Skip to main content Skip to footer

Fenestration Replacement: Identifying Design Solutions for Existing Buildings

February 9, 2024

systems, often without any consideration of
engineering issues. However, current building
codes have added complexity to fenestration
unit replacement. For example, Chapter C503
of the 2021 International Energy Conservation
Code (IECC)1 mandates that all new building
elements used in renovations must comply with
the current code requirements. Local jurisdictions
may impose stricter requirements than the model
codes, further increasing the differences between
existing and new fenestration. Specific aspects of
building codes are discussed later in this article.
When planning the replacement of
fenestration units, designers and building
enclosure consultants should be aware of
how contemporary construction methods and
materials differ from the methods and materials
used originally. For example, 50 to 100 years
ago, mass masonry or transitional masonry
were prevalent structural systems. Transitional
masonry walls typically have less masonry with
the addition of steel, which limits the mass to
one or two wythes of masonry. Fenestration
in older buildings was typically fabricated off
site but glazed in place and windows were
often installed using exterior scaffolding. In
contrast, many newer buildings feature steel or
concrete framing with engineered backup wall
construction. If a brick masonry facade is used
in a new building, the facade is typically a cavity
wall. Windows in new buildings may be installed
from the interior with limited exterior access.
To specify a suitable, cost-effective
replacement system for a particular fenestration
replacement project, the designer must
determine whether design approaches for new
buildings can be directly applied to the existing
building or need to be modified to fit with the
building’s architecture, structural condition, or
aesthetics. Also, as noted previously, projectspecific
considerations, such as occupancy during
replacement, affect the ease of fenestration
Fenestration Replacement:
Identifying Design Solutions
for Existing Buildings
By Scott Bondi, PhD, PE, LEED AP;
Leonidia M. Garbis, PE, LEED Green
Associate; and Michael Colella
This paper was presented at the 2023 IIBEC
Building Enclosure Symposium.
Interface articles may cite trade, brand,
or product names to specify or describe
adequately materials, experimental
procedures, and/or equipment. In no
case does such identification imply
recommendation or endorsement by
the International Institute of Building
Enclosure Consultants (IIBEC).
unit installation. Thorough investigation of the
project conditions is therefore a critical step
toward success.
INVESTIGATION
CONSIDERATIONS
Identifying air drafts or water leaks within a
fenestration unit is crucial to pinpoint issues
with the fenestration or its interface with the
adjacent wall assembly. Field investigations can
be instrumental in determining the location
and severity of such leakage. The methods
used in such investigations can be classified as
noninvasive or invasive procedures (Fig. 1).
ASTM E7832 and ASTM E11053 present
noninvasive methods that can be used to
measure air and water leakage, respectively
(Fig. 1A), without disturbing existing conditions.
Techniques such as tracer fog (Fig. 1B) or
pressurization can identify the source of leakage
from either the fenestration unit itself or the
adjacent wall assembly.
Invasive field investigations offer detailed
insights into structural conditions surrounding
fenestration units. Invasive investigations can
also be essential to understand how the existing
building was constructed (Fig. 1C and 1D). Many
older buildings do not have the same level of
construction documentation that is expected of a
modern construction project.
Careful planning for invasive investigation,
especially in areas without drawings, is necessary.
WHEN FENESTRATION REACHES the end of
its service life, and after attempts to patch and
repair have been unsuccessful, replacement
becomes necessary. Common indicators
of failure include persistent air or water
leakage, inadequate reduction of solar loads,
condensation, occupant comfort complaints,
and compromised functionality of operable
units. Upgrading the units can enhance
aesthetics, reduce air and water leakage,
improve energy efficiency, and acoustics.
Fenestration replacement may also lower
building operation costs and upgrade expenses
for other systems like mechanical equipment.
Changes in interior programming are also
ideal opportunities for considering window
fenestration replacement.
Whatever the motivation for replacement,
designers and owners must be prepared
to tackle various challenges. These include
ensuring proper support of the new
fenestration within the existing wall assembly,
meeting building codes and structural design
requirements, and reconciling differences
between past and present construction
methods. The replacement design must also
account for project-specific factors such as
schedule limitations, the owner’s performance
criteria, and minimizing disruptions for
occupants during construction.
BUILDING CODE AND
STRUCTURAL CHALLENGES
Building owners have traditionally replaced
aging fenestration in kind with new off-the-shelf
Feature
14 • IIBEC Interface February 2024
Probed areas may contain hazardous materials,
and prior coordination of a safety plan before the
investigation begins is highly recommended.
DESIGN CONSIDERATIONS
Various design options exist for remediating
fenestration issues, with no universal solution
suitable for all buildings. Each option has
its own complexities and considerations,
warranting thorough evaluation to match project
requirements. Important variables for designers
to consider include the severity of problems, the
project budget, and the anticipated lifespan of
repairs or replacements.
Repairs and Modifications
Although this article focuses primarily on
fenestration replacement, it is important to note
that localized fenestration repairs are adequate
for minor or limited issues. For example,
deteriorated gaskets or failed sealant joints
between the fenestration and the surrounding
wall can be remedied with simple solutions such
as new sealant joints (Fig. 2A) or silicone sheet
patches (Fig. 2B). However, these types of repairs
cannot fully resolve broad performance concerns
such as insulating value or acoustic transmission.
They should typically be considered as shortterm
solutions, and ongoing maintenance may
be required. To effectively address air or water
leakage problems, any repair plan should be
supported by a field investigation to identify the
specific leakage path and maximize the chances
of resolving the issue.
In certain cases, modifying existing
fenestration can be a more practical option than
complete replacement. Storm windows, whether
installed externally or internally, may offer a
viable solution for underperforming windows
(Fig. 2C). They add an additional layer of glazing,
improving thermal and acoustic performance
without removing the existing system. This
approach is suitable for buildings where
removing the current system is inconvenient or
impractical due to aesthetic requirements or the
need to maintain occupancy during construction.
However, adding storm windows introduces
challenges that should be evaluated on a projectspecific
basis. The interstitial cavity created by
storm windows can lead to condensation and
increased maintenance costs due to additional
glass surfaces requiring access and cleaning.
Also, a storm window may not provide the same
thermal performance as a high-performing
replacement window, and proper integration of
the storm window system with the surrounding
wall system is crucial for achieving a balance of
thermal and waterproofing performance.
Understanding and addressing potential
leakage paths is highly recommended when
considering storm windows. Neglecting this step
may lead to unsatisfactory performance.
Replacement
Fenestration replacement provides an
opportunity to start with a new, warranted
system that can be properly integrated with the
surrounding wall system (Fig. 2D). Improvements
may include an effective air and water barrier,
reduced air leakage, and enhanced thermal and
acoustical performance. However, fenestration
replacement brings its own challenges, such as
the need to remove existing components and,
especially for older buildings, the presence of
Figure 1. Invasive and noninvasive investigative procedures. (A) Water testing; (B) Tracer fog air infiltration testing; (C) Invasive opening at
masonry; (D) Invasive opening at steel framing.
Figure 2. Design options for remediating fenestration issues. (A) New sealant joints; (B) Silicone
sheet patches; (C) Storm window installation; (D) Window replacement; (E) Overcladding with
curtainwall system.
February 2024 IIBEC Interface • 15
unforeseen conditions that must be addressed
during the project. Detailed project-specific
planning and coordination are necessary to attain
the desired performance outcomes.
Overcladding is an alternative to replacement
that is often used in older high-rise office
buildings with curtainwall systems (Fig. 2E).
It provides an opportunity to renovate the
building’s appearance while simultaneously
achieving performance improvements.
The overcladding process, which typically
necessitates a custom design approach,
involves placing a facade system outboard of
the existing facade system, possibly requiring
new anchorage back to the primary structure.
Vision areas, louver areas, and spandrel areas
can be incorporated into the design. This
approach is often used to minimize disruption
inside the building by using the existing facade
as a temporary weather barrier and means
of occupant protection during construction.
Existing attachments and framing members may
need to be worked around during the process.
The project team has an option to keep or remove
the existing facade in the final configuration
depending on how the system is designed.
Overcladding may appeal to owners because
it may allow for maintaining partial occupancy
inside the building during the work—a crucial
factor for the owner’s revenue.
Code Requirements
As noted earlier, the need to meet building
code requirements may be a considerable
challenge in fenestration replacement projects.
For example, to meet the IECC’s thermal
performance requirements, new fenestration
units may need to be thicker and heavier than
existing fenestration, and those differences can
have implications for the design of the support
systems. Similarly, windborne debris resistance
may be mandated by codes and insurance
companies. While thermal performance can
often be estimated by computation, windborne
debris requirements necessitate physical testing
rather than relying exclusively on analysis.
Code requirements can also influence various
components of the glazing system. For example,
triple glazing may be needed for energy code
compliance, or laminated glazing may be
specified for acoustic and/or windborne debris
performance. Additionally, evolving jurisdictional
requirements, such as those related to birdfriendly
glass, can restrict glass coating types,
locations, and fabricators. The product options
that meet specific requirements may be limited,
especially when physical tests are necessary, and
that limitation can affect installation techniques
and project costs.
System Integration into
the Existing Building
One of the greatest challenges with a
replacement fenestration system is how to best
integrate it into the existing building (Fig. 3).
Manufacturers’ instructions and performance
testing data are often available for fenestration
systems. However, that information will not be
specific to the particular project underway, so the
designer will need to produce project-specific
details to ensure the integration is effective.
A key design consideration is how to maintain
a continuous air and weather barrier along the
perimeter of the new fenestration unit. For
many older buildings that rely on mass masonry,
the existing masonry alone will not facilitate a
continuous weather barrier.
The drainage system of both the fenestration
unit and the adjacent wall assembly will dictate
how to best waterproof the interface between the
two systems. For example, if a new fenestration
system has an internal drainage system, it is
necessary to transition the waterproofing such
that the drainage system is not blocked and can
weep properly, while the rough opening in which
the drainage system sits is fully waterproofed.
The characteristics of the surrounding wall
system will considerably influence the placement
of the waterproofing tie-in. Mass masonry walls
may require full sill-pan flashing to catch any water
that may bypass outer seals of the window-to-wall
interface and drain that water to the exterior. In
other cases, the replacement fenestration system
is constructed of a stick-built curtainwall system
and the waterproofing of the veneer cavity is
directly tied into the glazing system.
Careful consideration is needed when
selecting materials for waterproofing integration,
with options, including sealant or sheet
membrane.4 In our opinion a membrane is
typically more reliable; however, implementation
requires thorough planning.
The interfaces between fenestration and
the surrounding wall may need additional
elements for proper integration. In traditional
window replacement projects, receptors can be
used to simplify interior installation. Receptors
are framing pieces that shrink the window
opening to facilitate installation. They can
accommodate prefabrication, interior installation
techniques, and construction tolerances.
However, depending on their configuration, the
use of receptors can complicate waterproofing
integration. In some cases, window receptors are
fastened into the sill of the rough opening, which
may complicate a sill-pan-flashing approach that
aims to avoid any piercings. Overcoming this
challenge requires careful planning and creative
detailing approaches.
Verifying performance is always important.
Drawings may not accurately reflect the actual
project challenges. It is highly recommended
that project teams conduct preliminary
preconstruction mockup installation and testing,
as well as quality assurance testing. These tests
should include air and water infiltration testing
according to AAMA 501.15 and 501.26 standards.
Preconstruction testing offers the advantage of
a “dry run” so that the entire team can address
challenges before the actual construction begins.
Coordination among all stakeholders is
paramount in a fenestration replacement project.
Figure 3. Considerations when interfacing a replacement fenestration system with an existing
building.
February 2024 IIBEC Interface • 17
The owner’s schedule, budget, and occupancyimpact
expectations will drive the design. The
structural engineer evaluates primary and
secondary structural members against the loads
imposed by fenestration system attachments
to the existing building. If the project includes
interior refitment, the mechanical engineer
assesses thermal performance requirements
such as air infiltration, U-factors, and solar heat
gain coefficients. The contractor implementing
the design will also have input on appropriate
installation methods and will inevitably discover
during demolition that some existing conditions
deviate from assumptions made during the
planning stage. Successful outcomes depend on
collaborative problem-solving by all team members.
CASE STUDIES
Senior Care Facility
Our first case study involves a senior care
facility housed in a 1970s building with vertical
modules of bay windows. The existing windows
and surrounding metal panels were steel framed
extending past the concrete building slabs.
The exterior also had a textured cast-in-place
concrete facade. The fenestration replacement
project aimed to improve performance. The
goal was to reuse the existing steel framing
whenever possible.
The senior care facility needed to ensure
occupant comfort and safety while remaining
fully operational during construction. The project
team’s understanding of the installation process
and its coordination with ownership and the
contractor enabled a phased installation strategy
(Fig. 4) to meet these requirements within an
efficient timeline. The design process became
iterative and collaborative, with the construction
team influencing changes to perimeter detailing
in certain areas.
The design team requested several invasive
openings at the beginning of the design process
to assess and verify the installed structural
conditions, which varied. These openings
facilitated calculations to determine the capacity
of the steel framing members. To accommodate
the inconsistent structural conditions of the
existing building, new structural elements were
added to create a uniform surface for window
framing and waterproofing attachment.
For the opaque spandrel conditions of the
building, the design solution involved installing
new insulated metal panels with a continuous
weather-resistive barrier over the existing
metal cladding. Use of swing-stage access
and this exterior installation method allowed
the building to remain fully occupied during
construction without the interior space being
disturbed.
Sheet-applied waterproofing membrane
was used to create a water-resistant transition
between the windows and the surrounding
cast-in-place concrete facades. Precise removal
of the textured concrete surface was necessary
to create a flat surface for proper application
and termination of the waterproofing
membrane.
Unforeseen conditions in existing buildings
often necessitate modifications to the project
details. The design team collaborated with
the contractor to create a guide for evaluating
each window bay during the demolition phase.
This guide helped identify and communicate
conditions requiring design modifications. It
included criteria such as maximum acceptable
steel framing section loss, shimming heights,
and minimum welding lengths. Preinstallation
mock-ups were instrumental in verifying the
viability of the drawn details and estimating
the window replacement timeline. Successful
project execution was facilitated by effective
communication among the architect, contractor,
and owner.
School Building
Our second case study is a 1950s school
building with hung windows placed between
expressed concrete fins. The spandrel areas
beneath each window feature a concrete and
brick masonry facade. After a thorough condition
assessment and field investigation, which
revealed multiple leaks and performance issues,
the owner decided to replace the windows
and rehabilitate the opaque exterior facades.
This project involved recladding the brick
and overcladding the concrete areas with an
exterior insulation and finish system. The main
challenge for the school was coordinating the
active construction schedule within the limited
time of a few months, aligned with the school
calendar recesses.
Integrating replacement windows and
spandrel cladding within existing concrete
fins posed a design challenge. The exposed
concrete fins relied on a barrier waterproofing
approach.4 To achieve the desired aesthetic,
transition waterproofing had to be attached
to the face of the concrete while remaining
concealed. The window support design used
an interior steel angle attachment to the
concrete fins, allowing for waterproofing from
the angle onto the concrete fin. Sheet-applied
waterproofing was installed at the window
jambs, concealed by the window frame, and
sealed to the concrete with dual-stage sealant
joints (Fig. 5). A metal sill-pan flashing system
with end dams was used at the windowsill,
and reglet-set into the concrete fins to drain
any water that penetrated the initial sealant
line. Between spandrel zones, new concrete
masonry units were designed to support the
new windows and brick exterior, while also
receiving face waterproofing. This approach
facilitated cavity wall construction for the
reclad facade. The window’s sill-pan flashing
accommodated the offset between the window
and the new brick masonry.
Figure 4. Phased installation of a fenestration system at a senior care facility.
February 2024 IIBEC Interface • 19
CONCLUSION
Fenestration replacement in existing
buildings is a complex task requiring careful
consideration and coordination. With an
in-depth understanding of existing conditions,
appropriate selection of replacement windows,
and meticulous planning and execution,
it is possible to significantly enhance the
performance of the building, while minimizing
disruption to the occupants and improving
their comfort. The lessons learned from the
projects described herein offer valuable insights
for future fenestration replacement projects,
contributing to the ongoing evolution of best
practices in the field.
REFERENCES
1. International Code Council (ICC). 2021. International
Energy Conservation Code. Country Club Hills, IL:
ICC.
2. ASTM International. 2018. Standard Test Method for
Field Measurement of Air Leakage through Installed
Exterior Windows and Doors. ASTM E783-02(2018).
West Conshohocken, PA: ASTM International.
3. ASTM International. 2023. Standard Test Method
for Field Determination of Water Penetration of
Installed Exterior Windows, Skylights, Doors,
and Curtain Walls, by Uniform or Cyclic Static Air
Pressure Difference. ASTM E1105-15 (2023). West
Conshohocken, PA: ASTM International.
4. Garbis, L. M., and C. C. Wowk. 2022. “Exploring the
Dos and Don’ts of Curtainwall Transitions.” IIBEC
Interface 40 (8): 20-27.
5. Fenestration and Glazing Industry Alliance (FGIA).
2017. Standard Test Method for Water Penetration of
Windows, Curtain Walls and Doors Using Dynamic
Pressure. AAMA 501.1-17. Schaumburg, IL: FGIA.
6. FGIA. 2015. Quality Assurance and Diagnostic Water
Leakage Field Check of Installed Storefronts, Curtain
Walls and Sloped Glazing Systems. AAMA 501.2-15.
Schaumburg, IL: FGIA.
ABOUT THE AUTHORS
Scott Bondi, PhD, PE,
LEED AP, is a principal
at Simpson Gumpertz
& Heger. He has
extensive experience
in building enclosure
design and specializes
in building science and
numerical analysis.
Bondi consults on both
new construction and
historic renovation
projects, from conceptual design through
construction administration, applying his
specific expertise in curtainwall and custom
glazing systems. In addition, he is experienced
in providing forensic engineering services
and expert witness support for both building
enclosure and mechanical systems. Bondi is
also an adjunct professor at Cooper Union,
where he has lectured and developed courses in
mechanical engineering since 2007.
Leonidia M. Garbis,
PE, LEED Green
Associate, is a senior
project manager
specializing in
building enclosures at
Simpson Gumpertz &
Heger. With 10 years
of experience, she
designs and evaluates
new and existing
building enclosures,
focusing on custom
curtainwall assemblies from design through
construction administration. Her portfolio
includes commercial, high-rise residential,
and infrastructure projects. She is also skilled
in enclosure forensic engineering, including
curtainwall and custom glazing system
investigations. Garbis has extensive knowledge
of facade, roofing, and waterproofing systems.
She actively participates in the Commercial Real
Estate Women Network and the Association of
Medical Facility Professionals, demonstrating
her commitment to professional engagement.
Michael Colella is a
project consultant at
Simpson Gumpertz
& Heger and has four
years of experience
in the Building
Technology Group. He
specializes in design
of new construction
projects from
conceptual design
through construction
administration. Colella uses advanced computer
simulation tools, including computational
fluid dynamics and finite element analysis, to
support his design work. He has experience with
several types of facade and roofing systems.
Figure 5. Perimeter waterproofing detailing. (1) Install perimeter waterproofing flashing
membrane; (2) Lap sill waterproofing flashing membrane onto cavity wall waterproofing
membrane; (3) Form sill pan flashing with fully soldered upturned end dams; (4) Lap jamb
waterproofing flashing membrane into sill pan flashing; (5) Install termination bar along the
edge of the wall waterproofing membrane.
SCOTT BONDI, PHD,
PE, LEED AP
LEONIDIA M. GARBIS, MICHAEL COLELLA
PE, LEED GREEN
ASSOCIATE
Please address reader comments to
chamaker@iibec.org, including
“Letter to Editor” in the subject line, or IIBEC, IIBEC Interface Journal,
434 Fayetteville St., Suite 2400, Raleigh, NC 27601.
February 2024 IIBEC Interface • 21