Skip to main content Skip to footer

Blindside Waterproofing Systems for Hydrostatic Conditions:  Lessons Learned & Good Practice

March 13, 2025

Blindside Waterproofing Systems for Hydrostatic Conditions:  Lessons Learned & Good Practice

 

INTRODUCTION
With the increasing demand for housing and
expansive growth of multi-unit residential
building (MURB) developments in downtown
Toronto and neighboring communities, the
number of below-grade levels, particularly
for parking, continues to extend deeper.
Blindside below-grade waterproofing has
become an essential component of multi-unit
residential building developments in
constructing watertight foundation walls,
primarily to accommodate parking spaces. The
proximity of the communities in and around
downtown Toronto to Lake Ontario has led
to these below-grade assemblies inevitably
reaching hydrostatic conditions with high water
table conditions.
Given the current local municipal restrictions
on collecting and discharging water around and
below-grade foundations into the municipal
storm and sanitary systems, all new buildings
within the Toronto municipal area are required
to be 100% watertight through an application
method of below-grade waterproofing, widely
known as “bathtubbing.” This is achieved
through a combination of excavations using
caisson wall soil retention (tiebacks, rakers,
and other retention methods), site dewatering
(removal of active water to lower the water
table during construction), raft slabs, and a
waterproofing system that fully encompasses the
below-grade structure (“bathtub” waterproofing).
To improve project schedules and reduce
construction costs, developers consistently
source alternative construction methods, and
one such method is shotcrete. Shotcrete is a
method of concrete placement that has been in
the industry for several decades and has recently
been used for foundation wall construction with
blindside waterproofing applications. Shotcrete
allows for faster foundation wall construction,
which allows for a reduction in the construction
schedule. There are also the A-frame (Fig. 1)

 

Blindside Waterproofing
Systems for Hydrostatic
Conditions

 

By Christopher McConnell, BTech
This paper was presented at the 2024 IIBEC/
OBEC BES.
and the conventional poured methods (utilizing
a wall form with threaded rods to hold forms
in place) (Fig. 2). The A-frame allows for the
construction of foundation walls that would
produce the fewest penetrations through the
blindside waterpoofing. This is achieved by
supporting the reinforcement cage above the
forms and above the waterproofing system
and then removing the anchors when the next
level is poured, allowing for waterproofing to be
installed without penetration. The conventional
poured method utilizes a threaded rod technique
that holds the interior form in place by anchoring
it to the soldier piles. This method will require the
securement of the form and the reinforcement
bar cage through the membrane, and it will be
necessary for the waterproofing to be detailed
around them.
In addition to the construction methods,
considering the water table for a specific site
is also important. Understanding if a site has
a high, medium, or low water table and the
number of below-grade floors being constructed
helps to identify what type of hydrostatic
condition the below-grade floors will be
under. Once the level of hydrostatic pressure is
confirmed, selecting suitable materials and the
details to accompany them is the next step.
With the new requirements needing
“bathtub” application of blindside waterproofing
and the condition of hydrostatic pressure behind
the foundation walls, shotcrete foundation
walls have proven to contribute to failures in
achieving the watertight condition required
Interface articles may cite trade, brand,
or product names to specify or describe
adequately materials, experimental
procedures, and/or equipment. In no
case does such identification imply
recommendation or endorsement by
the International Institute of Building
Enclosure Consultants (IIBEC).
©2025 International Institute of Building Enclosure 10 • IIBEC Interface Consultants (IIBEC) March/April 2025
for the below-grade structure. The installation
process of the shotcrete creates situations that
are detrimental to the waterproofing adhesion
process, wherein for most systems 100%
adhesion is required to be an effective and
reliable waterproofing system. Therefore, other
means of construction, aside from shotcrete, are
required to achieve a watertight condition for the
blindside “bathtub” waterproofing systems.

WATERPROOFING
MATERIALS FOR BLINDSIDE
“BATHTUBBING”

Understanding the problem is only the
beginning of establishing a path toward a
successful watertight structure. To start, let us
review the different types of waterproofing
systems that are presented by their various
manufacturers as being the right product for
the site conditions. Some systems are sheet and
liquid membranes that require 100% adhesion,
while others require a two-stage system utilizing
sheet membranes and a bentonite layer in
hydrostatic conditions. The two-stage system
is required to have a sheet membrane over
the entire foundation wall structure but also
requires a bentonite sheet layer within and
just above the water table area. This additional
layer of protection provides a back up to the
main waterproofing membrane sheet. The
bentonite is intended to swell and seal a breach
in the main sheet reducing the possibility of
water penetrating through the membrane and
subsequently through the foundation walls.
There are several types of blindside
waterproofing products, but the most common
fully adhered systems are high-density
polyethylene (HDPE) sheets, elastomeric
sheets, styrene-butadiene-styrene (SBS)
modified bitumen sheets, bentonite sheets,
and spray-applied elastomeric coatings. There
are other waterproofing systems that are used
in the industry that are not as common in
the residential construction industry. These
materials are thermoplastic polyolefin (TPO),
polyvinyl chloride (PVC) and Bentonite systems.
These are not all fully adhered systems and
depending on the soil and ground water
conditions these systems may not be suitable
for selection. With all the different types of
materials, it is a challenge to know when to
use which product to give the project the best
chance for success.
The more we allow for a hydrostatic condition
to occur around the below-grade structure, the
higher the waterproofing system’s risk of failure.
It has been recently identified that the use of
drainage boards for the “bathtub” waterproofing
systems can allow for water to flow freely around
the structure and fill up with water to a point that
is equal in elevation to the existing water table.
Therefore, under these conditions, hydrostatic
pressure has not been eliminated as intended
with the introduction of a drainage board. If
the drainage board can be eliminated and the
waterproofing applied to a relatively smooth
surface, this could reduce the amount of water
directly behind the foundation wall and reduce
the risk of excessive water infiltration. This can
also be achieved by installing diaphragm soil
retention walls, which have a higher strength
than the conventional caisson walls we see in
today’s construction. This can act as an additional
line of defense for keeping the water away from
the foundation walls and assist the waterproofing
system to achieve watertightness protection.
INVESTIGATION OF WATER
INGRESS THROUGH
FOUNDATION WALLS
Having had the opportunity to investigate a
couple of structures with systemic failures of
their waterproofing systems, we have begun
to understand the causes of the failures
and understanding these are common
occurrences on construction sites. These
failures are resulting in excessive amounts
of water leakage through the foundation
walls at cracks and construction joints. These
investigations involved foundation walls
constructed using a shotcrete method, and the
structure was subjected to high water table
conditions (high hydrostatic head). We utilized
a number of nondestructive investigation
methods for this investigation. One of the
investigation techniques was the review of
documentation from the construction process,
such as third-party or Bulletin 19 (B19) field
observation reports (Ontario requirement for
new homeowner constructed developments),
manufacturer reports, and a review of the
dewatering decommissioning process. Using
this information, we were able to identify
suspected failure modes. Shotcrete foundation
wall construction introduces several high-risk
situations if not completed correctly or in the
appropriate timelines. Due to shotcrete’s low
water to cement ratio, the dryer mix will cure
much faster and will result in waterproofing
adhesion failures if not applied in smaller
increments. There is also the potential for rebar
shadowing, unconsolidated material (voids),
and overspray on the membrane creating a
bond breaker within the waterproofing system,
this has led to several failure modes of the
waterproofing membrane not bonding as
required and allowing for water travel through
the foundation wall. If water leaks in the
foundation wall are more localized and isolated,
this could potentially point to a single failure
mode as the source of the issue. One of the
non-destructive testing methods we utilized
to confirm a failure mode was ultrasonic pulse
echo (UPE) analysis. The UPE analysis helped to
assess the condition of the shotcrete while also
identifying items such as tiebacks, potential
waterproofing membrane failures, and the
thickness of the walls at given locations.
During the review of the documentation,
we were able to identify several areas where
the waterproofing was covered in overspray
material from the shotcrete process (Fig. 3 and
4). This information helped us to see a possible
correlation between some of the leak locations
of the constructed walls (Fig. 5 and 6). We used
this information to help in the selection of walls
Figure 1. A-frame for foundation walls
construction method cross section.
Figure 2. Conventional framing for foundation
walls construction method cross section.
March/April 2025 IIBEC Interface • 11
for the non-destructive investigation method
utilizing the UPE analysis.
The UPE analysis provides information
through acoustic stress waves from the interior
surface of the foundation wall to the caisson wall
and, in some cases, through the caisson wall.
These waves help to locate defects or anomalies
in the concrete wall that are dissimilar to solid
concrete. This information can be utilized to
extract information pertaining to the condition
of the shotcrete, which identifies anomalies
along the path of the UPE signal. A review of
these results can tell us if there are areas of voids,
cavities, or gaps in construction. We were able
to use this information to not only find areas of
concern in the shotcrete but also to find areas
of membrane bonding issues, with a good
degree of accuracy. In addition, we found and
mapped out the locations of tiebacks where the
signal reflection was much shorter due to the
tieback being closer than the expected thickness
of the foundation walls. Utilizing this process,
we were able to select locations to conduct
concrete coring through the foundation wall to
collect physical data and compare them with the
analysis information.
Following the coring process, it was
confirmed that the membrane had adhesion
issues. This appears to have been caused by
shotcrete overspray, unconsolidated concrete
(voids) and material bonding issues with
the dryer mix of the shotcrete. What we did
not expect to find was that the shotcrete
and liquid waterproofing materials that are
used to detail tiebacks were not adhered,
either. It was also discovered that one area
had unconsolidated concrete at the backside
of the foundation wall (Fig. 7 and 8), rebar
shadowing had occurred (Fig. 9 and 10), and
a waterproofing lap joint was not fully adhered
(Fig. 11 and 12). The extensive water intrusion
through the foundation wall was the result of
several failure modes such as tieback anchors,
unbonded membrane at shotcrete overspray
locations, and partially bonded overlap joints.
For more information on this subject please
refer to my first paper published through
the 16th annual Canadian Conference on
Building Science and Technology titled
“Lessons Learned: Moisture Ingress Protective
Waterproofing Systems.”
HOW TO REMEDIATE A
SYSTEMIC “BATHTUB”
WATERPROOFING SYSTEM
FAILURE
As there are several products to waterproof
the blind side of a below-grade structure,
there are also several materials available to
assist in remediating a systemic failure of the
waterproofing system. A repair method called
curtain grout injection uses the following
materials currently on the market: bentonite
polymers, acrylic/ acrylates, polyurethane
foams, and rubber polymer gels. These
materials are either hydrophobic or hydrophilic
in nature. Hydrophobic materials are those that
repel water; while they will use some water
for the activation process, once the curing
process has begun, they will disperse water
away. Hydrophilic materials are those that
absorb water; they will use the water as part
of the curing process and require moisture
to maintain their gelatinous states. There are
pros and cons to each material, and the site
condition is critical to the selection of the
appropriate materials. The curtain grouting
process is an intrusive procedure and will
act as the new watertightness defense if the
Figure 3. Shotcrete overspray on sheet
membrane after form work was removed. No
additional overspray removals were expected.
Figure 4. Shotcrete installation on sheet
membrane and overspray is approximately 2 ft
(0.6 m) beyond construction joints.
Figure 5. Water infiltration through
foundation wall at column location.
Figure 6. Water infiltration through
foundation wall cracks at corner.
12 • IIBEC Interface March/April 2025
membrane and construction system have
failed to keep the building in a dry condition.
Therefore, material warranty and material
selection to accommodate the site conditions
are critical to ensuring a successful remediation
process. This is a scenario where one solution
does not fit all, and therefore appropriate
research into the product and retaining a
consultant that has adequate experience is
essential. Most of these materials require
water to be present behind the walls during
the injection process, which is beneficial, as
dewatering the site after the structure is in
place is extremely costly and difficult.
MATERIAL MOCK-UP PROCESS
We conducted a full-scale mockup of
four blindside “bathtub” waterproofing
system material types on an A-frame and
a conventional form and pour construction
process. We incorporated the different types
of details in the mockups that would reflect
in-situ construction practices, such as pre- and
post-applied penetrations, reinforcement
anchors, tieback boxes, changes in surface
elevation (soil retention), and smooth surface
application (soil retention) without drainage
Figure 8. Extracted core from foundation wall showing unconsolidated
concrete.
Figure 7. Ultrasonic pulse echo analysis measurement at
unconsolidated concrete location.
Figure 9. Ultrasonic pulse echo analysis measurement at
reinforcement bar shadowing location.
Figure 10. Extracted core from foundation wall showing reinforcement bar
shadowing.
Figure 11. Ultrasonic pulse echo analysis of concrete where lap detail
and waterproofing adhesion failure were found.
Figure 12. Extracted core of foundation wall waterproofing where the
membrane was not adhered due to shotcrete overspray.
March/April 2025 IIBEC Interface • 13
boards (Fig. 13-16). The intent of these
mock-ups was to review the waterproofing
systems following the installation of
reinforcement and concrete for a 1.83 m (6 ft)
high wall with details reflective of real-world
construction practices (as can be reasonably
duplicated). The concrete was poured using a
bucket attached to a crane to drop the concrete
into the forms with no protection to the overlap
waterproofing material.
Once the concrete reached acceptable
structural capacity (confirmed using concrete
cylinders cast for each wall) the backside of the
forms where the waterproofing was installed
against were removed (Fig. 17). This exposed
the waterproofing material which was bonded
against the exterior face of the foundation
wall mock-up. Following the exposure of the
waterproofing materials, we removed the
drainage boards where possible (some of the
systems the drainage board are bonded to the
membrane as part of the installation process)
to expose the membrane at these drainboard
locations. A visual and tactile review of the
membranes took place to identify possible areas
of debonding. Areas that were suspected of
debonding were checked by completing a field
adhesion test (the membrane was cut with a
knife in a rectangle around the suspected area
and grabbing the top of the cut section and
attempting to remove by pulling perpendicular
to the wall). A majority of the suspected areas
were unbonded with some membranes
performing better than others. A contributing
factor to the unbonded waterproofing appears
to be due to consolidation issues of the concrete
(vibration was inadequate). During the visual
review we also noted that the top of the
waterproof membranes were covered in concrete
splatter from the installation of the concrete
(Fig. 18). Based on these findings the details
and material selection are not the only major
requirements but also the installation of concrete
and the placement of the reinforcement within
the foundation walls.
Lastly the walls were then sectioned off
and laid down on their backs to facilitate the
dissection and collection of the samples to be
sent to an ASTM rated lab. We are having three
tests performed for each membrane type:
Hydrostatic Head Testing (ASTM D5385—
Modified), Lateral Water Migration (AATCC
TM127) and Concrete Adhesion ASTM D4541.
These tests are to verify how the waterproofing
would perform in the hydrostatic conditions
of a blindside “bathtub” application including
their ability to bond to post applied poured
concrete. Quantitative test results are currently
outstanding and will be received later.
Hydrophobic Pros Hydrophobic Cons Hydrophilic Pros Hydrophilic Cons
Pushes water away Displaces water Absorbs water; will
continue to absorb water
Shrinks when it dries
Remains in a solid
state, regardless of
moisture presence
Has poor adhesion on
wet surfaces
Is flexible and can
bridge cracks
Loses flexibility when
it dries
Becomes lighter than
water when curing
Has poor flexibility
after curing; cannot
bridge cracks
Has better adhesion to
wet surfaces
Figure 13. Elastomeric sheet waterproofing
installed.
Figure 14. High-density polyethylene sheet
waterproofing installed.
Figure 15. Elastomeric spray applied
waterproofing installed.
Figure 16. Styrene butadiene styrene
modified bitumen waterproofing installed.
Figure 17. Formwork in place for pouring of
concrete from bucket.
Figure 18. Concrete splatter is found on
overlap joint above the concrete pour.
14 • IIBEC Interface March/April 2025
HIGH TO MEDIUM
HYDROSTATIC CONDITIONS
Understanding the performance of the materials
and their restrictions can help in identifying
what changes are needed to the design of
the soil retention system and the selection
of a framing method. In some cases the
height of the water table could dictate which
measures are needed to increase the chance
of success. In a high to medium hydrostatic
conditions, the water table could be four (or
more), to two levels above the slab on grade.
Understanding the site at the design stage
and its expected hydrostatic condition is more
important these days, due to the inherent risk
it poses to ensuring the watertight condition
of the below-grade structure. Upgrading the
soil retention system to a higher-strength wall
with water impermeability, specifically in the
use of a Diaphragm wall, needs to be greatly
considered. The implementation of this soil
retention can allow for minimal damage to the
caisson wall during the excavation process,
resulting in a smoother surface. This will allow
the waterproofing membrane to be installed
directly on the wall without the use of a
drainage board. Without the drainage board
present, the chance for excess water to build
behind the foundation wall will be reduced.
Isolation of the tiebacks using tieback boxes is
required at the structural design stage by the
structural engineer. This detail will allow for the
isolation of the tieback from the foundation wall
embedment and remove the risk of difficult
detailing of the tieback.
The use of A-frame construction to reduce
the number of penetrations through the
membrane will increase the chances of a
successful watertight structure. The use of
a dewatering system that carries the water
behind the waterproofing system through
the collection at pits can be very beneficial
to the success of the waterproofing system.
Some dewatering systems are completed with
a series of water tubes and follow behind the
waterproofing. However, this method requires
that a large breach in the membrane be used
to collect the tubes at one location from the
dewatering wells. This penetration and method
of dewatering can lead to water infiltration if
the details are not completed adequately or if
there is water coming through the dewatering
system if it is not adequately sealed. Finally,
the selection of a waterproofing system that is
designed and approved for these hydrostatic
conditions is important. The system must be
able to withstand the hydrostatic conditions
at the weakest points of the system (that is,
penetration details, lap joints, and repair
patches). If the system cannot demonstrate
successful applications in similar project
conditions and the manufacturer cannot
provide a letter of approval for the use of their
system for your specific site conditions, a new
material or system needs to be considered
LOW TO MINIMAL
HYDROSTATIC CONDITIONS
Low to minimal hydrostatic conditions can
be considered with a water table being
one to zero levels above the slab on grade,
respectively. These conditions are at less risk
of failure but still need to be given respect
and attention to achieve the successful
performance required. Use of the A-frame
method in water table conditions for the site
and tieback boxes are still recommended, but
this process could potentially be modified in
the non-hydrostatic levels. The membrane
system will still need to be capable of
preventing water infiltration, but the areas
with no hydrostatic conditions may alter the
manufacturers’ requirements for a successful
system. In these scenarios, it is often the
under-slab waterproofing and the lowest level
of the structure that are in the water tables.
This will allow for a more conventional process
for the levels above the water table that should
be able to be performed as required.
CONCLUSION
Construction methods and blindside “bathtub”
waterproofing systems have their appropriate
uses, and knowing their limitations or
restrictions is vital. Identifying the necessary
construction methods early in the design stage
can reduce the risk of critical items during the
construction process. It is necessary to select
appropriate waterproofing systems with the
intention to protect the reinforced concrete
elements and reduce the moisture ingress
into spatial conditions. The waterproofing of
below-grade structures is successful only when
it is done correctly the first time. Repairs or
remedial measures to a failed waterproofing
system applied to a buried structure are
financially impractical from an excavation
and repair standpoint. Remedial repairs from
the negative side (interior space) by way of
curtain grout injection can be a viable option,
but they are very costly and intrusive due
to the required process. The extent of water
migration is dependent on the path that the
water finds through the concrete elements
and its ability to move laterally between the
membrane system and the structure. If the
waterproofing membrane system is not fully
bonded to the structure, water can travel
to areas that have a high risk of moisture
ingress. Therefore, an appropriate material
selection and construction methodology at the
design stage, accompanied by quality control
during the construction stage, is essential to
mitigate potential failures of the waterproofing
system and premature failure of the building
components.
APPLICABLE STANDARDS
Ontario Building Code, 2012
ASTM D903-98(2017), Standard Test Method
for Peel or Stripping Strength of Adhesive Bonds
ASTM D5385-93(2006), Standard Test
Method for Hydrostatic Pressure Resistance of
Waterproofing Membranes
ASTM E154-08, Standard Test Methods for
Water Vapor Retarders Used in Contact with Earth
under Concrete Slabs, on Walls, or as Ground
Cover
ASTM E96/E96M-14, Standard Test Methods
for Water Vapor Transmission of Materials
ASTM D412, Standard Test Methods
for Vulcanized Rubber and Thermoplastic
Elastomers—Tension
ASTM D1970, Standard Specification for Self-
Adhering Polymer Modified Bituminous Sheet
Materials Used as Steep Roofing Underlayment
for Ice Dam Protection
ASTM D4833, Standard Test Method for Index
Puncture Resistance of Geomembranes and
Related Products
ASTM D4068, Standard Specification for
Chlorinated Polyethylene (CPE) Sheeting for
Concealed Water-Containment Membrane
ABOUT THE AUTHOR
Over his 10-yearsplus
career,
Chris McConnell has
gained experiences
in a wide variety of
fields and disciplines,
including custom
house design,
general contracting,
and consulting
services related to
noise, vibration, new
construction, concrete rehabilitation, facade
restoration, and waterproofing failure problem
solving. At Synergy Partners, he provides a
variety of services to several types of clients in the
commercial, industrial, and residential sectors,
including services across Canada where he
remotely liaise with local teams to deliver highly
successful projects. He is a graduate of McMaster
University, where he finished summa cum laude
in his Bachelor of Technology program.
CHRIS MCCONNELL
March/April 2025 IIBEC Interface • 15