 L/(s m2) @ 75 Pa (0.004 cfm/sf @ 0.3 in. w.c.). This test is based on the air permeance of 13-mm (½-in.) gypsum. While it is fairly easy for materials to pass, as with all tests, it is important that the air barrier manufacturer has the evaluation performed by an accredited third-party testing facility.
Assembly Testing
ASTM E2357, Standard Test Method for Determining Air Leakage of Air Barrier Assemblies, is more rigorous than ASTM E2178, as it evaluates an entire assembly rather than just the AWB material. Since it is performed in a lab, manufacturers can use fastener cap washers, tapes, and sealants not typically employed in the field to pass the test. This is a pass/fail test in which an opaque wall is evaluated against one with a mock window buck, penetrations, and an outlet. The air barrier system is also terminated at what would be the foundation and the roof.
The sample walls are put under sustained cyclic and gust loads, replicating worst-case conditions. If the wall with the penetrations leaks more than 10 percent at 75 Pa versus the opaque wall, it fails. When ABAA evaluates air barrier products, part of the assessment includes ASTM E2357. The association uses 0.20 L/(s m2) @ 75 pa (0.04 cfm/sf @ 1.56 lb/sf) as its pass criteria.
Whole-building Airtightness
ASTM E779, Standard Test Method for Determining Air Leakage Rate by Fan Pressurization, is the gold standard in air barrier performance testing. The U.S. Army Corps of Engineers (USACE), having proven airtight buildings offer profound energy savings, has required ASTM E779 for several years. The standard requires testing the
October 2018 RCI Interface • 13
Figure 3 – Similarities and differences between pressure-equalized and drained and back-ventilated rainscreen systems.
• Open joinery; cladding is allowed to leak
• Drains most of the water at outer cladding
• Relies on cavity ventilation to drain and dry residualwater
• 25-mm (1-in.) gap for brick cladding; 13-mm (½-in.)minimum gap for other claddings
• Requires robust, continuous, properly flashed air andwater barrier
• Not pressure equalized
• Developed in Europe
building @ 75 Pa. However, while a material
can leak at 0.02 L/(s m2) @ 75 Pa (0.004
cfm/sf @ 0.3 in. w.c.), an entire building can
only leak at 2 L/(s m2) @ 75 Pa (0.4 cfm/sf
@ 0.3 in. w.c.). USACE lowers the standard
to 1.25 L/(s m2) @ 75 Pa (0.25 cfm/sf @ 0.3
in. w.c.).
This whole-building airtightness standard
is showing up in more building codes.
Additionally, there is an uptick in passive
house designs in commercial buildings.
Passive houses take ASTM E779 to a whole
new level where the air leakage standard is
0.6 ACH (air changes per hour) @ 50 Pa (0.6
ACH @ 50 Pa = 0.03-0.15 CFM/ft2@75 Pa).
THERMAL RESISTANCE AND CI
Beginning with the 2012 IECC, ci is
required in all above-grade walls for all
climate zones (Figure 4). ASHRAE 90.1,
Energy Standard for Buildings Except Lowrise
Residential Buildings, defines ci as:
“Insulation that is uncompressed and continuous
across all structural members without
thermal bridges other than fasteners
and service openings.”
Stuffing insulation between Z-girts is
not consistent with ASHRAE 90.1. If a
project uses horizontal girts, they should
be shimmed from behind so water is free to
run down the AWB and not become trapped.
Although spray polyurethane foam (SPF)
and expanded polystyrene (EPS) are used
as insulation in cavity wall assemblies,
thermoplastic extruded polystyrene (XPS)
is a much more prevalent ci. XPS is a thermoplastic
rigid foam insulation board. As
a combustible thermoplastic polymer, XPS
generally melts and drips prior to ignition
when exposed to a fire source.
Due to its fundamental
combustion properties,
XPS is not used
behind combustible
claddings in cavity wall
systems that must pass
NFPA 285 for resistance
to fire propagation. In
such situations, mineral
wool or fire-enhanced
polyisocyanurate (polyiso)
must be used instead. For
noncombustible-cladded
NFPA 285 assemblies,
XPS is a realistic option,
as the masonry or other
noncombustible cladding
provides adequate fire
protection.
XPS also has the highest
resistance to water
absorption of any type of
foam plastic insulation,
allowing it to maintain its
R-value in wet cavity wall
locations. According to
the Extruded Polystyrene
Foam Association (XPSA),
the aged R-value of XPS
at 50 mm (2 in.) is R-5.0
per inch @ 24°C (75°F).
Since polyiso is a
thermoset plastic, it is
less susceptible to burning
than XPS, but will
char and smolder when
exposed to fire. This
behavior enables certain types of polyiso,
with additives in the foam, to be
used behind combustible claddings and
pass NFPA 285. Designers should check
with the manufacturer to verify the polyiso
under consideration is suitable for such
1 4 • RC I I n t e r f a c e Oc t o b e r 2 0 1 8
Figure 4 – Mineral wool continuous insulation. Image courtesy
Owens Corning.
Everybody likes a project profile!
RCI Interface is particularly interested in submission of project
profile articles concerning unique building envelope projects.
Profiles should be 1500 to 2500 words with five to 15 high-quality
photos and should describe a building issue that is diagnosed
or solved or an unusual building or condition worked on in the
course of a building envelope consultant’s work. Submit articles to
Executive Editor Kristen Ammerman, kammerman@rci-online.org.
RCI Interface Seeks Project Profiles
applications. According to the Polyisocyanurate Insulation Manufacturers Association (PIMA):
Among all foam plastics, polyiso possesses the highest level of inherent fire resistance due to its unique structure of strong isocyanurate chemical bonds. These bonds result in improved high-temperature
resistance (up to 390°F [200°C], more than twice the temperature resistance of other building insulation foams), which in turn leads to enhanced fire resistance.
It is uncommon to see more than a 76-mm (3-in.) layer of polyiso pass an NFPA285 test with a combustible cladding. Theaged R-value of foil-faced polyiso, per ASTMC518, Standard Test Method for Steady-State Thermal Transmission Properties byMeans of the Heat Flow Meter Apparatus, at50 mm (2 in.) is 6.25 to 6.5 per inch.
For NFPA 285 compliance, mineral wool offers designers a get-out-of-jail-free card. Offering a heat resistance of 850°C (1562°F) and a melting point of 1177°C (2150°F), mineral wool essentially will not burn. Mineral wool is not limited by thickness, so any thickness of insulation can be installed and maintain compliance. Mineral wool has a flame spread and smoke developed rate of zero per ASTM E84, Standard Test Method for Surface Burning Characteristics of Building Materials. The R-value of one manufacturer’s exterior wall product ranges from R-4.0 to R-4.3 per inch.
NFPA 285 COMPLIANCE
Perhaps the most vexing element of cavity wall design is compliance with NFPA 285. As defined by the NFPA, the standard is a Standard Fire Test Method for Evaluation of Fire Propagation Characteristics of Exterior Non-loadbearing Wall Assemblies Containing Combustible Components Using the Intermediate-Scale, Multi-story Apparatus. (Prior to its IBC adoption in 2000, a similar, larger-scale test appeared in the 1988 Uniform Building Code [UBC].) The code applies to Type I through Type IV construction on multistory projects, or single-story walls in excess of 12 m (40 ft.).
The defining characteristic of NFPA 285 is that it is an assembly test (Figure 5), just like a UL or Factory Mutual (FM) roof assembly test. A manufacturer may market an air barrier as “fire resistant” or “fire rated,” but such designations have no bearing on compliance with NFPA 285. Complicating matters, there is no single clearing house to provide designers with tested and passed assemblies.
In the late 1980s, NFPA required exterior insulation and finish system (EIFS) manufacturers to test their systems. Other foam plastic insulation manufacturers (e.g., those involved with XPS) have been vigilant with their testing for years, and have very thorough reports of assemblies with which their products comply. In the 2012 IBC, AWBs had to comply with Section 1403.5, as all AWBs are combustible. However, when some states and the District of Columbia adopted the 2012 IBC, they excluded 1403.5.
According to the 2015 IBC, 1403.5 can be excluded if the AWB is the only combustible component in the assembly. The 2015 IBC also specifies if the AWB falls below a certain level of fuel contribution (based on ASTM E84 Class A and ASTM E1354, Standard Test Method for Heat and
October 2018 RCI Interface • 17
®
Innovation based. Employee owned. Expect more.
For information, call214-515-5000or visit our website at www.PolyguardBarriers.combyYou design the building.Our innovative waterproofing and non-chemical termite barrier systems come with employee owners who can advise how to best envelope your structure. Dealing with an owner gets you more.to ourand the Leave theWATERPROOFING TERMITECONTROLOWNERS
Visible Smoke Release Rates for Materials
and Products Using an Oxygen Consumption
Calorimeter), and it is the only combustible
component in the assembly, it will not
require NFPA 285 compliance. Further,
rough opening flashings associated with the
AWB system are also excluded from NFPA
285 compliance requirements.
Ultimately, NFPA 285 compliance is
all about preventing loss of life. Recall the
case of the 72 people who perished in the
Grenfell Tower in London on June 14,
2017. The cladding on this building was
aluminum with polyethylene foam insulation
core. Inside of the cladding was a
50-mm ventilation space. Secured to the
existing cladding was 150-mm polyisocyanurate
insulation. The cavity wall assembly
in the Grenfell Tower would not comply with
NPFA 285. Accordingly, the United Kingdom
Parliament has committed £400M (about
$536M) to remove all “Grenfell-style” cladding
from high rises in the United Kingdom.
THE CAVITY WALL BALANCING ACT
While each of the preceding topics could
be expanded into an article of its own, they
are highlighted here to help make building
designers aware of the competing requirements
and standards involved in modern
cavity wall design. Designers should know
that continuous air barriers and continuous
insulation, along with NFPA 285, are
code-compliance issues that must be balanced
with the goal of keeping water out
of the building. Achieving this balance will
help designers go a long way toward designing
the safest, most energy-efficient building
envelopes possible.
1 8 • RC I I n t e r f a c e Oc t o b e r 2 0 1 8
Todd C. Skopic,
CDT, LEED AP, is
a building science
manager at Henry
Company. He has
been in the air barrier
industry for
18 years, working
with different manufacturers.
Skopic is
active in CSI, BEC,
RCI, and ASTM. He
can be contacted via
e-mail at tskopic@
henry.com.
Todd C. Skopic,
CDT, LEED AP
Researchers at ETH Zurich University in
Switzerland have developed an innovative
3-D sand printing technique with which they
have fabricated their first full-scale concrete
slab. The 80-square-meter (861-sq.-ft.) slab
at the DFAB House, dubbed the “Smart Slab,” carries a two-story timber unit above it.
The intricately designed ceiling maintains load-bearing characteristics with precision narrowed down to millimeters.
The software coordinated and recorded all the parameters of the room. After the forms were created, the sand mold was
sprayed with fiber-reinforced concrete, creating an organic, ribbed surface. The team then cast the remaining concrete
into the timber form-work, creating the final
form. Following completion, the mold can be
dismantled and reused for other projects.
Eleven segments were allowed to harden
for two weeks, and then they were transported
to the designated site and installed using
a crane and steel cables to pre-stress the
concrete mold into the structure.
To view a video of the process, visit:
https://www.youtube.com/watch?time_
continue=17&v=FUw3MWhD9dY.
— Archdaily.com
Swiss University
Fabricates World’s
First Full-Scale
3-D Sand Printing
Architectural Project
Installation of Smart Slab on DFAB House
in Zurich, Switzerland.
Researchers make 3-D-printed sand mold at ETH Zurich.