Skip to main content Skip to footer

Ensuring Installation Quality: Field Testing Methods for Building Enclosure Components

February 21, 2025

Field Testing Methods for Building Enclosure Components

 

THIS CASE STUDY illustrates some of the
testing methods which can be employed
in a new construction project to assess the
adequacy of the installation of the building
enclosure components. The testing techniques
include ASTM D4263, Standard Test Method for
Indicating Moisture in Concrete by the Plastic
Sheet Method (concrete moisture testing);1
ASTM E1186, Standard Practices for Air Leakage
Site Detection in Building Envelopes and Air
Barrier Systems, Procedure 4.2.7, Chamber
Depressurization in Conjunction with Leak
Detection Liquid;2 and dry film thickness
(DFT) measurement. While these field-testing
methods contribute to quality assurance, they
should be viewed primarily as tools for an
evaluation of the adequacy of installation of
certain building enclosure components. By
recognizing potential issues and addressing
them, the project aims to reduce the likelihood
of structural problems, which may lead to
improved energy efficiency and cost savings.
INTRODUCTION
This case study focuses on a four-story surgery
center under construction in Sacramento,
California. The project has a progressive
design-build delivery method, with the
design-builder selected by the owner. The
project’s design phase commenced in late
2021, and the construction phase began in
November 2022. The anticipated substantial
date of completion is July 2025. The facility
will encompass 268,000 ft2 (approximately
24,900 m2), featuring operating rooms, pre- and
post-operative recovery bays, clinical exam
rooms, clinical treatment rooms, single-occupant
overnight patient recovery rooms, public space,
operations spaces, imaging spaces, physical
therapy spaces, and an administrative support
space to facilitate patient support and education.
Our client, the design team, requested
building enclosure testing and consulting

Ensuring Installation Quality:
Field Testing Methods
for Building Enclosure
Components
Feature

 

By Sadil Eidda, EIT services and provided a matrix of requested
building enclosure testing on a mock-up and
on the building. While our scope of services for
this project included multiple phases and tests,
our focus in this case study will be on some of
the tests that were conducted on the low-slope
roof and the exterior wall fluid-applied air- and
water-resistive barrier (AWRB) to ensure quality
assurance/quality control and support the
long-term performance of the building enclosure
components and systems. It is worth noting that
we did not select any of the test methods, as
other parties, such as the architect of record and
manufacturers, selected the test methods.
The roofing assembly consists of a vapor
barrier that was torched onto a primed
concrete deck. Polyisocyanurate insulation was
adhered to the vapor barrier using a low-rise
urethane foam adhesive with ribbon patterns,
spaced per manufacturer’s recommendations.
The coverboard was then adhered to the
polyisocyanurate insulation using a similar
installation process. Finally, the PVC membrane
was fully adhered to the coverboard using a
bonding adhesive. The substrate of the roofing
assembly consists of a concrete composite
steel deck, providing the necessary structural
support and strength for the roof. The exterior
walls consist of multiple systems including
glass-fiber-reinforced concrete, a metal panel
system, and a curtainwall system.
The testing conducted on the low-slope
roof slab was the ASTM D4263.1 This method
helps detect the presence of moisture at the
Interface articles may cite trade, brand,
or product names to specify or describe
adequately materials, experimental
procedures, and/or equipment. In no
case does such identification imply
recommendation or endorsement by
the International Institute of Building
Enclosure Consultants (IIBEC).
©2025 International Institute of Building Enclosure 34 • IIBEC Interface Consultants (IIBEC) February 2025
concrete surface prior to the installation of
the vapor barrier. It is worth noting that ASTM
D4263,1 has been considered unreliable by
many respected practitioners in the roofing
industry. For example, in the article “Concrete
Deck Dryness,”3 the author has described that
such historical and nonscientific method is
inadequate for determining the dryness of
concrete. This test, however, was included in the
project specifications by the architect of record
and approved by the roofing manufacturer. As
a result, we performed it to meet the project
requirements. Although there are alternative
options for determining the dryness of the
concrete, they may require more setup time,
potentially resulting in an extended schedule.
This testing was performed to confirm dryness
of the concrete surface prior to applying the
vapor barrier as the presence of moisture in the
concrete surface can still impact the installation
of the vapor barrier, including the primer
and adhesive.
Building enclosure performance testing is
typically conducted during the construction
phase of a new building, but it can also be
provided in a retro-commissioning mode for
existing structures when trying to ascertain
the cause of leaks. Thermal transmittance
in poorly insulated buildings results in heat
and energy waste. To detect weak points such
as thermal bridges in a building enclosure,
a leak detection test identifies heat leaks, a
specific type of heat loss. A heat leak is the
phenomenon of unwanted heat transfer through
a building enclosure from inside the building
to the outside, or vice versa. Heat loss also
includes air leakage, where outside air enters
or exits the building and disrupts the indoor
temperature regulation.
In this project, ASTM E11862 focuses on
identifying air leakage locations within the
building enclosure and air barrier system. These
leaks would eventually lead to heat loss or gain.
These test results help avoid unnecessary energy
consumption or waste, saving resources.
Additionally, a DFT test was conducted to
determine if the exterior wall fluid-applied AWRB
met the manufacturer’s required thickness.
DFT testing provides a quantitative testing that
can help ensure that the AWRB thickness is in
conformance with the manufacturer’s installation
requirements and will serve as the air control
layer as intended. Moreover, preventing air
leakage is vital for the performance of the
building, as uncontrolled air movement can
contribute to moisture problems and subsequent
deterioration of building materials.
The condition of the building enclosure
components is important. If any component
is compromised, potential problems will
likely follow. This is where building enclosure
field testing can help detect issues and offer
immediate solutions.
FIELD TESTING PROGRAM
The concrete moisture testing was conducted
using ASTM D4263, Standard Test Method for
Indicating Moisture in Concrete by the Plastic
Sheet Method. This test aims to detect the
presence of moisture in concrete surfaces.
This method helps in determining whether
moisture is escaping the concrete’s surface,
suggesting possible issues with moisture vapor
transmission4 that could affect the adhesion
of adhesives, flooring materials, and coatings.
However, as previously mentioned and noted
by industry professionals, this method has
been criticized for its unreliability. An 18 in.
by 18 in. (457 mm by 457 mm) polyethylene
sheet is placed over the concrete surface by
sealing its edges to conduct the test. The
sheet is taken off after 16 to 24 hours, and the
underside of the sheet along with the concrete
surface are inspected for moisture. Visible
condensation on the sheet or darkening of the
concrete indicates excessive moisture, which
indicates that moisture is being emitted from
the concrete; thus, if the vapor barrier is applied
over the concrete without allowing the concrete
to dry first, it will affect the performance of its
adherence (Fig. 1).
Figure 1. Plastic sheet taped at concrete surface on the roof per ASTM D4263, Standard Test Method for Indicating Moisture in Concrete by the
Plastic Sheet Method.
February 2025 IIBEC Interface • 35
This test was performed on the roof, which
had a footprint of approximately 58,000 ft2
(5,400 m2). The polyethylene sheets were
specified in the project to be placed at fixed
intervals to cover approximately 500 ft2 (47 m2)
(Fig. 2). A vapor barrier was planned to be
installed on top of the concrete slab to prevent
any moisture from passing through once the
slab was confirmed to be adequately dry. This
test helped determine whether any moisture
was being emitted from the concrete’s surface.
Several moisture issues could result from the
moisture absorption by the slab, including
mildew growth, structural problems, and
damage to the roofing materials. Furthermore,
these issues could cause the applied vapor
barrier to debond and fail to adhere correctly to
the slab.
The testing was planned to cover 10 locations
per day, with each location representing about
500 ft2 (47 m2), resulting in approximately
5,000 ft² (465 m2) tested daily. While this
suggests the testing would only take 11 days,
given the total roof area of 58,000 ft2 (5,400 m2),
the actual testing period extended over
2 months due to December weather conditions in
Sacramento, California. Sacramento experiences
hot, dry summers and cool, wet winters, and
frequent rain during this time repeatedly
interrupted the schedule, making it difficult to
conduct tests daily.
On days when rain occurred, all locations
that were tested prior to the rain were retested
afterward, as the concrete surface could absorb
moisture from the rain. Moisture tests would
fail if the concrete surface had not dried fully,
causing condensation to be formed at the
underside of the plastic sheet. On other days,
testing had to be postponed entirely due to
the rain.
The roofer’s schedule required installing
the vapor barrier on 5,000 ft² (465 m2) of dry
concrete surface daily. However, if it rained
between completion of the test and the
installation of the vapor barrier, the concrete
moisture testing would need to be redone, even
if the test had passed earlier that day.
The weather became the main factor in
order to decide whether daily testing would
be performed or not. These weather-related
delays required careful coordination and
scheduling to deal with the changing weather
conditions. The extended time frame helped
in completing the testing effectively by
ensuring that the concrete had sufficient time
to dry and monitoring the moisture level,
thus preventing any moisture issues and
protecting the roofing system.
In order to confirm that the concrete had
sufficient time to dry and to monitor the
moisture, we had to address the concrete
moisture issues in cases where some sections
did not pass the test prior to installing
the vapor barrier, we had two available
options based on the project conditions and
limitations5:
1. Waiting for the concrete to dry out on
its own, which is typically the preferred
method if it does not delay or disrupt other
ongoing work.
2. Dehumidifying, which is typically done by
adding fans to accelerate drying.
The dehumidifying technique was utilized for
this project to keep up with the project timeline
(Fig. 3). The tests performed after implementing
dehumidification passed, as this method
expedited the drying of the concrete.
Moving on from the roof, the exterior walls
were also tested at this new complex. Various
methods were used to test them in order to
ensure quality control and compliance with the
manufacturer’s standards and specifications of
the fluid-applied AWRB membrane, which was
installed on the sheathing.
The Chamber Depressurization in
Conjunction with Leak Detection Liquid test
was conducted following Procedure 4.2.7
of ASTM E1186, Standard Practices for Air
Leakage Site Detection in Building Envelopes
and Air Barrier Systems. This method was
selected by the architect of record because
it is a non-destructive technique that aligns
with the project’s requirements and minimizes
disruption. The purpose of this test was to
detect and locate localized air leakage points
in building enclosures and air barrier systems,
which could potentially help in reducing energy
loss and enhancing indoor air quality.
The testing involved the utilization of the
DeFelsko PosiTEST AIR device, which consists
of a polycarbonate test dome connected to
an electronic unit for depressurization. A test
solution, which consisted of a soapy liquid that
would detect any air leakage, was uniformly
applied to the test location, and then the
Figure 2. Plastic sheets placed at fixed intervals (shown by red arrows).
Figure 3. Fans added around concrete for
dehumidifying purposes (shown by red
arrows).
36 • IIBEC Interface February 2025
test dome was attached to the surface of the
building enclosure at the test location and
securely sealed (Fig. 4). The test area was
depressurized from the normal atmospheric
pressure of 14.7 psi to 0.0725 psi (101,325 Pa
to 500 Pa). In case of failure, bubbles would
be formed in the test solution, and the air
barrier would need to be patched at the leak
location to repair it. This test was done 8 to 10
times at isolated locations at each elevation
of the building, focusing on sheathing joints
and cladding attachments (Fig. 5). The test
was passed at every location we tested during
this project. In other words, no bubbles were
observed throughout the test locations at all
elevations. This test helped in detecting air
leaks, which would have been eliminated
if identified.
While the building may have some level of
air leakage resistance regardless of the test,
identifying and addressing specific air leaks can
lead to more efficient operation of the HVAC
system, eventually leading to energy savings and
comfort for occupants.
Moreover, controlling air leakage is important
for the structural integrity of the building,
as uncontrolled air movement can lead to
condensation when warm air infiltrates cool
areas, increasing the moisture issues and
causing damage to the building materials
over time.
DFT testing was performed at selected
locations on each elevation of the building to
verify the thickness of the coating, which was
applied on top of the sheathing, after it had dried
(Fig. 5). The testing was done at nine locations
at each of the north and south elevations and
three locations at each of the west and east
elevations. The north and south elevations were
divided into three areas based on the completion
of the coating installation, and each area was
assigned three locations to be tested, totaling
nine tests per elevation. For the west and east
elevations, each elevation was treated as a single
area, with three test locations assigned to each.
The assignment of the areas was based on the
differences in the elevation lengths, as the north
and south elevations measure approximately
410 ft (125 m), and the east and west elevations
measure approximately 152 ft (46 m).
This method was selected based on the
AWRB manufacturer’s recommendations that
specified using this test in order to verify the
coating thickness. The test involved taking a 1 in.
by 1 in. (25 mm by 25 mm) cut, including the
sheathing facer, and measuring the thickness
using a caliper. The caliper was applied lightly
so that it would not leave any marks on the
coating.6 The sheathing facer was measured to
be approximately 15 mils (0.38 mm), consistent
with the sheathing manufacturer’s specifications.
The AWRB manufacturer’s minimum
requirement is 17 mils (0.43 mm) DFT at the
cured state.
In Fig. 6, the test result came out to 1.06 mm
(42 mils). Since the cut included the sheathing
facer, which was 15 mils (0.38 mm), the DFT for
the coating alone would be 27 mils (0.69 mm),
which is greater than the AWRB manufacturer’s
minimum requirement of 17 mils (0.43 mm).
Thus, passing the test like the majority of the
other locations that were tested. However,
some of the other results yielded less than
17 mils (0.43 mm). The subcontractor was
instructed to reapply the coating over the
Figure 4. Testing process per ASTM E1186, Standard Practices for Air Leakage Site Detection in
Building Envelopes and Air Barrier Systems. No bubble formation was observed.
Figure 5. Partial view of an elevation prior to the dry film thickness and chamber
depressurization in conjunction with leak detection liquid tests.
February 2025 IIBEC Interface • 37
existing coating, using careful control to
achieve the correct thickness that matched
the AWRB manufacturer’s standards. Ensuring
that the membrane met these specifications
confirms that it will serve as the air control layer
as intended, as the membrane plays a crucial
role in preventing air and water infiltration.
This testing method validated the application
process and confirmed that the installed
thickness meets the AWRB manufacturer’s
specifications.
CONCLUSION
The tests carried out were helpful in assessing
the adequacy of the installation of the building
enclosure components as part of the quality
assurance process. The concrete moisture testing
detected moisture on the surface, which could
affect the roofing system. Early detection allows
for the implementation of preventive measures,
such as using fans to accelerate drying and
ensuring that the vapor barrier is applied only
when the concrete is deemed adequately dry.
Performing the DFT testing at isolated
locations at each elevation confirmed that the
fluid-applied AWRB membrane was applied
to the specified minimum thickness, ensuring
that the membrane was applied in accordance
with the AWRB manufacturer’s standards and
specifications.
The Chamber Depressurization in Conjunction
with Leak Detection Liquid testing confirmed that
air leakage was not present at the test location.
This test showed how effective thorough checks
are in identifying air leakage in specific locations,
which potentially helps in saving energy and
maintaining good indoor air quality.
These tests confirmed that the installation of
the building enclosure components conformed
to manufacturer and industry standards. The
results of these testing methods highlighted the
value of ensuring quality in the installation of
building enclosure components and the role of
quality assurance. While the focus of this article
is on those three tests, it is essential to note that
more comprehensive testing will be conducted
in the subsequent construction phases. These
future tests will further ensure the building’s
performance and address any potential issues.
By proactively assessing building enclosures,
risks are efficiently reduced, and potential
enclosure-related failures are prevented. This
approach helps maintain high construction
standards, enhance quality, increase client
Please address reader comments to
chamaker@iibec.org, including
“Letter to Editor” in the subject line, or
IIBEC, IIBEC Interface Journal,
434 Fayetteville St., Suite 2400,
Raleigh, NC 27601.
satisfaction, and protect against future
issues.
REFERENCES
1. ASTM International. 2018. Standard Test Method for
Indicating Moisture in Concrete by the Plastic Sheet
Method. ASTM D4263-83(2018), West Conshohocken,
PA: ASTM International.
2. ASTM International. 2022. Standard Practices for Air
Leakage Site Detection in Building Envelopes and Air
Barrier Systems. ASTM E1186-22, West Conshohocken,
PA: ASTM International.
3. Mark S. Graham. 2012. “Concrete Deck Dryness:
Alternative Approaches Are Needed to Determine
When Concrete Decks Are Dry.” Professional
Roofing. Rosemont, IL: National Roofing Contractors
Association.
4. Milmar Building Systems. “Roof Vapor Barrier.”
Accessed September 7, 2024. https://www.milmarpolebuildings.
com/roof-vapor-barrier/.
5. Association for Materials Protection and Performance
(AMPP). “Concrete Moisture Testing and Mitigation.”
Accessed September 7, 2024. https://www.
ampp.org/technical-research/what-is-corrosion/
protective-coatings-learning-center/concrete-moisture-
testing-and-mitigation#:~:text=Concrete%20
moisture%20testing%20methods&text=ASTM%20
D4263%20%E2%80%93%20Indicating%20
Moisture%20in,the%20concrete%20indicates%20
excessive%20moisture.
6. Fireshell Coatings. “Coating Measurement
Procedure.” Accessed September 7, 2024. https://
fireshellcoatings.com/wp-content/uploads/2019/03/
Coating-Measurement-Procedure.pdf.
ABOUT THE AUTHOR
Sadil Eidda, EIT, has
been working as a
Restoration Engineer II
at Walker Consultants
in Houston, Texas,
since 2022. She
became involved with
IIBEC in 2020 while
studying at Drexel
University, where she
earned her bachelor’s
degree in architectural
engineering in 2022. Before her current role,
she held co-op positions at Pennoni Associates,
Jacobs Engineering Group, and Trauner
Consulting Services, gaining valuable experience
across a wide variety of projects. In her current
position, Eidda conducts condition assessments
on building envelopes and parking garages,
assists in creating construction documents,
provides construction administration services,
and performs field testing.
SADIL EIDDA, EIT
Figure 6. Passing result in the dry film thickness test.
38 • IIBEC Interface February 2025