Effective Utilization of Mock-Ups Within The Building Envelope Commissioning Process

April 26, 2009

ABSTRACT
One aspect most critical to the building
envelope commissioning process is mockup
evaluation. To accurately assess the
design aspects of any component, assembly,
or system prior to installation at site,
mock-ups of the key system details should
be constructed for review and testing by the
commissioning authority for compliance
with the owner’s performance requirements
(OPR), basis of design (BOD), and contract
documents. It is critical that each mock-up
installation be representative of the performance
requirements specified for the project
and the quality standard of the future
construction. While that concept seems
simple, the mock-up phase remains one of
the more misunderstood and misapplied
processes during building envelopecommissioning,
such that the full benefits
offered through mock-up evaluation are
often not realized.
This paper will examine numerous
aspects of the mock-up evaluation as it pertains
to the commissioning of building envelope
systems, including: how and what to
specify, selection of components and
assemblies, procedures for constructing,
available test methods and procedures,
interpreting test results, and resolving performance
problems. Additionally, this paper
identifies the different types of mock-ups
(including the pros and cons of each and
how to determine where each is applicable)
and the difference between functional and
aesthetic mock-ups.
INTRODUCTION
One of the most significant advances in
the construction industry over the past several
years has been the increased recognition
of whole-building commissioning as an
effective tool to aid in the assurance of
building performance over its expected life
cycle. The National Institute of Building
Sciences (NIBS) Guideline 3-2006, Exterior
Enclosure Technical Requirements for the
Commissioning Process, refers to commissioning
as “a quality-oriented process for
achieving, verifying, and documenting that
the performance of facilities, systems, and
assemblies meets defined objectives and
criteria.”
Commissioning of a building system can
be defined as a systematic process of ensuring
that the building system performs interactively
according to the designer’s design
intent and the user’s occupational requirements,
through verification of the system’s
performance during the construction period.
Historically, commissioning has been
associated with a building’s mechanical
systems. However, the demand for improved
energy efficiency and longer life cycles in
today’s buildings led to the development
and implementation of whole-building commissioning,
which specifically focuses on
the building envelope. Indeed, with building
owners, design professionals, and contractors
having a greater awareness of the bene
fits that a building envelope-commissioning
program can provide, it is not surprising
that the inclusion of building envelope commissioning
in commercial construction project
specifications continues to increase in
prevalence.
The building envelope-commissioning
process commences at BOD and continues
through the duration of the project to completion
and, in some cases, beyond completion.
For simplicity, the tasks comprising
the process are often separated into the following
phases:
• Predesign
• Design
• Preconstruction
• Construction
• Operations and maintenance (O&M)
The objectives of the building envelopecommissioning
process are driven by build-
18 • I N T E R FA C E F E B R U A RY 2010
This article was originally published in the Proceedings of RCI, Inc.’s October 26-27, 2009,
Building Envelope Technology Symposium in San Diego, CA.
ing type, expected life cycles, geographic
location, climatic considerations, desired
energy efficiency, budgetary constraints,
and tolerance for leakage, all of which may
vary considerably among projects. While the
precise tasks comprising the commissioning
process will differ from project to project,
Annex F of the NIBS Guideline 3-2006
contains a fairly comprehensive list of the
roles and responsibilities that remain consistent
throughout the commissioning
process.
To date, the majority of research and
development in building envelope commissioning
appears to have focused primarily
on either the design phase, through drawing
and specification review, or the construction
phase, by inspection and testing
the as-built construction. However, numerous
issues that may arise during construction,
such as applicator skill level, site conditions,
material incompatibilities, scheduling
or sequencing conflicts, and confusion
or disagreements over testing procedures,
can be eliminated through proper commissioning
procedures conducted during the
preconstruction phase of the project.
Specifically, the utilization of mock-ups and
the construction, inspection, and testing
thereof, can significantly reduce the number
of issues encountered during the construction
phase.
MOCK-UP OBJECTIVES
Mock-ups are full-sized structural models
made with the exact construction techniques,
materials, and technicians that will
be used on a project, providing the project
team (owner, designer, contractors, consultants)
with the opportunity to assess a
three-dimensional representation of a
design and serving as a means to evaluate
functionality, determine compliance with
project documents, assess aesthetics,
establish quality standards, and enhance
workmanship. A primary mock-up objective
is to address issues prior to construction to
minimize disruption to the critical path of
construction through the following:
• Verifying that design details will
function in accordance with the
design intent by determining performance
characteristics through functional
testing and subsequent comparisons
with project requirements;
• Determining whether the installers
possess the required skill level necessary
to install the components,
assemblies, or systems such that
the as-built construction will satisfy
specified project requirements;
• Providing the opportunity for different
trades to experience the se –
quence of construction and discuss
alternative sequencing options;
• Serving as the benchmark for the
standard of workmanship and aesthetics
to be replicated throughout
the project; and
• Affording an opportunity to recog-
Figure 1 – Mock-up constructed at laboratory of Architectural Testing Inc.
Roofing contractors &
specifiers choose Durapax
coal tar roofing systems.
Coal Tar:
First Choice for Flat Roofs
Durapax:
First Choice in Coal Tar
610.579.9075 Durapax.com
• Coal tar roofing provides low cost and
long life (25+ years)
• Many coal tar roofs last more than
50 years
• Coal tar’s cold flow properties provide
self-healing
• Superior technical & customer support
• Delivery you can depend on
• Comprehensive warranties
• UL & FM approved systems
Specify your next flat roof with a
Durapax coal tar roofing system.
F E B R U A RY 2010 I N T E R FA C E • 1 9
nize and resolve potential areas of conflict prior to the commencement
of construction.
MOCK-UPS AND THE BUILDING ENVELOPE COMMISSIONING PROCESS
Given the ever-growing importance of schedule, increased performance
expectations, the swell of construction litigation, a flood of
new construction products, and diminished experience of the tradesmen,
it should come as no surprise that mock-ups have become
standard practice in most commercial construction projects as a
means to evaluate the design aspects of a system or assembly as it
is to be installed on site. As mock-up evaluation is an integral part
of a complete building envelope commissioning process, it is imperative
that the building envelope commissioning agent (BECA) be
involved in all stages of the mock-up process, from the design phase
through testing and posttest evaluation and troubleshooting. The
BECA should assist the designer in specifying the components,
details, and assemblies to comprise the mock-ups, as well asfdsa the
inspection and testing protocols to which the mock-ups will ultimately
be evaluated.
MOCK-UP TYPES
There are four primary mock-up types that can be considered for
inclusion on projects:
A. Off-site laboratory mock-ups – Full-scale mock-ups constructed,
examined, and tested in a laboratory setting under
controlled conditions (Figure 1),
B. On-site “stand-alone” mock-ups – Freestanding mock-ups
constructed, examined, and tested at the building site (or at
a remote location such as a contractor’s facility) that are built
separately from the building (Figure 2),
C. Integrated mock-ups – Mock-ups constructed directly onto
Figure 4 – Mini mock-up of
air barrier installation.
Figure 2 – Construction of an on-site, stand-alone mock-up.
Figure 3 – Integrated mock-up.
20 • I N T E R FA C E F E B R U A RY 2010
the building structure where, if
deemed compliant to contract documents
after evaluation, they become
a portion of the final construction
(Figure 3), and
D. Mini mock-ups or detail mock-ups
– Small mock-ups for review of
details that could not be included in
the larger, start-up mock-up (Figure
4).
The pros and cons of each of the above
types are identified below:
A. Laboratory mock-ups
Pros:
• As the mock-up is evaluated
long before construction, issues
that arise can be addressed and
rectified with minimal impact to
the construction schedule.
• Construction and evaluation of
the mock-up are performed un –
der controlled conditions.
• It is often more practical to perform
certain tests under laboratory
conditions as opposed to on
site.
• Several conditions that are
remote from each other on the
actual building can be integrated
into a single mock-up.
Cons:
• The transfer of labor and materials
to the laboratory may be
costly.
• The mock-up is constructed
under significant scrutiny such
that the level of workmanship
may be inadvertently raised
compared to the field construction.
• Laboratory mock-ups typically
do not address transitions and
various field conditions that will
involve the coordination of various
trades.
B. Stand-alone mock-ups
Pros:
• Mock-up construction is local
and, therefore, less costly.
• The mock-up can be constructed
prior to the commencement of
site construction, so issues that
arise can be addressed and rectified
with minimal impact upon
the construction schedule.
• It is more practical to perform
certain tests when the mock-up
is freestanding as opposed to a
part of the building structure.
• Several conditions that are
remote from each other on the
actual building can be integrated
into a single mock-up.
Cons:
• The laboratory needs to be
transferred to site and constructed
around the mock-up,
making it more difficult to perform
certain tests.
• There is less control over the
environmental and site conditions,
as the mock-up may be
exposed to climatic conditions,
site security breaches, and damage
from adjacent activities.
C. Integrated mock-ups
Pros:
• The up-front cost to the owner is
typically less than that of laboratory
mock-ups and stand-alone
mock-ups of similar assemblies.
• As the mock-up is a part of the
final construction, the owner is
not paying for the same assembly
twice.
􀁳􀀀􀀬􀁅􀁁􀁋􀀀􀁐􀁒􀁏􀁏􀁆􀀀􀁒􀁏􀁏􀁆􀀀
􀁃􀁏􀁎􀁎􀁅􀁃􀁔􀁉􀁏􀁎􀀌􀀀􀁏􀁖􀁅􀁒􀀀
􀀒􀀑􀀌􀀐􀀐􀀐􀀀􀁉􀁎􀁓􀁔􀁁􀁌􀁌􀁅􀁄􀀀
􀁎􀁁􀁔􀁉􀁏􀁎􀁗􀁉􀁄􀁅􀀀􀁗􀁉􀁔􀁈􀁏􀁕􀁔􀀀
􀁁􀀀􀁓􀁉􀁎􀁇􀁌􀁅􀀀􀁌􀁅􀁁􀁋
􀁳􀀀􀀰􀁒􀁅􀀍􀁅􀁎􀁇􀁉􀁎􀁅􀁅􀁒􀁅􀁄􀀀
􀁆􀁏􀁒􀀀􀁁􀁎􀁙􀀀􀁗􀁉􀁎􀁄􀀀􀁌􀁏􀁁􀁄
􀁳􀀀􀀭􀁏􀁄􀁕􀁌􀁁􀁒􀀌􀀀
􀁂􀁏􀁌􀁔􀀍􀁔􀁏􀁇􀁅􀁔􀁈􀁅􀁒􀀀
􀁄􀁅􀁓􀁉􀁇􀁎
􀀣􀁁􀁌􀁌􀀀􀁕􀁓􀀀􀁔􀁏􀁌􀁌􀀀􀁆􀁒􀁅􀁅􀀀􀁁􀁔
􀀘􀀖􀀖􀀍􀀲􀀯􀀯􀀦􀀳􀀣􀀲􀀥􀀥􀀮
􀀘 􀀖 􀀖 􀀍 􀀗 􀀖 􀀖 􀀍 􀀓 􀀗 􀀒 􀀗
􀁒􀁏􀁏􀁆􀁓􀁃􀁒􀁅􀁅􀁎􀀎􀁃􀁏􀁍
When you really need your
equipment covered, call
RoofScreen!
F E B R U A RY 2010 I N T E R FA C E • 2 1
• Integrated mock-ups most accurately
represent real site conditions
and installer capabilities.
Cons:
• It is even more difficult to transfer
the laboratory to the site, as
working on the building structure
may inhibit the practicality
of performing certain tests.
• Often, the mock-up is pushed
back until after the commencement
of building construction,
making issues inherent on the
already installed work difficult
and costly to rectify and disruptive
to the critical path of construction.
• If testing damages a portion of
the final construction, such as
during a structural load test, the
warranty on that work will be
voided or the affected areas re –
placed at a cost to the owner.
D. Mini mock-ups
Pros:
• As they are typically a part of the
final construction, they provide
many of the same benefits as
integrated mock-ups.
• Details that were not included as
a part of the up-front mock-up
but may be prevalent throughout
the building (such as the air
barrier tie-in at the roof-to-wall
junction) can be evaluated.
Cons:
• As they are typically a part of the
final construction, they have
many of the same weaknesses as
integrated mock-ups.
• Typically, only simple, smallerscale
tests are applicable for
these mock-ups.
The type and quantity of mock-ups that
should be specified will vary from project to
project and are dependent upon several factors,
including building type, complexity
and uniqueness of design details, the building’s
intended function, life-cycle expectancy,
climatic conditions to which the building
would be reasonably expected to be ex –
posed, owner’s expected level of diligence,
budgetary constraints, and cost to repair.
Typically, the greater the expected performance
level of the building or the greater
the complexity of the detailing, the more
diligent the preconstruction phase of the
commissioning process and, therefore, the
more thorough the mock-up requirements.
To simplify the above, a designer must
ask, “What is the basis of design?” If the
building is the same as the last hundred
built, in the same location and with the
same detailing (for example, a big-box
store), the only significant variable (and
thus the only one being evaluated) is workmanship,
as the details and assemblies
have already been proven. In this case, a
simple on-site mock-up evaluation primarily
consisting of visual examination and simple
testing would likely suffice. A building
with more stringent performance requirements
and higher life-cycle expectancy, but
with simple detailing and components
where feasible, might require greater diligence,
such as a more complex stand-alone
mock-up with a limited number of mini
mock-ups utilized throughout. On a building
such as a hospital or laboratory, with
complex building systems and details and
where the performance requirements are
most stringent and the life-cycle expectancy
at its highest, a diverse and thorough mockup
protocol would be prudent. This might
consist of a complex laboratory mock-up
built far in advance of building construction
and subjected to meticulous examination/
testing, one or more stand-alone or integrated
mock-ups of different assemblies or
systems, and numerous mini mock-ups of
unique details not included in the larger
mock-ups.
It is important also to differentiate
between aesthetic and functional mockups.
Quite often, the designer simply wants
to assess the building aesthetics and calls
for a mock-up to be built to gauge how the
completed building will look by viewing the
color, shape, alignment, or other visual
RCI Foundation Mission
To support research, education, and the dissemination of
information for issues important to the industry.
800-828-1902 www.rcifoundation.org
22 • I N T E R FA C E F E B R U A RY 2010
Figure 5 – Aesthetic mock-up to view
appearance of glazing.
characteristics of
the components
comprising the ex –
terior façade. As
performance is sec –
ondary, these
mock-ups are not
tested, though they
can be visually
observed for compliance
to contract
documents. As an
example, an owner
might call for a curtain
wall mock-up
comprising several
glazing sections to
determine whether
the color or shade
of the glass appears
pleasing (Figure 5), without concern at that
time as to whether the curtain wall system
can effectively perform its required functions.
That said, while not its primary purpose,
aesthetic mock-ups can provide the
project team with an opportunity to observe
the sequence of construction and, to a
degree, evaluate the function of the details,
even in the absence of performance testing.
SPECIFYING THE CONSTRUCTION AND TESTING OF
MOCK-UPS
The designer will typically specify the
requirement for the construction and testing
of mock-ups during the building envelope-
commissioning phase. A crucial function
of the BECA is to assist the designer in
developing a mock-up construction-andtesting
protocol that ensures that the intent
of the designer’s specifications and requisite
quality assurance program are achieved.
Specific components to be included, the
F E B R U A RY 2010 I N T E R FA C E • 2 3
Figure 7 – On-site air infiltration
testing of window-wall mock-up.
Figure 6 – Window-wall “mockup”
that was quite different
from the designer’s intent.
number of mock-ups, performance requirements,
test parameters, and other requirements
specific to a particular component or
assembly are included in the corresponding
sections of the specifications. It is imperative
that the specifications be precise in
what is being requested for the mock-up so
that there is no misinterpretation of the
contractor’s responsibilities and so that
what is constructed is a reasonable representation
of the future work as it is to be
installed on site (Figure 6).
While mock-up installations can be
specified for any component or assembly,
when it comes to functional-performance
testing of mock-ups of building envelope
systems, we are primarily referring to the
testing of window/curtain wall assemblies
(and other fenestrations) or the opaque wall
systems and their ability to perform the
four key functions of building envelope performance:
control of air movement, control
of vapor diffusion, thermal performance,
and water management, while withstanding
the structural loads under which they can
be reasonably expected to be exposed.
ASTM E20991 describes procedures and
documentation to assist the design team in
specifying and evaluating preconstruction
laboratory mock-ups of exterior wall systems
by addressing mock-up design and
construction, evaluation and test result
analysis, and procedures for documentation
www.rci-online.org
24 • I N T E R FA C E F E B R U A RY 2010
Figure 8 – Laboratory dynamic water penetration testing of mock-up window-wall section.
throughout the mock-up process. This
standard places an emphasis on the coordination
needed between the key parties by
providing a protocol for exchange of information
between said parties.
On laboratory mock-ups or larger freestanding
or integrated mock-ups, it is common
to find multiple assemblies, such as
window and opaque wall, contained in a
single mock-up. This allows for testing not
only of multiple assemblies under a single
protocol, but also of the interface between
the assemblies. In fact, when citing a building
envelope mock-up, one is most commonly
referring to a mock-up containing
both a window unit or curtain wall section
and the adjoining opaque wall and its typical
components (air barrier, masonry ties,
insulation, etc.).
While precise combinations of test
methods and sequences can be many, typical
testing on a window-to-wall laboratory
mock-up includes air infiltration (Figure 7),
static and dynamic water penetration
(Figure 8), thermal cycling, condensation
resistance, interstory drift, and design load
and structural overload tests (typically 1.5
times the design load). Depending on project
requirements, additional or different
tests may be added to the basic sequence.
Air infiltration and the static and dynamic
water penetration tests are often repeated
upon completion of many of the tests listed
above to verify the influence of these tests
on the overall performance. For example, a
building’s thermal movement, caused by
heating and cooling the structure, is often
simulated on the mock-up, followed by airinfiltration
and the static and dynamic
water-penetration tests.
Often, additional “visual” tests are
incorporated into the test sequence to aid in
interpreting the test results. Airtightness
“smoke” tests, qualitative testing conducted
using a smoke candle in conjunction with
pressurization or depressurization of the
test enclosure, are often performed in conjunction
with quantified air-infiltration testing
in order to identify precise air-leakage
paths or identify system point failures.
Other, simpler tests or tests specific to a
particular component such as membraneto-
substrate tensile adhesion or airtightness
testing of membrane seams and penetrations,
can also be incorporated into the
test protocol on large mock-ups to provide
additional diligence or to be used as the primary
means of performance evaluation on
integrated mock-ups and mini mock-ups.
Test methods commonly utilized during
testing of mock-ups of building envelope
components are identified in Table 1.
ANALYSIS OF TEST RESULTS
The significance of the involvement of
the BECA during the mock-up process
becomes most apparent during analysis of
failure. In the case of a failure, it is the role
of the BECA to assist the designer and contractors
in determining the cause of that
failure, be it installation, materials, design,
or other factors. Assessing the direct cause
of failure in a multiassembly mock-up is
often difficult, and success of failure analysis
relies on the BECA’s experience and
understanding of the following:
• Material composition, installation,
and design of all of the different
Table 1 – Test methods commonly utilized in window/curtain wall or opaque wall mock-up testing.
TEST CRITERION TEST STANDARD
Airtightness (lab) ASTM E283, Standard Test Method for Determining Rate of Air Leakage Through Exterior
Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the
Specimen
Airtightness (field) ASTM E783, Standard Test Method for Field Measurement of Air Leakage Through Installed
Exterior Windows and Doors
Airtightness (field or lab) ASTM E1186, Standard Practices for Air Leakage Site Detection in Building Envelopes and
Air Barrier Systems
Structural integrity ASTM E330, Standard Test Method for Structural Performance of Exterior Windows, Curtain
Walls, and Doors by Uniform Static Air-Pressure Difference
Static water penetration (field) ASTM E1105, Standard Test Method for Field Determination of Water Penetration of Installed
Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform or Cyclic Static Air-
Pressure Difference
Static water penetration (lab) ASTM E331, Standard Test Method for Water Penetration of Exterior Windows, Skylights,
Doors, and Curtain Walls by Uniform Static Air-Pressure Difference
Dynamic water penetration AAMA 501.1, Standard Test Method for Water Penetration of Windows, Curtain Walls, and
(field or lab) Doors Using Dynamic Pressure
Membrane-to-substrate tensile ASTM D4541, Standard Test Method for Pull-Off Strength of Coatings Using Portable
strength (field or lab) Adhesion Testers
Condensation evaluation Controlled interior and exterior temperatures on finished interior and exterior wall components
(field or lab) to evaluate wall cavity temperatures and locate dewpoint
Interstory drift (field or lab) AAMA 501.4, Recommended Static Test Method for Evaluating Curtain Wall and Storefront
Systems Subjected to Seismic and Wind-Induced Interstory Drifts
Thermal cycling (field or lab) AAMA 501.5, Test Method for Thermal Cycling of Exterior Walls
Airtightness (field) ASTM E783 (modified for opaque wall evaluation), Standard Test Method for Field
Measurement of Air Leakage Through Installed Exterior Windows and Doors
F E B R U A RY 2010 I N T E R FA C E • 2 5
assemblies;
• The different diagnostic tools and
equipment available, as well as the
associated limitations of each; and
• How the interaction of the different
assemblies affects overall performance.
The interaction of assemblies is often
complex and may be counterintuitive. For
example, mock-up test results for Assembly
B may be influenced by the presence of
Assembly A. Specifically, the presence of
Assembly A leads to a failure of Assembly B,
where under normal testing parameters,
each of the two assemblies would pass if
tested independently. Consider a mock-up
composed of a curtain-wall section and an
adjoining metal-panel wall assembly subjected
to air- and water-penetration testing,
where the test results show the total
air/water infiltration through the curtainwall
system has exceeded the allowable. Is
there, in fact, a breach within the curtainwall
system, or are the curtain-wall test
results presenting symptoms from a breach
within the interface between the assemblies
where the air/water infiltration would not
be present if the curtain-wall section were
tested as a stand-alone system?
While the
BECA’s involvement
in analysis
of test failures
may be apparent,
what may
not be as obvious
is the need
for proper analysis
of “positive”
test results. In
order to pass,
the mock-up test
results must
satisfy the specified
performance
requirements for
the project. But even test results that
appear to be compliant to project requirements
need to be analyzed to ensure that
they are truly representative of system performance.
If the concentration of a deficient
condition is significantly less on a mock-up
than on the intended as-built construction,
failures could be observed at site but not on
the test mock-up. (Figure 9).
This phenomenon was recently ob –
served on a window/wall mock-up for a
high-performance laboratory, where the
results of airtightness
testing conducted
in general
accordance with
ASTM E783, Stan –
dard Test Method
for Field Measure –
ment of Air Leakage
Through Installed
Ex terior Windows
and Doors, showed
that the measured
air-flow rate for
both the window
(0.011 cfm/ft2 at
1.20 in water) and
opaque wall (0.008
cfm/ft2 at 0.03 in water) fell within the
allowable leakage rates of 0.2 cfm/ft2 at
1.20 in water and 0.020 cfm/ft2 at 0.03 in
water, respectively. However, qualitative airtightness
smoke testing conducted on the
sample in general accordance with ASTM
E1186, Standard Practices for Air Leakage
Site Detection in Building Envelopes and
Air Barrier Systems, Method 4.2.6, showed
the air infiltration was concentrated at the
plenum area above the soffit, an area representing
approximately 20% of the opaquewall
sample. In other words, the air infiltration
localized to an area representing 20%
of the sample was accounting for 40% of the
total allowable air leakage for the entire
sample area. In this case, the results of the
mock-up hinge on the amount of square
footage that each assembly is allotted in the
mock-up.
On a similar window/wall mock-up, the
measured air-flow rate was found to be
approximately 80% of the allowable for the
test area, signifying a “pass” result. Upon
further analysis of the test sample, it was
determined that the leakage was occurring
at breaches in the seals at masonry tie locations,
and that only 16% of the masonry ties
in the test sample were leaking. That is, a
failure rate of only 16% in one component
was accounting for 80% of the allowable air
leakage for the whole sample. Hence, the
concentration of deficient conditions has a
direct correlation with the results of the
mock-up testing and the relevance in representing
field-installed performance.
LESSONS LEARNED
Ultimately, the desired result from
mock-up evaluation is to be able to take a
proven assembly or system and replicate its
installation onto the building. Lessons
RCI, Inc. 800-828-1902 www.rci-online.org/international-convention.html learned during mock-up construction and
25th RCI International Convention & Trade Show
Exploring the Sustainably Built Environment
March 25 – 30, 2010
Rosen Shingle Creek Resort
Orlando, Florida
30 Hours of Continuing Education | Learn Advanced Knowledge from Leading Experts
Educational Programs – Continuing Educational Credit
Attendees will receive Continuing Educational Hours (CEHs) from RCI.
Additionally, each educational program is registered to provide Learning Units from the American Institute of Architects (AIA).
Trade Show – Continuing Educational Credit
Earn CEHs for attending the RCI Trade Show. Attendees will earn 1.0 CEH for spending up to three hours on the trade show floor.
Attendees who spend more than three hours at the trade show will receive 2.0 CEHs.
Networking Opportunities | Trade Show | Keynote Speaker: Chuck Todd | Golf Tournament
26 • I N T E R FA C E F E B R U A RY 2010
Figure 9 – Qualitative airtightness smoke test
showing concentration of air leakage over
small area on a mock-up where quantitative
airtightness-test results indicated a “pass.”
evaluations are transferred to the job site
such that mistakes made during the mockup
phase are not repeated during actual
site construction. This speaks to several
important notions:
• As much as is practically possible,
the mock-up must be representative
of the site conditions. The mock-up
should be constructed by the same
personnel who will be erecting the
assembly or system on the project,
overseen by the key personnel who
will be acting as site supervisors
during actual construction, and
using the same materials, by type
and brand, that will be used on the
on-site installations.
• Mock-up testing procedures should
verify compliance with all of the
owner’s performance requirements,
not just select test procedures that
are easy to complete and that have
little relevance in simulating actual
performance.
• The goal of the mock-up should not
simply be to pass, but rather to pass
the first time using reasonable construction
practices and, in the case
of a failure, determine the cause of
that failure and adjust the design,
materials, and/or installation practices
accordingly. Too often, a mockup
fails initial testing and, rather
than assessing the cause of failure,
the mock-up is simply (in the case of
excessive air leakage, for example)
“patched up” and retested, with this
sequence of events continuing until
a pass result is finally achieved. The
same flawed practices are then carried
over to the site, resulting in
installations that do not satisfy project
specifications.
• Documentation is a key link in
ensuring that lessons learned during
the mock-up phase are carried
through to actual building construction.
ASTM E2099 requires that the
contractor provide shop drawings
that report all modifications made
during the mock-up process for
approval by the designer, with all
changes clearly noted. What is gradually
becoming common practice is
for the contractor to develop an
assembly manual whereby the specific
installation procedures utilized
on the mock-up can be accurately
repeated on site.
The combination of the growing complexity
of building envelope design, increasing
numbers of different construction materials,
the shrinking of schedules, increasingly
stringent performance demands, and
the need to construct energy-efficient buildings,
has led many building owners, designers,
and contractors to adopt building envelope
commissioning as a means to ensure
that the building envelope is constructed to
meet the design intent, expected service life,
and code requirements, and to aid in the
prevention of complications that otherwise
might arise during the construction pro –
cess. A well-designed and accurately de –
fined preconstruction phase that includes
relevant mock-up testing evaluation can be
an important tool in the arsenal of the
building envelope commissioning process
as a means to evaluate the design aspects of
a system or assembly as it is to be installed
on site.
REFERENCES
F. Aldous, J.J. Godfryt, and D.J.
Lemieux, “Building Enclosure Com –
mis sioning – A Review of ‘Com mis –
sioning Under the Influence,’ ” Na –
tional Conference on Building Com –
missioning, April 22-24, 2008.
S.P. Bentz and M. Howell, “Minimizing
Risk with Mock-ups,” Applicator,
29.3, Sealant Waterproofing & Res –
toration Institute, 2007.
S. Hodas, “Preconstruction Mock-ups
for Construction Are Becoming In –
dustry Standard Procedure,” New
England Real Estate Journal, 2007.
B.S. Kaskel and T.R. Wegener, “Building
a Better Wall System: The Appli –
cation of ASTM E2099, Standard
Practice for the Specification and
Evaluation for Preconstruction Lab –
oratory Mock-ups of Exterior Wall
Systems,” Performance of Exterior
Building Walls, ASTM STP 1422,
P.G. John son, Ed., ASTM Inter –
national, 2003.
K.D. Knight and B.J. Boyle, “Com –
missioning Airtight Building En clo –
sures: The Importance of the Pre –
construction Phase Commissioning
Process,” Journal of Building
Enclosure Design, National Institute
of Building Sciences/Building En –
clo sure Technology and Environ –
ment Council, Winter 2007.
K.D. Knight and B.J. Boyle, “Com –
missioning the Building Envelope
for Compliance with Part 5 of the
Test your knowledge of building
envelope consulting with the follow ing
ques tions devel oped by Donald E.
Bush, Sr., RRC, FRCI, PE, chairman of
RCI’s RRC Examination Develop ment
Subcommittee.
Humidity and water
pressure can be very
important elements
that must be
addressed during
the design phase
of building envelope
projects.
1. What is absolute
humidity?
2. What is humidity
ratio?
3. What is specific
humidity?
4. What is relative
humidity?
5. What is water
vapor pressure?
Answers on page 28
F E B R U A RY 2010 I N T E R FA C E • 2 7
National Building Code of Canada,”
Building Envelope Forum, 7th ed.
online newsletter, January 2007.
K.D. Knight and B.J. Boyle, Guidelines
for Delivering Effective Air Barrier
Systems, Canada Mortgage and
Housing Cooperation, Ontario Asso –
ciation of Architects, 2004.
K.D. Knight, J.A. Runkle, and B.J.
Boyle, “Procedures for Com –
missioning Building Envelopes,”
Symposium on Building Envelope
Technology, RCI, Inc., 2008.
D.J. Lemieux and P.E. Totten, “Building
Envelope Design Guide – Wall
Systems,” Whole Building Design
Guide, National Institute of Building
Sciences, 2009.
NIBS Guideline 3, Exterior Enclosure
Tech nical Requirements for the
Commissioning Process, National
Institute of Building Sciences, 2006.
H. Taylor, “Curtain Wall Mock-up Test –
ing,” Journal of Building Enclosure
Design, National Institute of Building
Sciences/Building Enclosure Tech –
nology and Environment Council,
Sum mer 2007.
FOOTNOTE
1. At the time of this writing, a standard
guide for governing the specification
and testing of field exterior
wall system mock-ups for fenestration
air leakage and static air pressure
water penetration resistance
was in development by the American
Society for Testing and Materials
(ASTM).
Answers to questions from page 27:
1. Absolute humidity is the ratio of
the mass of water vapor to the
total volume of the air sample. In
international system units (SI
units), absolute humidity is
expressed as kg/m3. In in/lb
units, it is expressed as lb/ft3.
2. Humidity ratio is the ratio of
mass of water vapor to the mass
of dry air contained in the
sample. In SI units, humidity
ratio is expressed as grams (g) of
water vapor per kilogram (kg) of
dry air.
3. Specific humidity is the ratio of
the mass of water vapor to the
total mass of the dry air. In SI
units, specific humidity is
expressed as kgs of water vapor
per kg of dry air.
4. Relative humidity is the ratio, at
a specific temperature, of the
moisture content of the air
sample if it were at saturation,
and the actual moisture content
of the air sample. It is given as a
percentage.
5. Water vapor pressure is the
partial pressure exerted by the
vapor at a given temperature,
also stated as the component of
atmospheric pressure contributed
by the presence of water vapor.
In in/lb units, vapor pressure is
given most frequently in inches
of mercury (in Hg). In SI units, it
is given in Pascals (Pa).
REFERENCES: Moisture Analysis and
Condensation Control in Building
Envelopes, ASTM Stock Number MNL 40;
Chapter 1 – Moisture Primer by Heinz R.
Trechsel; RCI, Inc. education programs.
Kevin D. Knight is associate director for building envelope
commissioning for Architectural Testing Inc., York, PA. He
has over 20 years of experience in building envelope technology.
He is a contributing editor for the Journal of Architectural
Coatings, is a frequent lecturer on building envelope science,
and has had numerous papers published through the
American Society for Testing and Materials (ASTM), the
Canada Mortgage and Housing Corporation (CMHC), and
architectural and trade journals. Knight currently sits on the
ASTM E-06 subcommittee, is a board member of the Building Environment and
Thermal Envelope Council (BETEC), and is a member of the Society for Protective
Coatings (SSPC).
Kevin D. Knight
John A. Runkle, PE, is the director of forensic services for
Architectural Testing Inc. (ATI) in York, PA, and manages
both a greater Chicago and Los Angeles regional office. These
offices offer both consulting and field-testing services for new
construction, renovations, and litigation projects. Runkle also
worked for a nationally recognized consulting engineering
firm in San Francisco, Los Angeles, and Washington, DC, that
specialized in building façades.
John A. Runkle, PE
Bryan J. Boyle is the operations manager for Retro-Specs
Consultants Ltd., a firm in Winnipeg, MB, specializing in
building envelope commissioning, testing, and diagnostic
investigation. Boyle has over 10 years of experience as a
researcher and technical writer in the building envelope
industry and has had numerous research studies and papers
published through ASTM, CMHC, and other architectural
and trade journals.
Bryan J. Boyle