Skip to main content Skip to footer

Detailing Basement Waterproofing

March 16, 2014

Detailing Basement Waterproofing
Justin Henshell, FAIA, FASTM
Paul Buccellato, RWC, REWC, AIA, FASTM
Henshell & Buccellato, Consulting Architects
166 Patterson Avenue, Shrewsbury, NJ 07702
Phone: 732-530-4734 • Fax: 732-747-8099 • E-mail: paul.buccellato@verizon.net
2 9 t h RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 2 0 – 2 5 , 2 0 1 4 B u cc e l l a t o a n d He n s h e l l • 1 0 3
Abstract
Waterproofing details that are prepared for below-grade projects by the architect or
waterproofing consultant typically indicate horizontal/vertical transitions and pipes/conduits
that penetrate through the foundation or at sump pits. However, there are conditions
that—if left solely to the contractor or addressed hastily in the field—can cause problems
that are difficult and expensive to correct or remediate.
More often than not, details that are critical due to the requirements of the support of
excavation (SOE) are frequently omitted by the designer because he often fails to review
them or is unaware of the fact that such drawings actually exist.
Waterproofing designers need to be aware that these conditions exist and must make
provisions for providing proper membrane terminations where they occur.
Speakers
Justin Henshell, FAIA, FASTM – Henshell & Buccellato, Consulting Architects
Justin Hens hell has been a registered architect for 61 years, is licensed in six states,
and is board certified by the National Council of Architectural Registration Boards. He is
a Fellow of the American Institute of Architects and a member of the New Jersey Society
of Architects, the Construction Specifications Institute (past president Metropolitan New
York Chapter), and The Masonry Society (past director). Henshell was the recipient of the
Walter C. Voss Award in 2000 “for distinguished contributions to knowledge in the field of
architecture and building technology, particularly the performance of roofing and waterproofing
systems,” and the William C. Cullen Award in 2010 for “distinguished contributions
and personal commitment to Committee D08.” He is a member of ASTM Committees
D08, Roofing & Waterproofing (past chairman of Subcommittee D08.20, Roofing Membrane
Systems); C15, Masonry Units; and E06, Performance of Building Constructions. He serves
on the International Council for Building Research Studies & Documentation, Commission
W086 on Building Pathology. Henshell has lectured on roofing for the Roofing Industry
Educational Institute and at the University of Wisconsin. He has also lectured on waterproofing
for RCI. Henshell has authored and presented more than 45 technical articles and
papers in North America and Europe. He is the author of an ASTM standard on waterproofing
design and a coauthor of an NCARB monograph on built-up roofing. He is also the
author of The Manual of Below-Grade Waterproofing Systems.
Paul Buccellato, RWC, REWC, AIA, FASTM – Henshell & Buccellato, Consulting Architects
Paul Buccellato is a registered architect in four states and is board certified by the
National Council of Architectural Registration Boards. He is a Registered Waterproofing
Consultant and Registered Exterior Wall Consultant with RCI, Inc. Buccellato is a member of
the American Institute of Architects; the New Jersey Society of Architects; the Construction
Specifications Institute; RCI, Inc.; and ASTM, Committees D08 on Roofing & Waterproofing
(chairman Subcommittee D08.20, Roofing Membrane Systems), C15 on Masonry Units,
and C-24. He received ASTM’s Award of Merit in 2007 “for outstanding leadership, distinguished
service, and personal dedication in developing and promoting voluntary standards,”
and he was afforded the honorary title of Fellow. Buccellato has authored several technical
papers on waterproofing and roofing, four ASTM standards on roofing, and has lectured at
Brookdale College, NJ. He wrote a column on roof design for The Roofing Specifier and is a
coauthor of an NCARB monograph on built-up roofing. He has presented papers relating
to waterproofing and roofing for RCI, Inc. and ASTM. He is the principal author of three
ASTM standards. Buccellato is a member of RCI’s Education Committee and the chairman
of the Registered Exterior Wall Examination Committee. He is a former member of NRCA’s
Educational Resource Committee.
1 0 4 • B u cc e l l a t o a n d He n s h e l l 2 9 t h RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 2 0 – 2 5 , 2 0 1 4
ABSTRACT
Waterproofing designers, more often
than not, prepare their details based on
the structural, architectural, and MEP
drawings without reviewing the support-ofexcavation
drawings. These often contain
members that encroach on the membrane
and require special treatment to ensure
that the waterproofing maintains its watertight
integrity. Raker foot blocks penetrate
underslab membrane, tiebacks protrude
into the foundation wall, and walers are left
in place and must be flashed into the system.
Not all of these are indicated on shop
drawings. This paper reviews many of these
conditions. Failure to address them can
result in a blizzard of requests for information
(RFIs), extras, or a leaking basement.
INTRODUCTION
Among the most overlooked details of
below-grade waterproofing are those that
illustrate membrane penetrations and terminations.
Although many manufacturers
devote a number of pages in their literature
to typical details that are generally encountered
on most projects, they often fail to
address special conditions that are required
by the earth-retaining system installed to
support and protect the excavation. The
components of the system are indicated
on drawings that are usually prepared by
the excavator to illustrate the methods by
which he intends to support the excavation
during the construction of the basement.
These are called support-of-excavation or
SOE drawings. Sometimes the drawings
are prepared by the project foundation
structural engineer with input from the
geotechnical engineer; but often they are
considered to be “means and methods” and
are assigned to the excavation contractor’s
engineers. It is the waterproofing designers’
responsibility to obtain these drawings
in order to prepare details that address
each penetration and termination. Failure
to do so may result in a blizzard of RFIs
and extras after the waterproofing contract
is awarded. However, even if preliminary
SOEs are prepared by the foundation engineer,
cost increases and design changes
can be expected after the final documents
are submitted by the excavation contractor.
Basements subject to hydrostatic pressure,
whether from rainfall or an existing
water table above the basement floor slabs,
are waterproofed by membranes either preapplied
to the earth-retaining system using
one-sided forms or postapplied to the foundation
after it is erected, using two-sided
forms. The latter requires that the walls of
the excavation be far enough outside of the
building line to enable the applicators to
install the membrane, usually not less than
30 inches (750 mm).
The membranes discussed in this paper
are those that are fluid-applied or applied
in sheets and those that are bonded to the
concrete components. Bentonite-based and
most unreinforced fluid-applied membranes
are not included, although many of the conditions
discussed herein are similar.
BASEMENT CON STRUCTION
There are many different methods of
supporting the excavation when the basement
is constructed in urban areas with
tight, restricted spaces and not just simply
installed in open excavations and backfilled.
The earth-retaining systems can be
used solely to support the earth and act as
deep-water cutoff walls or additionally be
designed as structural foundation walls to
support the building above.
For the purposes of this paper, a
basement is defined as a habitable space
enclosed by foundation walls that retain
earth. Where the water table cannot be
maintained at least 6 in. below the bottom
of the lowest floor on-ground, the
International Building Code requires basements
to be waterproofed. Waterproofed
basements are constructed of concrete or
reinforced masonry walls designed to withstand
the pressure of the earth and water,
and slabs-on-grade designed to resist uplift
pressure created by the buoyancy of the
water.
Basements can be constructed by two
methods:
• Bottom-up construction: With this
method of construction, the earth
enclosed by the foundation wall is
excavated, the walls braced, and the
pressure slab cast on grade.
• Top-down construction: With this
method, the foundation and interior
columns are cast in trenches or
holes drilled in the earth, the firstfloor
slab is cast on the grade at the
ground level, and the soil removed
below it. If required, the foundation
is braced with cross-lot blocking or
rakers and walers as the earth is
excavated below the slab, exposing
the foundation wall. Intermediate
floor slabs are cast as the earth is
excavated, eliminating the need for
bracing.
Bottom-up is the most common form
of construction and requires that the walls
that support the excavation be braced
either internally by structural members or
tied back into the surrounding earth.
Earth Retention Systems
Earth retention systems are not standardized
within the United States or in a
particular state. They are typically custom
systems, depending on the local experience
of the contractor, site conditions, availability
and cost of materials, and the amount of
shoring that may be required.
These systems may be designed to
both support the excavation and serve as
the foundation wall or only to support the
excavation and minimize the inward flow of
groundwater. In the latter system, the components
are socketed into the earth or rock
to create a dam.
Common earth-retention systems are:
• Sheet piles of profiled steel. Sheet
piling was patented in the 1890s
Detailing Basement Waterproofing
2 9 t h RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 2 0 – 2 5 , 2 0 1 4 B u cc e l l a t o a n d He n s h e l l • 1 0 5
and began production
in the early 1900s.
Sheet piling is manufactured
from rolled
steel and can be
purchased in various
shapes. Sheets
are interlocked in a
number of ways in an
attempt to limit the
passage of water and
soil particles.
• Trench boxes are
steel fabrications
that are installed
into the trench and
dragged along with
the excavation. The
walls are constructed
from sheet steel and
braced apart with
steel tubes. The box
protects workers in
the trench and the
work under construction
that could be
damaged from collapse.
• Soldier piles and lagging.
This is the most
common shoring solution in urban
areas. Piles are vertical, H-shaped
structural sections or pipes closely
spaced with wood members connected
to them as the earth is
removed.
• Secant piles are cast-in-place concrete
in drilled holes designed as
interlocking tubes or cylinders.
Every second tube or cylinder is
reinforced with a wide-flanged steel
section or, alternately, with a reinforcing
steel cage. The inboard faces
can be cut back to the face of the
steel pile flanges, or a concrete or
sand wall installed over them. The
reinforced piles are called “primary”
piles, and the intervening piles, “secondary”
piles.
• Drilled/concrete soldier piles.
These are drilled steel tubular piles
that are to be filled with concrete.
The cylinders are closely spaced,
and shotcrete or sand walls are
installed on the inboard faces to provide
a smooth substrate to receive
the waterproofing.
• Slurry or diaphragm walls are constructed
of bentonite/cement for
cutoff walls or cast-in-place concrete
for structural walls as panels with
interlocking ends that may incorporate
waterstops. They can serve
a dual purpose of shoring the site
during excavation and acting as a
permanent wall once construction is
complete.
• Precast concrete panels installed
in excavated trenches.
• Soil nailing/shotcrete. Soil nailing
consists of inserting slender
reinforcing elements into the soil.
The reinforcing is installed into
predrilled holes and then grouted.
Shotcrete (pneumatically applied
concrete) is then applied over the
surface to act as a rigid facing. The
terms “soil nails,” “rock anchors,”
“soil anchors,” and “tiebacks” are
sometimes used interchangeably.
Other types of retention systems that
are not detailed in this paper include timber
shoring, churn-drilled soldier piles, wet-set
soldier piles, and cylinder pile walls, to
name a few.
Sometimes several earth retention systems
may be used in the same excavation.
COMPON ENTS OF EARTHRETAINING
SYSTEMS REQUIRING
SPECIAL DETAILING
Some components require details that
are fundamental to all projects but are not
discussed in this paper. These include:
• Membrane transitions between pressure
slab and foundation walls
• Transitions between underslab
membrane and pits
• Terminations at the top of foundations
and grade beams
• Transitions between preapplied and
postapplied membranes
With the exception of top-down basement
construction, components of the
earth-retaining system require bracing to
resist earth and water pressures. Generally,
these are temporary and are removed during
the construction of the basement walls.
The components of the bracing systems
almost always penetrate the membrane and
require special details to maintain their
watertight integrity.
1 0 6 • B u cc e l l a t o a n d He n s h e l l 2 9 t h RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 2 0 – 2 5 , 2 0 1 4
Figure 1 – Detail of a raker.
TYPICAL EARTH-RETENTION
BRACING SYSTEMS
Tiebacks or Soil Nails
Tiebacks are rods or a bundle of strands
that are placed in cored holes outboard of
the foundation. The end that is buried in
the earth is grouted into place. The tie is
connected to an angle that spans between
soldier piles, welded to sheet piling or to
bearing plates cast into slurry walls.
Ties are usually left in place after the
building is completed. Care must be used
in installing ties when there are utilities
outboard of the foundation or adjoining
buildings.
The inboard end of the strand ties is
jacked to provide the requisite tension and
secured to head plates.
The ends of rods are also jacked and
secured with nuts and washers. Strands
and rods projecting beyond the base plate
are removed, but the plates, nuts, and
washers remain. Since they project through
the waterproofing, they must be boxed-in
to maintain the watertight integrity of the
membrane.
Rakers
Rakers (Figure 1) are
structural steel-rolled
shapes installed as
angled braces with the
top secured to the earthretaining
system and
the bottom to anchors
installed in the pressure
slab or, more frequently,
to a block of concrete
located at or below
the pressure slab. This
block is called the heel
block or foot block and
is installed prior to the
pressure slab. When the
foot block is below the
underslab membrane,
the raker will penetrate
it. The penetration usually
is made through a
block-out in the pressure
slab. Sometimes,
the foot block can be
incorporated in the pressure
slab and the membrane
carried under it.
After the pressure slab is
cast, the raker is burned
off at or below the floor
level, the waterproofing is patched, and the
block-out is filled in.
At the top, the raker is usually connected
to an angle spanning between two
soldier piles. Sometimes it is connected
directly to the face of the soldier pile. If the
earth-retaining system is set outboard of
the foundation wall, the raker may pass
through it in a block-out or connected to
a steel brace extending through the wall.
Sometimes the raker is connected to a
waler.
Rakers are cut off or burned off after the
foundation is cast. The heat from torches
may melt heat-sensitive membranes, and
the removal protocol should be reviewed
and discussed at the prewaterproofing
meeting.
Walers
Walers are horizontal, wide-flange
beams connected to the earth-retaining
system that are usually continuous around
the basement walls. They are held in position
with rakers and diagonal beams at the
corners and may also be braced with crosslot
blocking.
Walers may be left in place and buried
in the foundation wall (holes are cut to
permit the passage of vertical rebars), or
burned off or partially burned off where
they encroach on the interior face of the
finished foundation wall. If the waler is
installed on the inside of the earth-retaining
system, the structure can be constructed by
boxing out around it.
Cross-Lot Blocking
Cross-lot blocking (Figure 2) is accomplished
by installing large-diameter pipes
that span between opposing foundation
walls, often located at the top of the excavation
or at every horizontal construction
joint. They are welded to the walers and
removed after the foundation wall is cast.
Brackets that connect the pipes to the
earth-retention system may be left in place
and cut off at the face of the foundation.
PENETRATION S
The authors recommend that a single
drawing of the points of entry (POE) be
prepared for all penetrations through the
waterproofed components. These should
contain a plan and foundation wall elevations
and include all MEP piping with sleeve
2 9 t h RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 2 0 – 2 5 , 2 0 1 4 B u cc e l l a t o a n d He n s h e l l • 1 0 7
Figure 2 – Cross-lot blocking is accomplished by installing large-diameter pipes spanning opposing
foundation walls.
sizes. These penetrations, more often than
not, occur at varying elevations through
the foundation wall. They may occur at the
transition between preapplied and postapplied
waterproofing.
There are frequent penetrations through
the membranes applied to the pressure
slab and the foundation wall. These are
not always indicated on the drawings; and
some, like well points, may come as a surprise
to the designer. All of these require
special details.
Most often, water leakage occurs at
penetrations. It is desirable, therefore, to
minimize them by incorporating pits and
piping into the thickened or depressed pressure
slab.
Penetrations Through the Pressure Slab
Penetrations that frequently occur
through the pressure slab include:
• Caissons and pile caps that don’t
penetrate the slab, but which interrupt
the membrane under it. (Not
usually indicated on the contract
documents are special foundations
for construction cranes.)
• Rock anchors
• Lightning ground rods, as well as
the building’s electrical grounding
systems
• Well points
• Drains and cleanouts
• Pits such as sumps and elevator pits
• Foot blocks or heel blocks, which
have been discussed previously
• H ydraulic elevator pistons
While the basement is under construction
and the dewatering system is operational,
the weight of the foundation and
pressure slab holds it in position. However,
when the pumps are turned off, the basement
will have a tendency to float or rise
vertically. As the superstructure is constructed
above, the imposed dead load will
cause the basement to settle back down.
Where the basement is not constructed
on rock, some movement (generally in the
range of 1 to 2 inches) should be anticipated.
Movement is usually resisted by caissons,
pin piles, or rock anchors to secure
the pressure slab to the strata below and
1 0 8 • B u cc e l l a t o a n d He n s h e l l 2 9 t h RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 2 0 – 2 5 , 2 0 1 4
Figure 3A
and 3B – The
waterproofing
at the top of a
caisson prior
to casting the
grade beam.
either support it or restrain it from floating
when the pumps are shut off. Where they
penetrate the pressure slab and mud mat,
provision must be made to permit differential
movement.
Penetrations Through the
Foundation Walls
Some penetrations through the foundations
are for utilities that require watertight
sleeves when they are below the groundwater
line. These include:
• Sewer and water pipes
• Conduits for power and electronic
cables
Frequently, conduits are ganged, leaving
very little space between them for proper
flashing. These require precast concrete or
heavy-gauge sheet metal manifolds that are
sealed to the foundation and flashed to the
membrane.
Other penetrations are anchors to tie
the foundation back to another wall or to
the soil as discussed earlier.
DETAILS
The following details suggest methods by
which these components and penetrations
of the support-of-excavation systems can
be flashed into the membrane and maintain
their watertightness. They illustrate
general design principles and should be
modified for specific waterproofing systems.
Keep in mind that waterproofing details are
executed prior to installation of the field
membrane. Understanding sequencing is
critical to properly assembling the flashing
components.
Details at Penetrations of the
Pressure Slab With Thermoplastic
and Modified Bitumen Sheets
Figure 3 shows the waterproofing at the
top of a caisson prior to casting the grade
beam. Figure 4 shows a typical rock anchor
or minipile penetrating the pressure slab.
The flashing must be arranged to accommodate
movement between the mud mat
and the penetration.
Lightning-grounding conductors are
usually stranded cables. They cannot be
made watertight where they penetrate
waterproofing membranes, because water
flows between the strands capillarily. A coupling
to transition from a stranded cable to
a solid rod is required (see Figure 5).
Details at Penetrations of the
Foundation Wall With Thermoplastic
and Modified-Bitumen Sheets
Figure 6 shows a typical condition
where lagging is installed behind soldier
2 9 t h RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 2 0 – 2 5 , 2 0 1 4 B u cc e l l a t o a n d He n s h e l l • 1 0 9
Figure 5 – A coupling to transition
from a stranded cable to a solid rod is
required.
Figure 4 – Typical rock anchor
penetrating the pressure slab.
piles. It is not unusual to find that the
lagging has been secured with nails that
are bent over the soldier pile flanges. The
lagging must be boarded out with plywood,
EPS, drainage composites, or a combination
thereof.
Figure 7 shows typical pipe penetrations.
Single-pipe penetrations are not difficult
to solve, but ganged pipes pose a problem.
This often occurs at transformer vaults
where utility companies dictate the conduit
spacing. The pipes or conduits are often
so closely spaced that they are impossible
to flash in the manner illustrated in the
waterproofing manufacturer’s catalogue.
The easiest solution is to provide an assembly
composed of plates with welded sleeves
that can be placed in the form with the
edges flashed into the wall. Care must be
taken to avoid interrupting the rebar cages
and to provide a frame to support the wall
construction.
Pipes and
conduits are
inserted in the
sleeves and made
watertight with
a series of rubber
modular
seals that are
tightened with a
wrench to form
a watertight seal
in the annulus
around the pipe.
See Figure 8.
Figure 9
shows a typical
tie-back penetration.
This may vary depending on whether
the tie is a tension rod or cable strands. In
either case, the tie will remain in place during
the life of the building
and must be flashed into
the wall waterproofing
system. This is usually
accomplished by covering
the tie with a prefabricated
wood or metal
box and flashing the box
at the perimeter. There
are some manufacturers
that market factory-fabricated
tie-back covers
for this detail. The onesize-
fits-all covers may
not be as flexible as the boxes fabricated by
the waterproofing contractor.
Figure 1 (page 106) shows a typical
condition where the raker penetrates the
pressure slab and underslab waterproofing.
If possible, the SOE contractor should be
encouraged to eliminate the penetration of
the membrane by one of the following:
• Raise the foot block so that the top
is above the underslab membrane.
• Depress the mud mat and thicken
the pressure slab to absorb the foot
block.
• Cast a section of the pressure slab
and provide bolted angles to anchor
the bottom end of the raker.
1 1 0 • B u cc e l l a t o a n d He n s h e l l 2 9 t h RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 2 0 – 2 5 , 2 0 1 4
Figure 6 – Typical condition where lagging is
installed behind soldier piles.
Figure 8 – Pipes and conduits are inserted and
sealed with rubber modular seals.
Figure 7 – Typical
pipe penetrations.
When these steps are not implemented,
the penetration of the bottom of the raker
must be flashed into the underslab membrane.
1. The raker is boxed out with metal
and the flanges are flashed into the
membrane. The void formed by the
metal box is then filled with quicksetting
grout.
2. Alternately, the raker is flashed to
the membrane using tapes and the
liquid component of the membrane
system.
Walers pose another problem. If they
are held off from the earth-retaining system,
the stand-offs must be boxed in. The
problem when cross-lot blocking or walers
are to be removed is to avoid damage to the
flashing from the heat of the cutting torch.
This requires careful sequencing and, often,
repairs, after the steel members are burned
off.
Often, the problems can be resolved by
staging the backfill or installing upper and
lower tiers of rakers and walers. By selectively
removing upper and lower tiers and
providing interim bracing with berms, the
earth-retaining wall is made available to
hang the waterproofing. One SOE contractor
used the following sequence:
1. Install walers and cross-lot blocking.
2. Excavate to subgrade, leaving
required berms against sheeting to
allow installation of lowertier
bracing.
3. Pour a section of mat slab in
the middle of the excavation,
and install upper tier bracing.
(The base of the raker is
braced against this slab.)
4. Excavate to subgrade
around perimeter, and pour
mat slab extending to the
earth-retaining system.
5. Remove lower-tier bracing
(install waterproofing), and
pour lower tier wall.
6. Rebrace lower pour wall,
and remove cross-lot bracing.
Install waterproofing.
7. Pour upper-tier wall.
Another method is to locate
the walers above an intermediate
basement slab. The waterproofing
is then carried up the foundation wall to
the bottom of the waler, and the slab is cast
against it. The waler is then removed, and
the waterproofing is continued.
The above strategies should be reviewed
when the excavation contractors are interviewed.
Waiting until the prewaterproofing
conference may be too late.
SUMMARY
Maintaining continuity of waterproofing
is critical when it is penetrated by
permanent and temporary components of
the earth-retaining system. Prudent waterproofing
designers should get involved early
in the process of selecting excavation contractors
to minimize problems that arise
from the support of excavation systems.
They should acquire SOE drawings prior
to detailing the membrane to make certain
that all conditions have been addressed and
to ensure that the watertight integrity of the
waterproofing membrane is maintained.
2 9 t h RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 2 0 – 2 5 , 2 0 1 4 B u cc e l l a t o a n d He n s h e l l • 1 1 1
Figure 9 – Typical tie-back penetration detail.