Skip to main content Skip to footer

Case Study: Thermal Contraction of a PVC Membrane and EPS Insulated Roof Assembly in Alaska’s North Slope Borough

January 5, 2024

28 • IIBEC Interface January 2024
By Grace Wong, AIA, PE, LEED AP BD+C; and
Christian Gorry, RRC, RRO, PE
SINGLE-PLY POLYVINYL CHLORIDE (PVC) roof
membranes have been in use in the US and
Canada since the 1970s and remain a popular
choice for low-slope roof coverings, making up
an estimated 5–10% of the global low-slope
roofing market.1 Expanded polystyrene (EPS)
rigid insulation has been in use in the roofing
industry for at least as long.2 Whereas we
found extensive testing data and best practice
recommendations for the installation of PVC
and EPS in low-slope roof assemblies, we did
not find widely accepted practices on their
installation in arctic and subarctic climates
where winter temperatures can dip to -40°F
(-40°C). Our findings from a forensic study of
a large low-slope PVC and EPS roof assembly
installed in Alaska’s North Slope Borough
suggest specifications that perform adequately
in most other climate zones may require an
additional level of oversight during design and
installation to prevent assembly shrinkage and
premature failure.
BACKGROUND
We investigated the failure of a low-slope
PVC roof assembly in Deadhorse, Alaska, in
2018. Deadhorse is a small town in Alaska’s
Interface articles may cite trade, brand,
or product names to specify or describe
adequately materials, experimental
procedures, and/or equipment. In no
case does such identification imply
recommendation or endorsement by the
International Institute of Building Enclosure
Consultants (IIBEC).
Figure 1. Overview of the building (looking northeast).
Figure 2. East elevation.
Feature
Case Study: Thermal
Contraction of a PVC
Membrane and EPS Insulated
Roof Assembly in Alaska’s
North Slope Borough
January 2024 IIBEC Interface • 29
North Slope Borough and exists primarily
to service the oil industry that operates in
Prudhoe Bay. It is a place with short summers
and long winters where everything, including
building construction, has an added degree
of complication and something as routine as
material delivery may have an outsized impact if
limited to delivery by barge and a three-month
roofing season. The roof assembly was installed
on a one-story steel-framed industrial building
with premanufactured insulated exterior wall
panels (Figs. 1 through 4). The building was
substantially complete in the fall of 2015, and
the owner first discovered roof edge failures in
the spring of 2017. Failures identified at that time
included the perimeter membrane, prefinished
metal roof edge flashing, and wood curb below
visibly peeling off, as well as water entry at the
exterior wall-to-roof interface.
INVESTIGATION
OBSERVATIONS
Field Investigation—Roof Survey
We performed a visual survey of the roof
assembly from the interior and exterior and
noted that the roof membrane at each corner of
the building was wrinkled in a diagonal pattern
that pointed toward the corners (Fig. 5).
Membrane adhesion to the cover board
generally appeared intact, but we noted “excess”
or wrinkled membrane at several locations at the
cover board joints where the membrane was not
adhered (Fig. 6).
From a lift and from the roof, we observed
that the top edge of the roof curb had rotated up
and back toward the building and failed along
the entire roof perimeter (Figs. 7 and 8). The
wood-framed curb was constructed from four
pieces of 2 x 6 (38 x 140 mm) and 3 x 6 (64 x 140
mm) dimensional lumber attached with 0.130
in. (3.3 mm) nails in two rows spaced alternately
at approximately 8 in. (203 mm) on center (Figs.
9 and 10). The top plate of the wall appeared to
be intact and had not been displaced. The failure
of the roof edge at all four elevations was clearly
visible and appeared to be the most severe at the
center of each elevation (Figs. 11–13).
Roof Openings
We created two openings into the roof. The
first opening was made at the north elevation,
approximately in the center of the building,
and the second opening was made at the south
elevation, toward the southwest corner. Figure
14 shows the existing roof assembly observed
during our investigation, which was in general
agreement with the construction documents.
Figure 3. Overview of roof (looking northeast)
Figure 4. The plant interior.
30 • IIBEC Interface January 2024
At each opening, we noted the components
and attachment methods described in the
roofing submittal issued during construction
appeared to be present. Also, the adhesion
between the roof membrane and cover board
and between layers of rigid insulation appeared
to be intact. At both openings, there was an
approximate 2 in. (51 mm) gap between the
edge of the insulation and the inside face of curb
(Figs. 15 and 16).
Membrane fasteners and washers were
present beneath the membrane flashing and
spaced in general conformance with the roof
membrane manufacturer’s recommendations
(that is, 12 in. [305 mm] on center). However,
at both openings, roofing screws appeared to
have been displaced (Figs. 17 and 18); they
were not plumb and had begun to tear through
the insulation. In addition, the roof membrane
appeared deformed around the head of one of
the screws (Fig. 16).
Underneath the vapor retarder, the roof
deck remained tight to the wall and generally
intact. The thickness of the PVC roof membrane
measured 72 mils.
ANALYSIS
From our brief analysis of the as-built
documents, we concluded that the appropriate
wind uplift design loads were used for the area,
type, and time of construction. Therefore, we
would not expect the roof curb fasteners to fail
in wind uplift. Indeed, the observed failures
were relatively consistent on all elevations and
not aligned with expected wind directions. In
addition, the observed failures were generally
inconsistent with the pull-out behavior we would
expect to see from a wind uplift failure.
Another possible cause of fastener pullout
at the roof curb might be movement of the
structure such as repetitive movement in the
roof deck due to load-deflection response.
However, we observed from as-built drawings
that the metal pan roof decking ran exclusively
in the north/south direction (Fig. 19). The ribs
of the metal decking were significantly stronger
in one direction than the other. If the damage
were caused by structural deflection, we would
expect the damage to be different in the two
primary directions. That was not the case, as we
observed that the damage was consistent on
all four elevations. Also, roof deck and adjacent
structural components exposed during the
exploratory investigation, and as observed from
the exposed ceiling below, remained in-place,
planar, and displayed no signs of distress.
Therefore, we ruled out structural movement as a
possible cause.
A third possible cause of the observed pullout
failure might be stress imparted by the roof
Figure 5. Roof plan and a related photo of the shear pattern observed at the roof corners.
Figure 6. Ridges of unadhered membrane at panel joint.
The membrane
appeared to be pulling
away from the roof
edge at all elevations
and toward the center
of the roof.
January 2024 IIBEC Interface • 31
membrane itself. We suspect this was the case
because the pattern of wrinkles on the roof was
strongly correlated with patterns of uniformly
and concentrically applied tensile stress on the
roof membrane on a square-shaped roof
(Fig. 5). The membrane appeared to be pulling
away from the roof edge at all elevations and
toward the center of the roof. The built-up wood
roof curb was attached with 0.130 in. (3.3 mm)
× 3½ in. (89 mm) nails at approximately 8 in.
(200 mm) on center—staggered, providing
an uplift resistance of 78 lb/ft (115 kg/m). This
amount of resistance was adequate to resist the
design wind uplift demand but less than that
recommended by the Single Ply Roofing Industry
(SPRI). Per ANSI/SPRI/FM 443/ES-1, Wind Design
Standards for Edge Systems Used with Low Slope
Roof Systems,3 “Nailers should be . . . secured
to structural components of the building by
corrosion-resistant means sufficient to resist a
80-MIL PVC ROOF MEMBRANE – BASE
FLASHING/EXPANSION JOINT
2″ Ø FOAM BACKER ROD
FULLY ADHERED 80-MIL
PVC ROOF MEMBRANE
TILTED MEMBRANE FASTENER –
BREAKS THROUGH LOWER
LAYERS OF INSULATION
3 LAYERS OF EXPANDED POLYSTYRENE
INSULATION (TOP LAYER W/ INTEGRAL
POLYISO COVER BOARD) – ALL LAYERS
ADHERED
VAPOR BARRIER
MECH. ATTACHED GYPSUM BOARD
MTL. DECK
80-MIL PVC ROOF MEMBRANE – BASE
FLASHING/EXPANSION JOINT
2″ Ø FOAM BACKER ROD
FULLY ADHERED 80-MIL PVC
ROOF MEMBRANE
TILTED MEMBRANE FASTENER –
BREAKS THROUGH LOWER
LAYERS OF INSULATION
3 LAYERS OF EXPANDED POLYSTYRENE
INSULATION (TOP LAYER W/ INTEGRAL
POLYISO COVER BOARD) – ALL LAYERS
ADHERED
VAPOR BARRIER
MECH. ATTACHED GYPSUM BOARD
MTL. DECK
APPROX.
2″ GAP
Figure 7. Roof assembly at a failed roof edge—as designed.
Figure 8. Roof assembly at a failed roof edge—as observed.
vertical load of 200 lb/ft (300 kg/m) or the design
load, whichever is greater.”
As part of our analysis, we compared the
breaking strength of the PVC membrane to the
anchorage capacity of the wood curb. Basically,
we wondered if the PVC membrane had the
capacity to pry back the wood curb before failing.
The breaking strength for Type III reinforced
PVC membrane required by ASTM D4434,
Standard Specification for Poly(Vinyl Chloride)
By using SlopeShield Plus SA with self-drying technology – the expansive
Newark reroof project (375,000 sq.ft) – was able to reuse existing deck
materials while keeping the terminal fully functional during months long
construction. Once the finished roof was installed, SlopeShield Plus SA
transitioned to being an air barrier and vapor retarder, greatly reducing
condensation and other air movement issues.
Order a free sample at VaproShield.com
SELF-DRYING
TECHNOLOGY
WITH
SLOPESHIELD®PLUS
SELF-ADHERED
60 mil PVC roof covering
(by others)
Additional gypsum coverboard
(by others)
New insulation (by others)
SlopeShield Plus SA breathable
underlayment
Recovery board (by others)
A
A
B
B
C
C
D
D
E
F
E
F Re-used existing insulation
Newark Airport Reroof
Vapor Permeable Air Barrier
Roofing Underlayment
January 2024 IIBEC Interface • 33
Sheet Roofing,4 is 2,400 lb/ft (3,570 kg/m)
or approximately 30 times greater than the
withdrawal capacity of the installed curb and 12
times greater than the capacity of a curb installed
in conformance with ANSI/SPRI/FM 443/ES-1.
Even at half the published capacity (that is, 1,200
lb/ft [1,785 kg/m]), which would account for
material imperfections and weakened sections at
welded seams, the membrane would be highly
unlikely to tear before the roof curb fasteners
were pulled out.
Material Properties
of PVC Membrane
The observed pattern of wrinkles on the PVC
membrane and the evidence of the concentric
direction of stress suggested that the roof system
(PVC roof membrane and rigid insulation)
could be experiencing stress due to material
contraction. This hypothesis appears to align
with the published material properties of these
components and their expected response to
changes in temperature.
We looked at two material properties of
PVC while considering the effects of thermal
contraction—the coefficient of thermal
expansion and dimensional stability. The
coefficient of thermal expansion does not
need explanation, but it is worth remembering
that this property remains constant and is
“recoverable.” In other words, a material will
continue to expand and contract as a function
of temperature and return to its previous state
unless otherwise restricted. Dimensional stability
can generally be described as a material’s
capacity to maintain its dimensions (length,
width, and thickness) and shape over time with
changes in variables such as temperature.
ASTM D4434 defines three types of PVC
membranes: Types II, III, and IV. Of these, only
Type II is reinforced to provide “dimensional
stability.” Type II is defined as “reinforced sheet
in which fibers are incorporated into a production
process . . . [that] may provide other desirable
characteristics, such as dimensional stability.”4
ASTM D1204, Standard Test Method for Linear
Dimensional Changes of Nonrigid Thermoplastic
Sheeting or Film at Elevated Temperature,5 is the
relevant standard for measuring the dimensional
stability of PVC.
For this test, samples of PVC membrane
are heated to 176°F (80°C) for a period of six
hours and allowed to cool. The change in length
is measured and represents dimensional
stability—the membrane’s ability to maintain
or keep its original shape. The maximum linear
dimensional change as tested per ASTM D1204
in Type II membranes is 0.1%, compared with
0.5% in Types III and IV membranes. Despite
this difference, and the expected exposure
to an extreme climate, a Type III membrane
was installed for this project. This test is not a
perfect substitute for the conditions observed
on the subject building; it involves heating the
membrane first, not cooling to -40°F (-40°C).
We suggest it here only as an additional
consideration during the specification process.
The difference between 0.1% and 0.5% may
seem negligible but could have been as great
as 11 in. (280 mm) over 240 ft (73 m). Again, we
are not saying this occurred, only that not all PVC
membranes respond equally when subjected
to temperature changes and that a permanent
change in dimension has an associated force that
must be restrained.
Alpine, Alaska, is the closest weather
station to Deadhorse. Between the substantial
completion of the building in the fall of 2015
and the discovery of roof edge failures in the
Figure 9. Top of roof curb.
Figure 10. Built-up roof curb.
34 • IIBEC Interface January 2024
spring of 2017, Alpine registered seasonal
temperature swings of over 100°F (38°C)
between summer and winter, with the lowest
temperature recorded being -44°F (-42°C). The
average temperature in January 2016 was -4°F
(-20°C), and the lowest temperature was -29°F
(-34°C). The average temperature in January
2017 was -4°F, and the lowest temperature
was -44°F (-42°C). The conditions for the
months of December and February after were
similar. We consulted with material scientists,
who calculated that the combined coefficient
of thermal expansion for PVC membrane
adhered to EPS is approximately 4.0×10-5 in./
in. °F (9.0×10-5 cm/cm -°C), meaning the total
unrestrained thermal movement of the roof
assembly in this climate would be approximately
12 in. (305 mm). The installed roof assembly
was fully adhered, mechanically anchored at the
perimeter, and theoretically restrained against
movement. But these values indicate that the
roof was subjected to substantial forces of
contraction in the winter.
Refer to Fig. 5 and note that the membrane
at the perimeter is in “shear” with respect to the
main field of the roof; also, the pattern of distress
is consistent with membrane that is being
“drawn” toward its center. Also note, ridges in
the membrane at insulation panel joints indicate
lack of adhesion, but there was also a significant
amount of “extra” membrane at these joints, and
it would not have been possible to install the
membrane in this manner. These ridges occurred
after the original installation, and they were most
likely the result of contraction of combined PVC
and EPS in the winter followed by expansion of
the PVC membrane in warmer weather.
Material Properties of Insulation
Since both membrane and insulation displaced
inward and the membrane was largely well
adhered to the insulation, thermal movement in
the insulation was also a significant consideration
in determining whether thermal deflections
could manifest in the structure. The approved
project submittal stated that the rigid insulation
was Type II EPS.
As with the PVC membrane, we considered
both the coefficient of thermal expansion for
EPS and its dimensional stability as part of
our analysis. The test method for measuring
dimensional stability is described in ASTM
D2126, Standard Test Method for Response of
Rigid Cellular Plastics to Thermal and Humid
Aging.6 The dimensional stability, or percent
Figure 11. Failed roof edge at north elevation.
Figure 12. Failed roof edge at west elevation.
Figure 13. Failed roof edge at south elevation.
January 2024 IIBEC Interface • 35
linear change, allowed by this standard is 2%.
In other words, an 8 ft (2.4 m) insulation board
could permanently shrink by 1.9 in. (48.3 mm)
and still be considered within tolerance. It is
our understanding from studies carried out
by Structural Research Inc.2 and RDH Building
Science7 that permanent shrinkage of insulation
(dimensional stability) is primarily a chemical
change and a function of heating (above 176°F /
80°C), not cooling. But the amount of shrinkage
allowed by this standard is large in the context of
a 240 ft (73 m) building and has not been ruled
out as a contributing factor. As a reminder, we
observed an approximate 2 in. (50 mm) gap at
each end of the roof representing a total of 4 in.
TYPE III 80 MIL PVC MEMBRANE, FULLY ADHERED
COMPOSITE INSULATION COVERBOARD (1/2 INCH HIGH
DENSITY POLYISOCYANURATE COVERBOARD FACTORY
LAMINATED TO 3 1
2 INCH EXPANDED POLYSTYRENE
INSULATION), FULLY ADHERED
(2) LAYERS 4 INCH THICK (8 INCHES TOTAL) TYPE II, 1.5
LB/SF, EXPANDED POLYSTYRENE, RIGID INSULATION,
FULLY ADHERED
RUBBERIZED ASPHALT SHEET FULLY ADHERED
5/8 INCH THICK DENSDECK PRIME GYPSUM BASED
ROOF BOARD, MECHANICALLY ATTACHED
METAL PAN DECKING
METAL BAR JOISTS (ROOF FRAMING)
EXTERIOR
INTERIOR
FIGURE 1
Figure 14. Typical detail for the roof assembly.
Figure 15. An approximate 2 in. gap was observed at both openings.
As with the PVC
membrane, we
considered both
the coefficient of
thermal expansion
for EPS and its
dimensional
stability as part
of our analysis.
TYPE III 80-MIL PVC MEMBRANE, FULLY ADHERED
COMPOSITE INSULATION COVER BOARD (1/2 INCH HIGH
DENSITY POLYISOCYANURATE COVER BOARD FACTORY
LAMINATED TO 31/2 INCH EXPANDED POLYSTYRENE
INSULATION), FULLY ADHERED.
(2) LAYERS 4 INCH THICK (8 INCHES TOTAL) TYPE II 1.5
LB/SF, EXPANDED POLYSTYRENE, RIGID INSULATION
FULLY ADHERED
RUBBERIZED ASPHALT SHEET VAPOR RETARDER,
FULLY ADHERED
5/8 INCH THICK DENSDECK PRIME ROOF BOARD, METAL PAN DECKING
METAL BAR JOISTS
36 • IIBEC Interface January 2024
(100 mm) of shrinkage over 240 ft (73 m), so
substantially less shrinkage than is allowed by
ASTM D2126.
The coefficient of thermal expansion for Type
II EPS is 3.5×10-5 in./in. °F (6.0 x 10-5 cm/cm
°C), ASTM D696,8 and unrestrained EPS cooled
from 5°F (-15°C) to -40°F (-40°C) would shrink
by approximately 4.5 in. (114 mm) over the
length of the roof. Likewise, a fully adhered and
restrained roof assembly would need to resist
the force associated with the thermal contraction
of EPS.
Due to the limitations of the short arctic
roofing season and logistics of getting multiple
experts to this remote location, we were limited
to one day of exploratory investigation and two
openings. We observed an approximate 2 in.
(50 mm) gap at both openings, but we suspect
that this gap existed around the entire perimeter
of the roof. The original contractor indicated
that the insulation was installed tight to the
curb, i.e., the insulation gap was not present
initially and therefore developed over time,
which is consistent with our field observations.
Out-of-plumb membrane fasteners tore
through the insulation in a manner suggesting
all components were in place prior to failure,
with small particles of EPS insulation balanced
delicately on one side of the fastener only. This
result would have been difficult to achieve
during installation of a rotating screw.
Figure 16 shows the roof membrane
displaced locally around the washer, indicating
tension between the membrane and fastener/
washer and that anchorage of the membrane at
this location had failed. The screw orientation,
membrane displacement, and the characteristics
of torn insulation indicate that the 2 in. (50 mm)
gap observed at both roof openings was not
present at the time of installation and that roof
assembly had in fact shrunk.
CONCLUSION
The roof assembly as designed and installed
does not seem to be appropriate for the extreme
climatic conditions of Alaska’s North Slope
Borough. Multiple winters with two to three
months of average 4°F (-15°C) temperatures
and periodic lows of -40°F (-40°C) caused the
membrane or the insulation (or possibly both)
to contract, resulting in pull-out failure of the
nails connecting the built-up wood curb and
water intrusion into the interior. Several steps
could have been taken to mitigate the effects
of thermal contraction and the associated
force imparted on the roof perimeter. A layer of
stone wool insulation could have been used on
top to isolate the EPS from direct contact with
the exterior temperatures.7 A better effort at
Figure 16. Membrane under tension at fastening plate.
Figure 17. Downward view of rotated membrane screw tears through insulation.
Figure 18. Close up look at the bottom of the insulation, showing more damage on the bottom
layer of insulation.
January 2024 IIBEC Interface • 37
connecting the wood curb to the structure to
at least meet the requirements of ANSI/SPRI3
would have been appropriate. A different choice
of PVC membrane, one with greater dimensional
stability, while not a surefire fix, seems like
inexpensive insurance in retrospect.
Roofing in arctic, and even subarctic,
climates may deny designers and installers
a level of forgiveness otherwise available in
milder climates. Temperatures below 40°F
(-40°C) induce abnormal thermal movement
and associated force into materials such as
PVC roofing and EPS insulation that must be
accounted for.
In our research, we found that design
guidelines for PVC roofing tend to focus on
issues such as fastener pullout from wind uplift,
and recommendations for movement joints in
metal components, including edge flashings
and gutters; however, we did not find widely
accepted standards on how to accommodate
thermal movement in extreme climates.
We recommend that additional research
and material testing be conducted so that easyto-
use guidelines and industry best practices
can be developed to help designers choose
appropriate materials and details for extreme
cold climates.
REFERENCES
1. https://www.datamintelligence.com/researchreport/
roofing-membranes-market.
2. Dupuis and Dees,1984, Expanded Polystyrene
Insulation for Use in Built-up and Single Ply Roofing
Systems. Structural Research Inc.
3. ANSI/SPRI/FM 443/ES-1 Wind Design Standards for
Edge Systems Used with Low Slope Roof Systems.
4. ASTM International. 2021. Standard Specification
for Poly(Vinyl Chloride) Sheet Roofing. ASTM
D4434/ASTM D4434-21. West Conshohocken, PA:
ASTM International.
5. ASTM International. 2020. Standard Test Method
for Linear Dimensional Changes of Nonrigid
Thermoplastic Sheeting or Film at Elevated
Temperature. ASTM D1204-14(2020). West
Conshohocken, PA: ASTM International.
6. ASTM International. 2020. Standard Test Method
for Response of Rigid Cellular Plastics to Thermal
and Humid Aging. ASTM D2126-20. West
Conshohocken, PA: ASTM International.
7. Ricketts and Tatara, 2018, Impact of Insulation
Dimensional Stability on Conventional Roof
Performance. RDH Building Science.
8. ASTM International. 2016. Standard Test Method for
Coefficient of Linear Thermal Expansion of Plastics
Between -30°C and 30°C with a Vitreous Silica
Dilatometer. ASTM D696-16. West Conshohocken,
PA: ASTM International.
ABOUT THE AUTHORS
GRACE WONG, AIA,
PE, LEED AP BD+C
Grace Wong, AIA, PE,
LEED AP BD+C, is the
energy lead in the
Building Sciences
group at OAC Services
Inc. She is a registered
architect and civil
engineer with 12 years
of experience in the
investigation and repair
of existing building
enclosure systems, full
re-clad design, and new building enclosure
design. She regularly conducts research related to
the real-world performance of building enclosure
systems. Her research on the time required for
code requirements to translate into real-world
benefits in successfully performing building
enclosure systems has been published and
presented nationally and internationally. Wong
serves on the board of the Seattle Building
Enclosure Council.
CHRISTIAN GORRY,
RRC, RRO, PE
Christian Gorry, RRC,
RRO, PE is a
Registered Roof
Consultant (RRC) and
Registered Roof
Observer (RRO). He is
a licensed engineer in
10 states and
specializes in forensic
investigations and
repair design for
buildings subjected
to water intrusion. His depth of knowledge in
building enclosure and roofing design includes
K–12 facilities, higher-education facilities,
commercial developments, and healthcare
facilities.
Please address reader comments to
chamaker@iibec.org, including
“Letter to Editor” in the subject line, or IIBEC, IIBEC Interface,
434 Fayetteville St., Suite 2400, Raleigh, NC 27601.
Figure 19. Roof framing plan.