Skip to main content Skip to footer

Practical Considerations for Whole-Building Air-Leakage Testing

May 15, 2023

IIBEC Interface March 2023
Practical Considerations
for Whole-Building
Air-Leakage Testing
AS THE REQUIREMENT to complete whole building
air-leakage testing becomes more
prevalent through both building codes and
various voluntary energy standards, the
industry is now grappling with the complexity
of completing these tests, particularly in
buildings that are fully occupied. Many nations,
including Canada, have made commitments to
achieve net-zero emissions by 2050. In Canada
specifically, the focus has shifted from primarily
addressing the energy efficiency of new
buildings to also include expediting the rate
of deep energy retrofits completed on existing
buildings.1
While the inclusion of whole-building
air-leakage testing in these projects is not yet
mandated on a wide scale, it is one tool that
can help new buildings and retrofits alike
achieve the desired energy performance. This is
highlighted in the Illustrated Guide: Achieving
Airtight Buildings2 where an archetype case
study was modelled with varying levels of air
airtightness, both above and below a theoretical
target. In the cases where the airtightness target
was “missed” the estimated energy associated
with heating increased by as much as 70%. By
planning for whole-building airtightness testing,
the importance of the air barrier system will be
emphasized to the entire project team.
So how does one go about testing a large
building? Or an occupied building? There
are three main components that need to be
considered and communicated early in the
planning stage: environmental conditions, setup
requirements, and occupants.
ENVIRONMENTAL CONDITIONS
While the need to consider the environmental
conditions for testing is not something
exclusive to testing in occupied buildings, it
can be especially important when buildings
are occupied because any change in the date
or timing of the testing will require significant
additional effort and communication with the
occupants. Before testing takes place, you
must understand the requirements of the test
standard you are applying; some have very
specific limitations regarding environmental
conditions.
For example, ASTM E779-19, Standard
Test Method for Determining Air Leakage
Rate by Fan Pressurization,3 requires that
you measure and record the indoor and
outdoor temperatures at the beginning and
end of the test and average the values for
each to determine the interior and exterior
temperature to be used in any calculations.
Then the absolute value of the air temperature
differential (the difference between the
average interior and exterior temperature as
measured on site) is multiplied by the height
of the building. If the result is greater than
1180 ft•°F (200 m•°C), the pressure difference
induced by stack effect is too large and will
affect the accuracy of the test findings.
One way to address this problem on the day
of testing is to adjust the interior temperature
of the building to reduce the temperature
differential. Depending on the season, this
could mean using the HVAC systems or
introducing exterior air before beginning
the test to lower the temperature sufficiently
Feature
By Jennifer Hogan,
CET, RRO, REWC, CRE, LEED AP,
Certified Passive House Consultant
Interface articles m ay c ite t rade, b rand, o r
product names to specify or describe adequately
materials, experimental procedures, and/or
equipment. In no case does such identification
imply recommendation or endorsement by the
International Institute of Building Enclosure
Consultants (IIBEC).
www.iibec.org IIBEC Interface • 9
before shutting down the system and closing
or sealing all exterior openings.
Wind speed and direction should be
recorded during the testing. It is best to avoid
ASTM E779 testing on extremely windy days,
when possible, as the wind can impact the
ability of the blower door to achieve the desired
test pressures. However, ASTM E779-19 does
not provide a specific limit for wind speed. In
any case, the pressure taps should be located
at the base of leeward walls whenever possible;
it is important to avoid both inside and outside
corners as well as any other equipment or
adjacent structures that could affect pressure
readings. When a building is occupied, it is
also important to protect the pressure taps
(cordoning them off, if possible) to prevent
intentional or accidental tampering.
SETUP REQUIREMENTS
Before beginning to plan any individual test,
it is important to ensure that you have in place
an internal program or process to maintain
your equipment and supplies. Some of this is
straightforward, like ensuring that after each
test you replenish the consumable materials
used like batteries, tape, plastic sheets, or fog
fluid, while others (like full calibration of the
blower door equipment) require more significant
time and effort.
ASTM E1258, Standard Test Method for
Airflow Calibration of Fan Pressurization Devices,4
is one of the most commonly used standards for
blower door equipment calibration. Since the
calibration of blower fans requires a specially
manufactured test chamber, it is typically
performed by the manufacturer. The turnaround
time for these tests is typically a couple of weeks;
however, the total duration and cost of the
testing will somewhat depend on how far the
equipment needs to be shipped and whether it
needs to be shipped to another country.
The interval at which the fans need to be
tested varies depending on which standard
you reference (manufacturer recommendations
also vary), but most require calibration at
least once every two to four years, at any point
when you suspect the equipment has been
damaged, or when the equipment fails your
internal calibration checks. Most manufacturers
provide a process for performing these interim
checks within the product manuals. The process
typically includes checking the motor and fan
blade position and checking the flow sensor for
leaks, and it is recommended that you complete
an internal calibration check prior to each test.
When it comes time to look at preparing for a
specific project, it is important to plan the entire
setup to ensure that a sufficient amount of
the correct equipment to complete the testing
is available. Regardless of the test standard
used, planning starts with understanding
the number of blower door fans (Fig. 1) that
will be required to successfully pressurize
the space and determining where they will
be positioned within the building to best
distribute the pressure and combat stack effect.
Check with the blower door manufacturer
to verify the operating range for the
selected fan. For example, I know from the
manufacturer’s data that one of the fans I use
can provide accurate measurements from 300
to 6300 cfm (141 to 2973 L/s) with the flow
rings that were originally included at the time
of purchase. However, for our Passive House
and EnerPHit testing, we have also purchased
additional flow rings that can go as low as 11
cfm (5 L/s).
Figure 1. Technicians running a series of blower doors connected through a central hub.
10 • IIBEC Interface March 2023
We then use the building enclosure area
and the target air leakage rate to determine
the volumetric flow rate required. The
following are sample door calculations:
• Building enclosure surface area: 86,111 ft2
(8000 m2)
• Target air infiltration: 0.254 cfm/ft2 (1.27 L/sm2)
at 0.01 psi (75 Pa) of pressure.
• Total target leakage: 21,872 cfm (10,160 L/s )
• Total number of blower doors required: 3.42 at
peak airflow.
Knowing that we will require a minimum
of 3.4 blower doors to achieve the desired airleakage
rate gives us an excellent starting point
for our planning. We can now review the floor
plans, considering stack effect and building
geometry, and identify our ideal locations to
position the doors. In the real-life application
of this example, we ended up using only four
doors because the building was a large two-story
rectangle. More complex forms or buildings
with more floors would likely have necessitated
operating more doors at a lower fan rate.
If a tall building is to be tested, it is necessary
to monitor the interior pressure approximately
every few floors to ensure that the pressure
distribution is uniform. It is also best practice
to monitor the pressure drop across the
roof throughout testing to ensure that the
entire building remains either pressurized or
depressurized. Additionally, there must be
compensation for stack effect. The stack effect
can be mitigated by reducing the temperature
difference between the building’s interior
and exterior, as noted previously. However,
that is not always possible; for example, on an
extremely cold winter day reducing the interior
temperatures to near freezing could damage
interior finishes or cause pipes to freeze.
Generally, test pressures will need to be
shifted, so that they allow all test points to be
at negative pressure during a depressurization
test. For example, if the stack pressure at the top
of the building is 0.0029 psi (20 Pa), all the test
pressures should be below −0.0029 psi (−20
Pa) to ensure that even the top floor achieves
a negative pressure. At some buildings it will
not be possible to overcome the impact of stack
effect with fans (the pressures would be too high,
preventing the necessary number of readings from
being possible); in such cases, the building will
need to be split into multiple zones. For example, a
50-story building would likely need to be split into
at least two test areas of 25 floors each.
Beyond the technical requirements for
door positioning, there are also practical and
installation considerations that should be
factored into the planning. For example, you
will need to confirm that the door frame size
is compatible with the blower door frame. If
one of the locations selected is a double door
and your blower door assembly is only suitable
for a single door frame, it may be necessary to
construct a temporary frame to properly seal one
of the doors and provide an edge against which
to install the blower door frame. It is helpful to
identify this need early, and to request help from
a qualified contractor when necessary.
There is also a need to consider the
interconnectivity of the blower doors. While
there are wireless options available, it is not
Figure 2. Sample door and central hub layout.
Which workers find their jobs the most meaningful and the least stressful?
According to self-reported data, the answer is workers in the agriculture, logging,
and forestry sector.
Since 2010, the US Bureau of Labor Statistics’ American Time Use Survey has
asked workers to rate their happiness and stress at work and how meaningful
their work is on a scale from 0 (low) to 6 (high). Compared with workers in
other industries, workers in agriculture, logging, and forestry had the highest
self-reported level of happiness and the lowest-self-reported level of stress,
and they gave their work the highest rating in meaningfulness. Respondents in
the finance and insurance industries were the most stressed and least happy
of all participants, and they gave their work the lowest rating of any sector in
the meaningfulness category. Collectively, the data for all industries “paint a
simple picture,” wrote Andrew Van Dam. “A white collar appears to come with
significantly more stress than a blue one.”
Analysts hypothesize that relatively high degree of worker satisfaction in
agriculture, logging, and forestry may be linked to the locations where these
types of work occur. “We found that while your workplace looms as the single
most stressful place in the universe, the great outdoors ranks in the top three for
both happiness and meaning,” Van Dam said. “Researchers across the social and
medical sciences have found a strong link between mental health and green space
or being outdoors. Even seeing a tree out your window can help you.”
Source: washingtonpost.com Tridsanu Thopet/shutterstock.com
always practical or possible at an existing
building to connect all blower doors to a single
Wi-Fi network. Therefore, you may need to
rely on wired connections. Choosing your
door locations relative to the central hub and
ensuring that the cables are long enough is
critical. Figure 2 shows a sample blower door
and central hub plan. The wires should be taped
down, preferably along the outside edge of any
corridors, so that they are not tripping hazards
for occupants who move throughout the space
during testing.
There are a few other key pieces that
require planning, and these relate to the
interconnectivity of spaces and the sealing of
openings. Most standards for whole-building airleakage
testing will require that all interior spaces
are interconnected during the testing to ensure
uniformity of interior pressure distribution.
Typically, you must deploy a surprising number
of door stoppers to fulfill this requirement.
Confirming the number of interior doors in
advance of the testing ensures that there are
enough door stoppers on hand. A local hardware
store will only have so many, and you might even
garner a few funny looks at the checkout when
you clean out the entire shelf. The implications
of opening all doors are further discussed later in
this article.
OCCUPANTS
Most of the challenges in testing occupied spaces
come down to the doors and their dual function
of facilitating movement and providing security.
When the testing is in progress, the doors that are
meant to facilitate movement are blocked, and
those providing security must remain open.
When interior doors need to be open within
a building, it is often necessary to provide
additional security to set occupants at ease. In
residential buildings, where each unit entry
door into the corridors will remain open for the
duration of the testing, residents need to be
reassured that their space and their belongings
will be protected. Depending on the comfort
level of the occupants, you might need to station
a security guard on each floor to monitor the
activity in the corridors.
Meanwhile, the exterior doors (and windows)
need to remain in the closed position while the air
flow readings are recorded at each test pressure.
ASTM E779-19 requires a minimum of five
readings at intervals of 0.00072 to 0.0014 psi (5
to 10 Pa) (Fig. 3).
Looking for Meaningful Work?
Look Outside
Special interest
1083527_Editorial.indd 1 21/09/22 12:10 PM
12 • IIBEC Interface March 2023
www.iibec.org IIBEC Interface • 13
The day of the test will require cooperation
from 100% of the people within the building,
and the best way to ensure that is to build
buy-in by communicating the plan clearly and
concisely. For example, during the planning
stage for a high-rise residential project, we
understood that the building occupants,
primarily seniors, would not be able to go
without access in and out of the building for the
duration of the testing. All the team members
agreed that it would be necessary to provide
breaks between readings to allow residents to
exit or support personnel to enter the building.
This arrangement would increase the overall
duration of the testing but minimize the
inconvenience to the residents. To streamline
the process, the team selected a single door
to be identified as the testing access door,
and residents were informed that a stop-sign
system would be implemented: During the test
readings, the stop sign would be posted. Once
the reading was complete, the door manager
would be notified by walkie-talkie, and the door
would be open for approximately two to three
minutes to allow individuals to exit or enter. All
other exterior doors would need to remain fully
closed and would be monitored on a roving
basis.
In high-rise buildings, the elevator should be
treated in one of two ways. When the building
Figure 3a/3b. Building
leakage measurements
at 5 Pa increments as
collected using TECLOG
4 software. Note: 1 Pa
= 0.00014 psi; 1 cfm =
0.47 L/s.
is being tested as a single compartment, it is
beneficial to open the elevator doors to allow
the air to flow through all the floors more easily
and help pressurize everywhere equally. Guards
should be installed at each elevator door for the
full duration of the test, and use of the elevators
is not possible.
Alternatively, if the building is being split
into multiple zones, the elevator doors must
be sealed and the area of the elevator shaft
must be excluded from the test. To allow use
of the elevators between readings, they can be
sealed with a dust containment door that can be
opened and closed as needed without having to
reseal the elevator doors.