Skip to main content Skip to footer

Hail Events and Structural Decking: A Case Study

January 10, 2018

Reading, Pennsylvania,
experienced two hailstorms
on May 22,
2014 (Figure 1).
These hail events
caused significant
and widespread damage to property
around the area. Damage was
reported to vehicles, sheet metal,
and windows, as well as roofs and
rooftop equipment.
ASTM, FM, and UL all provide
standards for roofing system
hail impact resistance that take
into account hail size and speeds
that are or can be converted into
the force the hailstones impart
to the substrate when impacted.
The standards typically stop there
and simply replicate conditions
and forces, allowing professionals
1 6 • RC I I n t e r f a c e J a n u a r y 2 0 1 8
Figure 2 – Interior of building showing low bay and high bay with clerestory windows.
Figure 1 – National Weather Service storm report for May 22, 2014.
to subject new roofing products and assemblies
to these conditions and record their
performance. This is fairly well understood
in the roofing industry, but what about
the structural deck below the roofing?
What effect does a hailstorm have on the
framing of the building?
The Reading hailstorms
brought on a spate of insurance
claims in which the claimants
and their licensed structural
engineers asserted that the hail
hitting the roofing had caused
damage not only to the roofing,
but had also caused structural
damage to the decking below
the roofs. We will be presenting
a case study of a single building
that was impacted by the
hailstorm and the results of our
investigation.
The building in question is
a fabrication warehouse and is
comprised of an original building
with several different structures
that had been added on over the
years. The claim of damage to
decking was limited to the original building
and, as such, this article will be similarly
limited to this portion of the building.
The original building is a steel-framed
structure with riveted steel trusses and
beams. It is approximately 225 feet long
YOU CALL ME RAIN
HYDROTECH CALLS
ME OPPORTUNITY
2.3889×10.indd 1 8/1/17 5:29 PM
J a n u a r y 2 0 1 8 RC I I n t e r f a c e • 1 7
Figure 3 – Dented
exhaust hood.
Figure 4 – Damage
to A/C fins.
Figure 5 –
Damaged
solar panel.
with multi-wythe brick
masonry mass walls at
both ends. A section taken
across the long axis of the
building shows it to be a
classic “low-bay/high-bay”
structure, approximately
125 feet across, where train
cars were directed through
the high bay and unloaded
into the low-bay areas
on either side. The central
third of the building has
a low-sloped roof approximately
35 feet above a finished
floor, while the two
low bays have a low-sloped
roof approximately 25 feet
above the floor. In Figure 2,
you will see the interior of
the building, including the
overhead rolling crane used
to unload railcars.
The investigation began
with the roof assembly.
There were all the classic
and obvious signs of a hail event: dents,
deflections, and shattering of rooftop accessories
such as exhaust fan hoods (Figure 3),
A/C fins (Figure 4), K-style gutters, and—on
this building—solar panels (Figure 5). There
was also claimed damage to the low-sloped,
fully adhered EPDM roofing on the newer
buildings, but that is beyond the scope of
this case study.
The roofing over the original low-bay/
high-bay building is a loose-laid and ballasted
EPDM installed over 3-in.-thick isocyanurate
(iso) insulation that was laid
directly over the original slag-covered coal
tar pitch roof membrane (Figure 6). The
1 8 • RC I I n t e r f a c e J a n u a r y 2 0 1 8
7 ft
Figure 6 – Overview of roof
assembly at low-bay area.
Figure 7 – Precast
concrete channel
slab planks at
the roof deck.
gravel ballast was relatively heavy, approximated
at 20 pounds per square foot, but
included a large amount of fines.
The roof decking below the EPDM and
coal tar pitch is precast concrete channel
slabs that are gravity-set with retaining
clips, spanning approximately seven feet
between steel purlins (Figure 7). These precast
planks are common throughout the
roofing industry—not because they are typically
installed today—but rather because
they were often installed prior to World War
II and they are so durable that if the building
remains, so, too, do the precast concrete
planks. The concrete planks on this
building are two feet wide by seven feet long
and are one inch thick at all areas except
the two long edges where the concrete was
thickened to three inches thick. This effectively
gives the planks the shape of a blunted
“C.” The planks in question were weighed
and measured and were determined to have
been made with lightweight structural concrete
with #4 reinforcing steel bars located
at the thickened edges (Figure 8).
The condition that was cited and claimed
as damage to the concrete planks was the
loss of cover concrete at the underside of
the #4 steel reinforcing bar. This area of
spalled concrete was pervasive throughout
the building; however, it was not uniformly
distributed. Also, the exposed steel and
concrete of the plank were observed to be in
very different conditions. Some areas of the
building had an interior renovation prior to
the storm. At these locations, the underside
of the planks were painted white and netting
was installed under the planks. When
the netting was inspected after the storms,
large sections of concrete cover were found
in the netting, the underside of the concrete
plank had many areas of unpainted concrete,
and corroded reinforcing steel was
exposed (Figure 9).
The date of the interior renovation and
painting allowed us to determine that the
spalled concrete occurred after the renovation;
however, we could not determine if
it existed prior to the storm. Other areas
of the deck were observed, and we found
spalled concrete and the exposed #4 reinforcing
steel, but these areas were painted
white, indicating they were in this condition
prior to the hail events (Figure 10). With
these conflicting observations, it could not
be determined with a reasonable degree of
engineering certainty that the hail did or
did not cause the spalling of the concrete
plank. As a result, further investigation was
required.
Research into hail and its impact upon
the framing of a building revealed virtually
nothing. No definitive method to calculate
the load transfer from the hail to the structure
was found. The reason this is difficult
is because the hail event creates an impact
load on the structure. Impact loads are
different from steady state or dead loads
because they can be of a very high magnitude
but are of such a short duration that
typical structural analysis methods simply
do not apply. As a result, we outlined and
completed a dynamic hail impact load analysis
for the roof planks.
To be conservative and also to greatly simplify
the analysis, it was assumed that the
hail impact loads were transmitted directly
to the concrete planks. That is to say that
the gravel ballast and the 3-in.-thick iso
insulation had no cushioning effect on the
load imparted to the concrete plank. This is,
of course, a wild oversimplification, because
it is obvious that as a hailstone strikes a
ballasted roof, it can break apart and will
move some of the existing ballast by imparting
some of the hail energy to the ballast.
Additionally, the hailstone will give up more
of its energy by tearing the paper facer and
causing an indentation in the iso insulation.
We chose to ignore these losses of energy
and assumed a worst-case scenario as when
there was no insulation or ballast between
the hailstone and the structural deck.
IMPACT LOAD ANALYSIS
Plank Analysis
The first step was to determine the structural
capacity of the planks. Since there are
still manufacturers of this product, we were
able to obtain published data related to the
ORDINARY ROOFS
WASTE ME
HYDROTECH ROOFS
LEVERAGE MY
POTENTIAL
2.3889×10.indd 2 8/1/17 5:29 PM
J a n u a r y 2 0 1 8 RC I I n t e r f a c e • 1 9
Figure 8 – Design of concrete planks.
dimensions, as well as the strength
of this product. We also calculated
the strength of the plank in accordance
with ACI 318-11, Building
Code Requirements for Structural
Concrete. Loading combinations
per ASCE 7-10, Mini-mum Design
Loads for Buildings and Other
Structures, were applied, and it was
determined that the planks can support
approximately 45 pounds per
square foot of live load.
Load Calculation
and Duration
Based upon weather data, FM
classifications, and a desire to be
conservative, a “severe” impact model
was selected; therefore, the load was
assumed to be no greater than that
represented by the FM Class I-SH
Model (Crenshaw and Koontz, 2000
and 2002) and is the equivalent
impact energy of a 1.75-in. diameter
steel ball dropped from 17 ft., 9 in. The impact
force of this missile was calculated to be 84
pounds with a load duration of 10 milliseconds
and was assumed to be uniform
throughout its applied duration. This uniform
load application is again conservative,
as it will, of course, start at zero, increase to
84 pounds, and then decrease to zero—all
within the calculated 10 milliseconds.
Frequency and Location of Load
Once the load of a single hailstone was
calculated, a statistical analysis was performed
of the number and location of individual
hail strikes—and thereby loads—that
occur on a single plank over a specific time
interval. A randomly applied hail impact load
can be represented by a statistical model of
random occurrences over a time period, or a
Poisson process (Ang and Tang, 1975):
The inputs of storm duration from
hail-tracking data (hail fell for approximately
15 minutes), and the number of hail
impacts per square foot observed at multiple
test cuts taken at the roof (average of 58
per sq. ft.) were used, and it was calculated
that on a single plank, on average, one hail-
2 0 • RC I I n t e r f a c e J a n u a r y 2 0 1 8
Figure 9 – Spalled concrete caught
in netting with exposed unpainted
concrete and reinforcing steel.
Figure 10 – Spalled
concrete and exposed
reinforcing steel with
paint from interior
renovation completed
prior to storm.
stone landed every 1.1 seconds. Based upon
this, the mean occurrence rate of impact
loads is approximately 0.90 hailstones per
second. Therefore, the probability that a
single roof plank was subjected to more
than one impact over a hail strike loading
duration of 0.01 seconds (10 milliseconds)
is 0.004%, and is calculated by:
A probability of 0.3% is generally considered
to be the threshold for practical certainty
in statistical analysis for engineering
design per ASTM E122, Standard Practice
for Calculating Sample Size to Estimate,
With Specified Precision, the Average for a
Characteristic of a Lot or Process. Therefore,
it was estimated that any single concrete
plank may have been subjected to upwards
of four hail strikes over a duration of 1.1
seconds (the average time between hail
strikes), based upon the low probability of
occurrence of 0.3%.
Due to the calculated duration of loading
from a single hail strike, and the statistical
improbability that two strikes will occur
simultaneously, we chose to assume the
next most conservative loading scenario of
four hail strikes occurring—one immediately
after another—over a duration of approximately
1 second. Two cases were assumed:
one where all four of these hail strikes
occurred at the center span of the plank,
and a second case where all loading was
applied near the support. These two loading
scenarios will impart the maximum moment
and shear forces to the plank, respectively.
See Figure 11. Again, this loading scenario
was done so as to be as conservative as possible
by calculating the worst-case scenario,
no matter how unlikely it is to occur.
The concrete planks were modeled using
CSI SAP2000 structural analysis software
with 84-pound loads applied at 0.01-second
intervals. Based on the above statistical
analysis, four impact forces were applied at
intervals equal to the period of vibration of
the planks (which we calculated to be equal
to approximately 0.06 seconds), resulting in
a cumulative application of impacts, adding
to the amplitude of the precast concrete
plank response (Figure 12). This approach
is considered to be somewhat conservative
because during the hailstorm event, it is
likely that half of the hailstones landed on
the roof surface in sync, while the other half
landed out of synch, which thereby reduced
the amplitude of the dynamic response of
the planks.
THE GARDEN ROOF®
ASSEMBLY
INTRODUCED OVER
20 YEARS AGO,
PROVIDING:
stormwater management solutions
reduce
retain
delay
extended roof longevity
additional usable space
full assembly warranty
Learn more today at
hydrotechusa.com/power-of-rain
HELPING YOU
HARNESS THE
POWER OF RAIN™
© 2017 Garden Roof is a registered trademark of American Hydrotech, Inc.
Harness the Power of Rain is a trademark of American Hydrotech, Inc.
2.3889×10.indd 3 8/1/17 5:29 PM
J a n u a r y 2 0 1 8 RC I I n t e r f a c e • 2 1
Figure 11 – Case 1 (a): concentrated impact force at mid-span; and Case 2 (b): concentrated
impact force near the support.
Figure 12 – Idealized impact force history.
Plank Reaction to Applied Loading
When the calculated loads were applied
in accordance with the calculated timing,
the resultant deflections, shear force, and
bending moments were determined and are
plotted in Figures 13 through 15. All calculated
loads were marginal when compared
to the plank structural capacities that were
initially calculated.
As can be seen in Table 1, the worstcase
scenario is when the planks’ shear
service capacity is 61% utilized when the
plank is loaded at center span.
The fact that the shear capacity of the
planks will be reached/exceeded by exterior
loading before the moment capacity of the
planks can be reached is enlightening. Shear
and moment failures of concrete planks result
in very different types of failures. “Classic”
moment failures of concrete planks are when
the concrete at center span deflects downward
and develops cracks on the bottom surface
and can result in loss of reinforcing steel
cover as was seen at the site. However, since
these planks are limited in strength by shear,
excessive loading failure should be evidenced
by shear failures. Classic shear failures are
ones where the concrete plank fails at or
immediately adjacent to the support and are
very different from the conditions observed at
the site (Figure 16).
Since the allowable/usable moment and
shear capacities were always 40% or more
than the applied loading, assuming all
worst-case scenarios, it was concluded that
the loading due to hail did not cause the
damage to the concrete planks.
Once the structural analysis proved
it was not the applied loading that led to
the damage, it was fairly simple to show
that long-term corrosion of the reinforcing
steel caused rust-jacking that caused the
concrete to spall and expose the steel. This
causation of the damage was corroborated
by the fact that many areas of spalled concrete
were painted white (indicating that
2 2 • RC I I n t e r f a c e J a n u a r y 2 0 1 8
Table 1 – Structural review of precast concrete planks.
Figure 16 – Location of a shear failure is at
support, not mid-span of structural member.
Graphic courtesy of http://boulderlibrary.
net/timber-framing-for-the-rest-of-us-robroy/
shear-and-shear-failure.html.
Figure 13 – Deflection results for Case 1 (a) and Case 2 (b).
Figure 14. Shear force results for (a) Case 1 and (b) Case 2.
Figure 15 – Bending moment results for Case 1 (a) and Case 2 (b).
the spalling of the concrete cover over the
reinforcing bars occurred prior to the hail
event), as well as the lack of any damage
to the ballasted EPDM roofing above these
allegedly damaged concrete planks.
REFERENCES
Ang, Alfredo Hua-Sing, and Wilson
H. Tang. Probability Concepts in
Engineering Planning and Design.
New York: Wiley, 1975.
ASCE 7. 2010. Minimum Design Loads
for Buildings and Other Structures.
Reston, VA: American Society of Civil
Engineers, 2010.
ASTM International. 2000. ASTM E122
Standard Practice for Calculating
Sample Size to Estimate, With
Specified Precision, the Average for
a Characteristic of a Lot or Process,
2000.
ASTM International. 2015. ASTM D
3746 Standard Test Method for
Impact Resistance of Bituminous
Roofing Systems, ASTM D3746
/ D3746M-85(2015)e1. West
Conshohocken, PA, 2015.
ACI 318. Building Code Requirements
for Structural Concrete (ACI 318-11)
and Commentary. 2011. Farmington
Hills, MI: American Concrete
Institute, 2011.
Computer & Structures, Inc. “SAP2000
17: Integrated Structural Analysis
& Design Software.” Computer software,
released in 2015.
Crenshaw, Vickie, and Jim D. Koontz.
2000. “Simulated Hail Damage and
Impact Resistance Test Procedures
for Roof Coverings and Membranes.”
Crenshaw, Vickie, and Jim D. Koontz.
2002. “Hail: Sizing It Up!” Western
Roofing Magazine.
Factory Mutual. FM 4470: Susceptibility
to Hail Damage, Test Standard for
Class 1 Roof Covers.
Underwriters Laboratories, Inc. 2010.
Standard UL 2218: Impact Resistance
of Prepared Roof Coverings.
Underwriters Laboratories, Inc.,
January 25, 2010.
Remo R. Capolino,
a principal with
WJE, grew up in a
family-owned specialty
roofing contracting
business,
and graduated
from the University
of Connecticut with
a BS in civil engineering.
After more
than 15 years in
contracting and
leadership roles
with the Association of General Contractors
(AGC), Northeast Roofing Contractors
Association (NERCA), and the National
Roofing Contractors Association (NRCA), he
turned to consulting. He is a member of the
RCI Interface Peer Review Board.
Remo R. Capolino
Since joining Wiss,
Janney, Elstner &
Associates (WJE)
in 2014, Dziugas
Reneckis has performed
field investigations,
condition
surveys, construction
period services,
and special
inspections involving
steel frame,
masonry, wood,
and reinforced
concrete structures. Additionally, he has
provided structural services associated with
the renovation of building façades and interiors.
Before joining WJE, he concentrated
on the design of special structures in glass
and steel, as well as façade engineering.
Reneckis completed his undergraduate and
graduate studies in civil engineering at the
University of Illinois at Urbana-Champaign.
Dziugas Reneckis
J a n u a r y 2 0 1 8 RC I I n t e r f a c e • 2 3
The Schuylkill County Area Vocational Technical School
Board in Mar Lin, Pennsylvania, hired a construction manager
to replace the roofs at the Schuylkill Technology Centers in Mar
Lin and Frackville recently at a projected cost of $1,710,000—
approximately $800,000 less than would have been spent had
it gone through with a state contract Master Intergovernmental
Cooperative Purchasing Agreement arrangement with The
Garland Co.
The board had been planning to hire Garland, a roofing
manufacturer it had worked with numerous times, to do the
project for $2.519 million. But board member David Frew suggested
the roof committee investigate alternatives to the no-bid
Garland deal. Frew wrote in an e-mail to the Republican Herald
that Garland was “the manufacturer and the installer and
the designer, and it was specified just for their product.” As
a result, the district had “expected that they would come in a
few percentage points lower” than the “not-to-exceed” number
of $2.519 million established through the U.S. Communities
cooperative purchasing deal. This was not the case.
“The state contract procurement, while convenient, may
not offer the most competitive approach to this type of work.
Our experience with other school districts is that better pricing
can be obtained from the marketplace via competitive bids vs.
the state contract,” Frew wrote.
Instead of signing the contract, the committee researched
options and hired Performance Construction Services as the
district’s construction manager. Performance suggested an
EPDM synthetic rubber roofing membrane roof with a 30-year
warranty, and estimated the two projects should come in
closer to $1,710,000. The project will be bid and will include
architecture, engineering, and roof consulting fees to observe
the installations.
PA SCHOOL DISTRICT REJECTS COOPERATIVE
PURCHASING AGREEMENT ROOF REPLACEMENT;
SAVES $800,000