Skip to main content Skip to footer

Roof Drainage

May 15, 2021

in overflow drainage design theory.
Historically, most primary and
secondary roof drainage systems
were designed based upon the
1-hour duration, 100-year rainfall
rate. This 1-hour duration, 100-
year rainfall rate is the amount of
rain that is likely to fall in one
hour once every 100 years. However,
in 1991, the Standard Building
and Plumbing Code changed
the requirements for overflow
design. The 1991 Standard
Plumbing Code adopted the 15-
minute duration rainfall rate for
design overflow drainage systems,
which is the amount of rainfall
that can be expected to fall in 15
minutes once every 100 years. To
put it in perspective, the 15-
minute, 100-year rainfall rate is
approximately twice the 1-hour,
100-year rainfall rate.
1507.3 Maximum Rainfall
Rate for Secondary Drains.
Secondary (emergency) roof
drain systems or scuppers
shall be sized based on the
flow rate caused by the 100-
year, 15-minute precipitation
as indicated on Figure 1507.3.
The flow through the primary
system shall not be considered
when sizing the secondary
roof drain system.
The National Standard Plumbing
Code has also adopted this
criterion. The rationale for using
the 15-minute duration, 100-year
rainfall is based on the concept
that roof drains may become
blocked during extreme storms
like hailstorms and hurricanes.
The Standard Plumbing Code was
formerly the Southern Building
Code, which was adopted primarily
throughout the Southeast part
of the United States, including the
hurricane-prone Gulf and Atlantic
Coast states. Blowing debris during
hurricanes commonly block
roof drains, and hurricanes often
produce extraordinary rainfall.
The combination of blowing debris
and extraordinary rainfall can be
catastrophic for roof drainage systems.
The first International
Plumbing Code (1997) also adopted
this 15-minute, 100-year rainfall
rate, but reverted to using the
1-hour, 100-year rainfall rate for
overflow systems in 2000.
Also gone is the old Uniform
Building Code standard of using
Proceedings of the RCI 22nd International Convention Patterson – 129
overflow scuppers three times the
area of the roof drains. The Uniform
Building Code first provided
the overflow scupper option in the
1967 Edition, which follows:
(c) Overflow Drains and
Scuppers. Where roof drains
are required, overflow drains
having the same size as the
roof drains shall be installed
with the inlet flow line located
two inches (2″) above the low
point of the roof, or overflow
scuppers having three times
the size of the roof drains may
be installed in adjacent parapet
walls with the inlet flow
line located two inches (2″)
above the low point of the
adjacent roof and having a
minimum opening height of
four inches (4″).
Overflow drains shall be
connected to drain lines independent
from the roof drains.
There is a major flaw in this
drainage criterion. This criterion
does not take into account the
depth of water that develops at
the scupper based upon the
geometry of the scupper. The fundamental
function of the scupper
is to control the depth of water, so
as to limit the load on the roof
structure and prevent a collapse.
The geometry of a scupper is critical.
For example, a 6-inch
drain has an opening of
approximately 28 inches.
Using the old Uniform Building
Code’s standard of providing
an overflow scupper
three times the area of the
roof drain, the overflow
scupper size would be 84
square inches. The problem
with this standard was that
a designer could select an 8-
inch-wide by 10.5-inch-high
scupper and meet the code
requirements. However, the
head (depth) of water at the
scupper would have to be
8.4 inches to achieve the
flow rate required.
The net result would be a
depth of water of 10.4 inches
at the scupper, as the
overflow scupper is located
2 inches (10.4 + 2) above the
roof. This depth of water
could easily cause a collapse
in many circumstances.
Based upon the old
UBC, it was possible to collapse
a roof using overflow
scuppers three times the
area of the roof drains.
Roof drains are roughly
three times more efficient
than scuppers in terms of
flow. The 8-inch-wide by
10.5-inch-high scupper has
the flow capacity of almost
790 gallons per minute,
which is slightly more than
a 6-inch drain. Unfortunately,
the head of water required
to achieve that flow
through the scupper is 8.4
inches, while the head of
water required to achieve
approximately the same
flow is only about 3.6 inches.
In 1991, the Standard Plumbing
Code introduced a requirement
to determine the depth of
water that can accumulate on the
roof and to notify the structural
engineer to design the structure
based upon this depth of water,
assuming the primary drains are
blocked, which is today’s standard.
The excerpt from the 1991
Standard Plumbing Code (above)
shows the chart used to determine
the depth of water that can
accumulate at a scupper.
The 1991 Standard Plumbing
Code began requiring designers to
assume that the primary drains
are blocked and to calculate the
depth of water that could accumulate
over the secondary or
overflow drainage system. This is
the basis of the design requirements
provided in the initial
ASCE 7 in 1988 and the initial
International Building Code in
2000. This is the most logical
approach and simply reinforces
the concept that the structural
engineer should design the structure
to support the loads that
could be expected to occur on a
building.
ASCE/SEI 7-05 provides a
basis for calculating the head of
Patterson – 130 Proceedings of the RCI 22nd International Convention
water over drains and
scuppers. There are also
methods for calculating
the head of water over
scuppers and drains
provided in Roof Drainage.
There are methods
for determining the
head of water (depth) in
scuppers and over
drains. At the right is
the chart from data
included in ASCE/SEI 7-05.
The overflow drainage system
controls the depth of water that
can accumulate on a roof and is
the most critical part of the
drainage system. The roof structure
should be designed to support
all the loads anticipated on
the roof, and water build-up is
one of the most important sources
of loads on a roof. The requirement
for overflow systems goes
back to the beginning of the modern
national codes, and these
requirements have been refined
over the years. Today, the codes
are pretty simple and straightforward.
Calculate the depth of water
that can accumulate on the roof
assuming the primary drainage
system is blocked, and design the
structure to support those loads.
The structure must be evaluated
for ponding instability any time
the slope is less than 1/4:12.
These are basic concepts that
have been articulated in codes
and standards for years.
Location of Overflow
Drains and Scuppers
Overflow drains and scuppers
should be located above the low
point of the roof to help prevent
the overflow drains and scuppers
from becoming blocked. Debris is
carried by the flow of water on the
roof, which is to the low point. The
primary drains are located at the
low point, which is what makes
them susceptible to becoming
blocked by debris.
Placing the overflow drain or
scupper approximately 2 inches
above the low point of the roof
reduces the likelihood that debris
will flow into the overflow system
and become blocked. Additionally,
overflow drain outlets should be
located in a prominent location so
that maintenance personnel can
readily observe water flowing out
of the overflow. This is an indication
that the primary drains may
be blocked and maintenance
needs to be performed.
Sometimes it is difficult to
place overflow scuppers 2 inches
above the low point of the roof,
due to the location of the drains.
Today, there is no specific requirement
to locate the overflow
drain or scupper 2 inches above
the low point of the roof. The
requirement is to find out how
much water can accumulate above
the overflow system and
design the structure accordingly.
However, the overflow drain or
scupper should be located approximately
2 inches above the
low point to prevent debris from
blocking the overflow, but the
scupper can be located at a higher
elevation, provided the structure
is adequate to support the
load.
PRIMARY DRAINAGE DESIGN
General Requirements
The primary drainage system
is an important element in
drainage designs, but it is the
least important of the three elements
of drainage design. These
elements include the slope of the
roof and ponding instability, the
overflow drainage system, and the
primary drainage system. However,
it is important that roofs
drain freely, and the primary
drainage system is designed to
remove water efficiently. This
author has investigated roof
drainage systems that were
under-designed, resulting in
water depths deep enough to
cause leaks at low curbs and
expansion joints.
The primary drainage system
generally consists of either roof
drains or scupper drains. Most
roof drains today are manufactured
by companies like Josam,
Zurn, and J.R. Smith and have
standard flow rates, which are
reflected in the various plumbing
codes. These drains are designed
with sumps and strainers that
conform to the codes. Strainers
are important, as they block the
debris from getting into the drains’
lines. Also, strainers can actually
improve the flow into drains
by breaking up the vortex of the
water flowing into the drain.
Scupper drains, on the other
hand, are generally shop- or fieldfabricated,
and generally, flow
rates must be calculated. There
are no standard strainers
designed to promote water flow
and function with debris.
Scuppers also generally require a
greater depth of water to achieve
the designed flow, so the depth of
water at scuppers can be significant.
Scupper drains and overflow
drains should be separate and
should not be connected.
Proceedings of the RCI 22nd International Convention Patterson – 131
Drainage Rates for Roof Drains
The various plumbing codes
generally agree on the design criteria
in principle. However, there
are variations in the flow rates
between the rates provided in the
International Plumbing Code and
the other two national plumbing
codes – the National Standard
Plumbing Code and the Uniform
Plumbing Code. It should be
noted, however, that the flow rates
in the International Plumbing
Code are the same as the old
BOCA Plumbing Code, old Standard
Plumbing Code, and old
Uniform Plumbing Code (prior to
1997). Adjacent is a comparison
of the flow rates.
The National Standard and
Uniform Plumbing Codes (after
1994) are more conservative. All
these flow rates are based upon
Manning’s equations, but there
are slightly different assumptions
regarding the amount of open
area in the pipe, which results in
the differences in the charts. Roof
drain manufacturers also publish
drainage design literature, and
most of these manufacturers use
the same drainage design assumptions
as the International
Plumbing Code’s standards.
Drainage Rates for Scuppers
Scupper drains must be
designed, and there are also variations
in the formulas used for
calculating the flow through a
scupper. It is important to understand
that water has to build up
to a relatively high elevation in
order to achieve the design flow
rate through the scupper. The
depth of water that develops is
primarily an issue of the width of
the scupper. The wider the scupper,
the lower the head of water
that will develop at the scupper,
which is desirable even if the
structure is designed to support
the loads from a large head of water.
The flow rate of water through
scuppers is generally determined
by the derivation of an equation
known as the Francis Formula,
which is Q = 3.33LH1.5 where Q is
the flow rate, L is the length of the
weir (scupper), and H is the head
of water. Because experiments
have shown there is a contraction
in the water flowing through the
weir, the equation has been modified
to adjust for this reduction.
The modified form is Q = 3.33(L-
0.2H)H1.5. Below is a chart derived
from this equation.
The design of the primary
drainage system is relatively
straightforward. There are variations
in flow rates of drains and
scuppers, and further research
into these variables would be
helpful in establishing consistent
design guidelines.
DRAINAGE DESIGNS FOR ROOF
REPLACEMENTS
Requirements to Modify
Drainage for Reroofing
The 1967 Uniform Building
Code added Chapter 32 to the
appendix of the code, which was
titled Re-Roofing, and the first
section (3209) in that chapter
stated that all re-roofing had to
comply with Section 32 in the
Building Code. This was a significant
change in the code. However,
the most significant change
came in 1988 with the addition of
the statement that roof systems
shall be sloped a minimum 1/4-
Patterson – 132 Proceedings of the RCI 22nd International Convention
inch in 12 inches for drainage.
This requirement to provide a
minimum slope in Chapter 32 of
the 1988 UBC in combination
with the changes made to Chapter
32 in the appendix for Reroofing
had major implications for reroofing
design. Chapter 32 in the appendix
required a re-roof to conform
to Chapter 32 of the code,
which required the roof be sloped
a minimum 1/4 in 12 inches.
There was no reference to
draining within 48 hours or allowing
1/8-inch per 12 inches for
coal tar pitch. From a fundamental
design perspective, this was
the most appropriate code dealing
with roof drainage and roof slope.
A minimum slope of 1/4-inch in
12 inches has long been recognized
as the most appropriate
minimum slope for low-sloped
roofs. A minimum 1/4-inch per
12 inches is also important from a
structural design perspective, as
any roof with less than this slope
has to be designed for ponding
instability. Deflections in structural
elements with less than 1/4-
inch per 12-inch slope can result
in a progressive collapse due to
deflection. In other words, the roof
deflects, allowing more water to
accumulate until the roof collapses.
Clearly the authors of the
1988 UBC were addressing the
issues that cause roof collapses.
Below is Section 3210 from
Chapter 32 in the appendix to the
1988 UBC.
Inspections
Sec. 3210. New roof coverings
shall not be applied
without first obtaining an
inspection by the building official
and written approval from
the building official. A final
inspection and approval shall
be obtained from the building
official when the re-roofing is
complete. The pre-roofing
inspection shall pay particular
attention to evidence of accumulation
of water. Where
extensive ponding of water is
apparent, an analysis of the
roof structure for compliance
with Section 3207 shall be
made and corrective measures,
such as relocation of
roof drains or scuppers, resloping
of the roof, or structural
changes shall be made.
An inspection covering the
above-listed topics prepared
by a special inspector may be
accepted in lieu of the preinspection
by the building official.
These changes in 1988 were
met with less than an enthusiastic
response from elements of the
roofing community. In fact, this
change was a mind-altering event
for many in the roofing industry.
A great number of existing buildings
did not have a minimum 1/4-
inch per 12-inch slope. In some
cases, it was not only impractical
but it was virtually impossible to
provide the minimum slope. Then
there were the issues from the
coal tar pitch industry, where
1/4-inch per 12-inch slope could
be too much slope for the system.
The result of these issues and
others was a watering down of the
requirements.
Current Design Standards
Today’s International Building
Code is relatively ambiguous
regarding positive drainage. As
defined, “positive drainage” is
based upon ensuring drainage
within 48 hours of precipitation.
As previously stated, water standing
for 48 hours does not constitute
good drainage. What does “48
hours from precipitation” mean?
Does it mean 48 hours in summertime
conditions or wintertime
conditions? A properly sloped roof
should drain freely. Other than
anomalies in the roof created
around penetrations or crickets
and valleys, there should be no
water ponding after a rain.
Clearly, the code requires reroofs
to have positive drainage,
but since the definition is ambiguous,
enforcement is difficult.
Some building officials have ruled
that the design professional is
responsible for making the determination
of what constitutes positive
drainage, but often there is
no design professional in the case
of reroofing. Certainly, positive
drainage is a benefit in terms of
roofing longevity and performance,
and providing 1/4-inch
per 12-inch eliminates many
structural concerns. In those
cases where achieving 1/4-inch
per 12-inch is not practical, care
should be taken to help limit the
amount of water that can accumulate
on the roof and involving a
structural engineer should be
considered.
It is important to understand
that simply re-sloping a roof
with tapered insulation may
not be adequate. It is imperative
that the drainage system
function properly after the tapered
insulation is installed.
Often, increases in insulation
thickness can restrict drains
and overflow systems.
One of the most important
requirements for reroofing is to
make sure there is a proper overflow
system. This is a code requirement
that is often overlooked
by many in the roofing industry,
but the overflow system is critical
in terms of limiting the amount of
water that can accumulate on a
roof and in preventing roof collapses.
As a rule of thumb, some
try to limit the depth of water to a
maximum of 4 inches, which prevents
the load from water buildup
from exceeding the minimum
20-psf live load used throughout
much of the southern regions of
the country. It is also important to
understand that even though
there is a minimum 20-psf live
load requirements in the code,
there are live-load reductions that
are allowed by code, which can
reduce live loads on certain structural
elements to 16 psf and even
12 psf in some cases.
Proceedings of the RCI 22nd International Convention Patterson – 133
CASE HISTORIES
Drainage design problems
come in all types, from poor
drainage deteriorating a roof to
causing major roof collapses.
Most of the roof collapses investigated
by this author have involved
defects in drainage design, usually
in combination with other factors.
The build-up of rainwater is
nature’s way of load-testing structure,
and sometime structural design
or construction deficiencies
are identified. Realize that most
drainage systems are designed
based upon the 100-year rainfall
occurrences, so it may take a long
time before the structure really
gets tested by one of these rainstorms.
Below are some examples
of some of the collapses investigated
by this author.
• The first roof collapse investigated
was a simple
case of the contractor roofing
over the scuppers during
construction. Unfortunately,
that roof received
its first load test before the
contractor had time to cut
in and flash the scuppers.
• One of the first really large
losses involved a computer
assembly facility. A looselaid,
ballasted, single-ply
had been installed over an
existing built-up roof without
evaluating the structure.
The extra dead load
for the roof dramatically
reduced the live-load
capacity of the structure,
resulting in deflection
between the drains. This
structure failed as a result
of a progressive deflection
of the joists as the water
depth kept increasing between
the drains.
• One of the most expensive
collapses occurred in a
building that had no overflow
scuppers. Instead of a
conventional strainer,
screens were installed in
front of the drainage scuppers
to catch debris. The
screens worked efficiently
and soon became blocked
with debris. One eyewitness
reported water lapping
over the top of the 12-
inch parapet wall just
before the roof collapsed.
• Another large collapse in
volved the irregular spacing
of the roof drains and a
defective joist girder. There
were enough drains if the
drains had been spaced
evenly, but the end bays
were 50% larger than the
typical bays, resulting in
50% more water. Additionally,
there were no provisions
for overflow. The head
of water over the drain was
high enough to cause the
defective joist girder to fail.
• One of the most dramatic
collapses involved a concrete
structure. The roof
was designed to drain to
an outside wall through
drainage scuppers, but
the roof had deflected as a
result of long-term plastic
deformation. The roof
sagged in the middle,
resulting in ponding. The
roofer decided to install
drains in the center and
add slope from the outside
walls to the center of the
roof. The drains were too
small, and the drain lines
were not sloped, restricting
drainage. There were
no overflow scuppers or
drains, and the roof collapsed
during a heavy
rain.
• One collapse was actually
predicted by this author
after a routine roof inspection.
The core sample indicated
that there were multiple
roofs, one on top of
the other, weighing more –
than 20 psf. The recommendation
was to remove
the roofs immediately, as
the roof could collapse
during a heavy rain. The
roof was flat, and the addition
of all the roofs over
the years reduced the live
load capacity to zero.
Unfortunately, the owner
waited, and the roof collapsed
several months
after the inspection.
This sampling of collapses
illustrates some of the issues
related to collapses involving roof
drainage design. Lack of overflow
is a common problem, along with
inadequate drainage and too
much weight from the roof(s)
installed. Sometimes the weight of
the water simply finds the weak
link in the structure.
FINAL COMMENTS
The basic concepts of proper
roof drainage design have been
around for many years, and there
are extensive data and design
guides available. Roof Drainage,
published by the RCI Foundation,
provides a much more complete
discussion of roof drainage, and
every roof consultant should have
a copy in his or her library. There
are still issues that need clarification
and additional research is
needed, particularly in the area of
water accumulation on roofs and
the appropriate flow rates of
drains and scuppers.
The roof consultant can play
an important role in preventing
roof collapses. It is essential that
there is a properly functioning
overflow system on a building.
Checking roofs for an appropriate
overflow system and recommending
corrective action to add or
enlarge overflow drains and/or
scuppers should be a standard
part of the roof investigation
process. Further, improving the
drainage and the design and
installation of overflow systems
should be part of a reroofing project
where these systems are
inadequate.
Patterson – 134 Proceedings of the RCI 22nd International Convention