Skip to main content Skip to footer

Challenges in Preservation Engineering: Restoring a 100-Year-Old Historical Terra Cotta Facade

November 16, 2015

Challenges in Preservation Engineering:
Rest oring a 100-Year-Old
Hist orical Terra Cott a Façade
Car ly Connor, Hannah Thevapa lan, and Hamid Vossoughi, PEng
WSP Canada Inc .
2300 Yonge Street, Suite 2300, Toronto, Ontario, Canada M4P1E4
Phone: 888-425-7255 • Fax: 416-487-9766 • E-mail: hthevapalan@halsall.com
S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5 C o n n o r a n d T h e v a p a l a n • 1 1 7
ABSTRACT
Set in the heart of Toronto’s financial district is a 100-year old, 11-story Beaux-Arts
designated heritage building named 1 King Street West. The exterior walls at the base of the
building are smooth Quebec granite, with glazed speckled terra cotta above. Five years of
evaluation and research lead to restoration of the building fabric, including replacement of
deteriorated terra cotta and installation of a new copper cornice in 2014-2015.
This paper focuses on lessons learned during the construction phase of the historical
restoration of 1 King Street West, with examples of how identification of specific masonry
repairs and anchorage scenarios at early stages significantly impact project success.
SPEAKERS
Carly Conn or — WSP Canada Inc .
Carly Connor combines an academic background in masonry restoration with experience
as both a heritage masonry contractor and consultant to provide a unique perspective
on the industry and best practices from all sides of a project. This leads to better anticipation
of potential problems and developing innovative solutions. Carly has a bachelor’s in engineering
and management and a master’s in applied science (masonry focus).
Hann ah Thevapalan — WSP Canada Inc .
Hannah Thevapala n has consulting experience in New York City and Toronto with
exposure to new construction projects and heritage restoration. She continues to gain
knowledge at both ends of the construction spectrum. Her combination of a bachelor’s in
architectural sciences and a master’s in engineering (building science majors) provides her
with unique tools to approach challenges in building restoration.
1 1 8 • C o n n o r a n d T h e v a p a l a n S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5
S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5 C o n n o r a n d T h e v a p a l a n • 1 1 9
INTRODUCTION
Constructed in 1914 and set in the
heart of Toronto’s financial district, 1 King
Street West is an Ontario designated heritage
property and recently celebrated its
centennial. The building was the headquarters
of the Toronto Dominion Bank. Darling
and Pearson architects were the designers,
and Harkness & Oxley
were the project’s consulting
engineers. The
architects were among
the leading designers
who contributed to the
construction of significant
buildings across
Canada. The 14-story,
150-ft.-tall building is
a steel-framed building
clad with terra
cotta and manufactured
by Northwestern
Terra Cotta Company.
1 King’s owners, after a lengthy process of
evaluation and analysis, committed to proceed
with a major repair program to restore
the historical façade’s fabric. Despite preplanning
that considered potential design
and construction issues, the façade rehabilitation
was faced with challenges common
to complex restoration projects. This
paper discusses highlights of the project
from design through construction.
BACKGROUND
1 King Street West is a Beaux-Arts
former Toronto Dominion Bank Building
set in the heart of downtown Toronto. The
original building was constructed in 1914
(Photo 1A) and is now designated under
Part IV of the Ontario Heritage Act
(Photo 1B), listed by the city of Toronto.
A 52-story, high-rise tower was constructed
between 2003 and 2005 and
is connected to the west elevation of the
historic building (Photo 1C). The building
complex is now a mixed-use hotel
and residential condominium.
Challenges in Preservation Engineering:
Rest oring a 100-Year-Old
Hist orical Terra Cott a Façade
Photo 1A – 1 King
West (1914) with
ornate cornice and
parapet features
(TD Archives).
Photo 1C – 1 King West circa 2013,
prior to restoration and without cornice.
Photo 1B –
The Dominion
Bank Building
Heritage
designation
plaque.
The exterior walls at the base of the
building are composed of smooth Quebec
granite, while the remainder is constructed
of glazed, speckled terra cotta (Photo 2 and
Figure 1) supported on steel framing and
tied back to the structure using a combination
of steel
hooks, ties, and
straps. Canadian
Steward Co. Ltd.
was the contractor,
and the terra cotta
was manufactured
by Northwestern Terra Cotta Company of
Chicago, which also supplied terra cotta
to buildings such as Chicago’s Wrigley
Building, the Civic Opera House, and the
Chicago Theatre. In the peak of terra cotta
use in steel-framed buildings following the
Industrial Revolution, Northwestern Terra
Cotta took the lead in establishing the
national standard for specification and
detailing, promoting the advancement of
the industry.1
The structural framing at the building
perimeter included two lines of supporting
frames (Figures 2A and 2B): an interior
beam to support the floor, and the exterior
to support the walls. This was indicative of
a shift from the transitional (i.e., hybrid)
systems to curtain wall (veneer) systems,
where the exterior wall was no longer
1 2 0 • C o n n o r a n d T h e v a p a l a n S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5
Figure 1 – Typical elevation and
wall section (Darling & Pearson
Architects, Drawing 120, June 24, 1913).
Figure 2A – Typical floor framing plan
(Harkness and Oxley Consulting Engineers, ninth-floor
framing plan, Drawing S-145-26, November 1913).
Figure 2B – Typical wall sections (Harkness
and Oxley Consulting Engineers, Drawing
S-145-25, April 1913).
Photo 2 – Typical wall elevation.
a load-bearing structural system
and thus was intended to act as
a barrier and exterior skin only
(Photos 3A and 3B).2
The top of the building was
decorated with a highly detailed,
internally drained terra cotta cornice
and parapet capped with
terra cotta ornamental features
(Photo 4A). However,
archived documents
indicate that the cornice and decorative
features showed signs of
distress and were removed prior
to the 1930s. The cornice was
replaced with a copper facsimile in
the 1930s, with reduced decorative details
and also removal of finials at the top of the
building (Figure 4B). Further, in 2007, the
copper cornice was removed due to deterioration
of the supporting structures (Photo
4C), and the building lost its crown completely
(Photo 4D).
Under new ownership, building management
decided to proceed with a full-scale
S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5 C o n n o r a n d T h e v a p a l a n • 1 2 1
Photo 3A – Building under construction, circa 1913
(TD Archives, Photo No. 30, December 13, 1913).
Photo 4A – Terra cotta cornice
and parapet (Darling & Pearson
Architects, Drawing 109, terra
cotta details, Melinda Street,
ninth floor, July 17, 1913).
Photo 4B – Copper cornice
(TD Archives, prior to
removal in 2007).
Photo 4C – Copper cornice and
support prior to removal in 2007.
Photo 4D – Copper cornice removed with
tarp over masonry backup, TD Archives).
Photo 3B – Fifth-floor façade under construction
(TD Archives, Photo No. 30, December 13, 1913).
terra cotta repair and restoration program that included reinstatement
of the copper cornice. In 2011, we began a series of evaluations
and studies to assess and develop options and management strategies
to restore the façade to meet the client’s expectations.
EVALUATION
An evaluation was authorized to develop a benchmark for future
monitoring, maintenance, and restoration. This included identifying
potential safety concerns, evaluating the existing condition of
the terra cotta façade, developing a repair strategy, and reviewing
options for cornice replacement.
Scope
The evaluation involved review of available historical documents
and drawings from historic archives and a previous condition evaluation
report (completed in 1989). These documents established the
baseline for the building condition assessment. Select areas of the
building were accessed “up close” via a swing stage to review and
sound the terra cotta units, to remove select terra cotta units in order
to evaluate concealed conditions, and to collect samples for material
testing. During the up-close review of the façade, loose materials
were removed or stabilized to limit potential hazards to public safety.
Laser scanning of the façade was completed to develop electronic
(CAD) elevation drawings. A 100% façade survey was then completed
using industrial rope access to document existing conditions (Figures
4A and 4B) and determine quantities of repairs. A thermographic
scan of the façade was also carried out to review airtightness and
thermal effectiveness of the wall system. The scan showed that there
were no major thermal anomalies within the field of the terra cotta.
Key Findings
The evaluation revealed that the façade was generally in good
condition; however, terra cotta was at risk of further deterioration,
primarily at building corners. Previously repaired corner
terra cotta units exhibited cracking, which suggested continuing
deterioration following the previous repairs.
Widespread hairline cracking and localized spalling
were observed on skyward-facing sills, in addition to localized
deterioration of terra cotta glazing, which included
“coining” and crazing, both conditions that can contribute
to increased water entry into the façade and possible dete-
1 2 2 • C o n n o r a n d T h e v a p a l a n S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5
Figure 3 – Comparison of 1914 terra cotta and 1930s copper
cornice profile (McGillivray Architect/Halsall, Drawing 2/A-4,
Original and Proposed Cornice Profile Study, March 29, 2011).
Figures 4A and 4B – Existing condition partial elevation
and legend (Vertical Access, Drawing 2, East Elevation, All
Conditions, 1 King West Façade Investigation, October 14, 2011).
rioration of the terra cotta units.
Material testing and analysis of terra
cotta samples indicated that the material
was durable and in good condition for its
age and exposure to Toronto weather conditions.
Compressive strength and water
absorption of terra cotta was found to be
about 10,000 psi and 12% respectively,
which is comparable to historic published
material data (Figure 5).3 Lack of visible
distress is an indication that the façade was
installed with diligence and care.
The existing structural steel frame and
anchorage reviewed were in good condition
with minimal to moderate corrosion (Photo
5). Terra cotta cracking at building corners
was attributed to lack of continuity in steel
framing and resultant stress concentrations,
further exasperated by lack of expansion
joints (vertical and horizontal), which
was typical and part of the lessons learned
in the transitional building construction.2
The evaluation revealed
that there was widespread
sealant deterioration at subsequent
vertical joints that
was created at an earlier date,
including debonding, hardening,
and splitting. Mortar
appeared to be cracked and
debonded from terra cotta,
which can lead to increased
water ingress into the façade.
Accelerated deterioration of
mortar may have been caused
by the lack of flashing at horizontal
projections.
Based on the findings
and repair strategies presented
to the owner, a shortterm
repair program was
implemented in
2012, followed by
a longer-term restoration
program,
which was initiated
in 2014.
Cornice Option
Analysis
As noted above,
the original terra
cotta cornice and
subsequent copper
cornice were
removed from the
building. A key part
of our evaluation
and restoration program was to reinstate the
cornice in order to complement the building’s
historic fabric. The main goal of the analysis
of cornice options was to present feasible
designs for cornice replacement while taking
into account durability,
constructability, and economics.
The review and schematic
design process involved consultation
with an historic
preservation architect.
Several material options
(terra cotta, metals, and
composites) were evaluated,
and the profile of the original
cornice was also studied.
Advantages and disadvantages
of the options were presented
to the owner. Installing a
new terra cotta cornice would
have matched the original
cornice and remainder of the
building; however, it presented challenges
regarding drainage, the need for structural
reinforcement, constructability, and cost.
Metal options considered included leadcoated
copper, red copper, and terne-plated
stainless steel. Metal options were the least
structurally demanding option. Further,
lead-coated copper that is workable and
durable was presented as a material used
regularly in heritage buildings. Composite
materials considered included glass-fiber
reinforced concrete (GFRC) and fiberglassreinforced
polymers (FRP). The composite
options presented the ability to match aesthetics
of the existing terra cotta, but their
durability and maintenance were questionable.
The owner opted to proceed with red
copper as the primary fabric of the cornice.
DESIGN
The decision was made to proceed with
a full façade repair program that addressed
S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5 C o n n o r a n d T h e v a p a l a n • 1 2 3
Figure 5 – Historical terra cotta properties.3
Figure 6 – New steel support design at building corners (Limen Group, Drawing 2/14-06R-1706,
12th floor, Yonge and Melinda, Steel Support, July 14, 2015).
Photo 5 – Existing steel column-to-beam intersection.
potential risks, thus maintaining property
standards, improving durability of the
façade, extending its useful life, and reinstating
the cornice, thereby deferring future
maintenance. The scope of work included
replacement of severely cracked and spalled
terra cotta units, which accounted for less
than 2% of total units on the building. The
repair program also included terra cotta
repair, localized stabilization of isolated
units, repointing of all mortar joints, and
reglazing of cracks and patch repairs.
A key to the project’s success was availability
of quality terra cotta. Prior to bid and
tender, Boston Valley Terra Cotta (BVTC)
was selected to supply new units for the
project, given that they are a leading manufacturer
of custom architectural terra cotta
and are located within two hours of the project
site. BVTC worked with the design team
during the design phase and also during
restoration to assist with a full survey of the
façade, creating shop drawings and setting
elevation drawings for replacement units,
which can be a time-consuming process
that, if deferred, could impact the construction
schedule.
Steel repairs were anticipated as part
of the scope once terra cotta units were
removed. At building corners, the shelf
angle support structure was known to be
discontinuous, which required modification
(Figure 6) to the existing framing system.
Additionally, any exposed steel was to be
cleaned and coated.
Cornice design development considered
feasible changes to the dimensions, level
of detail, and profile. The original terra
cotta cornice provided poor drainage, with
embedded drainpipes through building interiors,
which increased long-term risk of the
system. The new reduced-profile 24-oz. red
copper cornice with positive slope provided
a more effective drainage and a lower-cost
solution. A higher level of ornamentation
from the first (1930s) copper cornice was
introduced in the new design. Full-size
mock-ups were prepared in a shop and
reviewed for approval.
The outcome was a reduced cornice
profile (Figures 7A, 7B, and Photo 6) that
was economical and met Toronto Heritage
Preservation Services’ approval. The existing
steel structure and cornice framing were
modified to incorporate a new galvanized
steel support frame (Photos 7A and 7B).
The building’s 12th-floor terra cotta braided
band course and windowsills were to be
1 2 4 • C o n n o r a n d T h e v a p a l a n S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5
Figures 7A and 7B – Copper
cornice original profile vs.
proposed profile (McGillivray
Architect/Halsall, Drawing 1 &
2/A1, Rev. 1, 5 & 6/A1, Rev. 1,
Original and Proposed Cornice
Profile, August 22, 2013).
Photo 6 – Off-site
mock-up of cornice.
A: Original copper cornice profile.
B: New copper cornice profile.
flashed with corrugated
24-oz. copper to
protect the terra cotta
units (Photo 7C).
Project logistics,
access, and phasing
of the project were
considered, presented,
and discussed
with the clients to
solicit their input.
The client’s preferred
choice was to allow
the contractor full
access to all façades
to complete the project
as quickly as possible.
However, in the
end, it was agreed
that project logistics
and phasing options
are best left to the
contractors.
RESTORATION
To tackle a project
of this magnitude
with the planning and
precision required to
properly execute the
work, only preferred prequalified trades were
invited to bid for the project. The successful
bidder was selected following a thorough
interview process to confirm that the scope
and magnitude of the project were fully comprehended.
Limen Group, a major national restoration
contractor, was selected as the
contractor who portrayed enthusiasm and
presented the most competitive pricing and
most aggressive schedule. Heather & Little
Limited (H&L), who assisted with cornice
mock-up, was also retained as a subcontractor
to perform all copper restoration work.
The aggressive schedule set by the contractor
proved to be optimistic, as the project
experienced numerous obstacles and
delays. 1 King Street West is located at one
of the busiest intersection in Toronto. As
such, pedestrian and vehicle access had
to be maintained at all times, with public
safety being paramount. Delays were experienced
at the front end of the project due
to site logistics and the high level of involvement
with the city officials to erect a scaffold
for access to the building façade. Due to this
lost time, the project team rushed to meet
imposed deadlines. The push to follow the
original schedule put a strain on the project
team and the client. Given the multifunctional
use of the property as a hotel and a
condominium, as well as a prime destination
for conferences, weddings, and large
events, the owner required that target dates
for completion of work and scaffold removal
be met in order to satisfy their clients’
expectations.
Additional scheduling delays were realized
due to escalation of repair quantities.
Once the building was fully accessed, we
extended some of the terra cotta repair scope
and the quantity of terra cotta replacement
units to perform a comprehensive restoration.
Review and approval of shop drawings
by the contractor also became a hurdle
in proceeding with production. Given the
required lead time for the production of
terra cotta units (measuring, shop drawings,
production, drying time, inspection,
shipping, etc.), identifying an additional
unit requiring replacement in a timely manner
became critical.
Any project that involves the replacement
S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5 C o n n o r a n d T h e v a p a l a n • 1 2 5
Photos 7A, 7B, and 7C – New cornice
structural support, copper and
12th-floor water table, and sill flashing.
A
B
C
of a large number of masonry
units is specifically governed
by the pattern and location of
the units to be replaced (Figure
8 and Photo 8). The pattern
of replacement units governs
required shoring, installation
constraints, and anchorage
requirements—just to name a
few. For large openings where
many units have been removed,
units must be installed from
the bottom, working towards
the top to properly support the
new units. If terra cotta units
are not delivered in a specific
order, site crews may experience
great fluctuations in workload
with times when they are
unable to progress with further
installations, even with a positive
inventory of units on-site.
This situation directly results
in a delay towards the end of
the schedule, making planning
during the ordering and delivery
of terra cotta units critical
to avoid this backlog and
inefficiency. Terra cotta setting
drawings (Photo 8) must be analyzed and
utilized to their full extent to identify any
critical scenarios that may have delivery or
installation constraints.
In the terra cotta replacement project at
1 King Street West, setting drawings were
not efficiently used to plan and identify
the specific and unique terra cotta anchorage
scenarios. During original construction,
terra cotta was often built from the bottom
up (Photo 3), frequently utilizing interlocking
elements between units to provide the
required lateral anchorage and support that
the units require. When such a unit requires
replacement, the constraints of the surrounding
units require that a new anchorage
scenario be developed. Additionally,
anchorage to secure units to steel supports
can be installed with ease when the
1 2 6 • C o n n o r a n d T h e v a p a l a n S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5
Figure 8 – Terra cotta setting
drawing, partial elevation
(area noted was most severely
distressed area) (BVTC,
Setting Drawing Priority 2,
1KS-S-2.E, March 5, 2015).
Photo 8 – Newly received terra cotta
unit inspection prior to installation.
walls are wide open, similar
to original construction
(Photos 9A and 9B). When
access to install anchorage
to the existing wall is limited
(Photo 9C and 9D), each scenario
must be analyzed; and
often, a unique design must
be developed for each case.
At 1 King, new anchorage
scenarios needed to be developed
for isolated units, headers,
cartouche shields, balustrades,
and units in series.
As is often the case with
existing structures, backup
wall conditions are not the
same throughout the building, nor do they
always match original design details. In limited
cases, existing steel was supplemented by
extending shelf angle horizontal legs to provide
additional support for the new terra cotta.
Additionally, the existing steel angles greatly
impacted installation of terra cotta units at
select locations where the profile of the terra
cotta unit had to be modified to fit around the
protruding angles. It was surprising that the
overall extent of remedial repairs to the existing
steel was less than what we anticipated.
In addition to the repairs mentioned above,
addressing corrosion was typically limited to
cleaning and coating of exposed steel frames.
Given the heritage designation of the property,
matching of repairs (color, texture, etc.) to
the original material was a priority, with repair
of existing materials preferred over replacement
wherever possible. Repair products and tech-
S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5 C o n n o r a n d T h e v a p a l a n • 1 2 7
Photo 9A – New terra cotta header suspended
from shelf angle above using J-hooks and
threaded rods, similar to original design.
Photo 9B – Reconstruction
of terra cotta jamb.
Photo 9C – Isolated terra cotta
header location prior to anchorage
and unit installation.
Photo 9D – Newly installed
terra cotta balustrade units.
niques used were compatible with existing
materials and sympathetic to the heritage
nature of the building façade. Crews working
on the project were outstanding and
highly skilled in their execution of the
repairs.
CONCLUSION
The terra cotta façade of 1 King Street
West is an exemplar demonstrating
advancement of the terra cotta industry
and construction of transitional masonry
buildings in 1914. The relatively minimal
level of deterioration is a testament to the
quality of the terra cotta used, the original
design details, and the workmanship
implemented to execute the work. A century
later, extensive research and preplanning
efforts led to restoration of this heritage
façade. Attention to detail, including selection
and coordination of the project team,
was part of the effort to make the project a
success. The construction team was faced
with challenges including increased scope
of work, scheduling, and the need for trade/
supplier coordination. In all, the project was
completed several months behind schedule.
However, care was taken by the trades
to perform their work to a high standard
in a similar fashion to the pride taken
by the original masons on the building.
The overall lessons learned from the restoration
were that a phased approach to
execution and performing the work over
two years could have been more beneficial.
This would require breaking up the project
and performing the work on a representative
portion of the building during year one,
including terra cotta documentation and
fabrication. This would allow ironing out
site challenges for a more efficient approach
to project delivery.
Project Team
Owner – TSCC 1703 c/o Y.L. Hendler
Ltd.
Heritage Architect – McGillivray Architect
Consulting Engineers – WSP Canada
Inc. (formerly Halsall Associates)
Existing Documentation Support –
Vertical Access
Restoration Contractor – Limen Group Ltd.
Terra Cotta Supplier – Boston Valley
Terra Cotta
Sheet Metal Subcontractor – Heather &
Little Ltd.
REFERENCES
1. A.M. Didden, 2003. “Standardization of
Terra Cotta Anchorage: An Analysis of
Shop Drawings From the Northwestern
Terra Cotta Company and the O.W.
Ketcham Terra Cotta Works: A Thesis
in Historic Preservation.” University of
Pennsylvania Libraries.
2. R.L. Will and E.A. Gerns, 2014.
“Detailing in Transition: Hybrid
Walls and the Evaluation of Terra
Cotta Detailing,” Proceedings of the
Symposium on Building Envelope
Technology, October 2014, pp.
81-92. RCI, Inc.
3. S.M. Tindall, 1989. “How to Prepare
Project-Specific Terra Cotta
Specifications,” APT Bulletin, Vol.
21, No. 1 (1989), pp. 26-36, APT.
1 2 8 • C o n n o r a n d T h e v a p a l a n S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 5
Figure 9 – Typical wall sections (Harkness and Oxley Consulting Engineers,
Drawing S-145-26, April 1913).
Photo 10 –
Originally
designed steel
shelf angle
support was
extended locally
to support new
terra cotta.