Skip to main content Skip to footer

Fasteners and Self-Sealability of Weather-Resistive Barriers

September 2, 2014

BACKGROUND
The basic function of the envelope or
enclosure of a building or structure is to
protect the covered or otherwise conditioned
interior spaces from the surrounding environment.
Basic Exterior Wall Types
Exterior wall types commonly associated
with above-grade, commercial building
enclosure design and construction in North
America can generally be classified as follows:
cavity wall, barrier wall, or mass wall.
For the purposes of this article, the topic
will only include the cavity wall assemblies
(Diagram 1).
Cavity Wall
A cavity wall (also referred to as “screen”
or “drained” wall systems) is considered by
many to be the preferred method of construction
in most climatic zones in North America.
This is due primarily to the pressureequalization
that can be achieved and the
redundancy offered by this type of wall
assembly to resist uncontrolled water penetration.
“Cavity wall” is used more generically
to define any wall system or assembly
that relies upon a partially or fully concealed
air space and drainage plane to resist
water penetration and, depending upon the
design, to improve the overall thermal performance
of the building enclosure. Drained
cavity walls typically include the following
general characteristics:
• An exterior cladding element that is
intended to either shed or absorb the
majority of water penetration before
it enters the cavity spaces of the wall
assembly
• A drainage cavity or air space that is
intended to collect and control moisture
that passes through the exterior
cladding element and to redirect that
water to the building exterior. The
cavity can also facilitate the drying
of a wall assembly.
• An internal drainage plane is intended
to function as the primary line of
defense against water penetration
into the building interior. This plane
serves functionally as the dividing
line between the “wet” and “dry”
zones of the exterior wall assembly.
This layer can be created using
a variety of sheet-goods—sprayapplied,
roller-applied, or trowelapplied
products depending upon
the climate in which the building is
to be located and the desired level
of performance necessary to prevent
condensation and potential biological
growth on the dry side of the
exterior wall assembly.
• An insulating layer, which can be
located inboard, outboard, or a combination
of both, of the internal
drainage plane, depending upon the
geographic region and climate in
which the building is located
The internal drainage plane is either
any element exposed to weather or otherwise
located at the line between the “wet”
and “dry” zones of an exterior wall system.
This plane is generally intended to
be vapor-impermeable, vapor-permeable, or
water-resistant, depending upon wall type,
material selection, and climate. This plane
is designed to move liquid water and/or
condensation downward and outward in
a manner that will prevent uncontrolled
water penetration into conditioned spaces
of a building. In cavity wall construction,
the principal drainage plane and primary
line of defense against water penetration
is located inside the wall cavity, generally
S e p t e m b e r 2 0 1 4 I n t e r f a c e • 2 9
Diagram 1 – Cavity wall.
on the inboard side of the air space (either
directly applied to the outboard surface of
the exterior sheathing layer or, in the case
of insulated cavity walls, on the outboard
surface of the rigid or otherwise moistureimpervious
insulation layer).
CURRENT TRENDS
The composition of exterior building
cavity wall or stud-framed commercial construction
has changed over the years from
the common use of plywood to a significant
and almost exclusive use of glass-faced
gypsum board for the exterior sheathing,
commonly referred to as the “backup wall.”
Terminology for the material applied to the
backup wall or exterior sheathing has also
changed from “dampproofing” to materials
commonly referred to as “weather-resistive”
or “water-resistive barriers” (WRBs) and “air
barriers.” The exterior gypsum sheathing
serves as the substrate for the application
of the WRB at the drainage plane.
The exterior wall assembly has changed
from the application of dampproofing on
exterior sheathing such as traditional bituminous-
based emulsions that were troweled,
rolled, or sprayed onto the backup
wall (Photo 1) to now include elastomeric
sheets, synthetic building wraps, spray-applied
polyurethane foam, rigid foam board,
and liquid-applied synthetic materials that
are either mechanically attached or adhered
to the backup wall.
The use of air barrier materials within
exterior wall assemblies of commercial
buildings, as well as single- and multifamily
housing, has become widespread in the construction
industry as a practice for reducing
heating/cooling energy consumption and
to improve the
overall energy
efficiencies
of buildings.
As defined
by ASTM, an
air barrier is
a “material
or system in
building construction
that
is designed
and installed
to reduce air
leakage either into or through the wall.”
Although the material is selected and used
to reduce air leakage, another primary function
is its ability to restrict water infiltration.
For the purposes of this article, the primary
emphasis will be on liquid-applied (Photo 2)
and self-adhered sheet products, and the
issues associated with permeability of air or
vapor will not be considered.
Air barrier materials have productspecific
properties that must be tested to
ensure they will meet rigors encountered
during their service life and under the buildings’
imposed loads. An air barrier assembly
is a collection of air barrier materials and air
barrier accessories (i.e., sealants, tapes, and
transition membranes) assembled together
to form a continuous barrier to air infiltration
into the conditioned space.
One of the performance characteristics
that the Air Barrier Association of
America (ABAA) requires for fluid-applied
membranes, self-adhered membranes,
and factory-bonded membranes to sheathing
is self-sealability or fastener sealability.
This property is determined by the
test procedure outlined in paragraph 7.9,
Self Sealability (Head of Water Test), of
ASTM D1970 Standard Specification for
Self-Adhering, Polymer-Modified Bituminous
Sheet Materials Used as Steep Roofing
Underlayment for Ice Dam Protection.
This test method specifically refers to
self-sealability of self-adhered sheet-applied
membranes that are commonly used for ice
dam protection in roofing, but it is also used
for testing the performance characteristics
of both liquid-applied and self-adhering
sheet materials in weather-resistive barriers.
The test consists of driving two galvanized
nails positioned 1 to 2 inches apart
through the air barrier material that is
applied to a 3/8-in.-thick by 12-in. x 12-in.
piece of plywood. Then the pointed ends of
the nails are tapped so that the heads of
the nails are backed out approximately ¼
in. from the surface of the air barrier membrane.
A 1-gallon container is attached over
the nail heads and sealed to the air barrier
material applied on the plywood.
A second container is positioned below
the pointed ends of the nails. The upper
3 0 • I n t e r f a c e S e p t e m b e r 2 0 1 4
Photo 1 – Application of emulsion dampproofing.
Photo 2 – Application of liquid-applied WRB.
3 2 • I n t e r f a c e S e p t e m b e r 2 0 1 4
container is filled to a depth of 5 inches with
water (which equates to a 101-mph wind
speed), and the specimen remains in this
position for three days at 4± 2ºC (40 ± 5ºF).
After the test, the lower container, shanks
of the nails, and underside of the plywood
are inspected for the presence of water. The
upper container is removed from the air
barrier material, and then the air barrier is
peeled or removed from the plywood back to
the nails. The underside of the removed portion
of air barrier material is inspected for
the presence of water. Evidence of water at
any of these inspected locations constitutes
a test failure.
CONSTRUCTION
Current construction
practices
of exterior cavity wall
assemblies on commercial
buildings
commonly include
the installation of
glass-faced gypsum sheathing mechanically
attached to light-gauge metal stud framing,
with an air barrier applied over or onto the
gypsum sheathing. A variety of cladding or
finish materials is then installed over the
air barrier. These cladding materials can
include, but are not limited to, such items
as: metal lath and stucco, metal panels on
furring strips, mechanically
attached Exterior
Insulation and Finish
Sysems (EIFS), masonry with metal ties or
anchors, and other similar systems that
require the use of mechanical fasteners to
secure to the structure.
The intention during construction and
as required by manufacturers and code is
to install the various cladding materials
so that fasteners penetrate through the
WRB and gypsum sheathing, and into the
underlying metal-stud framing. However,
this intention is not always achieved due
to dimensional issues or
ill-fated installation procedures.
For example, the various
accessories that are
common in plaster systems
such as prefabricated
sheet metal reveals,
control joints, casing
and corner beads, and
expanded metal latch are
designed to be mechanically
attached to underlying
studs, but often the fasteners
for securing these
components are installed
through the WRB material
and do not penetrate into a
metal stud (Photo 3).
It is believed to occur
Photo 5 – Steel brick tie not conforming to substrate. Diagram 2 – Brick tie color (courtesy of Sto). because of the lack of an
Photo 3 – Holes in sheet WRB from fastener
attachment of lath.
Photo 4 – Brick tie depressed into and damaging WRB.
actual metal stud in the selected fastener
placement location or at an assumed or
believed location of an underlying metal
stud. It may also be that in the haste to
meet critical construction timeframes, the
attention to fastener placement, positioning,
and embedment, and the overall quality
of installations have become diminished.
Furthermore, the fact that these WRB materials
are often promoted as having “self-sealing”
characteristics creates a false sense of
comfort regarding fastener installation.
Unlike securement into a plywood substrate
that has historically been used in
exterior wall construction (particularly
for plaster applications), when a fastener
is installed into and through gypsum
sheathing that does not penetrate into a
sound substrate, the fastener continues
to spin, reaming out the hole. The density
of gypsum sheathing is not substantial
enough to allow the fastener to “bite” and
attain adequate compression against the
WRB material (either liquid-applied or selfadhering
sheets); consequently, the fastener
hole becomes enlarged as the fastener
spins. With a plywood backup, a fastener
could be placed in almost any location to
achieve adequate compression, even though
it may not penetrate into a framing member.
In addition, variabilities introduced during
field installation of fasteners can create
conditions that result in inadequate application.
For example, if the fastener or other
element is not installed straight and true
or is installed over-aggressively, the WRB
can be damaged, which can result in water
leakage, even if the fastener is driven into a
framing member (Photo 4).
Damage to the WRB may also occur due
to poorly installed fasteners, removed fasteners,
or fastener length for attachment of
cladding components exceeding the depth of
the sub-framing member (i.e., hat channel).
When light-gauge steel framing, sub-girts,
hats, and masonry ties are installed on top
of the WRB, and fasteners are secured into
the backup structure, the rigid steel subframing
or steel tie typically cannot conform
to uneven areas in the substrate, and the
fastener cannot develop full compression
against the WRB to achieve an adequate
seal (Photo 5).
Some manufacturers of liquid-applied
WRBs recommend installation of cut strips
of self-adhering sheet between the steel
girt or tie and the WRB to aid in achieving
an adequate seal at fastener penetrations
(Diagram 2).
Additionally, the heads of fasteners may
need to be treated with a dollop of compatible
sealant or trowelable version of the
liquid membrane to provide a more suitable
S e p t e m b e r 2 0 1 4 I n t e r f a c e • 3 3
Photo 6 – Sealant applied over fastener heads securing brick ties.
Photo 7 – Multiple fastener holes in flange of hat channel.
Diagram 3 – Brick tie plan view (courtesy of
W.R. Grace).
3 4 • I n t e r f a c e S e p t e m b e r 2 0 1 4
seal (Diagram 3 and Photo 6). Another practice
could include setting the masonry tie in
“wet” liquid-applied WRB when securing to
the substrate.
Once the WRB has been applied over the
sheathing, screw heads used to attach the
sheathing to the studs are concealed and
the actual location of the stud is not readily
visible or known by the installer of the cladding.
Furthermore, if the actual stud placement
varies from the project drawings or
specified spacing due to large or excessive
tolerances or construction variances, then
locating the stud becomes a “hit-or-miss”
target practice by the installer (Photo 7).
CONSTRUCTION OBSERVATIONS
Price Consulting, Inc. (PCI) was involved
in an investigation of a newly constructed
multistory office
building where
water infiltration
had been reported.
The exterior wall construction consisted
of metal stud framing, glass-faced
exterior-grade gypsum sheathing, liquidapplied
air barrier material, metal lath, and
a three-coat Portland-cement plaster. The
plaster system incorporated standard metal
accessories, including control joints, casing
beads, and corner beads. Additional metal
accessories, including expansion joints and
aesthetic reveals,
were also incorporated
into the
plaster. The exterior
walls included
curtain wall
systems installed
in punched openings
in each floor
elevation. Several
of the floors of the subject building had
yet to have their interior finishes completed;
therefore, the backside of the exterior
sheathing was readily accessible and visible
at numerous locations.
Upon initial visual inspection of the
interior, the pointed ends of many screw
fasteners were protruding through the exterior
gypsum sheathing and not penetrating
into any metal stud framing at numerous
locations throughout the floors that did not
have any interior finishes (Photo 8). These
“missed” fasteners were typically located at
Photo 8 – Fasteners missing studs.
Photo 9 – Calibrated water spray rack on wall.
Photo 11 – Water leak at missing fastener
hole in gypsum sheathing.
Photo 10 – Water dripping from fastener
installed through gypsum sheathing.
the reveals and expansion joints in the plaster. Some were located
along corner and casing beads, and others were located in the
field of the wall believed to be for general securement of the lath.
Water spray testing was performed by others using a calibrated
water spray rack as specified in ASTM E1105, Standard Test
Method for Field Determination of Water Penetration of Installed
Exterior Windows, Skylights, Doors, and
Curtain Wall by Uniform or Cyclic Static Air
Pressure, on the subject exterior walls in
an attempt to recreate the leakage that had
recently occurred during rain events (Photo
9).
The spray rack was suspended on the
exterior of the building, and water was
directed onto suspect areas while observations
were gathered in the building interior.
The water spray testing was directed at
various locations, including the punched
window openings, control and expansion
joints in the plaster, and reveals in the plaster.
Water infiltration was observed almost
immediately to within a few minutes after
commencement of the water testing at the
exposed fastener penetrations through the
exterior sheathing at each of the tested
locations.
Further investigation revealed that water
infiltration occurred through the actual curtain
wall systems and at sealant joints at
the perimeters of the curtain wall system
that migrated back to the surface of the
WRB. Unsealed joints in the reveals and
expansion joints were found to be sources
of water infiltration that also migrated
back to the WRB surface. Minor separation
cracks between the plaster and the metal
accessories were also believed to be allowing
similar moisture migration. Regardless of
S e p t e m b e r 2 0 1 4 I n t e r f a c e • 3 5
www.rci-online.org/document-competition.html
DownloaD Your EntrY Form toDaY!
RCI, Inc. 800-828-1902
Entry deadline: October 31, 2014
rCI 2015 DoCumEnt CompEtItIon
Earn rCI Dollars anD othEr InCEntIvEs
The winners of the 2015 RCI Document Competition will receive a plaque and
recognition during the annual awards luncheon at the 30th RCI International
Convention and Trade Show, publicity of their winning projects in Interface,
and RCI Dollars. Prizes will be awarded to nine winners in three categories.
largE projECt | small projECt | rEport
First-place winners ……… 1,000 RCI Dollars
Second-place winners ….. 500 RCI Dollars
Third-place winners …….. 200 RCI Dollars
RCI Dollars will be redeemable for any product or service provided by RCI or
the RCI Foundation. RCI Dollars are redeemable by the award winner or by
anyone specifically designated by the award winner. Use winnings for yourself
or to help a friend or colleague buy a reference book or attend a seminar.
Photo 13 – Holes in WRB adjacent to brick tie.
Photo 12 – Multiple holes in WRB.
3 6 • I n t e r f a c e S e p t e m b e r 2 0 1 4
the source, the moisture manifested itself in
the building interior at the many “unsealed”
fastener penetrations that were not installed
into metal studs (Photo 10).
Other obvious entry points for moisture
were unrepaired small holes through the air
barrier material and sheathing where fasteners
were presumably originally installed
and subsequently removed—apparently due
to their lack of contact with an adequate
substrate (Photo 11).
In the process of performing on-site
inspections for building envelope commissioning
or for general project requirements,
PCI has observed many of the air barrier
conditions noted in this article. One of the
most common issues PCI observed has been
holes in the WRB due to installation and
removal of fasteners and lack of a subsequent
suitable repair (Photos 12 and 13).
Another issue that PCI has observed that
could result in potential water migration is
the placement of horizontally oriented steel
subgirts/framing on top of the WRB. This
placement could create a “damming” effect,
whereupon moisture that accumulates at
the surface of the WRB migrating downward
could be prevented or dammed by the
steel element, allowing the moisture to be
directed and concentrated at the fastener
penetrations. Installing properly positioned
shims between the steel element and the
WRB could create an adequately sealed
drainage plane.
DISCUSSION
ASTM E283, Standard Test Method for
Determining Rate of Air Leakage Through
Exterior Windows, Curtain Walls, and Doors
Under Specified Pressure Differences Across
the Specimen; and E2357, Standard Test
Method for Determining Air Leakage of Air
Barrier Assemblies, go beyond material testing
and measure air leakage through an
assembly of air barrier materials. In doing
so, these tests encompass fastener penetrations—
at least those that exist at the plane
of the air barrier or those that are installed
and can be sealed at the time the air barrier
is being installed. The specimen is a realistic,
8- x 8-ft. wall mock-up, complete with typical
wall penetrations, including a window,
galvanized duct, PVC pipe, post-applied
brick ties, and hexagonal and rectangular
electrical junction boxes (Diagram 4).
Most of the materials that are currently
identified as air barrier materials successfully
pass this test published by ABAA.
However, the test does not encompass
fastener penetrations that are not installed
into a suitable substrate (i.e., metal stud) or
ones that are improperly installed.
The potential for water intrusion
through fastener penetrations—particularly
with claddings like siding, stucco, and
adhered masonry veneer, where thousands
of fasteners can be used to attach the components
through the WRB—can be minimized
by following these common practices:
• Confirm fasteners engage with
studs/framing or a sound substrate.
• Avoid the use of supplemental fasteners,
sometimes used incorrectly
to attach accessories between studs
like control joints and other accessories
in stucco (required to be wiretied
between studs).
• Avoid errant fasteners that do not
go through studs or that spin and
create a larger opening and a loose
connection (particularly in gypsum-
based sheathing).
• Remove “loose” fasteners and seal
the holes.
• Avoid the use of powder-actuated
fasteners.
Another concern is that the extent of
water that migrates through these unsealed
fasteners/holes may not be of sufficient
quantity to be readily detectable by building
users/occupants. Water leakage may occur
for many years without notice until the
occupants encounter some other unintended
consequences.
In summary, while lab tests demonstrate
the ability of properly installed fasteners
to seal to some extent where they
penetrate liquid-applied or sheet WRBs,
penetrations can become sources of water
intrusion, depending on many variables:
the type of fastener, the angle at which the
fastener is driven, and the amount of water
and pressure at the fastener penetration,
regardless of material type and claims that
may be made about self-sealing characteristics.
Use air barriers that are fully and
independently qualified as water-resistive
barriers to diminish the risk of water penetration
through fasteners.
REFERENCES
ASTM D1970, Standard Specification
for Self-Adhering, Polymer-Modified
Bituminous Sheet Materials Used as
Steep-Roofing Underlayment for Ice
Dam Protection
ASTM E2357, Standard Test Method
for Determining Air Leakage of Air
Barrier Assemblies
ASTM E1105, Standard Test Method
for Field Determination of Water
Penetration of Installed Exterior
Windows, Skylights, Doors, and
Curtain Wall by Uniform or Cyclic
Static Air Pressure
ASTM E283, Standard Test Method for
Determining Rate of Air Leakage
Through Exterior Windows, Curtain
Walls, and Doors Under Specified
Pressure Differences Across the
Specimen
RCI Technical Advisory RCI-TA-005-
2014, “Fasteners and Self-Sealability
of Weather-Resistive Barriers”
Karl A. Schaack,
RRC, PE, is president
of Price
Consulting, Inc.,
located in Houston,
Texas. A graduate
of Clemson University,
Schaack
is currently a
member of RCI’s
Technical Advisory,
RRC Exam,
RWC Exam, Document
Competition, and Nominating Committees.
He was awarded the Richard
Horowitz Award for Excellence in Writing
for Interface by RCI in 2007. Schaack is
an AWCI-Certified Inspector for EIFS and
has successfully completed the Tile Roof
Institute’s Certified Tile Installation program.
Karl Schaack,
RRC, PE
Diagram 4 – Test panel (courtesy of ABAA).