Skip to main content Skip to footer

Below-Grade Waterproofing in Urban Areas

May 23, 2017

3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7 B u cc e l l a t o a n d He n s h e l l • 1 7
Below-Grade Waterproofing
in Urban Areas
Paul Buccellato, RWC, REWC, AIA, FASTM
and
Justin Henshell, FAIA, FASTM
Henshell & Buccellato, Consulting Architects
595 Shrewsbury Ave., Ste. 207, Shrewsbury, NJ 07702
Phone: 732-530-4734 • Fax: 732-747-8099 • E-mail: paul.buccellato@verizon.net
Abstract
Building construction in urban areas with high water tables and/or mandated flood
plains presents design teams and contractors with unique logistical issues. Difficulties
can include site access, material delivery, construction of the structural framing system,
cladding, roofing, below-grade waterproofing, and governmental regulations. In an urban
environment, where buildings may be constructed with zero lot lines, the basement must be
formed by excavating and installing a soil retention system. When below-grade site conditions
include excavating through rock or a high water table, the cost of the work escalates
rapidly. The presenter will offer case studies of three buildings with basements located in
urban areas and how the support of excavation and waterproofing systems evolved.
Speaker
Paul Buccellato, RWC, REWC, AIA, FASTM – Henshell & Buccellato, Consulting Architects,
Shrewsbury, NJ
Paul Buccellato is a Fellow of the American Society for Testing and Materials (ASTM).
He serves as chairman of ASTM’s Subcommittee D08.20, Roofing Membrane Systems, and
is the past vice chairman of Subcommittee D08.22 on Waterproofing. Buccellato is also a
member Subcommittees C15 (Masonry Units) and C24 (Building Seals and Sealants). He
has authored a number of papers on waterproofing and roofing and four ASTM standards
on roofing. The speaker wrote a column on roof design for Roofing Specifier and is coauthor
of an NCARB monograph on built-up roofing.
1 8 • B u cc e l l a t o a n d He n s h e l l 3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7
Waterproofing failures can occur from
one or all of the following: design errors,
construction practices, or materials that
are defective or improperly selected by the
designer. Design errors can include the
selection of an inappropriate membrane.
The owner and general contractor can
also contribute to the failure of the waterproofing
system. The owner’s misguided
insistence on cost savings can extend to the
waterproofing system: “Out of sight is out
of mind.” When it comes time to cut costs,
value engineering has a tendency to focus
on the roof, exterior wall weatherproofing,
and the below-grade and plaza waterproofing.
And why not? No one sees these elements,
so why spend money on something
that is hidden from view? The funds from
these cost savings can be better spent on
other building elements.
Other factors can cause a waterproofing
failure. Building construction in urban
areas with high water tables and/or mandated
flood plains presents the designer and
contractor with unique logistical requirements
and restrictions, including those
imposed by state or municipal environmental
agencies.
In locations where space is unlimited,
basements can be formed by simply excavating
a hole in the soil and erecting foundation
walls. This luxury does not exist in
urban areas, where a building will often
be constructed with zero lot lines. In these
cases, installing a soil retention system is
mandatory. Excavating through rock or in
the presence of a high water table can cause
the cost of construction to escalate rapidly.
The following case studies illustrate
some of the problems that may be encountered
and how they affect the ultimate
design and construction process.
CASE STUDY 1: MUSEUM,
NEW YORK CITY
Background
In 2010, the board of trustees for a
prominent museum in New York City that
supports American art made a decision
to relocate from their current location
on the Upper East Side of Manhattan.
The new building would be located in the
Meatpacking District, which has been categorized
as one of New York’s most vibrant
neighborhoods. The building would be bordered
by the Highline to the east and the
Hudson River to the west.
The new building would be nine stories
high, with a two-level basement, and would
include 50,000 square feet of indoor galleries
and 13,000 square feet of rooftop exhibition
space. The basement would house the
electrical rooms, mechanical spaces, preexhibit
storage area, shipping and receiving,
and other ancillary support facility
areas (Figure 1).
The new building would be built on a
landfill created during New York City’s
explosive growth of 1836. As demand for
land grew, the city began selling water
lots along the shore, where daring entrepreneurs
could create their own plots.
Engineers would sometimes sink entire
ships to create a solid foundation for the
landfill. By 1900, the original footprint of
the island had expanded approximately
1000 feet into the Hudson and East Rivers.
Over time, these landfill areas became
the dumping ground for a host of materials
that rendered the land unsuitable for
construction. These included toxic waste
materials, abandoned fuel oil tanks, organic
materials, and construction debris with
limited load-bearing capacity. The water
table remained high, but was now contaminated
with aggressive chemicals, many
of which were harmful to both human
occupancy and below-grade waterproofing
materials.
Site Conditions
When the board of trustees decided to
relocate the museum to the proposed location,
they were unaware of the below-grade
issues they would need to address from
adjacent properties and the government
regulations that would dictate the design of
the below-grade waterproofing system.
The original below-grade structure was
designed as a cast-in-place concrete foundation.
The support-of-excavation (SOE)
Below-Grade Waterproofing
in Urban Areas
3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7 B u cc e l l a t o a n d He n s h e l l • 1 9
Figure 1 – Model of proposed museum.
was projected to be a piles and lagging. As
the project progressed, the general contractor/
construction manager (GC/CM) began
pricing the cost of the proposed changes to
the foundation design.
One change that the GC/CM proposed
to the owner was to utilize the SOE system
as the building foundation to maximize
cost savings. The system selected by the
GC/CM was a secant wall system (SWS). A
secant pile wall is formed by constructing
intersecting reinforced concrete piles. The
piles are reinforced with either steel rebar
or steel beams, and are constructed by
either drilling under mud or augering. The
cost savings for this change was reported to
be slightly over $1 million. Since the joints
between the alternating piles are not resistant
to water infiltration, the wall required
waterproofing.
As designers for the below-grade waterproofing
system, we presented two alternate
solutions if the SWS were to be utilized as a
foundation. These were:
Proposed System No. 1 (Figure 2)
• Securing wood blocking to the unreinforced
piles
• Installing plywood over the wood
blocking
• Applying a drainage composite panel
on the plywood substrate
• Adding a waterproofing membrane
• Laying reinforced shotcrete over the
membrane
Proposed System No. 2 (Figure 3)
• Placing a flowable fill over the
secant piles (the fill would be placed
between the secant piles and temporary
formwork)
• Installing a drainage
composite panel over
the fill
• Adding a waterproofing
membrane
• Casting a 6-in. reinforced
concrete wall
over the membrane
Each solution required the
pressure slab to be engaged
into the secant piles by raking
or notching out the bottom
of the piles to the face
of the steel beam (column).
The waterproofing below the
pressure slab would turn up
onto the piles approximately
6 in. (150 mm). A waterstop
and two injection tubes would
be installed between the face
of the piles and slab edge
(Figure 4).
During the design, the architect decided
to add a 1.5-ft. (457-mm) gravel base over
the pressure slab, which would then be covered
with a filter sheet and a 6-in. (150-mm)
reinforced concrete wearing slab. The space
between the concrete slab would be utilized
as a conduit for sanitary and storm piping
without the need to trench down below the
mud mat.
2 0 • B u cc e l l a t o a n d He n s h e l l 3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7
Figure 2 – Detail of proposed System No. 1.
Figure 4 – Slab termination at secant wall.
Figure 3 – Detail of proposed System No. 2.
Since the museum was being built
on landfill, and although the site did not
contain contaminates, adjacent sites did
contain varying levels of petroleum byproducts
and aggressive chemicals. The New
York City Department of Environmental
Protection (NYC DEP) ruled that there was
potential for these contaminated fluids to
infiltrate at the joints of the secant piles
and into the basement, where the fumes
could be harmful to human
occupancy. They directed the
owner to provide a system to
seal them off.
System Revision
Time was now of the essence,
since the secant pile wall or
support of excavation was being
installed on the southwest
and west sides of the property
(Figure 5), and a revised
foundation/waterproofing system
needed to be designed to
meet the NYC DEP directives,
which were to eliminate the passage
of chemicals through the
secant wall and into the building
interior. The design was to
construct a concrete foundation
on the basement pressure
slab where the secant wall was
constructed. The wall would be
located approximately 3 ft. (1.0
m) from the secant wall to allow
for installation of the waterproofing
membrane. Where the
SOE changed to piles and wood
lagging, blindside waterproofing would be
applied. The project was further complicated
by the use of walers and diagonal
bracing and cross lot bracing (Figure 6).
The walers and bracing would extend into
the basement walls in some locations that
required or necessitated extremely difficult
flashing.
Since the building was to be occupied
as a museum, a hydrophilic waterstop and
an injection hose waterstop were
specified in all horizontal and
vertical pour stops in the basement
construction to provide
added protection against future
leaks.
With a directive from the
NYC DEP and a revised foundation/
waterproofing design, the
project could move forward. A
pre-waterproofing meeting was
scheduled as was specified. The
only issue was the fact that
the GC/CM had already directed
the waterproofing trade contractor
to commence installing the
below-grade waterproofing. Not
only had the waterproofing commenced,
but also 65% of the
waterproofing had been installed
prior to the meeting. The project was now
deemed to be a renovation, since most of the
installed work was contrary to the contract
documents.
As the building was rising from grade,
Super Storm Sandy hit the Northeast.
The 20-ft.- (6-m-) deep basement flooded,
destroying the mechanical and electrical
systems and other services that had been
installed in the basement. The storm cre-
3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7 B u cc e l l a t o a n d He n s h e l l • 2 1
Figure 5 – Partial plan for support of excavation.
Figure 6 – Site conditions showing support of excavation, rakers, and cross bracing.
ated a whole other dimension
that would overlap
and require integration
of a flood-proofing system
with the waterproofing
system. Revisions to terminations
needed to be
addressed to fully transition
between flood proofing
and waterproofing.
As the project was
nearing completion, little
notice was given by the
construction team to discoloration
of the foundation
walls and floor slab
(Figures 7 and 8).
As the consultants to
the design architect and
executive architect, we were requested to investigate. After conducting a walkthrough
to observe the reported leaks and interviewing several persons from
the GC/CM, the following was ascertained:
• The hydrophilic waterstops were omitted at the pour stops and other
construction joints.
• The injection hose waterstop was also omitted.
The reason given for the omission: cost and time savings.
Conclusion
The project, although problematic during the design phase, was one in
which a watertight solution and installation were achievable. The lack of
reviewing contract documents and adhering to them was an issue that continued
throughout the project.
Some of the unilateral
decisions made by both the
GC/CM and trade contractor
during construction
may have resulted in cost
savings, but at the expense
of the watertight integrity
of the building.
The addition of flood
proofing did not contribute
to the waterproofing
failure, but enhanced
the watertightness of the
building at grade and
plaza levels.
CASE STUDY 2:
MEDICAL/HIGHER
EDUCATION FACILITY
Background
In May 2011, the
New York City Economic
Development Corporation
(NYCEDC), on behalf of the
New York City Department
2 2 • B u cc e l l a t o a n d He n s h e l l 3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7
Figure 9 – Aerial view of site.
Figure 8 – Water infiltration
at slab-to-wall joint
and at vertical crack.
Figure 7 – Water infiltration
at slab-to-wall joint
and at vertical crack.
of Sanitation (DSNY), issued a
request for proposals (RFP) to
redevelop the lot of land at East
73rd and East 74th Streets along
the FDR Drive. The RFP explicitly
required that the site be
redeveloped to create or expand
a health care, educational, or
scientific research facility.
The City University of NY
(CUNY) and a major and wellrespected
medical hospital/
research facility responded to
the RFP with a joint proposal
to develop two buildings that
would include an outpatient
cancer care facility for the medical
facility and a science and
health professions building for
the university.
In August 2012, Mayor
Michael Bloomberg announced
that the medical facility and
CUNY had been designated to
develop the site west of the East
River (Figure 9).
The successful team jointly
proposed to develop two separate but interconnected
buildings for a total of 1,150,000
sq. ft. (106,840 m2). The lot size is approximately
66,111 sq. ft. (6,141 m2).
Site Conditions
The site was originally used by the NYC
Department of Sanitation as a garage and
repair facility. The building size for the
medical/research facility would be approximately
747,000 sq. ft. (69,398 m2). The
university building would be approximately
403,000 sq. ft. (37,440 m2). Each building
would include a basement that would be
located 30 ft. below grade. The basement
for the medical facility would house the
garage, fuel tank room, stormwater tank
rooms, solid waste rooms, electrical feeder
rooms, and storage rooms. The university
basement would include an auditorium,
classrooms, and ancillary spaces.
The site is located south of a designated
masonry-clad historic building, north of
a 65-story residential building clad with
a curtainwall, and east of two three-story
masonry buildings constructed on a rubble
foundation and built circa-1940s.
The geotechnical report for the site
indicated a 6- to 7-ft.- (1.82- to 2.1-m-)
deep layer of mixed soil and gravel and
other debris. The remaining stratum was
bedrock. Removal of the mixed soil layer
would pose no issues. Excavating through
bedrock would present a challenge. Blasting
through the bedrock was not feasible, as
the city restricted its use to a small area in
the center of the site due to the location of
the historic building to the north and the
residential high-rise to the south. The only
way to remove the bedrock was to use an
excavator-mounted hydraulic jackhammer
(Figure 10).
The geotechnical report further indicated
an extremely high water table.
SOE/Foundation Systems
The upper portion of the site that contained
the mixed soil on the north, east,
and south sides would be supported with
steel piles and wood lagging. The lower
portion (bedrock) would be self-supporting
on the same sides. The west side of the site
against the existing circa-1940 buildings
would be an 8-in. concrete retaining wall
with the actual foundation pinned to the
8-in. retaining wall. The bedrock below the
mixed soil-gravel layer would function as its
own retaining system.
The slab-on-ground was designed as a
6-ft. (1.82-m) reinforced concrete pressure
slab to counter the buoyancy of the high
water table (Figure 11). The dewatering system
was to be maintained until the building
superstructure reached the 17th floor. This
would place sufficient downward forces to
counter the upward pressures due to the
high water table.
Designed Waterproofing System
The designed system would consist of:
• ¾-in. (19-mm) plywood over the
wood lagging (for boarding out)
• 1½-in.- (38-mm-) thick XPS insulation
• Drainage composite panel
• Waterproofing membrane
The identical components would be utilized,
with the exception of the plywood,
over the surface of the bedrock and at the
west 8-in. (200-mm) concrete wall.
The horizontal waterproofing would be
installed over a 3-in. (75-mm) unreinforced
concrete mud mat. A 4-in. (100-mm) concrete
protection slab would be placed over
the membrane.
The joint between the pressure slab
and foundation wall would include a hydrophilic
waterstop, as well as an injection
hose waterstop. Since the CUNY auditorium
would be located in the basement, injection
hose waterstops would be installed in all
pour stops, both vertical and horizontal.
3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7 B u cc e l l a t o a n d He n s h e l l • 2 3
Figure 10 – Site excavation.
The reinforced foundation wall was to be
secured to the bedrock with rock anchors.
The concrete specifications included a
crystalline additive to the concrete mix as
integral waterproofing.
System Revision
As the project progressed through bidding
and, as always, the value-engineering
phase, changes were presented for the
below-grade waterproofing to reduce cost
and expedite construction. One change,
although minor, was to remove the drainage
composite panel.
The other change was to eliminate the
insulation over the vertical rock surface
and install a 3-in.- (75-mm-) wide sand
wall. Over the sand wall, the insulation and
membrane would be installed.
What was not presented at the time
was the concrete trade contractor’s method
of supporting the reinforcing bar cage for
the concrete wall. The cage as it was being
constructed would be held in place with
horizontal steel dowels. The dowels would
be installed after the waterproofing membrane
was installed. Flashing the dowels
became extremely difficult since it would
need to be executed through the reinforcing
cage (Figure 12).
Waterstops and injection hose waterstops
were to remain as part of the original
design.
Conclusion
As the waterproofing membrane was
being installed, it became apparent that
issues would be forthcoming
regarding its ability to provide
a watertight system. Excavation
continued during the installation
of the waterproofing membrane.
The dowels to support
the reinforcing cage were becoming
difficult to make watertight.
Installation of the hydrophilic
waterstop became questionable.
These concerns became
fact when one of the dewatering
pumps failed. The result was
extensive leakage. Leaks were not
limited to the foundation wall,
but occurred through the 6-ft.
(1.82-meter) concrete pressure
slab.
A survey was performed that
indicated leaks were occurring at
pour stops, both vertical and horizontal
in the slab and walls, and
at penetrations through foundation
walls.
When the dewatering system
was back on-line, remediation of
the leaks commenced through
the use of urethane injection grouting. The
efficacy of the repairs will not be known
for at least two years, as the owner has
directed that the dewatering system remain
functioning until the building is completed.
2 4 • B u cc e l l a t o a n d He n s h e l l 3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7
Figure 11 – Six-foot-thick pressure slab at keyway.
Figure 12 – Unflashed rebar support of reinforcing cage.
CASE ST UDY 3: 135 E AST 79TH
STREET, N EW YORK, N Y
Background
In the early 2000s, a respected highend
developer purchased an older, outdated
building located on the north side of East
79th Street, between Park Avenue and
Lexington Avenue in New York City, with
the intention of a complete demolition and
construction of a new luxury condominium
building. The area was considered the oldmoney
Upper East Side, home of the Astors,
Rockefellers, and Roosevelts. The developer
understood that the neighborhood residents
wanted to maintain the area pretty much as
it was in terms of real estate, and knew a
glassy condominium building would not be
welcomed in the neighborhood.
The developer retained a known and
respected architect to design the new building.
What resulted was a 20-story reinforced
concrete structure clad with carved
stone, custom-manufactured hand-laid
brick, hand-cast ironwork, and customized
windows that created a façade that ranks
among the finest in New York (Figure 13).
Building amenities include landscaped
private gardens, a fitness center with a
private training studio, a residents’ lounge
with a separate catering kitchen, a family
club/game room overlooking the garden,
and private wine cellars.
Site Conditions
In 2009, the developer decided to move
forward with the plan for a new condominium
building. The site was located between
three existing buildings on the north, east,
and west sides, and is approximately 96
x 96 ft. (29 x 29 m). The existing building
was slated for demolition in the early part of
2011. The basement was designed to extend
north of the existing basement to accommodate
the fitness center, lounge, and game
room that were being located below-grade
and below the north garden/terrace area.
The geotechnical report for the site
indicated a stratum of bedrock. The use of
explosives to break through the bedrock
was rejected due to the location of adjacent
buildings. Excavation would be by hydraulic
hammers (Figure 14). The geotechnical
report also indicated a below-grade stream
(Figure 15).
During demolition, cost estimates for the
new building began to escalate. The developer
began to look for ways to decrease construction
costs. The architect and engineer
explored various options, including retaining
portions of the existing foundation.
The owner, after reviewing the various
cost-saving options, made a fatal decision
to retain portions of the foundation with the
intention of integrating the new and existing
foundation walls.
Designed Waterproofing System
The decision to
keep portions of
the existing foundation
walls in
place created difficult,
if not impossible,
waterproofing
solutions. This
was in addition to
the underpinning
required for the
existing buildings
on the east and
west sides of the site.
The waterproofing system would require
a hybrid design, incorporating both blindside
and a negative-side waterproofing on
the interior face of the existing foundation
3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7 B u cc e l l a t o a n d He n s h e l l • 2 5
Figure 13 – Elevation rendering of
building façade.
Figure 15 – Below-grade stream.
Figure 14 – Site excavation utilizing hydraulic hammers.
walls. Where new foundation walls occur,
the system would consist of (Figure 16):
• Foundations of the existing north,
east, and west buildings
• 1½ in.-(37 mm-) EPS insulation
• ¾ in.-(18.75 mm-) plywood
• Drainage composite panel
• Waterproofing membrane
• Reinforced concrete
The horizontal waterproofing would be
installed over a 3-in. unreinforced
mud mat (Figure 17). The membrane
would extend up vertically
where new foundation walls would
be cast. At existing foundation
walls, the membrane would terminate
approximately 8 in. and be
secured to the wall.
The surfaces of the existing
foundation walls would be scarified,
and two applications of crystalline
waterproofing would be made.
Hydrophilic waterstops were
specified to be installed between
the vertical face of the pressure
slab and the existing foundation
walls, as well as the vertical joint
between the new and existing walls
(Figure 18). The blindside waterproofing
for the new foundation
walls would also return onto the
vertical face of the existing walls.
System Revision
The developer wanted to further
control the construction cost and
looked towards the below-grade
waterproofing. The ageold
saying “out of sight is
out of mind” was beginning
to appear at project
design meetings.
The developer turned
his attention to the contractor
to seek recommendations
to reduce
the cost of waterproofing.
The waterproofing contractor
was more than
eager to give value-engineering
counsel to reduce
cost and further expedite
the construction schedule.
Some of these suggestions
included:
• Parging the
adjacent building foundation
walls and eliminating the EPS
insulation
• Eliminating the application of crystalline
waterproofing on the interior
face of the existing foundation walls
• Eliminating waterstops
With the basic decision to salvage portions
of the existing building foundation
and the revisions indicated above, the only
recourse was to wait until the dewatering
system was turned off. Once dewatering
ceased, leaks began to appear within six
months of the building’s completion as
reported by the developer’s representative.
Leaking started along the south foundation
and continued to the east foundation
wall. Leaking occurred predominately at
the joints between the new and existing
foundation walls. The interior of the walls
were cleaned, scarified, and coated with a
crystalline waterproofing, according to the
developer. This remediation appeared to
have stopped the leaks, until the spring of
2016.
One of the owners of a first-floor duplex
unit located on the west side had just
completed a $2,000,000-plus renovation.
Almost immediately after the renovation,
leaking appeared along the north side of
the west wall. Probes were made through
the interior walls to determine the exact
location of the water infiltration (Figure 19).
The building owner on the west side agreed
to allow access for the purpose of additional
investigation.
The developer, who was still responsible
for maintaining the building, rejected
our recommendation to utilize an injection
grout to remediate the leak because
of the higher cost. What they opted for
was to trench along the west foundation
2 6 • B u cc e l l a t o a n d He n s h e l l 3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7
Figure 16 – Plan view between existing and new
foundations.
Figure 17 – Waterproofing membrane applied over mud mat.
approximately 2-3 ft. below grade and to install a perforated pipe
surrounded by crushed gravel and a filter sheet. The pipe was
extended to discharge to a drained areaway. Presently, this solution
has relieved the water pressure along the foundation and
maintained a dry interior.
Conclusion
The owner’s initial decision to retain portions of the existing
foundation wall was a fatal flaw that continued with ill-advised
recommendations. The removal of the different components of the
waterproofing system (i.e., crystalline waterproofing, waterstops,
etc.) compounded the problems.
As leaks appeared, the designed system was slowly incorporated
and the leaking stopped, with the exception of the west leak.
The owner did not want to expend funds for any type of grouting
remediation because of logistics and cost. Their decision to install
a perforated pipe has provided relief, but the long-term effectiveness
of this solution is yet to be determined.
LESSONS LEARNED FROM EACH PROJECT
Like the five blind men encountering different parts of an elephant,
each of the participants in the process of planning, designing,
financing, constructing, and operating physical facilities has
a different perspective of any project. It behooves all participants
in the process to heed the interests of owners because,
in the end, it is the owners who provide the resources and
call the shots. Therefore:
• Right or wrong, the building owner is the final
decision-maker for any project, even when they are
uneducated about the decisions they may be making.
Owners tend to get their information from suppliers,
contractors and subcontractors, or associates that
may not have a full understanding of the building
design considerations.
• Inexperienced contractors, or even contractors who
have been in business for years, may be ignorant
about new technology or trends. Decisions that the
design professional has made regarding the waterproofing
system can be negated by the contractor,
even though the contractor may not fully understand
the basis of the design professional’s decisions.
• Value engineering should not exclude the design
professional. Value engineering should not include
the elimination or modification of elements that are
essential to successful performance of the material or
system selected and their required functions.
• Changes or revisions made to the building design
may equate to a reduction in immediate construction
cost, but can increase future maintenance or repair
costs.
The phrase “out of sight, out of mind” was originally translated
by a computer as “invisible idiot,” “blind and insane,” etc.
When decisions are made to reduce construction cost at the
expense of roofing, exterior wall weatherproofing, or belowgrade/
plaza waterproofing, the results can only lean towards
possible catastrophic failure. This is especially true of belowgrade
or plaza waterproofing.
3 2 n d RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 6 – 2 1 , 2 0 1 7 B u cc e l l a t o a n d He n s h e l l • 2 7
Figure 18 – Detail of waterstop locations.
Figure 19 – Water testing perforated pipe installation.