Skip to main content Skip to footer

Innovative Repairs to Terra Cotta Parapets and Cornices

March 16, 2015

Innovative Repairs to Terra Cotta
Parapets and Cornices
Steven P. Bentz, RBEC, PE, and Michael Payne, EIT
Facility Engineering Associates, P.C.
12701 fair lakes Circle, suite 101, fairfax, Va 22033
Phone: 703-591-4855 • fax: 703-591-4857 • e-mail: bentz@feapc.com
3 0 t h RC I I n t e R n a t I o n a l C o n v e n t I o n a n d t R a d e S h ow • M a R C h 5 – 1 0 , 2 0 1 5 B e n t z a n d p a y n e • 9 9
Abstract
This presentation will cover intermediate and advanced topics in historical restoration
of terra cotta and stone masonry. The successful restoration project was driven by the
implementation of innovative approaches to terra cotta and stone water table stabilization,
including a unique use of nelson stud-welding technology. Selective rebuild of the parapet,
resetting of coping stones, addition of through-wall flashings, and recoating of terra cotta
completed the restoration and created a long-lasting repair for a project budget that was
approximately $30 million less than that of the original estimates.
Speakers
Steven P. Bentz, RBEC, PE — Facility Engineering Associates, P.C.
STEVE BEnTz is a registered professional engineer in five states and the District
of Columbia and a registered roof Consultant, registered Waterproofing Consultant,
registered Exterior Wall Consultant, and registered Building Envelope Consultant with
rCi, inc. He has been involved in hundreds of projects with Facility Engineering associates,
P.C. (FEa), including in-field investigation; testing and evaluation; preparation of construction
documents; bidding; and construction administration of roof replacement, façade
repair, and historical rehabilitation projects. He is currently a senior engineer specializing
in building envelope repair and assessment at the Fairfax, Va, office of FEa and an associate
member of the Sealant, Waterproofing, and restoration institute, as well as secretary of
the Mid Atlantic Chapter of RCI.
Michael G. Payne, EIT — Facility Engineering Associates, P.C.
miCHaEl PaYnE is a project engineer with the Engineering Services Group at FEa.
His project roles include field assessment and reporting, design of repairs, and contract
administration during construction. in his time at FEa, michael has assisted in consulting
building owners and property managers on implementing repair and maintenance plans to
correct numerous deficiencies with building components. He has a growing experience with
evaluation and repairs of concrete, masonry, steel, and wood structures; building enclosure
and roofing systems; parking garages and pavements; waterproofing; historical rehabilitation;
and various other building systems.
1 0 0 • B e n t z a n d p a y n e 3 0 t h RC I I n t e R n a t I o n a l C o n v e n t I o n a n d t R a d e S h ow • M a R C h 5 – 1 0 , 2 0 1 5
3 0 t h RC I I n t e R n a t I o n a l C o n v e n t I o n a n d t R a d e S h ow • M a R C h 5 – 1 0 , 2 0 1 5 B e n t z a n d p a y n e • 1 0 1
imagine walking down a busy city street
where everyone is in a rush and no one
takes a moment’s notice of what is around,
when you come upon an ancient-looking
building at a street corner. This building
sticks out from the others, with large stone
columns and an ornate portico off the busy
street. intrigued, you take a moment to stop
and gaze at the beauty of the building and
notice that the ornament and detailed artisanship
continues throughout the façade.
it is unbelievable that man was able to construct
something so stunning and make it
last for such a long time. The moment ends,
and you continue on your way; but there is
a feeling of satisfaction knowing that you
witnessed a small glimpse of history.
This country, like many other countries
around the world, takes great pride in trying
to preserve its history. Whether it be a
landmark of constitutional significance or a
century-old building that has withstood the
test of time, historical pieces of architecture
have become intertwined into the fabric that
makes our society what it is today.
However, all too often, that fabric
becomes too tightly bound, and the general
mindset would have us believe that,
because these buildings have survived the
trials of times past, they will continue
standing for centuries to come with little to
no care. In fact, it is often not until a threat
of failure occurs that the mortality of these
historical pieces of architecture is realized.
It is at this point, when conditions
deteriorate to the point of endangering the
public on the streets and sidewalks below,
that many landmark buildings require
specialized thinking and understanding to
assess how known issues, such as thermal
expansion and contraction (also referred
to as thermal movement) and irreversible
moisture expansion have had centuries or
decades of effects on the buildings, leading
to failure. Simultaneously, proper repairs
need to be developed so that the problem is
adequately addressed with minimal change
to historical components.
a recent restoration project of an historical
government building within a populated
city highlighted the significance of
proper historical restoration techniques.
Understanding of the historical construction
allowed for a thorough and strategic assessment.
This translated to the identification
of several incorrect failure modes about
why the building’s parapet wall was moving
and the root cause of the problem with the
ornate terra cotta
cornice.
The successful
restoration project
was driven by the
implementation of
innovative approaches to terra cotta and
stone water table stabilization, including
a unique use of nelson stud welding technology.
Selective rebuild of the parapet,
resetting of coping stones, the addition of
through-wall flashings, and recoating of the
terra cotta completed the restoration and
created a long-lasting repair for a project
budget that was approximately $30 million
less than that of the original estimates.
ABOUT THE PROJECT
The subject property, seen in Photo 1,
was a nine-story historical municipal government
building constructed in 1913 and
occupying an entire city block in Pittsburgh,
Pennsylvania. The 144-foot-tall building
was built with a structural steel frame and
structural clay tile floor system. The exterior
cladding was comprised of granite and
terra cotta masonry, including an ornate
terra cotta cornice and parapet (see Photo
2). in 1968, the building was recognized
as an historical landmark by the city.
Maintenance of the parapet and cornice had
been deferred for many years.
Innovative Repairs to Terra Cotta
Parapets and Cornices
Photo 1 – Façade overview of the subject building.
Photo 2 – Ornate terra cotta
cornice and parapet wall.
In 2011, small pieces of terra cotta from the ornate cornice fell to the sidewalk
and street below, prompting the city to close the sidewalks around the building
and take emergency measures to protect the public. initially, the first team of
consultants developed a recommendation to completely remove and replace the
parapet and cornice. it was believed that the parapet wall and cornice were moving
due to corrosion of embedded steel and iron components, a phenomenon referred
to as oxide or rust-jacking. Complete removal and replacement of the parapet
was estimated at $34 million, and an initial emergency repair project was pushed
through to stabilize the parapet in the interim.
along with falling pieces of cornice, the parapet wall was believed to be leaning
towards the street. initial thoughts pointed towards rotation of the wall due to
rust-jacking, omission of terra cotta anchorages and grouted terra cotta cavities
during construction that were specified in the original design drawing, aging of the
exterior components, and excessive corrosion of structural framing and masonry
fasteners as the potential reasons for these failures. it was believed that a pivot
action failure (rotation of the wall due to uneven uplift forces) was occurring at
the bottom of the parapet wall, causing the entire wall (coping included) to lean
as a single element. This was presumed to be partly due to issues with the terra
cotta hangers (shown on the original details but not observed in the construction),
along with rust jacking of steel framing, pushing the wall up and outward. This
assessment summary can be observed in the diagram in Figure 1.
LOOKS A REN’T A LWAYS W HAT T HEY S EEM
in early 2012, a second team of consultants was brought in with a different
approach to the project. a better understanding of the failures based on an
understanding of failure modes of historical structures was applied,
and the previous conclusions were reviewed. The new approach first
had to show that the previous ideas about missing tie rods, excessive
corrosion, and rust jacking were not causing the parapet wall to shift
towards collapse.
The omitted tie rods at the cornice that were referenced in the
previous report were typical in construction of that time, as their use
during construction was as a formwork, and they were removed once
mortar set and the cornice developed arch action. missing grout may
not have been a defect, as numerous grouted terra cotta assemblies
on buildings built at that time have shown severe corrosion of embedded
steel due to moisture in the grout being held close to the steel and
iron components. With further study of the available drawings and
investigation into the openings created by the previous team, it was
found that corrosion of steel members at the cornice and roof level
were mainly in supplemental framing rather than main structural
components as first thought. rust jacking at the pivot point shown in
Figure 1 would result in upward movement and a backward tilt, which
was not observed at the building.
The second team of consultants focused on the idea that pivot
action failure was not occurring at a single location. Based on the
observed movement and deterioration, the team concluded that various
failure modes were occurring at specific elements of the parapet
wall and cornice simultaneously, causing the misconception that the
entire wall was leaning from a single point. in this second opinion, it
was believed that the cornice and parapet were failing due to expansive
forces of the adjacent parapet walls, expansive forces within each
wall, and movement and deterioration of the cornice elements below,
as indicated in Figure 2.
IRREVERSIBLE MOISTURE EXPANSION
Porous materials, such as clay brick, expand when they absorb
water. When a brick is taken from a kiln and is at its driest state, it
1 0 2 • B e n t z a n d p a y n e 3 0 t h RC I I n t e R n a t I o n a l C o n v e n t I o n a n d t R a d e S h ow • M a R C h 5 – 1 0 , 2 0 1 5
Figure 1 – Diagram indicating initial failure
mode and pivot point of the parapet wall and
terra cotta cornice.
Figure 2 – Diagram indicating revised failure mode of the
parapet wall and cornice. Thick black lines at the coping
indicate erosion of mortar joints that result in rotation of
the terra cotta base and coping. The black arrows along
the parapet wall represent the irreversible expansion of
the masonry due to the absorption of moisture. The stone
anchor highlighted at the water table was typically failed
due to corrosive section loss of the anchor and resulted in
rotation of the water table ledge.
immediately begins to absorb moisture and
expand. at first, this absorptive expansion
is quite extreme, but slowly levels off within
the first few weeks. During the typical life of
a brick, this absorptive expansion continues
to increase parabolically and is typically
very small (hundredths of a percent). This
process, in which brick continues to slightly
swell over its lifetime, is referred to as irreversible
moisture expansion.
Unlike thermal expansion and contraction,
which is a reversible volume-changing
process in which a material, such as brick
or steel, can increase/decrease in size due
to change in temperature, moisture expansion
is an irreversible process. That means
as brick or other fire masonry is subjected
to moisture after the initial drying process,
it permanently absorbs a portion of
the moisture and swells in all directions,
expanding the brick.
as the brick continues to experience
expansive wet cycles over a long period of
time—say decades or centuries—the additive
volume of the brick due to irreversible
moisture absorption can slowly add up.
at first, the shrinkage properties of the
cementitious mortar beds in brick walls
balance out the effects of the swelling brick.
However, as time continues, brick can begin
to swell to the point that stresses begin
to develop against adjacent surfaces. in
extreme conditions, this stress can become
strong enough to crack mortar beds or adjacent
brick.
Swelling can also become additive,
allowing whole walls to expand in all directions,
increasing the wall’s overall volume.
Expansion occurs in a similar ratio in all
directions. Typically, the amount of expansion
caused by moisture absorption, often
denoted by ke, is approximately 3 to 5 x
10-4 in./in. for brick masonry.1 That is,
per every inch of wall in each direction, it
can be expected that a gradual increase in
size of approximately 0.05% occurs over the
lifetime of the brick.
THERMAL EXPANSION
Thermal expansion and contraction is
directly related to the coefficient of thermal
expansion of a specific material. in the
simplest case, the equation used to analyze
the thermal expansion or contraction of a
certain object (in this case linearly) is:
where the change in length, Δl, is found by
multiplying the original length of the object,
l, by the coefficient of thermal expansion
for that particular object, αT, and the
change in temperature, ΔT.
Often, issues arise in buildings where
the original design does not take thermal
expansion into proper consideration, and
certain building components are allowed
to increase/decrease in size beyond what
would be considered an allowable design
limit. Once thermal expansion/contraction
reaches that limit, that material can begin
to cause tensile or compressive stress to
form on adjacent materials as it pushes
against or pulls away from the adjacent
material, leading to failure in extreme cases.
LACK OF EXPANSION JOINTS
Unlike today, where buildings are often
broken into isolated sections by horizontal
and vertical control joints, construction
joints, and expansion joints, buildings
that were part of early 1900s construction
typically did not include adequate detailing
to withstand differential movements.
This differential movement can be caused
by phenomena such as ground settlement,
cyclical loading of the structure, or even
changing wind pressures along a building
façade. One of the most common types of
differential movement, however, is caused
by thermal and moisture expansion.
in the case of the leaning parapet wall,
it was found that the original parapet wall
design did not account for enough thermal
and moisture expansion of each perimeter
edge. The corners of the roof did not include
any type of joint to take the movement
caused by an increase in temperature and
swell at the long-axis parapet walls. This
created a force at the adjacent parapet wall
perpendicular to it, pushing the wall outward
(see Photo 3).
Stress caused by thermal and moisture
expansion can be determined by the following
equation, where E is Young’s modulus
of the material:
Taking into account that the long-axis
walls of the subject building were 300 feet
long with no control joints, and using the
coefficient of thermal expansion of brick at
3.1*10-6 in./in. ºF, the irreversible moisture
expansion coefficient of brick is 5.0*10-4 in./
in.; the Young’s modulus of brick is 2.1*106
psi; and expansive change in length of the
wall over a period when the brick temperature
cycles through a 100ºF temperature
change is approximately 1.25 inches due
to thermal and 1.75 inches due to moisture
3 0 t h RC I I n t e R n a t I o n a l C o n v e n t I o n a n d t R a d e S h ow • M a R C h 5 – 1 0 , 2 0 1 5 B e n t z a n d p a y n e • 1 0 3
Photo 3 – Thermal and moisture expansion within the brick and granite parapet
wall elements caused a pushing motion to occur at the corners of the perimeter
wall.
expansion (3 inches of total expansion from
initial length). Or, assuming no movement
is accommodated at the corners, where
perpendicular parapet walls abut the long
walls, a stress of over 1,700 psi is
developed pushing on the adjacent
wall. The force is substantial, and
the movement that is occurring must
go somewhere, with the end result
being that the perpendicular walls
must be forced outward. When the
thermal movement relaxes, the long
wall returns to its original position,
but the perpendicular wall is left displaced.
Over time, this cycle results
in cracks at the corners (Photo 3).
LIFT AND ROCK
irreversible moisture expansion
appeared to have been the cause of
several failure modes at the leaning
wall. in addition to creating a pushing
motion from adjacent walls, moisture
expansion also created swell within
the subject wall that caused the
wall to lift upward. Because the wall
was built with a clay brick backup
(interior face) and a terra cotta facing
(exterior face), this lift was not
uniform along the width (interior to
exterior face) of the wall, causing a rocking
action to occur at the granite coping stone.
The inside faces of the parapet walls
were constructed of two wythes of brick,
while the outside face was of terra
cotta. The brick face at the inside
wall was previously covered by an
EPDm membrane to help protect the
wall from absorbing water. However,
moisture found a way into the bricks
over time by other means, such
as failed sealants at coping stones
above. The membrane then acted
as a cover to prevent normal drying
of the masonry at the inside face,
thus exacerbating moisture levels
and allowing the brick face to swell
at an increased rate from the other
wythes (as well as the terra cotta
face) due to irreversible moisture
expansion. Brick and mortar differences
between the two wythes may
have also played a role.
Swelling of individual brick
caused height expansion within the
brick courses. This expansion slowly
created stresses within the bricklayers
and began to push the wall
slightly upward. Because expansion
was unequal among the different
layers of the wall, a differential lift
was created, causing the copingstone
atop the wall to rock toward
the street. The amount of lift caused by
irreversible moisture expansion in the brick
can be seen in Photo 4.
1 0 4 • B e n t z a n d p a y n e 3 0 t h RC I I n t e R n a t I o n a l C o n v e n t I o n a n d t R a d e S h ow • M a R C h 5 – 1 0 , 2 0 1 5
Photo 4 – Cross-section of parapet coping. Arrows indicate rotation of coping. Solid line
is approximately level to show amount of rotation. Dashed lines indicate differential
amount of heave in back-up masonry due to irreversible moisture expansion.
Photo 5 – Mortar deterioration at joints below coping stone.
MORTAR DETERIORATION
It seems that the lift was not the only
action occurring at the parapet wall. The
rocking of the coping was intensified by
the erosion of mortar joints along the front
face of the coping stone between the coping
and terra cotta base course, as well as the
joint between the terra cotta base course
and decorative terra cotta weave (as seen
in Photo 5). mortar joint deterioration was
widespread throughout the parapet and
cornice, however, not just at these joints.
moisture intrusion and freeze/thaw cycles
had caused the mortar within these joints to
severely deteriorate. among other outcomes,
this allowed cornice and wall elements, such
as the terra cotta base course and coping
stone above, to settle at the outside face,
while the brick backup and steel framing
remained intact to support the remaining
sections, thus creating the appearance of an
outward-leaning parapet wall.
WATER TABLE FAILURE
The last piece of the leaning-wall puzzle
was solved by reviewing conditions of the
terra cotta cornice below the parapet level.
after observing the cornice area up-close
by use of a swing stage, it was determined
that there was movement within the cornice
stemming from lack of support at two locations.
This issue occurred most dramatically
at the corners, which helped to explain
why the parapet appeared to be leaning out
so much at the corners. Specifically, issues
were discovered at the granite water table
level and the fascia panel at the base of the
ornate terra cotta cornice.
Granite water tables were found to be
leaning down and outward, as depicted in
Photo 6. The most severe areas were at the
corners of the building, although stability
was questionable for the entire length.
Therefore, the question arose as to why
the granite water table pieces had started
to move. initial thoughts pointed to possible
failed or missing anchors. However,
it turned out that it was caused by several
different reasons.
Previously, areas of the existing roof and
roof deck were removed at several locations
to view conditions of presumed corroded
steel framing members. These areas were
reassessed by the second consultant team
to determine if the corroded steel observed
previously was related to the water tables.
it was found that steel anchors designed
to hold the water tables at the top edge to
prevent lateral movement had severely corroded
and failed in numerous locations, but
the shelf angle supporting the water table
was intact. This allowed the water table to
rotate down and outward from the top.
it was observed that the anchor rods,
which were hooked steel bars that were
intended to prevent water table rotation,
had corroded. The rods, connected to a steel
c-channel, went through back-up masonry
and attached to the top edge of the granite
piece to the steel framing. The rods had corroded
due to being packed tightly against
the masonry, which had been subjected to
water infiltration from above. as deterioration
of joint materials continued through
the years, open joints within the granite,
masonry, and terra cotta allowed water to
enter into the wall and continue to corrode
the steel anchors. This condition was most
notable at the corners, where the previously
discussed irreversible movement had
opened cracks and allowed even more water
into the assembly.
The fascia panel below the water table
was shown to be a solid piece of granite on
the original drawings, but had since been
removed and replaced with a cementitious
board set on a galvanized steel frame. The
cementitious board was later determined
to be asbestos-containing and thought to
be “Transite” panel, or something similar.
It was likely that the
original fascia stone had
deteriorated or shifted and
had been thought to be
an overhead hazard. There
were no records as to when
the stone was removed, but
anecdotal evidence suggested
it was in the early
1970s. The stone was
replaced with a pseudo fascia
panel to resemble the
original. However, the role
that the stone played in the
cornice stability seemed to
be underestimated when it
was removed. It appeared
that the removed stone had
helped to create confinement
in the cornice system
and allowed arch action to
develop in the cornice. Once
it was removed, the other
cornice elements began to
shift, including allowing the
water table to settle.
TERRA COTTA GLAZE FAILURE
REMEDIATION
Thus far, the failure modes discussed
have been related to the movement issues
noted with the parapet wall. However, it
was also noted in the introduction that the
original reason a repair project was implemented
was due to falling pieces of the
terra cotta cornice. Once investigation was
done by swing stage at the cornice level,
the terra cotta could be investigated. This
investigation showed that terra cotta was
deteriorated in numerous locations, with
various areas of loose or missing terra cotta
pieces present.
Terra cotta failure was associated with
several conditions present in the cornice.
As mentioned previously, mortar deterioration
was prevalent throughout the parapet
and cornice. Mortar deterioration created
open joints that allowed water infiltration
into terra cotta backup, along with cracks
formed in the terra cotta elements by
stresses or crazing of the glazing. Water that
entered these spaces could have created
expansive forces from freeze/thaw cycles,
which could have caused additional cracking
or spalling to occur.
mortar deterioration at joints may have
also created stresses within the terra cotta
components as mentioned previously. The
removed fascia stone prevented confine-
3 0 t h RC I I n t e R n a t I o n a l C o n v e n t I o n a n d t R a d e S h ow • M a R C h 5 – 1 0 , 2 0 1 5 B e n t z a n d p a y n e • 1 0 5
Photo 6 – Granite water table at the corner of the
cornice was noted to be rotating down and out from the
corner
ment, which allowed for movement of terra
cotta pieces at the soffit. Together with
mortar deterioration and thermal cycling
(differential expansion and contraction) of
adjacent pieces of terra cotta, this
allowed abutting pieces to pinch
together, causing additional stresses.
This stress may have also caused
cracking and spalling of pieces to
occur.
although the above conditions
were present and were assumed to
be contributing factors to terra cotta
failure, there was a more general
issue that was occurring at the
entirety of the terra cotta pieces
at the parapet, cornice, and soffit.
The terra cotta elements had been
subject to widespread glaze failure.
What was initially thought to be a
“speckled” finish in the glaze (see
Photo 7) was found, upon close-up
inspection, to be defects in the glaze.
The exact cause of the glaze degradation
failure was not determined, but
it was suspected that it was related
to atmospheric conditions (possibly
acid rain) or a very aggressive prior
cleaning of the building (anecdotal
evidence suggests that the building
may have been sand-blasted in the
late 1960s). regardless of the cause,
glaze failure was allowing water into
the terra cotta bisque (bisque is the term for
the clay mixture that, when fired, becomes
terra cotta) throughout the parapet, and
trapped moisture within the terra cotta
body was leading to spalls, cracks, and
other terra cotta failures.
UNIQUE RESTORATION SUITED
FOR HISTORICAL BUILDING
Discovering the origins of the issues
that were causing the historical building’s
cornice and parapet wall to fail was just the
first step in the restoration process. Once
this information was gathered and there
was a good indication of the actual failure
modes present, repairs had to be designed
and implemented. like the assessment process,
recommending and designing repairs
for an historical restoration project can be
challenging. it takes creative and innovative
thinking, paired with a good experience of
repairing historical elements on a building,
to come up with a strategy and design for
proper repairs that will be effective, affordable,
and long-lasting.
Case in point, as mentioned earlier in
this paper, the original proposal for the parapet
wall and cornice was to simply demolish
everything at these levels and rebuild
from the roof up. although this would have
likely been a successful solution, it could
have created numerous construction issues,
such as with the fragile terra cotta pieces
1 0 6 • B e n t z a n d p a y n e 3 0 t h RC I I n t e R n a t I o n a l C o n v e n t I o n a n d t R a d e S h ow • M a R C h 5 – 1 0 , 2 0 1 5
Photo 7 – Glazing degradation failure at terra cotta parapet, as well as areas of
cracked and spalled terra cotta.
Photo 8 – Limited rebuild of masonry parapet wall and installation of metal through-wall
flashing. Note half brick (approximately 2 in. high) used at top of wall; this represents
the amount of swell in the remainder of the wall due to irreversible expansion of the
masonry.
during removal, storage,
and replacement;
as well as cost a large
amount of money to
perform. Instead, the
revised restoration
program focused on
preserving as much of
the original construction
as possible and
concentrated on five
key repairs.
1. a dding joints
to accommodate
expansive
movement
caused by
thermal and moisture expansion
2. r esetting parapet wall brick and
coping stone and installing throughwall
flashing
3. Stabilizing the loose water table
granite
4. a dding confinement steel and
replacing the fascia at the fascia
panels to help stabilize the cornice
5. r epairing joints and terra cotta to
allow for a more water-resistant
system.
The first two repairs focused on the
parapet wall. To ensure that thermal and
moisture expansion did not create further
stresses on adjacent parapet walls, it
was recommended that masonry expansion
joints be installed at all four of the building’s
main corners to allow for movement.
To correct the heaving motion caused by
moisture expansion within the parapet walls
itself, the coping stones, brick backup, and
terra cotta base course were removed and
rebuilt to reestablish the back-slope profile
of the coping as shown in the original
drawings (see Photo 8). additionally, the
EPDm membrane was removed from the
back wall to allow for proper drying, and a
metal through-wall flashing was installed
under the copingstones to prevent additional
moisture from accessing the backup
wall. The coping stones were secured with
stainless steel dovetail anchors in slotted
holes to allow for movement. The skywardfacing
joints in the coping were sealed with
caulking. a rain-screen cladding on the
interior face of the wall is recommended for
future installation.
The stabilization of the water table was
an integral part of stabilizing the overall
cornice, but determining how to re-anchor
the stone and access the steel framing supports
without removing the roof along the
entire perimeter of the building required an
innovative repair. That is where a unique
use of a process often referred to as nelson
stud welding was employed. in this technique,
typically an electrical current from
a specialized welding gun is run through a
steel stud to create an electrical arc at the
tip of the stud that welds the end of the stud
to a metal surface. it was decided that, by
drilling holes into the existing granite water
table pieces until the steel support channel
was reached, the nelson stud welding
technique could be used to pin the stone to
the steel angle (See Figure 3). as the studs
were meant to take lateral load only, the
technique did not require a large force to
be supported. This was accomplished by
3 0 t h RC I I n t e R n a t I o n a l C o n v e n t I o n a n d t R a d e S h ow • M a R C h 5 – 1 0 , 2 0 1 5 B e n t z a n d p a y n e • 1 0 7
Photo 9 – Mock-up example of Nelson
stud used for repairs.
Figure 3 – Repair detail for granite water table stabilization.
Figure 4 – Repair detail for new fascia board and fascia support angle.
stud-welding two ½-in.-
diameter nelson studs
with washers and nuts
at the end through each
granite piece onto the
steel channel (see stud
mock-up in Photo 9). The
holes were covered with a
stone patch repair mortar
material, and the granite
water table was stabilized
without the removal of
any stone or adjacent
component.
Another issue that
arose concerned the fascia
board repairs. The
missing granite fascia
stone was causing confinement
issues with the
arched terra cotta soffit
and other adjoining elements
of the cornice. It
would have been monetarily
unrealistic to
replace the existing coverboard
with a new granite
band to match the
existing one, but stabilization
was required in
some way. To accomplish
this, a new steel angle
was welded to the bottom leg of the thenabandoned
granite fascia support angle,
and a stainless steel threaded rod was
drilled into the existing terra cotta at the
top of the soffit arch and epoxied into place
(see Figure 4). This replaced the lost confinement
from the removed granite band
and helped to restore stability in the entire
cornice system. The new angle was then
covered by a new painted galvanized steel
fascia panel that matched the adjacent
stone pieces. Similarly, the granite and
terra cotta base courses were reinstalled
with new, stainless steel masonry anchors
to tie them to the backup material. This
helped to stabilize the parapet level.
The final repair area was focused on
closing the gaps and sealing the cornice
system from water infiltration. To do this,
two methods were employed. First, joint
sealants and mortar joints that had deteriorated
previously, causing open joints into
granite and terra cotta, were pointed and
sealed. Cracks that were found within terra
cotta pieces were routed and sealed to close
the cracks and prevent water infiltration
within. Second, to prevent the porous surface
of the terra cotta where glazing failure
had occurred from absorbing water from
the surface in the future, a breathable protective
elastomeric coating was applied to
the surfaces of all the terra cotta elements
within the parapet, cornice, and soffit. This
process sealed the terra cotta system (but
allows it to breath or release trapped moisture
vapor) and had the added benefit of
creating a uniform, clean look to the entire
ornate cornice (see Photo 10). The repairs
to the parapet above were intended to limit
water entering the cornice.
CONCLUSION
With a clear understanding of the historical
systems involved, it was possible to
reevaluate assumed conditions at the subject
property and determine the root causes
of deterioration at the parapet and ornate
cornice. Furthermore, innovative thinking
and design approaches allowed a preservation/
restoration approach to the repair
methodology to be implemented without
causing a large variation from the historical
appearance of the building. The resulting
project was completed in november of 2013,
ahead of schedule and under budget at a
cost of approximately $4 million, or close
to a $30-million savings from the original
proposed restoration project.
REFERENCES
1 r Ci educational program, “masonry
Wall Systems.”
1 0 8 • B e n t z a n d p a y n e 3 0 t h RC I I n t e R n a t I o n a l C o n v e n t I o n a n d t R a d e S h ow • M a R C h 5 – 1 0 , 2 0 1 5
Photo 10 – Completed repairs at terra cotta cornice and parapet.