Skip to main content Skip to footer

Project Profile: EIFS Come and EIFS Go; A Case Study on EIFS Cladding Rehabilitation

February 8, 2017

Exterior insulation and finish
systems (EIFS) were cladding
systems that became very
popular in the United States
in the 1980s. They were initially
designed to be barrier
wall systems. However, significant failures
of barrier EIFS began occurring in the
1990s. These failures were primarily due
to water penetration through the EIFS to
moisture-sensitive substrate materials. As
a result, code officials around the country
began banning barrier EIFS wall assemblies,
or at least stiffening code requirements
for EIFS construction.
Most current EIFS wall assemblies
include a water-resistive barrier and drainage
plane between the insulation and the
exterior wall sheathing. The water-resistive
barrier prevents water that penetrates
through the EIFS from reaching moisturesensitive
substrates such as gypsum
sheathing and metal wall components that
can corrode. The drainage plane allows
penetrating water to drain out of the EIFS
wall assembly.
Fisher Corporate Center is a four-story
office building located in the Chicago suburb
of Elgin, Illinois. The building was primarily
clad in 6400 linear feet of prefabricated EIFS
panels and aluminum-framed strip windows
(Figure 1). The joints between EIFS panels
and around window perimeters were sealed
with an elastomeric sealant. Unfortunately
for the owners, the building was constructed
in 1992, before code requirements for
EIFS wall assemblies became more stringent.
Water leakage throughout the façade
began shortly after construction.
In 2009, a sealant replacement program
was initiated to address widespread water
leakage. While the program was somewhat
effective in reducing the leaks, the sealant
repairs did not address the underlying
deficiencies that caused the leaks. Leaks
continued where some repairs had been
performed, and new leaks developed where
no repairs had been performed.
1 6 • I n t e r f a c e J a n u a r y 2 0 1 7
Figure 1 – Overall view of Fisher Corporate Center.
During a façade evaluation in 2012, several
deficiencies in the EIFS cladding were identified as
potential contributors to the ongoing leakage. Such
deficiencies primarily included the following:
1. Failed primary and/or secondary sealant at
joints between EIFS panels (Figure 2)
2. Failed bond between EIFS finish coat and
base coat
3. Extension of EIFS base and finish coats
onto supporting steel stud and completely
through the thickness of the wall panels,
providing a direct path for water to reach
the interior of the building (Figure 3)
4. Lack of back-wrapping of the base coat
behind the EIFS panels
Follow-up water testing performed
in 2013 confirmed that deficiencies
in the strip windows were
also contributing to the leaks. Such
deficiencies primarily included the following:
1. Lack of cover plates over splice
joints between frame sections
at window heads and sills
(Figure 4)
2. Failure of retrofitted sealant at
splices due to thermal expansion
and contraction of the window
frame sections (Figure 5)
3. Failure of sealant at window
perimeters
4. Failure of sealant within glazing
pocket
J a n u a r y 2 0 1 7 I n t e r f a c e • 1 7
Figure 2 – Failed sealant between EIFS panels.
Figure 3 – EIFS base and finish coats
extended onto studs.
Figure 4 – Splice joint
with no cover plate.
The primary conclusion from the façade evaluation was that the
EIFS panels had surpassed their useful service life and that repairs
were necessary. A façade rehabilitation project was recommended that
included replacement of all EIFS panels and localized repairs of the
strip windows to address the deficiencies indicated above. Several
repair alternatives with order-of-magnitude cost estimates were
developed. Replacement options for the existing EIFS panels included
drainable EIFS, drainable stucco, or metal panels. The owner wanted a
leak-free, durable building that would maintain the company’s strong
image in the community and attract tenants to occupy the desirable
office space. Considering aesthetics, durability, anticipated future
maintenance, life cycle costs, and other factors, the owners selected a
three-coat stucco system as their most viable option.
Figure 5 – Failure of retrofitted
sealant at splices.
Figure 7 – Original EIFS cladding.
Figure 6 – Stucco system detail.
1 8 • I n t e r f a c e J a n u a r y 2 0 1 7
Figure 8 – Stucco system designed to
replicate original appearance.
The three-coat stucco system was
designed to appear nearly identical to the
existing EIFS system, but to incorporate
redundant resistance to water penetration
(Figure 6). The scope of work included complete
removal of the existing EIFS cladding
system and installation of new sheathing,
fully integrated water-resistive barrier, secondary
drainage cavity, insulation, drainage
composite, and three coats of Portland
cement stucco reinforced
with metal lath.
As is the case with any cement-based
material, controlling cracking is the biggest
challenge in stucco construction. Strict
limitations on panel sizes and aspect ratios
help minimize the possibility of cracking.
The existing EIFS panels
had horizontal reveals between colors
that could not be duplicated without compromising
the aspect ratio of the stucco
panels. The stucco system design included
an elastomeric textured finish coat, which
J a n u a r y 2 0 1 7 I n t e r f a c e • 1 9
Figure 9 – Window head flashing detail.
Figure 10 – Window
head flashing.
American Hydrotech, Inc.
303 East Ohio | Chicago, IL 60611 | 800.877.6125 | www.hydrotechusa.com
© 2016 Garden Roof is a registered trademark of American Hydrotech, Inc.
American Hydrotech introduces the Garden Roof® Planning
Guide mobile app, a first-of-its-kind digital brochure that
helps design professionals take a vegetated roof from initial
concept to completion.
Packed with photography, technical information and videos,
design professionals can explore assembly options and
components, growing media and vegetation, and learn
about topics such as design considerations, economic
and sustainable benefits, installation and maintenance,
and much more.
20 years of vegetated roof experience…
brought to life in one app.
Download your copy today at
hydrotechusa.com/GRPG
7.50W X 5H.indd 1 1/12/16 5:06 PM
was tinted to replicate the light and dark gray colors
of the original EIFS panels. An acrylic-based finish coating was then used to
replicate the red stripe accent bands (Figures 7 and 8).
Intricate flashing details were developed to redirect water that penetrates
the stucco system back to the exterior (Figures 9 and 10). The integration of
the new cladding system components made material selection a critical design
consideration. The stucco system manufacturer was
selected because of its capability to provide appropriate
water-resistive barrier (WRB) and fluid-applied flashing
materials, allowing the entire cladding system to be
captured under a single warranty. Using a single manufacturer
also helped minimize potential for compatibility
issues among various materials.
Prescriptive requirements for fastening metal lath
to light-gauge framing were based on the most common
stud spacing used in the industry (i.e., 12, 16, or 19.2
inches). However, the light-gauge steel studs at the
building were spaced at 24 inches. As such, detailed calculations
and fastener patterns were necessary to ensure
adequate resistance to wind loads, given the atypical
stud spacing. Additionally, the metal lath fasteners had
to span across 2 inches of insulation and the exterior
sheathing to anchor into the existing studs (Figures 11
2 0 • I n t e r f a c e J a n u a r y 2 0 1 7
Figure 12 – Metal lath fasteners spanning
across insulation and sheathing.
Figure 11 – Joint detail for metal lath fasteners
spanning across insulation and sheathing.
Figure 13 – WRB application around
signage support anchors.
Figure 14 – Reinstallation of signage
over finished stucco cladding.
and 12). As such, the anchors had to be designed to
withstand bending stresses in addition to shear and
pullout strength considerations.
The new stucco system was designed to be
thicker than the existing EIFS panels in order to
achieve redundant water resistance. Sheet metal
flashings were designed to minimize visual differences.
The increased thickness of the stucco
cladding system affected the interaction with adjacent
materials, as well. A proprietary coping cap
system was specified for installation over the new
wall assembly. Flashing details were developed for
wall penetrations such as overflow scuppers, light
fixtures, and security cameras that needed to be
reconfigured to accommodate the added thickness.
Signage support anchors and electrical
connection conduits needed to be replaced with
J a n u a r y 2 0 1 7 I n t e r f a c e • 2 1
ISSUE SUBJECT SUBMISSION DEADLINE
April 2017 Air and vapor control January 13, 2017
May/June 2017 Convention review February 15, 2017
July 2017 Testing April 14, 2017
August 2017 Health and safety May 15, 2017
September 2017 Building envelope (Misc.) June 15, 2017
October 2017 Coatings July 14, 2017
Publish in RCI Interface
RCI Interface journal is seeking submissions for the following issues. Optimum article size is
2000 to 3000 words, containing five to ten graphics. Articles may serve commercial interests but
should not promote specific products. Articles on subjects that do not fit any given theme may be
submitted at any time.
Submit articles or questions to Executive Editor Kristen Ammerman at 800-828-1902
or kammerman@rci-online.org.
Figure 15 – Strip window repair detail.
Figure 16 – Strip window repairs.
longer anchors and conduits to span across
the thicker stucco system. Location of the
anchors needed to be closely coordinated by
the various trades prior to installation of the
stucco system components so they could be
properly flashed with the fluid-applied WRB
(Figures 13 and 14).
Strip window repairs included repairing
internal seals and thermal breaks and
adding splice cover plates at head receptor
joints (Figures 15 and 16). Repairs to the
internal seals and thermal breaks required
temporary removal and reinstallation of
glass panels at frame splice locations where
leaks had been reported. The strip window
repairs were uniquely designed to be performed
independently. This gave the contractor
flexibility to complete the strip window
repairs before, during, or after installation
of the stucco system. Frame splices
were only repaired at known leak locations
during
this project.
As such, the
unique design
will allow for
future strip
window repairs
at
other locations,
if necessary,
without
affecting the stucco cladding system.
The first phase, which included the east
elevation only (approximately 10% of the
total façade area), was treated as a mock-up
phase where the contractor worked through
a learning curve in order to establish the
most efficient sequencing (Figures 17 and
18). The first phase was completed in three
months. The remainder of the building was
completed over a five-month period the following
year. Mast climbers were used for the
majority of the work. Although cumbersome
to set up, the general contractor ultimately
determined that the mast climbers provided
the most effective way to balance the various
trades and sequencing of work. Pipe
scaffolding was necessary at some locations
where mechanical equipment prevented
mast climber installation. Swing stages
were used to access two small areas at the
top of a glass atrium. Man lifts were used for
some of the strip window repairs
and to finish stucco panels where
mast climbers were attached to
the structure of the building. Strip
window repairs were performed
during off hours to minimize the
impact on building occupants.
The building remained open
during construction. As an office
building with significant pedestrian
traffic throughout the day,
overhead canopies were necessary
to protect building entrances and
walkways. Due to the size of the
building, the staging area was shifted
several times over the course of
the project to improve efficiency. In
each case, the staging areas were
fenced off to prevent pedestrian or
vehicular access.
2 2 • I n t e r f a c e J a n u a r y 2 0 1 7
Figure 17 – East elevation during construction.
Figure 19 – Metal lath installation several days after sheathing and insulation.
Figure 18 – Completed east elevation.
During construction, EIFS panels
were removed and new sheathing
was fastened directly to the existing
steel studs the same day. Metal lath,
which also needed to be fastened
directly to the steel studs, was typically
installed several days after the
sheathing fasteners had been covered
by the subsequent layers of the
stucco wall system (Figure 19). As
such, the detailed fastener patterns
previously discussed were critical to
ensure adequate resistance to wind
loads and to ensure proper staggering
for the “blind” installation of the
metal lath fasteners.
The fourth floor of the building
was not occupied and was unfinished
during the construction phase
of the façade rehabilitation project.
As such, fastener penetration into
the studs could be verified from the
interior on the fourth floor as a measure
of quality control. Metal lath
fasteners were also randomly tested
for pullout resistance using a calibrated
pull tester throughout the project to verify
their attachment to the steel studs (Figure
20). Fasteners had engaged the steel studs
at 100% of the tested locations.
As removal of the existing EIFS panels
progressed, some of the light-gauge
steel-framing members were found to be
severely corroded and needed to be reinforced
(Figure 21). A detail was developed
that allowed for a quick installation
of reinforcement at corroded framing members
to ensure openings could be closed the
same day and still provide a sufficient substrate
to which to fasten the stucco system
components.
The underlying conditions along a
building expansion joint were different than
anticipated. Alternate sheet metal closure
plate details were developed to properly
terminate the stucco wall system adjacent
to the expansion joints without restraining
movement.
J a n u a r y 2 0 1 7 I n t e r f a c e • 2 3
ENVIROSPEC INCORPORATED
The PAVE-EL®
Pedestal System
• Transforms flat roofs into attractive,
maintenance-free,
paver stone terraces.
• Elevates paver stones for
perfect drainage.
• Levels paver stones and ensures
their uniform spacing for
an ideal roof terrace surface.
• A perfect solution for laying
mechanical walkways for use
by maintenance personnel.
• Ideal for laying paver
walkways in roof gardens.
Turn roof tops into
beautiful deck areas
Easy to
Install
716-689-8548 • www.envirospecinc.com
Envirospec Ad 262-0801 1/21/08 9:03 AM Pa
Figure 21 – Corroded light-gauge steel-framing members.
Figure 20 – Fasteners tested for pullout resistance.
SUMMARY
Challenges in designing a cladding
system that would replicate the original
appearance include continuous insulation,
and incorporate redundant resistance to
water penetration made this a unique rehabilitation
project. Once construction began,
the general contractor was tasked with
balancing numerous trades to install integrated
parts of the stucco system, while
maintaining an aggressive construction
schedule. The project was a success in that
all the objectives were met. The project finished
on time and under budget, the owner
was pleased with the appearance, and, most
importantly, no leaks have been reported
since the work has been completed.
FOOTNOTES
1. A barrier wall system is defined as
any exterior wall system or assembly
that relies principally upon the
watertight integrity of the outermost
exterior wall surfaces and construction
joints to resist bulk rainwater
penetration and/or moisture ingress.
2. The EIFS finish coat extended into
joints between panels, which meant
sealant at those joints was only
adhered to the finish coat. The bond
between the finish coat and base
coat is not strong enough to accommodate
tensile stresses from thermal
contraction of the EIFS panels. As
such, joint sealants were effectively
pulling the finish coat off the base
coat, leaving these joints susceptible
to water infiltration.
3. This included calibrated spray nozzle
testing in general accordance
with AAMA 501.2 and calibrated
spray rack testing in general accordance
with ASTM E1105.
2 4 • I n t e r f a c e J a n u a r y 2 0 1 7
Christopher Kottra
is a senior engineer
at Building
Technology Consultants,
Inc. with
over 12 years of
experience as a
forensic engineer.
He is a licensed
professional engineer
in the state
of Illinois and a
Certified Construction
Contract Administrator. Kottra is
currently the president of the International
Concrete Repair Institute (ICRI) Chicago
Chapter. His project experience includes
façade and parking garage rehabilitation,
miscellaneous building envelope and structural
deficiency investigations, and reserve
studies.
Christopher Kottra
Josh Summers is
a principal structural
engineer at
Building Technology
Consultants,
Inc., a forensic
engineering
firm in Arlington
Heights, Illinois.
He is a Registered
Exterior Wall Consultant,
a licensed
structural engineer,
and a licensed professional engineer.
During his 23-year career, he has managed
over 450 structural repair and façade rehabilitation
projects. His experience includes
investigation of building façades and water
leakage issues, structural analysis and
design, condition assessments, nondestructive
testing, and failure investigation.
Josh Summers
A new Occupational Safety Health Administration (OSHA) rule that went into effect on December 1 does not
allow employers to “deter proper reporting” or retaliate against employees for reporting workplace injuries or illnesses.
This means that if a company has a policy in place that automatically mandates drug testing after every accident or injury, it
will now be in violation of the law.
In Texas, several employers have filed suit against the agency to reverse the regulation, claiming that the new rules are
unlawful because they would prohibit or limit the use of incident-based employer safety incentive programs and mandatory
post-accident drug testing programs currently in place. The plaintiffs say these programs exist to help employers promote
workplace safety. The action initially delayed the effective date of the provision’s implementation.
OSHA’s final rule states that employers’ procedures for reporting work-related injuries and illnesses must be “reasonable.”
Drug testing itself is not banned. “You may still use your discretion and drug test an employee after an incident. But if you do,
you must have a very good reason to believe that ‘employee drug use is likely to have contributed to the incident, and for which
the drug test can accurately identify impairment caused by drug use,’” according to an article by Optimum Safety Management.
— OSHA.gov and oshasafetymanagement.com
OSHA Rule Would
Curb Post-Accident
Drug Testing
© Can Stock Photo / cozyta