Skip to main content Skip to footer

The Last Few Feet: Parapet Design, Issues, and Repair

November 14, 2013

The Last Few Fee t:
Parape t Design, Issues, and Rep air
Logan Cook
Matthew Novesk y, RA
Wiss, Jann ey, Elstner Associates, Inc.
10 South LaSalle, Suite 2600, Chicago, IL 60603
Phone: 312-372-0555 • Fax: 312-372-0873 • E-mail: lcook@wje.com and mnovesky@wje.com
S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 3 C o o k a n d No v es k y • 1 5
ABSTR ACT
The design considerations and service life issues for parapet walls can be very complex.
If not detailed, constructed, or maintained properly, parapet walls can be a source of water
infiltration into the building and/or result in structural deficiencies of the façades and
structural roof system. This presentation will discuss general design principles and considerations
as well as common issues observed in both historic and modern parapet detailing
and construction. Case studies of parapet repairs and replacements will be presented. Case
studies will discuss the challenges of retrofit designs for the parapet wall structural system
and detailing of integral flashing systems.
SPEAKER S
Logan Cook – Wiss, Jann ey, Elstner Associates, Inc.
Logan Cook is an Associate II with WJE. Mr. Cook graduated from Purdue University
with a B.S. in construction engineering and management and an M.S. in engineering. Since
joining WJE in 2012, he has served as a project engineer on assignments related to the
analysis, investigation, repair, construction, and restoration of new and existing buildings.
Matthew Novesky, RA – Wiss, Jann ey, Elstner Associates, Inc.
Since joining WJE in 2000, MATTHEW Novesk y has been involved in projects related
to the inspection, investigation, and repair of distressed conditions in existing buildings.
He has conducted investigations related to distressed façade conditions and water leakage,
provided recommended repair options, and observed installation of repair solutions for
masonry construction and water leakage mitigation. Mr. Novesky has authored papers on
exterior façade materials related to typical construction detailing and failure mechanisms
for numerous building materials.
1 6 • C o o k a n d No v es k y S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 3
INTRODUCTION
The last few feet at the top of many buildings
consist of façade extensions above the
roof level, known as parapet walls. Parapet
walls can serve many functions, including
but not limited to fire protection from adjacent
buildings, concealment of mechanical
or HVAC equipment on rooftops, and guardrails
for outdoor roof terraces. Parapets can
significantly vary in design, material, and
construction technique. The tops of buildings
can be highly decorative, with projecting
cornices and balustrades; or they can
be minimal, with a low profile or no parapet
and only a gravel stop. Regardless of the
construction or function, the design, maintenance,
and repair of parapets is important
and can pose a number of challenges due
to as-built construction and exposure to
natural elements.
Building systems that interface parapet
walls—in particular, masonry parapet
walls—include roofing, waterproofing, water
management components, building façades,
structural components, and even mechanical
and electrical systems. Successful integration
of these systems requires planning,
communication, and foresight during
design and construction.
This paper will discuss the design of
masonry parapet walls and structural/
water-leakage issues and concludes with
two case studies of masonry parapet repair
projects designed by the authors.
DESIGN
The performance of building systems is
dependent on the design and construction
of proper detailing. Masonry parapet walls
are no exception to this generalization.
There are numerous important structural
and architectural-design criteria that must
be considered, including wind loads, thermal
movement, attachment to roof structure,
integration of various building materials,
exposure to environmental elements on
three surfaces, and water management.
Structurally, parapet walls behave as
a vertical cantilever or overhanging beam
projecting above the roof levels. Therefore
shear, axial, and bending forces must be
resolved at the base of the parapet wall.
Local building codes define structural
requirements for building elements based
on their height and exposure. At a minimum,
lateral resistance from wind loads
must be calculated. The lateral resistance
of a parapet wall is a function of the height
above the roof level (or highest connection
point to the building structure), width, and
reinforcing (if present).
Historically, parapets were mass
masonry walls constructed as an element
continuous with the façade. Expansion of
masonry parapet walls, due to the natural
absorption of moisture by clay material and
thermal properties, often results in displacement
and cracking within the wall.
Incorporation of expansion joints in building
façades, particularly at parapets, helps
to accommodate this movement. Expansion
joints in contemporary building types, when
integrating various construction materials,
are critical to allow the building to function
properly.
Successful integration of parapet walls
with roofing, waterproofing, and water management
systems requires knowledge of
these systems and their detailing requirements.
Detailing the termination of the
roofing system at the parapet needs to be
coordinated with wall flashings to ensure
that water is neither trapped in the parapet
wall nor allowed to bypass water management
systems. Proper detailing should be
developed between the two systems to facilitate
discharge of water that infiltrates the
system. In order to mitigate moisture that
can enter through the parapet wall, roofing
and waterproofing terminations should be
designed to provide adequate drainage of
the flashing systems. Water management
systems are ideally coordinated with parapet
designs to ensure the proper drainage of
water through scuppers or drains. In some
instances, parapet waterproofing systems
are integrated with flashing systems in the
façades; one example of this is at window
locations.
When constructing parapets, coordination
between the trades (roofers, masons,
sheet metal workers, etc.) is critical to successfully
execute proper detailing at the
parapet and create a watertight system.
Furthermore, it is important that the project
architect conduct regular site visits to
observe the construction and integration
of the building materials, particularly at
interfaces, to ensure that the as-built conditions
represent the original design intent
and function.
The construction of masonry parapet
walls has varied widely throughout history
and has changed with the integration of
multiple façade materials and waterproofing
systems. When investigating or repairing
masonry parapets, it is important to
investigate and document the system, as
repairs to appropriately address the issues
will vary. The following section will provide
an overview of historic and contemporary
masonry parapet systems and their performance.
Historic Masonry Parapets (pre-1950)
Historic masonry parapet wall construction
varies based on the time period and
style that the building was constructed.
Generally, historic masonry parapet walls
consisted of multiwythe mass masonry
walls with mortar-filled collar joints
between wythes and limestone or terra cotta
coping units. It was generally assumed that
the self-weight of these mass masonry parapet
walls resisted the demands from wind
loads, though the design was not based on
current factors of safety. Roofing systems
typically terminated on the face of the wall
or underneath the coping units.
Mass masonry walls were generally
intended to function as a barrier system
without flashing and integral waterproofing
systems. The outer wythe of the mass
masonry wall is depended upon to shed as
much water as possible; however, the porosity
of the brick and, more importantly, the
mortar joints, allows water absorption into
the wall. The backup brick masonry also
absorbs moisture as it penetrates through
the face brick and holds water until it evap-
The Last Few Fee t:
Parape t Design, Issues, and Rep air
S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 3 C o o k a n d No v es k y • 1 7
1 8 • C o o k a n d No v es k y S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 3
orates during drying periods. These periods
of wetting and drying, in conjunction with
temperature changes within the masonry
walls, result in expansion and contraction
as well as freeze/thaw-related deterioration.
This movement was accommodated by
incorporating various forms of setbacks in
the façade walls. Although designers were
aware of these movements within buildings
and materials, the technology of sealants
and expansion joints was not refined to current
standards until the 1960s.
Contemporary Masonry Parapets
(post-1950)
Contemporary masonry parapet walls
can be constructed from a number of different
materials and wall types. Often in contemporary
construction, masonry parapet
walls are constructed as cavity walls. Cavity
walls typically include an outer wythe of
masonry, an air cavity, an air/vapor barrier
system, insulation, and a backup wall.
The backup wall in contemporary construction
can consist of brick masonry, concrete
block, cold-form steel stud framing, structural
steel framing, or structural concrete
framing. Demands from wind forces are
resisted by the anchorage of the backup
wall to the building structure, which is
typically the roof framing. The face brick
is laterally anchored to the backup wall at
regular intervals to provide lateral resistance
to wind load on the exterior face of
the parapet wall. Sheet flashings and membranes
are applied to the exterior face of the
backup wall to minimize water infiltration
into interior space.
Similarly to mass masonry walls, the
face brick in cavity walls serves as a rain
screen for the wall’s moisture management
system. Water that enters the wall system is
managed by wall flashings and membranes
to direct moisture back to the exterior
through weeps.
Movement in contemporary masonry
parapet walls due to different thermal
expansion and contraction properties of the
materials is accommodated with vertical
and horizontal expansion joints. Expansion
joints are regularly spaced to divide the
wall system into individual sections to control
expansion or contraction of the given
materials. Expansion joints are also often
used to separate different wall materials
at transition locations. Sizes of the joints
vary based on anticipated movement of the
parapet. Backer rods and sealant are relied
upon to fill the expansion joints to create a
watertight barrier that accommodates the
movements of the joints.
THE ISSUES
Deficiencies that can be associated
with deterioration or poor performance of
a masonry parapet wall during its service
life are very similar to those found in
façade walls of similar construction. This
list includes water infiltration, freeze/thaw
deterioration, and displacements or cracking
due to building movement or material
expansion. The causes for these deficiencies
vary, and it can be challenging to identify
them and determine appropriate repairs.
Water Infiltration
Water infiltration into the top floor is
often immediately attributed to the roofing
system or the exterior façade system.
However, it may not always be due to
the material or installation itself but rather
to the detailing of these materials. As
discussed in the previous section, proper
detailing of the interface between the roofing
system and a masonry parapet wall
requires an understanding of how each of
these components performs individually.
If the masonry parapet wall incorporates
flashings, the roofing system details should
be coordinated to ensure that water draining
from the masonry via the flashing is
permitted to drain outside of the roofing
system. This solution is often detailed with
the masonry flashing system installed above
the termination of the roofing system.
As previously discussed, many mass
masonry walls were historically constructed
without the use of flashings, as it was
assumed that the multiple wythes of the
masonry wall would accommodate moisture
by retaining it until it evaporated during
drying periods. When terminating roofing
at these parapet walls, it is important to
understand that moisture will penetrate the
outer wythe of the masonry wall. Moisture
within a wall system can be trapped by and
damage a roofing system if not properly
detailed.
When a roofing system is replaced at
the end of its service life, the repair and
maintenance of masonry parapet walls are
often not included in the scope of work.
To maintain a watertight exterior building
envelope, it is important that parapet walls
be repaired and maintained, not only to provide
a good substrate for the roofing system,
but also to mitigate water that can bypass
the flashing or roofing systems.
Freeze/Thaw
Freeze/thaw deterioration in masonry
occurs when excess moisture saturates
masonry materials and repeated freezing
and thawing cycles result in expansion
forces due to natural expansion of water
as it freezes. Depending on the properties
of the masonry, the saturation level at
which freeze/thaw deterioration occurs varies.
Freeze/thaw deterioration is exhibited
by spalling or exfoliation of the masonry
and can cause excess moisture to enter into
the parapet wall system. In extreme cases,
it can result in the loss of capacity of the
parapet wall to resist the impact of wind.
There are a number of deficiencies that
can lead to the wetting of brick masonry and
freeze/thaw deterioration. Excess moisture
can enter the system through open or deteriorated
mortar joints, and moisture which
enters the parapet wall system may not be
able to adequately drain to the exterior due
to poor design or inappropriate repairs previously
implemented. This excess moisture
can accumulate and saturate the brick to
such a level that freeze/thaw occurs.
Displacements or Cracking
Masonry materials, particularly brick,
expand and contract based on their inherent
temperature and moisture content.
As the temperature or moisture content
increases, clay masonry expands. As the
temperature or moisture content decreases,
clay masonry shrinks. The rate of expansion
and contraction is dependent upon the
masonry materials, but buildings with long
uninterrupted lengths of masonry walls can
produce significant expansion and contraction
forces. When this movement is not
properly accommodated by expansion joints
or other methods, stresses in the masonry
can accumulate and cause cracking and
displacement. Permanent displacement or
“walking” of masonry can occur through the
natural expansion of masonry material. The
day that a clay masonry unit is fired and
removed from the kiln, it is the smallest size
it will ever be. Subsequent to manufacturing
and often corresponding with installation,
clay masonry units expand due to their
absorption of moisture from the environment.
Another cause of displacement and
cracking of masonry is the result of differS
y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 3 C o o k a n d No v es k y • 1 9
ential building movements. While this phenomenon
can occur in all building types,
it is more predominant in buildings that
mix structural and façade elements, such
as a concrete-framed building clad with a
masonry veneer. In contrast to masonry
materials, concrete tends to shrink and
creep. Shrinkage in concrete begins to occur
as the hydration process takes place, which
often corresponds to placement. Creep
occurs over longer periods of time with
sustained loading, such as the dead load
of the structure. The differential movement
of masonry façade materials and the concrete
structural frame can cause the accumulation
of stresses in masonry façade systems
that have been integrated with the structural
system, which results in cracking and
displacement. Often, the magnitude of the
displacements are greater at the top of the
façade due to the greater length of differential
movement due to uninterrupted length,
exposure to moisture on both sides, and
exposure to changing temperature on both
sides.
Another cause of masonry displacement
and cracking is due to the corrosion of
embedded steel elements. In most brick
masonry construction, steel elements are
incorporated into the system such as shelf
angles, lintels, lateral ties, or even building
structural members. Corrosion of steel is an
electrochemical process that requires the
presence of moisture and oxygen. If moisture
is permitted to come into contact with
unprotected, mild steel elements, and oxygen
is present, corrosion will occur. In contemporary
construction, corrosion-resistant materials
that are used include stainless steel,
galvanized steel or steel protected by corrosioninhibiting
coatings, and flashing systems.
Corrosion scale can occupy a volume
four to ten times the original volume. If
corrosion scale is permitted to accumulate
and is confined by adjacent materials, it
can cause cracking and displacement of
adjacent materials. Corrosion of embedded
steel elements at the base of the parapet
wall can introduce cracking and bond separation
between the parapet wall and the
main body of the building. In some extreme
instances, the accumulation of scale can
result in upward displacement of the entire
parapet. Lateral displacement or leaning of
the wall may then occur due to the dimensional
changes caused by the accumulation
of corrosion scale or decreased structural
capacity caused by cracking.
Falling Fragments or Collapse
If building movement or high loading
occurs while the masonry parapet exists
in a deteriorated state due to the distress
mechanisms described above or lack of
maintenance, falling fragments or collapse
can occur. Falling fragments or collapse of
masonry parapet walls pose a life safety risk
to pedestrians and property below.
CASE STUDY 1
Our first case study is a five-story condominium
building on the northwest side of
Chicago. Built in 2004, the exterior façade
consists of jumbo-sized face brick, cast
stone, and limestone accent units. Each
unit has a balcony on the exterior building
façade that is accessed through sliding
glass doors. The top of the building is
adorned with decorative parapet walls at the
building corners and centers of the façades.
These decorative parapets incorporate various
brick patterns (running bond, soldier,
and stack bond courses) and project outward
from the main façades with stepped
courses and corbeled brackets. The remaining
portions of the parapet walls are straight
and flush with the main building façades.
The top of the parapet walls were originally
capped with limestone units and overclad
with aluminum sheet metal. The roofing
membrane was turned up onto the backside
of the parapet wall and terminated underneath
the original limestone coping units.
Wiss, Janney, Elstner (WJE) investigated
an ongoing water leakage issue at
the top-floor level along the exterior walls.
Interior water leakage was observed at the
drywall soffits above the balcony doors and
at various random locations within the field
of the exterior wall to the fifth-floor ceiling.
Our investigation started with limited water
testing followed by inspection openings in
the masonry façade to document concealed
as-built details and material conditions.
During our investigation phase, we
reviewed the original architectural and
structural drawings that were provided by
the ABAA (hereinafter referred to as “the
association”). Details were limited for the
parapet wall construction, and differences
were noticed between the architectural and
structural sets.
In the structural drawings, the concrete
masonry unit (CMU) backup wall was identified
to be reinforced with vertical reinforcing
in fully grouted cells at 16-inch centers.
The structural drawings also called for the
CMU course above the head of the fifth floor
window to be a reinforced, fully grouted
bond beam. This bond beam was shown to
provide support and anchorage for the steel
bar truss roof joists. These details were not
called out or referenced on the architectural
drawings. Our limited inspection openings
at the parapet provided evidence that indicated
that some of the design details had not
been constructed. For example, open head
joints in the backup CMU course above the
fifth floor windows were open, indicating
that it was not a solid bond beam.
Water testing of the exterior face of the
parapet walls was performed using a calibrated
spray rack. Testing produced interior
leaks at window heads directly below the
shelf angle. Face brick was removed above
Brittle flashing
material without end
dams or mechanical
attachment to the
CMU backup wall
Loose laid
steel lintel
Figure 1 – Typical view of inspection opening with inadequate flashing details.
2 0 • C o o k a n d No v es k y S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 3
the shelf angle at the fifth-floor windows
to observe the condition of the underlying
flashing and construction of the façade
walls. The inspection openings revealed that
the original flashing had numerous issues,
including but not limited to embrittlement
of the flashing membrane that allowed cuts
and splits in the membrane, lack of sealant
at membrane splices, lack of mechanical
attachment of the membrane to the backup
wall along the top leading edge, and missing
end dams at the ends of lintels (Figure 1).
In addition to flashing issues, the as-built
construction of the wall system was also
problematic. The backup wall was CMU
with open head joints. No flashing system
or weather barrier had been applied to the
backup wall, and the cavity space between
the backup wall and the backside on the
face brick was insufficient for a true cavity
wall system. The cavity space was actually
a collar joint that measured approximately
½ to ¾ in. wide and was partially filled with
mortar.
Based on our testing and observations
from the inspection opening, we determined
that the interior leakage was a result
of improper flashing details and installation,
and as-built construction. Water that
entered the parapet wall past the face brick
could migrate past the flashing system and
enter into the building. We recommended
that the face brick from the window head
of the fifth floor, up to and including the
parapet coping, be removed to allow for the
installation of new flashing at the window
head, repair of the backup wall construction,
installation of a new weather barrier
on the backup wall, and reconstruction of
the brick veneer with new copings.
Because our initial investigation was
limited in regards to the amount of masonry
removed, we were not able to verify the
construction of the parapet wall in terms
of its reinforcing and structural capacity.
Therefore, we discussed with the association
our concerns that the existing parapet walls
were not constructed as originally designed
and recommended that the structural system
of the backup wall be reviewed as part
of the repair project to the flashing system.
Once the association retained a masonry
contractor, the removal of the brick veneer
began. When a substantial amount of the
veneer was removed, we began our evaluation
of the backup wall and structural system.
The sheet metal and limestone copings
were removed from a portion of the wall.
Looking down at the top of the CMU backup
wall, it was observed that the cores were
filled with mortar and debris. The contractor
drilled down into the cores at numerous
locations and determined that the fill was
only approximately one course deep. Since
vertical reinforcing and vertical grouted
cells could not be identified from the top
view, we used a metal detector in an effort
to locate vertical reinforcing bars. When
vertical reinforcement was not detected,
the masonry contractor drilled holes in the
CMU wall to verify whether or not cells were
grouted solid as per the spacing call-out on
the structural drawings. Vertical reinforcing
or grouted cells were not encountered at any
of our inspection locations.
In some areas, the contractor removed
the face cell of the CMU at the course
directly above the window head to verify
whether or not a bond beam existed at
this location. We observed that horizontal
reinforcement was installed at this course
level, but the CMUs were not grouted. The
reinforcement was loosely laid in the CMU
and was not engaged. During our structural
investigation, we also reviewed the anchorage
of the roof joints. The top flanges of the
joists were observed to have been installed
into and bearing on the interior face shell of
the CMU wall. The ends of the joists were
not mechanically fastened to the building.
Since the backup wall did not appear to
have any reliable structural reinforcement,
we performed a limited structural analysis
of the existing parapet walls. Calculations
revealed that the as-built taller parapet
walls at the building corners and center
of the façades were not adequately constructed
to resist wind loads specified in
the Chicago Building Codes for the time the
building was constructed. Based on these
observations, we presented additional repair
options to the association to address structural
deficiencies. Structural repair options
included the following:
• Install vertical reinforcement at
16-in. centers and grout the cells
solid to resist the required wind
loads or reduce the height of the
taller parapet walls to an adequate
height.
• Install 6-in.-long horizontal steel
bars at the roof joint embedment
location. These bars would be welded
to the flange of the joists, and the
cells grouted solid to provide positive
anchorage of the joists to the building
structure.
Since a contractor was already on site
and moving forward to perform the original
repair scope of work, the association moved
quickly in making repair decisions. They
decided to reduce the overall height of the
parapet walls to a consistent height around
the building and install the supplemental
anchorage at the ends of the roof joists.
With the additional structural repair
work defined, the entire scope of repair work
consisted of the following:
• Reduced the parapet wall height to
approximately 16 in. above the roof
level. CMU and brick veneer were
removed and the top course of the
remaining CMU wall was grouted
solid to allow for anchorage of wood
blocking and installation of a new
Joist flange
6-inch long steel
reinforcing bar
welded to joist flange
CMU cells to be
grouted solid
Figure 2 – Typical repair of steel joists in CMU wall.
S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 3 C o o k a n d No v es k y • 2 1
metal coping.
• The exterior face shell of CMU was
removed at the embedded joist locations,
and new 6-in.-long horizontal
steel reinforcing bars were welded to
the top of the joist flanges. The cells
with the horizontal bars were grouted,
and the face shells reinstalled.
See Figure 2.
• The remaining CMU backup was
pointed to fill the open joints solid.
• Steel shelf angles were cleaned
and painted. None of the angles
had experienced significant section
loss; therefore, replacement was not
required.
• A vapor-permeable liquid weather
barrier was applied on the exterior
face of the CMU wall.
• Self-adhered flexible membrane was
installed on top of the shelf angles
and turned up onto the face of the
backup wall.
• Stainless steel lateral wall ties were
installed at 16-in. centers vertically
and horizontally and staggered for
the height of the parapet wall.
• New face brick was installed, with
plastic cell vents at every other head
joint and placed directly on top of
the lintel at the top of the fifth-floor
windows.
See Figure 3 for typical view of parapet
repair.
To prevent the new parapet wall from
looking like a typical flat surface, we utilized
some aspects of the original parapet wall,
such as using two different brick colors
(one color at the flat walls and one color
at the building corners and center of the
façades) and various brick patterns at the
building corners and center of the façades.
These areas of decorative brick patterns
also incorporated changes in the plane of
the wall to provide
an aesthetic
appearance that
mimicked the
original design.
See Figures 4
and 5.
CASE STUDY 2
Background
Our next case
study is a nine-story
residential building,
rectangular in plan,
with dimensions of
approximately 100 ft.
by 75 ft. Construction
of the building was
completed in 2001.
Within one year of
completion, a routine
façade inspection
required by the City
of Chicago Building
Code identified cracking
and displacement of brick at the parapets
and façade corners. In 2002, masonry repairs
were performed at the parapet. In 2003,
cracks and distress in the masonry parapets
were again reported and subsequently
repaired. In 2004 and 2006, the center section
of all four-parapet walls, equal to 50
percent of the total length, was rebuilt in
another effort to address issues of cracking
and displacement. Later in 2006, the parapet
wall was deemed to be imminently hazardous
during a routine façade examination of the
building as required by the code. The building
installed a protective sidewalk canopy in 2006
to mitigate the life safety hazard. In 2007, the
building owners contacted WJE to investigate
the cause of continued cracking and displacement
of the masonry façade and parapet and
to provide repair recommendations.
Rebuilt parapet wall
Roof line
Vapor-permeable
liquid weather barrier
Stainless-steel
lateral wall tie
Self-adhered flexible
membrane with
stainless-steel drip edge
Figure 3 – Typical repair at parapet wall.
Figure 5 – Building façade after completed repairs.
Figure 4 – Building façade before repairs.
2 2 • C o o k a n d No v es k y S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 3
The Design
The residential building is clad with brick
masonry veneer with punched window openings
on all four façades. Steel lintels support
brick masonry and CMU at openings in the
exterior walls. No shelf angles were provided
in the field of the brick masonry walls. The
structural system for the building consists
of precast hollow-core concrete floor planks
supported by load-bearing CMU walls. The
openings in the façade occur as single windows
or as ganged windows separated by
masonry piers. Vertical bands of brick soldier
courses project slightly from the plane
of the brick field and extend from the first
floor to the parapet. The construction of
the façade is similar on all four sides of the
building. See Figure 6 for a view of the south
façade in 2007.
As originally designed, the parapets
are two wythes thick and three brick soldier
courses tall that are corbelled outward
(Figure 7), and the lowest parapet brick
course is arched above the ganged window
bays. The inner wythe of the parapet consists
of six courses of running-bond brick supported
on hollow-core concrete roof planks.
The use of hooked anchor bolts for the
coping and the use of shading symbols in the
collar joint cavity behind the brick veneer on
the original design drawings demonstrate
that the collar joint between the brick
veneer and CMU backup at the parapet is
intended to be fully grouted. The original
drawings specified horizontal adjustabletruss
reinforcing in the cavity wall installed
at 16 inches on center. The specified compressive
strength of the masonry (f’m) was
2,500 psi using a
type “N” mortar.
The original
design drawings
specify four vertical
expansion
joints to be provided
on each
façade. Horizontal
expansion joints
are not specified
on the drawings.
The EPDM
roofing membrane
was shown in the
original drawings
to extend up the
backside of the
parapet wall and
over the blocking
for the aluminum
coping.
The as-built condition of the parapet
varied from the original design and was
altered a number of times in attempts to
repair the distress exhibited by cracking
and inward displacement of the masonry.
The as-built condition of the parapet in
2007 consisted of a collar joint filled with
mortar and brick above the roof slab, typically
without lateral ties. See Figure 8 for
typical as-built condition during parapet
disassembly in 2008.
The Issues
Within a year of completed construction,
an investigation by other consultants
revealed cracking and displacement of the
masonry parapet wall. A 2006 investigation
by another consultant revealed maximum
inward leans of the parapet walls to be 4 to
6 inches from the vertical plane of the wall,
which resulted in the 2006 “imminently
hazardous” classification.
Our investigation in 2007, six years
after completion and after multiple repair
campaigns, revealed the current state of the
parapet wall consisted of an inward lean of
approximately 1 to 3 inches in three vertical
feet at the top-three soldier courses of
brick masonry above the arches (Figure 9).
Cracking of mortar joints and brick masonry
also existed on the parapet (Figure 10).
After inspection openings were made to
determine the construction of the parapet, a
structural evaluation was performed to evaluate
the as-built construction. The structural
evaluation concluded that the brick
Figure 6 – View of the south façade of the building in 2007.
Figure 7 – Typical parapet detail from the original design
drawings.
S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 3 C o o k a n d No v es k y • 2 3
veneer and typical exterior
bearing walls were
structurally adequate
to resist design loading.
However, evaluation of
expansion and shrinkage
of the façade resulted in
the total differential movement
between the CMU
backup wall and the
brick veneer of approximately
1.2 in. The estimated
vertical expansion
(moisture and thermal) of
the brick masonry for the
full height of the building
was approximately 0.9 in.,
and the estimated total
shrinkage of the CMU
was approximately 0.3
in. This differential movement
is consistent with
the observed angle of displacement
at the parapet
wall.
The total differential
movement was more pronounced
at the parapet
due to lack of relief angles
and horizontal expansion
joints in the field of the
wall, which accommodate
differential vertical movements
by creating brick
“panels” that move with
the structure. In the field
of the wall, the brick
veneer and CMU backup
were “isolated” with a cavity
wall and adjustable lateral
ties, permitting independent
movement. In
contrast, the parapet was
constructed in a manner
that integrated these two
systems, essentially bridging
the isolation. Due to
the sum of differential
movements increasing at
higher levels, this integration
at the parapet resulted
in the inward lean of
the parapet and cracking
of the brick masonry.
The inward lean was more
pronounced at the center
along the length of the
parapet wall due to the
Inner wythe of brick masonry
Mortar and brick-filled collar
joint above roof line
Treated wood blocking for
temporary parapet
Outer wythe of brick
masonry parapet
Hollow-core concrete
roof planks
Loose-laid steel lintel with
flashing above window
CMU backup at wall below
Figure 8 – As-built condition of the parapet from 2007. Photo taken during parapet disassembly in
2008.
Figure 9 – Typical inward lean of masonry
parapet wall in 2007.
Figure 10 – Typical cracking of mortar
joints at parapet wall in 2007.
2 4 • C o o k a n d No v es k y S y m p o s i u m o n B u i l d i n g E n v e l o p e T e c h n o l o g y • No v e m be r 2 0 1 3
inherent stiffness at the corners of the parapet,
which helped to restrain movement.
Cracking and displacement of the brick
masonry also existed at other locations in
the field of the wall, primarily adjacent to
window locations where the “isolation” of
the two systems was bridged by steel lintels
and window frames.
Repair
Following the investigation, we recommended
that the parapet be disassembled
and redesigned. In 2008, the parapet was
disassembled and replaced with a temporary
parapet constructed of treated wood
studs, plywood, and roofing membrane. The
EPDM roofing warranty holder was contacted
to coordinate the removal of the parapet
so that the existing roof warranties were not
voided. (See Figure 11.)
Construction of a new parapet is currently
in progress. The new parapet design
consists of light-gauge, steel-stud framing
with a brick veneer in running bond, and an
aluminum coping at a height of approximately
2 ft. above the roofline. The light-gauge,
steel-stud framing is anchored to the hollow-
core concrete roof planks with powderactuated
fasteners. The brick veneer is
laterally tied back to the framing with
stainless-steel lateral anchors spaced at 16
in. on center. Vertical expansion joints are
designed to be installed in the same location
as the existing vertical expansion joints.
The water management system of the
parapet wall consists of self-adhered wall
flashing in the cavity wall with end dams
and weeps. The design of the new roofing
flashing system was coordinated with the
EPDM roofing warranty holder to ensure
that the tie-in of the new roofing system
does not void the remaining warranty of the
roof. The tie-in of the new roofing flashing
consists of a fully adhered EPDM flashing
membrane extending over the wood blocking
and down the back face of the parapet,
and adhering to the existing EPDM membrane
with seam tape. A reinforced membrane
attachment with seam plates and
fasteners will be integrated at the interface
of the parapet wall and roofing to ensure the
membrane does not fail at the corners. See
Figure 12 for a typical parapet repair detail.
CONCLUSION
Masonry parapets serve a variety of
functions for a building and exist in many
different forms. From the decorative to the
purely functional, proper detailing of parapets
requires understanding of the number
of systems and materials that interface at
the parapet wall. Construction of parapets
requires the coordination of many trades and
ideally includes construction observation
by the architect to verify that the as-built
conditions adhere to the design intent. The
issues associated with masonry parapets
are similar to those found in the field of a
masonry façade. However, determining the
causes and the appropriate repairs for the
issues observed at the parapet wall requires
an understanding of the systems and materials
utilized, proving that sometimes, the last
few feet are the most challenging.
Figure 11 – Temporary treated wood-framed parapet wall installed in 2008.
Figure 12 – Typical repair detail for a new parapet wall.