Skip to main content Skip to footer

Evaluating Water Leakage in Mass Masonry Walls

February 5, 2016

INTRODUCTION
Prior to the 1950s, many buildings
were constructed using multi-wythe mass
masonry walls. Such walls typically did not
include air barriers, weather-resistive barriers,
vapor retarders, or thermal barriers, as
do modern wall assemblies.
Buildings consisting of mass masonry
are highly dependent on the thickness of
their walls and the quality of masonry units
and mortar joints within the walls to control
water leakage. Over time, such buildings
will inevitably exhibit water leakage or will
have components that exhibit deterioration
due to excess moisture accumulation
within the walls. Prior to implementing
a repair program to address such issues
and to extend the building’s useful life, a
systematic condition assessment and water
leakage evaluation should be performed.
This article describes a methodology for performing
water leakage evaluations for mass
masonry walls.
MASONRY WALL TYPES
Prior to the 1950s, multi-wythe mass
masonry wall systems consisting of solid
masonry for their entire thickness were
commonly used. Newer and lighter masonry
walls were developed after that time. By the
1980s, masonry cavity walls incorporating
a water management system were widely
used. These walls utilize a drainage cavity,
including through-wall flashing and weeps
to divert water that penetrates through the
single-wythe masonry veneer to the exterior.
Ideally, masonry cavity walls are designed
and constructed with a weather-resistive
barrier installed on the exterior face of the
back-up wall to prevent water within the
drainage cavity from penetrating further
into the wall. Cavity wall construction also
typically includes insulation on either the
interior or exterior side of the backup wall.
Both mass masonry walls and masonry
cavity walls rely on the bond between mortar
and masonry units to limit water penetration
beyond the exterior wythe of the wall or
the veneer. Aside from this similarity, mass
masonry walls function entirely differently
than modern cavity walls. Mass masonry
walls rely on their large mass to absorb
water that inevitably penetrates beyond the
exterior face of the wall. This water is stored
within the masonry until it can evaporate to
the exterior environment or into the building.
Since no insulation was typically used
on the interior of the walls, interior paint
was highly permeable, and interior spaces
were not air-conditioned prior to the mid-
1900s, moisture evaporation to the interior
did not typically pose significant issues.
Additionally, the interior finish on mass
masonry walls was often constructed of
cement plaster, which was not susceptible
to moisture damage like gypsum plaster.
Lack of insulation and the large thermal
mass of the masonry also helped keep mass
masonry walls relatively warm and reduced
temperature fluctuations.
Mass masonry walls can be either
load-bearing or non-load-bearing. Most
buildings with load-bearing walls have
been limited to approximately four stories
in height, though several such buildings
are much taller. Most mid-rise and highrise
buildings included non-load-bearing
mass walls constructed with masonry infill
between floor slabs. In some instances, the
structural concrete frame was exposed to
the exterior, with mass masonry infill walls
constructed between structural frame elements.
In other buildings, the structural
frame was completely concealed by the exterior
wythe of masonry. In these cases, the
exterior wythe of masonry was often supported
by shelf angles anchored to concrete
slab edges. The remaining wythes of masonry
were typically supported directly on the
floor slabs. The confinement of the masonry
infill walls by the building frame causes
several issues due to differential movement
between the frame and the masonry.
For example, deflection of floor slabs that
support the masonry can cause cracking.
Additionally, the irreversible expansion of
the masonry infill can cause stresses to
build up within the infill walls, sometimes
resulting in bowing.
In both load-bearing and non-load-bearing
masonry mass walls, the individual
masonry wythes were typically connected
using masonry header courses.
WATER PENETRATION THROUGH
MASS MASONRY WALLS
Mass masonry walls are susceptible to
water penetration due to several factors.
1 0 • I n t e r f a c e F e b r u a r y 2 0 1 6
These factors include the following:
1. The condition of mortar joints on the exterior
face of the walls greatly impacts the quantity
of water that is shed versus that absorbed
into the walls. Mortar joints that bond well to
masonry units typically serve to reject most
of the water that contacts the exterior face
of the walls. However, cracked and/or open
mortar joints will provide a path for water
penetration beyond the exterior wythe of
masonry (Photo 1). For several reasons, the
mortar and masonry units cannot be made
completely watertight.
2. Mass masonry walls were typically not
designed with movement joints to accommodate
irreversible expansion of brick masonry,
building frame movements, and movements
associated with temperature and moisture.
Lack of movement joints can result in stress
buildup. Such stresses can cause cracking,
localized displacement (Photo 2), failure of
headers, and/or bowing. The cracks will
provide a direct path for water penetration
beyond the exterior wythe of masonry.
3. Brick masonry headers were typically used
to connect the exterior wythe to the remainder
of the wall. Over time, these headers can
fracture due to shear stresses, deterioration,
or other means. Shear stresses can build
up due to differential thermal, frame, or
irreversible moisture movements between
F e b r u a r y 2 0 1 6 I n t e r f a c e • 1 1
Photo 1 – Open mortar joint between
limestone and brick masonry provides
a path for water penetration beyond
the exterior wythe of masonry.
Photo 2 – Parapet wall lateral
displacement due to inadequate
accommodation of irreversible
expansion of the brick masonry.
the exterior wythe and inner
wythes. Where headers fail,
the exterior wythe of masonry
can move independently
of the interior wythes, typically
manifesting as bowing.
Cracks in the mortar joints
and/or masonry will inevitably
develop due to this
movement, allowing for water
penetration beyond the exterior
wythe.
4. Embedded shelf angles were
often constructed without
sufficient protection to inhibit
corrosion. As the steel corrodes
and expands to several
times its original size, cracks
will develop, allowing water
penetration. Steel corrosion
can also cause shear stresses
that can lead to failure of
brick headers.
5. If the walls are not sufficiently
thick to provide a large
mass to absorb moisture, they
can transmit free moisture
through their thickness far
sooner than more massive walls. In
our experience, walls less than four
wythes thick are particularly susceptible
to occasional water leakage.
Where portions of walls become less
than four wythes thick at specific
locations, they will also be more susceptible
to leaks (Photo 3). Similarly,
the use of hollow units, such as hollow
clay tiles, in lieu of solid masonry
units as backup wythes, reduces the
mass of masonry that can absorb
1 2 • I n t e r f a c e F e b r u a r y 2 0 1 6
Photo 3 – Leak location at
wall section reduced from
four- to two-brick masonry
wythes to accommodate
internal drain pipe.
Photo 4 – Use of
hollow clay tile units
as backup wythes
reduces the mass of
masonry that can
absorb and retain
moisture.
and retain moisture, thus increasing susceptibility of
water leakage (Photo 4).
6. The exterior and interior surfaces of mass masonry
walls dry out faster than the center wythe(s) due to
their exposure to the environment. As such, thick
walls will retain moisture for a long duration, and
deterioration of mortar and masonry within the walls
is expected (Photo 5). Such deterioration reduces the
ability of the walls to absorb and retain additional
moisture, leading to more susceptibility to leaks. In
many cases, such deterioration goes unnoticed since
it is not visible without fi rst removing masonry from
the face of the wall.
7. Inadequate workmanship or use of substandard
materials during original construction can result in
voids within the walls or weak mortar joints that are
susceptible to freeze/thaw deterioration. This reduces
the ability of the walls to absorb and retain moisture
and provides paths through the wall for water penetration.
8. Mass masonry walls were typically constructed with
cement plaster directly applied to their interior face as
a fi nish. Properly applied, the cement plaster provided
for another line of defense against moisture intrusion.
However, more importantly, the cement plaster
was not susceptible to degradation when exposed
to moisture. Over time, many mass masonry wall
f e b r u a r y 2 0 1 6 I n t e r f a c e • 1 3
Photo 5 – Deterioration of masonry and mortar within the exterior wall.
www leadingedgesafety net
WE TAKE THE FIRST STEP
SO YOU DON T TAKE YOUR LAST
FALL PROTECTION
TEMPORARY PERMANENT
interior finishes have been repaired
using gypsum plaster or alternative
products such as gypsum sheathing.
These materials are far more
susceptible to degradation due to
exposure to moisture. As such, it is
not uncommon to encounter mass
masonry walls with gypsum-based
interior finishes that exhibit ongoing
plaster deterioration (Photo 6).
EVALUATING LEAKS IN
MASS MASONRY WALLS
ASTM E2128, Standard Guide for
Evaluating Water Leakage of Building Walls,
describes methods for evaluating causes of
water leakage of exterior walls. The recommended
sequence of activities for an exterior
wall leak evaluation program is summarized
as follows, with steps listed in parenthesis:
1. Background review (review of project
documents, evaluation of design
concept, determination of service
history)
2. Field investigation (visual inspection,
investigative testing, exploratory
openings, laboratory testing)
3. Analysis and reporting (analysis,
report preparation)
The recommended protocol established
by ASTM E2128 can be used as the basis
for an exterior wall leak evaluation, regardless
of wall system or material. With specific
regard to mass masonry walls, the following
items should be considered.
Review of Project Documents
Documents that may be helpful for the
investigator include original design documents,
codes and standards referenced in
the original design documents, submittals,
shop drawings, construction photographs
and field reports, project closeout documents,
and records pertaining to prior
repairs.
An accurate set of record drawings can
be particularly useful. These documents,
taken as a whole, can provide the investigator
with a considerably detailed description
of the wall construction.
Unfortunately, original design documents
for buildings constructed in the
late 19th and early 20th centuries usually
consisted of only a few sheets of drawings
describing the materials and work required
for construction. More detailed forms of
project documents were not consistently
used until after World War II.1
Because document reproduction was
once a time-consuming and potentially
cost-prohibitive undertaking, only a few
copies of the original design documents
may have been developed. In many cases,
the original design documents may have
been misplaced or inadvertently destroyed,
and thus unavailable to the investigator. In
cases where the original design documents
are available, they may not be legible. In
many cases, none of the original construction
documents or records related to prior
repairs have survived changes in building
management and ownership.
Nonetheless, investigators should make
every effort to obtain pertinent project documents
and glean as much information from
them as possible. For most projects, however,
the investigator will need to document
existing and as-built conditions during a
field investigation.
Evaluation of Design Concept
Understanding the moisture management
scheme used for a wall is a critical
component of the investigation.
Misunderstanding of how the wall system
was intended to manage moisture can lead
to improper investigation techniques and
false conclusions.
Mass masonry walls were not designed
with explicit water-resistance performance
requirements in mind. Rather, these walls
were designed and constructed of sufficient
thickness and mass to allow the walls to
absorb and store water until it could evaporate
under favorable conditions.
Understanding the structural behavior
of the wall is also important. For load-bearing
walls, wall thicknesses were typically
governed using empirical methods. For nonload-
bearing walls, exterior wythes of brick
were typically designed to be supported on
shelf angles. Details for such systems must
provide for the interfacing and integration of
components so that each one can perform
individually and so that the components
can perform collectively as a system.
Determination of Service History
Prior to recommending a field investigation
protocol, an investigator should
perform a cursory visual evaluation of areas
with known leaks, interview building occupants
and maintenance personnel, and
review leak records. Patterns of the reported
leakage and visible damage will provide
hypotheses as to the causes. In some cases,
obtaining historic weather records near the
building can also be useful.
Except under the most severe conditions,
leaks through mass masonry wall
systems are unlikely to manifest immediately
after a rain event. Typically, leaks due
to precipitation manifest after long periods
of rain, once the walls have become saturated.
As such, leaks reported shortly after
rain commences should be treated with
1 4 • I n t e r f a c e F e b r u a r y 2 0 1 6
Photo 6 – Deterioration of interior gypsum-based plaster finishes.
caution. The investigator should consider
whether water infi ltration could be due to
some other mechanism or source (condensation,
change in interior relative humidity,
piping systems, etc.), or through some other
building component (fenestration, window
perimeter sealant, wall penetrations, roofi ng
system base fl ashing, etc.).
Buildings that exhibit water leakage
may have been previously repaired on one
or more occasions. Although well intended,
these previous repairs may be contributing
to the current leakage. It will be necessary
to distinguish between original construction
and attempted repairs during subsequent
phases of a systematic evaluation.
Visual Inspection
The major objectives of a visual inspection
program are to determine as-built conditions,
document apparent water damage and
potential water leakage paths, and formulate
hypotheses about the cause(s) of water leakage.
When a visual inspection of the entire
building façade is not practical due to access
limitations, inspected areas should include
both typical and unusual conditions and
properly performing and non-performing
wall sections. A suffi cient number of inspection
locations on the interior and exterior of
the building must be selected to accomplish
these objectives. Other components, such as
fenestrations and perimeter sealant around
windows and doors, should also be reviewed
during this stage.
Since project documents for mass
masonry buildings will often not be thorough
enough to provide the investigator
with adequate background information,
more inspection locations may be required
than are typically needed for newer buildings.
Information lacking in the design
documents must be generated from observations,
measurements, and exploratory
openings in the fi eld. However, such exterior
exploratory openings should not typically
be made until after investigative testing is
performed to allow the wall to be tested in
its current “as-found” condition.
Investigative Testing
The primary objectives of investigative
testing are to recreate leaks that are known
to occur, trace internal leak paths under
controlled and reproducible conditions, and
correlate test results with observed damage.
Regardless of wall type, best practices for
investigative testing include the following:
1. For diagnostic purposes, a wall
should be tested in its current
as-found condition.
2. Effective diagnostic testing should
result in the identifi cation of entry
points by isolating adjacent wall
components during testing. Where
there are windows or other penetrations
adjacent to the masonry being
tested, they must be masked such
that defi ciencies in adjacent components
or systems cannot contribute
to observed water penetration. Those
components should also be tested
separately by isolating them from
the adjacent masonry.
3. Testing of isolated areas should
begin at the bottom of the test area
and progress vertically to the top.
4. Once testing produces a leak, the
entry point and the path followed
by the water within and through the
wall must be traced.
5. Interior fi nishes must be removed
in the vicinity of the water testing
to readily observe water penetration.
However, in the case of interior
cement plaster fi nishes, the removal
should be limited to the interior
paint to facilitate observation of wetting
patterns. Complete removal of
the interior plaster can also yield
misleading results.
6. Testing conditions should replicate
those that resulted in leaks as closely
as possible.
While item numbers 1 through 5 above
can be readily accomplished during a testing
program, replicating the actual conditions
under which leakage occurs is not always
possible when testing mass masonry walls.
Additionally, there are no widely accepted
diagnostic test methods that have been
specifi cally developed for evaluating leakage
through mass masonry walls. Fortunately,
ASTM E2128 allows diagnostic test methods
to be adapted from existing test methods
and procedures to meet specifi c objectives
for a particular building. Based on our
experience, we have found the following test
methods appropriate for use when diagnosing
leaks through mass masonry walls.
1. Calibrated Spray Rack Testing.
Procedures similar to those for ASTM
E1105, Standard Test Method for Field
Determination of Water Penetration of
Installed Exterior Windows, Skylights,
Doors, and Curtain Walls by Uniform
or Cyclic Static Air Pressure Difference,
can be utilized. This test is performed
by wetting a wall area with a matrix
of uniformly spaced spray nozzles
that deposit a fi lm of water to the
wall’s exterior surface, typically at a
rate of 5 gallons per square foot per
hour (Photo 7).
f e b r u a r y 2 0 1 6 I n t e r f a c e • 1 7
Photo 7 – Calibrated spray rack testing performed on mass masonry wall with adjacent
window opening masked to isolate the masonry.
Although ASTM E1105 utilizes an air
pressure differential between the interior
and exterior, tests performed on
mass masonry walls are typically performed
without differential pressure.
Due to the many different air paths
through the walls, use of a localized
chamber to induce an air pressure
difference across the wall thickness
is typically impractical. If a nominal
air pressure differential is desired by
the investigator, use of a blower door
apparatus can be considered.
During the test, water flowing down
the face of a wall by gravity is capable
of causing leaks under some
circumstances, even without differential
pressure. We have found these
tests, which simulate surface flow
alone and without differential pressure,
are a useful first test. However,
unless differential pressure is
applied across the wall assembly,
the time for the leaks to manifest on
the interior of the building can be
much longer than the standard test
duration of 15 minutes.
2. Calibrated Spray Nozzle Testing.
Procedures similar to those
for the American Architectural
Manufacturers Association’s Quality
Assurance and Diagnostic
Leakage Field Check of Installed
Storefronts, Curtain Walls, and
Sloped Glazing Systems (AAMA
501.2) can be used. This test
is performed by spraying water
through a designated nozzle at a
pressure of 30 to 35 psi while holding
the nozzle approximately 1 foot
from the tested wall surface.
This test is suited only for small
areas suspected to be problematic
(penetrations, cracked masonry,
etc.). This test can also be performed
at interfaces with dissimilar materials
or systems, provided that the
masonry is isolated from adjacent
construction. However, the authors
discourage the use of this test method
for diagnosing leaks through the
field of the masonry walls, as it is
primarily intended for glazing systems.
During the test, the nozzle can
be moved slowly across the interface
between the mass masonry wall
surface and adjacent components,
moving from low to high areas. As
with calibrated spray nozzle testing,
the time for the leaks to manifest on
the interior of the building can be
substantial.
3. Chamber Testing. Chamber testing
(with differential pressure) can be
performed in general accordance with
ASTM C1601, Standard Test Method
for Field Determination of Water
Penetration of Masonry Wall Surfaces.
Typically, such tests are performed
using a chamber pressurized to 10
pounds per square foot (psf), and
a water flow rate of 3.4 gallons per
square foot per hour. The test methodology
includes provisions to modify
water flow rates and differential
pressure based on actual in-service
conditions that resulted in leaks.
While this test method was originally
developed to measure water penetration
through the exterior surface of
the wall, the method can be adapted
to mass masonry walls (Photo 8). In
addition to providing for a quantitative
measure of water penetration
through the exterior face of the
wall, this test method also replicates
wind-driven rain far more accurately
than the tests discussed above.
1 8 • I n t e r f a c e F e b r u a r y 2 0 1 6
Photo 8 – Chamber securely anchored to
masonry wall during an ASTM C1601 test.
Photo 9 – Extent of
saturation detected
on the interior of the
building using infrared
thermography during a
calibrated spray rack test.
The following tools can be used during
water testing to assist in interpretation of
the results:
1. Infrared thermography can be used
to monitor water penetration and
extent of saturation on interior wall
surfaces in the vicinity of water testing.
Surface evaporation at water
penetration sites or damp areas
results in lower surface temperatures
that can be detected using an
infrared imager (Photo 9).
2. High internal building pressures
commonly caused by the mechanical
systems or stack effect can make
it difficult to recreate leaks that
occur under wind-driven rain conditions.
As such, differential air pressure
measurements should be made
during water testing to evaluate contributions
of internal building pressure
to interior water leakage. These
differential pressure measurements
are made using a digital micromanometer
by extending a plastic tube
from the micromanometer to the
exterior of the building.
In many cases, fenestrations will need
to be tested as part of a comprehensive
testing program. There are several standard
test methods that can used for such
purposes. As an example, sill dam tests
can be performed in general accordance
with AAMA 511. Water testing can also be
performed in accordance with ASTM E1105
or AAMA 501.2. Similarly, test methods
may be utilized to evaluate the roof membrane,
base flashing, and/or roof drains if
reported leaks are located near the top of
the building.
Exploratory Openings
Exploratory openings involve the progressive
removal of wall materials to reveal
underlying, concealed conditions. Exploratory
openings are made to evaluate the extent, significance,
and cause of observed deterioration
and hidden deficiencies that may be allowing
water leakage into interior areas.
A masonry restoration contractor will
typically be required to provide access and
to make and temporarily repair exploratory
openings. In many cases, the existing original
masonry will be damaged and cannot be
reinstalled. As such, new masonry should
be procured prior to the start of the field
investigation. The building owner should
be forewarned that it may not be possible
to match the new masonry to the existing
masonry in size, color, and texture. As
an example, pre-1950 masonry walls were
typically constructed using nonmodular,
standard-size units (8 inches wide). Modern
brick is typically constructed in modular
sizes (75/8 inches wide).
It is imperative that the investigator
observe the exploratory opening as it progresses.
Sometimes, damage to brick headers
can result from the removal process.
Carefully watching the removal process will
help an experienced investigator to evaluate
what caused the damage.
Exploratory openings also provide for an
opportunity to observe potential water travel
paths (Photo 10). In solid masonry walls,
dirt deposits within the wall are typical
indications of prolonged water travel. When
examining fractures, dirt deposits within
the fracture plane also help the investigator
evaluate if the fracture is fresh (i.e., a result
of the removal process) or old.
F e b r u a r y 2 0 1 6 I n t e r f a c e • 1 9
Building
Envelope
Technology Symposium
2016
Material samples can be taken from
exploratory openings for subsequent laboratory
testing.
Laboratory Testing
There are numerous laboratory-testing
methods that can be used to evaluate the
quality of materials within a solid masonry
wall or to assess deterioration mechanisms.
A complete review of these test methods is
beyond the scope of this article.
Some of the most common tests employed
as part of investigating older masonry walls
are petrographic examination and chemical
testing of mortar materials. These tests provide
valuable information regarding mortar
constituents and proportions. Such information
is important when specifying repair
mortars for repointing or reconstruction of
the masonry.
Analysis and Report
A comprehensive diagnostic program
should result in an explanation for most, if
not all, aspects of the leaks and interior damage.
The investigator is expected to establish
a cause-and-effect relationship between wall
characteristics and observed leakage.
It is imperative that conclusions are made
based solely on the facts and that false conclusions
are not made. Unfortunately, for mass
masonry wall systems, it may not always
be possible to extrapolate fi eld investigation
fi ndings to the remainder of the building
without performing an all-encompassing and
likely cost-prohibitive fi eld investigation. Such
limitations and disclaimers must be clearly
enumerated. The report can also include
recommendations for additional investigation
and/or recommendations for repair.
SUMMARY
Evaluating water leakage issues in mass
masonry walls should start with an understanding
of their water management characteristics.
Due to limited or nonexistent documentation
of original construction, lack of
obviously clear leakage paths, and potentially
insuffi cient industry standards for
guidance, evaluation of mass masonry exterior
walls for water leakage can seem like a
daunting task. However, experienced investigators
can develop exterior wall evaluation
protocols specifi cally for mass masonry
walls by following the methodology outlined
in ASTM E2128. Results obtained from a
well-implemented program can then be
used as the basis for repair design.
REFERENCES
1. The Construction Specification
Institute (CSI) was formed in 1948,
in part to address the growing need
in the design and construction
industries for a standard approach
to project documentation.
2 0 • I n t e r f a c e f e b r u a r y 2 0 1 6
Kami Farahmandpour
is the principal
of Building
T e c h n o l o g y
Consultants, PC, a
forensic engineering
fi rm in Arlington
Heights, Illinois.
Farahmandpour
has been involved
in the evaluation,
testing, and repair
of construction
materials and
building envelope
performance since
1984. Kami is a Fellow of RCI, Inc., and a
Fellow of the National Academy of Forensic
Engineers. He has served as an expert on
several cases involving defects in construction,
design, and maintenance of building
envelope systems.
Kami Farahmandpour,
FRCI, REWC, RRC,
RTWC, RBEC, PE,
FNAFE, CCS, CCCA
Patrick Reicher
is a senior structural
engineer
with Building
Technology Consultants,
PC, a
forensic engineering
firm in
Arlington Heights,
Illinois. Reicher is
a licensed structural
engineer in
the State of Illinois
and has over 10
years of specialized experience in the evaluation
and repair design of many types
of buildings, from recently constructed to
historic structures. He is also a Registered
Exterior Wall Consultant (REWC), Certifi ed
Construction Specifi er (CCS), and Certifi ed
Construction Contract Administrator (CCCA).
Patrick Reicher,
REWC, SE, CCS, CCCA
Photo 10 – Staining on backup brick masonry indicates water travel path through wood
windowsill into masonry wall.