Skip to main content Skip to footer

Best Practices for the Design and Installation of Thermoplastic Roofing Systems – Part 3 of 4

June 6, 2023

IIBEC Interface May/June 2023
Best Practices for the
Design and Installation
of Thermoplastic
Roofing Systems
Part 3 of 4: Roof Pipe Penetration Flashing Details
Feature
Interface articles may cite trade, brand,
or product names to specify or describe
adequately materials, experimental
procedures, and/or equipment. In no
case does such identification imply
recommendation or endorsement by the
International Institute of Building Enclosure
Consultants (IIBEC).
By Gary Gilmore, RRO, REWO, CIT Level I
PROPER DETAILING OF roof penetrations
is a vital part of a every completed roofing
assembly. Any penetration through a low-slope
roof assembly could represent a potential
point for leaks or breaches during the life
cycle of the roof. Roof penetrations come in
a range of shapes, sizes, and materials, and
they may be in varying proximity to each other
and other types of penetrations. Whether the
project involves new construction or reroofing,
roofing system manufacturers and design
professionals develop very specific detailing
procedures for these penetrations to reduce
the risk of breaches. To ensure project success,
the roofing installation crew should be well
versed and trained in the roof manufacturer’s
recommended installation techniques and have
the competency to achieve the design details
provided by the project architects and building
enclosure consultants.
This article offers general guidance on
flashing requirements for various scenarios.
These scenarios involve individual penetrations,
clusters of penetrations, penetrations in close
proximity to other types of flashing conditions,
and the various methods to flash these
penetrations.
INDIVIDUAL ROOF
PENETRATION TYPES AND
PENETRATION CRITERIA
Pipe penetrations can be polyvinyl chloride
(PVC) pipes; stainless steel pipes; cast iron
pipes; acrylonitrile-butadiene-styrene (ABS)
drain, waste, and vent fittings; galvanized steel
collars; structural steel; copper condensation
lines at HVAC units; or rigid and flexible electrical
conduits. The typical size, spacing, height, and
flashing requirements for these penetrations are
described herein.
To be flashed with flashing membrane or a
premanufactured pipe boot individually, each
penetration must meet the following criteria:
• The penetration should be at least 1 in.
(25.4 mm) in diameter. Penetrations that are
smaller than 1 in. in diameter are best flashed
by other methods, which are discussed later
in the liquid-applied or penetration-clusters
sections of this article.
• The individual penetrations must extend
above the roof so that a minimum of
8 in. (203 mm) of flashing material can be
installed above the horizontal roof membrane
plane, as required by the roof manufacturer
specifications.
• The individual penetrations must be a
minimum of 12 in. (305 mm) apart from each
other and away from other flashings at walls or
curbs to accommodate the membrane flashing
minimum coverages.
• The temperature of the pipe must not exceed
150°F (66°C), as higher temperatures would
damage the membrane flashing. There are
methods to flash these “hot pipe” types of
penetrations with metal collars, as discussed
later in this article.
• The penetration must have a smooth,
continuous surface, such as flexible conduit
with a monolithic membrane skin, or be
a rigid penetration, such as metal, PVC,
stainless steel, or iron. If the penetration is
flexible, it must be secured above the roof
surface such that the penetration flashing
will not move or flex. An uncoated metal
or plastic conduit is not a suitable conduit
material to be used or flashed on a rooftop,
as this type of conduit can allow moisture to
enter and pass through the flashing and into
the building interior.
• Individual wires, such as electrical or
thermostat control wires, should be encased
in a rigid conduit to be flashed as an
individual roof penetration.
• Insulated pipes must not be flashed onto the
insulating material or insulation cover, even
if the cover is monolithic, such as a wrapped
insulated water line, gas line, or similar.
There is potential for condensation to form
on the exterior surface of the pipe, given the
optimum humidity and temperature occurs.
This condensation would be present between
the pipe surface and the interior surface
of the pipe insulation wrap. The insulation
wrap could rupture and leak, which could
introduce moisture into the assembly.
Insulated pipes must be flashed directly to
the pipe, with a break in the insulating cover
(removing a small piece of the insulation so
that the roof flashing can be installed directly
onto the pipe). They should never be flashed
to the insulation wrap or cover.
• Wood post penetrations and supports should
never be flashed into a roof system because of
the moisture intrusion potential.
May/June 2023 IIBEC Interface • 31
FLASHING METHODS
Flashing methods for pipe penetrations vary
in accordance with the specified length of
the roof manufacturer’s warranty, the roof
system assembly and attachment method, the
geographic location and climate zone of the site,
and the membrane type. The typical methods are
described here.
Prefabricated Flashing Boots
The following criteria are for the standard
installation of prefabricated flashing boots:
• The pipe/penetration should be round
and at least 1 in. (25.4 mm) in diameter.
Square, I-beam, or other irregularly shaped
penetrations should be flashed via other
methods, as discussed later.
• The pipe/penetration must also be open/
unattached to any structure or equipment at
the top, as the pipe boot must be pulled down
over the penetration.
• The penetration must be tall enough
to accommodate the full height of the pipe
boot without distorting the boot (8 in.
[203 mm] minimum). Typically, this
requirement means that a structural support
post cannot be flashed with a pipe boot as
the post is normally welded or bolted to some
type of assembly that it is supporting.
• The premanufactured pipe boot cannot be
cut vertically to allow it to wrap around the
penetration.
• The penetration must be at least 12 in.
(305 mm) away from other penetrations.
The deck flange of the pipe boot must rest
fully on one plane or roofing membrane and
should not overlap another pipe boot flange.
Butyl mastic is placed between the top edge
of the pipe boot and penetration surface; a
stainless-steel hose clamp is installed over
the top edge of the pipe boot; and, when the
clamp is tightened, the clamp pressure forms
a watertight seal between the flashing and
penetration with the butyl mastic.
• Most roof manufacturers will require that
any exposed butyl mastic that remains on
the pipe surface above the top of the pipe
be removed. A bead of elastomeric sealant is
installed between the top of the pipe boot and
the pipe surface to protect the butyl mastic
from exposure to sunlight, heat, and humidity.
Sunlight, heat, and humidity will degrade the
butyl mastic. Rain hood collars are optional.
Figure 1 illustrates a standard detail for a
prefabricated pipe boot penetration. Figure 2
shows an example of incorrect installation.
Field-Wrapped Pipe Flashing
The following are criteria for the standard
installation of a field-wrapped pipe flashing:
• Penetration can be round, rectangular,
or irregularly shaped. Irregularly shaped
penetrations should not be flashed with
prefabricated flashings; rather, liquid-applied
flashings should be used.
• If the penetration is round, it should be
1 in. (25.4 mm) in diameter or larger. Field
wrapping of small-diameter pipes is very
difficult and should only be attempted by
veteran hand-welding technicians.
• Field-wrap flashing is a multistep process
with very particular flashing overlap coverage
tolerances, which make this option very labor
intensive.
Figure 1. Standard prefabricated pipe boot penetration flashing detail.
32 • IIBEC Interface May/June 2023
Figure 2. Example of an incorrectly installed prefabricated pipe boot penetration. The wrong
sealant was used at the exposed surface against the pipe, and T patches are missing where the
pipe boot flange crosses field seams.
Figure 3. Standard field-fabricated pipe flashing detail for a mechanically attached roof system. The fasteners
and seam plates are not required for adhered roof systems.
• A stainless-steel hose clamp is installed
over the top edge of the pipe boot over
round penetrations, and when the clamp
is tightened, the clamp pressure forms a
watertight seal between the flashing and the
penetration. A stainless steel clamping band
will not provide consistent compression on
square or irregularly shaped penetrations.
• Most roof manufacturers will require that
a bead of elastomeric sealant is installed
between the top of the pipe boot and the pipe
surface to complete the detail.
Figure 3 presents a standard detail for
field-fabricated pipe flashing for a mechanically
attached roof system. Figure 4 shows an
example of incorrect installation.
Liquid-Applied Flashing
The following are criteria for standard installation
of liquid-applied flashing:
• The penetration can be any shape, size, and
diameter. It may be composed of any material
except wood or any other porous material.
May/June 2023 IIBEC Interface • 33
• The surface of the penetration must be
cleaned and abraded using sandpaper or a
stiff-bristle wire brush. Abrading the surface
helps ensure that the liquid-applied flashing
achieves a solid “bite” onto the surface of the
penetration.
• The liquid-applied flashing is installed
in three layers: a base coat followed by a
reinforcement scrim to be embedded into
the base coat, followed by the top coat.
Please refer to the specific roof manufacturer
specifications for their installation techniques
and for drying or curing times between
application steps.
The process described here has been
simplified. The complete process includes other
steps, such as using masking tape to establish
the perimeter edges of the flashings onto the
roof surface, precutting the reinforcement scrim
to fit onto the penetration, and so on.
Figures 5 and 6 illustrate the installation of
liquid-applied flashing.
Penetration Clusters and
Sealant-Pocket Flashing
The following are criteria for the standard
installation of penetration clusters or sealantpocket
flashings:
• All penetrations should be rigid or affixed to
a structurally stable or secured element to
prevent movement, which could crack or cause
voids in the pourable sealant.
• All penetrations should be spaced at least
1 in. (25.4 mm) apart and have 1 in. of
clearance from the sides of the sealant pocket
pan walls. This requirement ensures that the
pourable sealant is able to fully encapsulate
and seal the individual penetrations and
properly adhere and seal the sealant pan.
• The pan must be at least 2 in. (50.8 mm)
deep because manufacturers require a
minimum depth of pourable sealant of
2 in. (50.8 mm) The pan may need to be
deeper to accommodate various penetration
connection points or other items. The bottom
portion of these deeper pans can be filled
with polyisocyanurate insulation, lightweight
concrete, or similar products to avoid more
than a 2-in. (50.8 mm) depth of pourable
sealer.
• All penetrations and the interior surface of
the metal pan must be cleaned and primed
with the manufacturer’s approved primer.
This priming will ensure that the pourable
sealer bonds with all surfaces.
• The pourable sealant must “crown” in the
center of the pan so as to provide positive
slope to prevent water from accumulating or
ponding on top of the sealant.
• All two-part pourable sealer products must
be properly mixed to ensure that they cure
properly after installation. Several one-part
pourable sealant products are shipped in
premixed packaging by the manufacturer
and do not require thorough mixing in the
field before installation.
Figure 7 illustrates a standard detail for
sealant pocket flashing. Figure 8 illustrates an
example of incorrect installation.
Hot-Pipe Flashing
As previously mentioned, any penetration that
will exceed 150°F (66°C) in surface temperature
cannot be flashed directly with thermoplastic
membrane because the heat will degrade the
flashing. The hot-pipe flashing options are
limited as follows:
• There must be a separation or metal collar
that is sized larger that the hot penetration.
The space between the collar and the hot pipe
must be sized such that the temperature of the
collar will stay below 180°F (82°C).
• If the diameter of the collar is less than
12 in. (305 mm), the hot collar can be installed
over the membrane and flashed in a method
similar to that for the field-wrapped pipe
condition (described previously).
• If the diameter of the collar is more than
12 in., the hot-collar deck flange must be
supported by wood blocking that is secured to
the structural deck. The hot collar is installed
over the roof membrane, which is installed
over the wood blocking. The metal flange is
secured into the wood blocking with approved
fasteners installed at the prescribed rate for
the assembly.
• The hot collar is then flashed in a manner
similar to that for the field-wrapped pipe
condition (described previously).
Figure 4. Example of incorrectly installed field-fabricated pipe flashing. The flashing is too high,
and butyl mastic is exposed on top of the pipe. Wrinkles are evident in the 1-in. (25.4 mm)
horizontal flange of the vertical flashing wrap.
Figure 5. Application of standard liquid-applied flashing on an I-beam.
Top of flashing and clamping band
are too close to the top of the pipe.
There is no room for the sealant bead
& butyl sealant is exposed.
Wrinkles are evident in
the 1″ horizontal base
wrap seam.
34 • IIBEC Interface May/June 2023
Figure 6. Standard detail for the installation of liquid-applied flashing on an I-beam.
Figure 7. Standard sealant-pocket flashing detail.
May/June 2023 IIBEC Interface • 35
• The hot-collar flange can also be installed onto
the structural deck with the roof insulation,
roof membrane, and flashings installed as
shown in Fig. 9.
Expansion-Joint Flashings
This section focuses on expansion-joint details
recommended by roofing material manufacturers.
Many of the manufacturer-approved methods
for incorporating their specific flashing materials
in expansion-joint flashing assemblies are
included in their roof system labor and material
warranties. There are also many different models
and manufacturers of aftermarket expansion-joint
assemblies. Most of these would not be covered
by the roof manufacturer’s warranty and are not
discussed here.
Roof-to-Roof Expansion Joints
Roof level-to-roof level expansion joints
are among the most common types of roof
expansion joints (see Fig. 10). Considerations
and requirements for this detail are as follows:
• The roofing membrane must be secured to
the structure or to wood blocking that is
secured to the structure on both sides of the
expansion joint.
• A vapor barrier or reinforced sheet good
product that will support compressible or
loose-fill insulation must be attached to the
substrate. This insulation should be installed
within the expansion-joint void in order to
mitigate thermal loss and condensation issues
at the expansion joint.
• The sheet good product and insulation must
also support the foam backer rod. The backer
rod diameter should be 1.5 times the width
of the expansion joint so that it will not fall
through the joint opening. The backer rod
provides support for the roof membrane
should any movement occur at the expansion
joint. Closed-cell backer rod is recommended.
• The expansion-joint cover flashing must be
wide enough to provide a hot-air weld that is
at least 2 in. (50.8 mm) wide on either side of
the membrane-securement fastening plates.
• If the expansion joint is longer than
standard length of flashing membrane, it is
Figure 8. Example of incorrectly installed sealant-pocket flashing. The sealant in the pan is not
crowned, and the contractor did not prime the thermoplastic olefin membrane flashing or the
pipe before installing the pourable sealer.
Pipe does not appear
to have been primed
prior to installing the
pourable sealer.
Sealant is not
crowned to prevent
ponding water.
1102965_Editorial.indd 1 12/04/23 1:57 AM
36 • IIBEC Interface May/June 2023
Figure 9. Standard hot-pipe collar flashing detail.
Figure 10. Standard roof-to-roof expansion-joint flashing.
BACKER ROD OR
COMPRESSIBLE TUBE (BY OTHERS) (SEE NOTE #3)
NOTE:
1. REFER TO WEBSITE FOR MOST CURRENT
INFORMATION
2. FOR WELD WIDTH 2″ MIN IS REQUIRED
3. COMPRESSIBLE TUBE (SUPPLIED BY OTHERS) DIAMETER
MUST EXCEED THE DECK OPENING BY 50% MIN. OR
DESIGNATED MOVEMENT (WHICH EVER IS GREATER)
4. MAXIMUM 10″ (254 mm) LONG FASTENERS. (NOTE: WOOD
BLOCKING MAY BE SUBSTITUTED FOR INSULATION TO
REDUCE FASTENER LENGTH REQUIREMENTS.
5. WHEN REINFORCMENT OF TPO MEMBRANE IS EXPOSED
INSTALL CUT EDGE SEALANT
COMPRESSIBLE INSULATION WITH INSULATION RETAINER
AND FASTENER AS REQUIRED (SUPPLIED BY OTHERS)
2″ METAL OR HD SEAM PLATE AND FASTENER
@ 12″ (305MM) O.C. MAX. (SEE NOTE #4)
WELDED SPLICE
(SEE NOTE #2)
TPO MEMBRANE
TPO
INSULATION
SUBSTRATE
INSULATION
SUBSTRATE
May/June 2023 IIBEC Interface • 37
recommended to align the flashing pieces and
complete the hot-air weld between the lengths
of the flashing on a flat, fire-resistant surface
before the cover flashing is installed over the
expansion joint. Workers should not attempt
to hot-air weld adjoining flashing sheets over
the foam rod, as the hot-air-welding process
can melt the foam backer rod, and the foam
backer rod does not provide a suitably firm
substrate for hot-air welding.
Curb-to-Curb Expansion Joints
The curb-to-curb expansion joint is another
common type of roof expansion joint (Fig. 11).
The considerations and requirements for this
detail are as follows:
• The roofing membrane must be secured
to the structure or to wood blocking that is
secured to the structure on both sides of the
expansion-joint curb.
• A vapor barrier or reinforced sheet good
product that will support compressible or
loose-fill insulation must be attached to the
substrate. This insulation should be installed
within the expansion-joint void to mitigate
thermal loss and condensation issues at the
expansion joint.
• The sheet good product and insulation must
also support the foam backer rod. The backer
rod diameter should be 1.5 times the width
of the expansion joint so that it will not fall
through the joint opening. The backer rod
provides support for the roof membrane
should any movement occur at the expansion
joint. Closed-cell backer rod is recommended.
• The expansion-joint cover flashing must be
wide enough to provide a hot-air weld that is
at least 2 in. (50.8 mm) wide on either side of
the membrane-securement fastening plates at
the base of the expansion-joint curb.
• If the expansion joint is longer than
standard length of flashing membrane, it is
recommended to align the flashing pieces and
complete the hot-air weld between lengths
of the flashing on a flat, fire-resistant surface
before the cover flashing is installed over the
expansion joint. Workers should not attempt
to hot-air weld adjoining flashing sheets over
the foam rod, as the hot-air-welding process
can melt the foam backer rod, and the foam
backer rod does not provide a suitably firm
substrate for hot-air welding.
Roof-to-Wall Expansion Joints
Roof-to-wall expansion joints are commonly used
along transition walls (Fig. 12). Considerations
and requirements for this detail are as follows:
• The roofing membrane must be secured
to the structure or to wood blocking that is
secured to the structure on the roof side of the
expansion joint.
• A vapor barrier or reinforced sheet good
product that will support compressible or
loose-fill insulation must be attached to the
substrate. This insulation should be installed
within the expansion-joint void to mitigate
thermal loss and condensation issues at the
expansion joint.
• The sheet good product and insulation must
Figure 11. Standard curbed expansion-joint flashing.
The roofing membrane must be secured to
the structure or to wood blocking that is
secured to the structure on both sides of
the expansion-joint curb.
TPO MEMBRANE NOTE:
1. REFER TO WEBSITE FOR MOST CURRENT
INFORMATION
2. FOR WELD WIDTH. 2″ MIN IS REQUIRED
3. COMPRESSIBLE TUBE (SUPPLIED BY
OTHERS) DIAMETER MUST EXCEED
THE DECK OPENING BY 50% MIN OR
DESIGNATED MOVEMENT (WHICH EVER IS
GREATER)
4. FIELD MEMBRANE FORMED INTO RETAINER
TO SUPPORT FOAM ROD.
5. WHEN REINFORCEMENT OF TPO
MEMBRANE IS EXPOSED, INSTALL CUT
EDGE SEALANT
TPO MEMBRANE
SEALANT
FASTENER
8″ (203 mm) MIN.
INSULATION INSULATION
SUBSTRATE WOOD NAILER
(SEE NOTE #5)
SUBSTRATE
WELDED SPLICE
(SEE NOTE #2)
1-1/4″ HOT DIPPED GALVANIZED ROOF
NAILS AT 4″ (102 mm) O.C. MAX.
BONDING ADHESIVE
2″ METAL OR HD SEAM PLATE
AND FIRESTONE FASTENER
@ 12″ (305 mm) O.C. MAX
BACKER ROD / COMPRESSIBLE TUBE
(SEE NOTE #3)
38 • IIBEC Interface May/June 2023
also support the foam backer rod. The backer
rod diameter should be 1.5 times the width
of the expansion joint so that it will not fall
through the joint opening. The backer rod
provides support for the roof membrane
should any movement occur at the expansion
joint. Closed-cell backer rod is recommended.
• The expansion-joint cover flashing must be
wide enough to provide a hot-air weld that is
at least 2 in. (50.8 mm) wide on the horizontal
surface of the roof outside of the membranesecurement
fastening plates at the base of the
expansion joint.
• If the expansion joint is longer than
standard length of flashing membrane, it is
recommended to align the flashing pieces and
complete the hot-air weld between lengths
of the flashing on a flat, fire-resistant surface
before the cover flashing is installed over the
expansion joint. Workers should not attempt
to hot-air weld adjoining flashing sheets over
the foam rod, as the hot-air-welding process
can melt the foam backer rod, and the foam
backer rod does not provide a suitably firm
substrate for hot-air welding.
ABOUT THE AUTHOR
GARY GILMORE, RRO,
REWO, CIT LEVEL 1
Gary Gilmore, RRO, REWO, CIT Level I, is the director of Beam
Professionals’ North Texas Region. He is responsible for overseeing and
executing building enclosure assessments, infrared scans, remediation
design, contract review, quality assurance observations and performance
testing services. Gilmore has extensive experience working with owners,
architects, and general contractors, providing guidance and assistance in
the selection of enclosure products and systems designs to satisfy facility
and client needs, meeting building code and energy requirements based
on building types, geographic location, and occupancy. He has direct
field experience in the installation of cladding, roofing, and
waterproofing systems.
Figure 12. Standard roof-to-wall expansion-joint flashing.
Please address reader comments to
chamaker@iibec.org, including
“Letter to Editor” in the subject line, or IIBEC,
IIBEC Interface, 434 Fayetteville St., Suite 2400,
Raleigh, NC 27601.
USE APPROPRIATE
TERMINATION
APPROPRIATE FASTENER (BY OTHERS)
TPO MEMBRANE
INSULATION TPO MEMBRANE
SUBSTRATE
WALL / CURB
TPO FLASHING
2″ METAL OR HD SEAM PLATE AND
FIRESTONE FASTENER @12″ (305mm)
O.C. MAX (SEE NOTE #4)
COMPRESSIBLE TUBE (BY OTHERS) (SEE NOTE #3)
BACKER ROD OR
COMPRESSIBLE INSULATION WITH
INSULATION RETAINER (SUPPLIED BY 0THERS)
NOTE:
1. REFER TO WEBSITE FOR MOST
CURRENT INFORMATION
2. FOR WELD WIDTH. 2″ MIN IS REQUIRED
3. COMPRESSIBLE TUBE (SUPPLIED BY
OTHERS) DIAMETER MUST EXCEED
THE DECK OPENING BY 50% MIN OR
DESIGNATED MOVEMENT (WHICH EVER IS
GREATER)
4. MAXIMUM 610″ (254 mm) LONG
FASTENERS. (NOTE: WOOD BLOCKING
MAY BE SUBSTITUTED FOR INSULATION
TO REDUCE FASTENER LENGTH
REQUIREMENTS
5. WHEN REINFORCEMENT OF TPO
MEMBRANE IS EXPOSED, INSTALL CUT
EDGE SEALANT