Skip to main content Skip to footer

Topics in Underground Parking Structure Repair

April 24, 2006

Proceeedings of the RCI 21st International Convention Gernetzke and Maki – 103
Topics in Underground
Parking Structure Repair
Roof Consultants Institute
Thomas M. Gernetzke, RRC, CDT
Daniel L. Maki, PE
Facility Engineering, Inc.
Madison, Wisconsin
ABSTRACT
The assessment and repair of underground parking structures provide a
unique business opportunity for many roofing/waterproofing and building
envelope consultant firms. This presentation will discuss the following topics
in underground parking structure assessment and repair:
• Key members of the assessment and design team
• Sources of exterior water infiltration
• Sources of interior water infiltration and moisture control
• Typical concrete repair techniques
• Expansion joint repair and rehabilitation
• Waterproofing repair and rehabilitation
• Parking and horizontal deck membrane repair and rehabilitation
• General project considerations
SPEAKER
THOMAS GERNETZKE has served as project manager on multiple projects involving underground
parking structures. These projects include initial condition assessments and recommendations,
waterproofing and expansion joint rehabilitation, structural concrete repair, parking deck
membrane replacement, and cathodic protection.
Gernetzke and Maki – 104 Proceeedings of the RCI 21st International Convention
INTRODUCTION
The assessment and repair of
underground parking structures
provide a unique business opportunity
for many roofing, waterproofing,
and building envelope
consultant firms. Discreet beneath
the surface, these structures
are continuously subjected
to moisture from external and
internal sources. These represent
some of the harshest conditions
in the built environment. Conversely,
these structures often
provide the first impression of a
facility to a visitor. Dripping water,
spalling concrete, stalactites, and
other moisture infiltration-related
conditions present an appearance
of poor maintenance and public
safety concerns. Moisture infiltration
and electro-chemical corrosion
processes develop exponentially.
Unchecked, these processes
will cause eventual structural failure.
With construction costs
sometimes exceeding $40,000 per
parking stall, combined with the
less-discernable value of damaged
first impressions, these structures
represent a significant investment
to an owner.
STRUCTURE ASSESSMENT
As with any rehabilitation project,
the first requirement is
assessment. The assessment of
the structure should be completed
in multiple phases. The initial
phase should include the assessment
team: owner’s representatives,
waterproofing consultant
(WC), corrosion specialist, and
structural engineer. The owner’s
representatives should include
the person most knowledgeable
about the structure in question.
The corrosion specialist and
structural engineer can be one
and the same. The intent of the
initial phase is site orientation for
the assessment team and collection
of relevant documentation,
such as as-built drawings and
repair history. Operations and
logistics, such as security and offhours
access, should also be discussed.
During this initial phase,
the owner should describe specific
concerns or questions he may
have, as well as specific requirements
for the assessment.
Based on the initial observations,
owner requirements, and a
plan review, a thorough inspection
should be conducted.
Whenever possible, as-built and
record drawings should be
reviewed. It is important to consider
shop drawings; construction
and contract documents may not
reflect actual conditions. Much of
the assessment will and should
occur off-hours, when there is the
least amount of traffic. The engineer
will probably require chain
dragging, hammer tapping, or
other initial non-invasive tests.
The WC may want to observe the
structure during a rain event. In
any event, flexibility in scheduling
inspections is critical; off-hours
inspections are often beneficial
and necessary for multiple reasons.
First, it is very important to
consider that a parking structure
can be a dangerous work environment.
Second, a parking structure
can be loud and distracting
for an assessment team. In many
instances, the assessment team
members should conduct their
inspections independently of each
other. While each party is looking
for deficiencies, different deficiencies
can be distracting for the
other members. A thorough
record of findings should be made
by each party and then compared
upon completion of the inspection.
After the assessment is complete,
a consolidated list of deficiencies
should be generated. It
may be beneficial to involve an
experienced parking structure
repair contractor if unusual or
difficult repairs are being considered.
COMMON AND RECOM –
MENDED ASSESSMENT
TECHNIQUES
One of the most important
assessment techniques is visual
inspection of all surfaces. Visual
inspection should include all surfaces
of a parking structure for
any indication of abnormal conditions.
Use of a drawing of the
structure and maintaining an
easily discernable pattern is
important. Carrying a masonry
hammer during the inspection to
sound questionable surfaces may
improve efficiency as well as
defining finish surface blemishes
from spalling or other deterioration.
Chain dragging is an important
and effective assessment
technique to determine the quantity
and location of horizontal surface
spalling. Typically, supported
concrete slabs are covered with
membrane or coating to protect
the slab from water and subsequent
chemical contamination.
These coverings or coatings
obscure spalls. Chain dragging is
conducted by dragging a length of
chain over the area to be inspect-
Proceeedings of the RCI 21st International Convention Gernetzke and Maki – 105
Topics in Underground
Parking Structure Repair
ed. When the chain
drags over a spall, a distinct
hollow sound is
heard. The size and
location of the spall can
be determined by
“sounding” around the
perimeter and marking
it with spray paint. If the
client is sensitive to permanent
marks, chalk
can be used.
Hammer tapping is
the same principle as
chain dragging. Hammer
tapping is primarily
used for vertical and
overhead surfaces. It
can be used to more
clearly define spall
perimeters discovered
during chain dragging.
Any amount of overhead
inspection will require
the use of a sounding
tool.
ASSESSMENT BY
STRUCTURAL
ENGINEER/
CORROSION
SPECIALIST
The involvement of a structural
engineer during the assessment
process is critical. While WCs are
trained to look for signs of moisture
infiltration (and possible subsequent
damage), a structural
engineer is trained to look for
signs of stress, fatigue, and other
damage or deterioration. A structural
engineer should determine
the extent of deterioration of
moisture infiltration and needed
repairs.
A structural engineer should
perform an analysis of the structure
to determine load capacities.
This is required information for
design and construction phases to
establish weight limits and capacities,
what removal techniques are
appropriate, and what repair
techniques may be possible or
required.
Gernetzke and Maki – 106 Proceeedings of the RCI 21st International Convention
Chain Dragging. When the chain drags over a spall, a distinct hollow
sound is heard. Spray-painted areas indicate spalls.
Sounding tool attached to pole. Teeth on gears tap on concrete.
As tool rolls over spalled areas, the sound changes.
A structural engineer may recommend
testing to determine the
condition of a structure. Testing
may range from non-invasive
(Swiss hammer, X-ray) to invasive
(coring).
A corrosion specialist may recommend
various testing methods
to determine the extent and severity
of corrosion in a structure.
These specialized methods include
chloride ion content sampling,
half-cell corrosion potential
testing, and electrical continuity
testing. These test results can be
used to determine appropriate
corrosion mitigation or corrosion
prevention techniques.
SOURCES OF EXTERIOR
MOISTURE INFILTRATION
Underground parking structures
experience the same external
moisture sources as any other
underground structure. Typically,
these sources of moisture include
stormwater (site) run-off, irrigation
systems, and naturally
occurring underground springs
and elevated water tables. In
coastal regions, salt water and
salt spray are a significant concern
for parking structures
because of the presence of chloride.
SOURCES OF INTERIOR
MOISTURE AND MOISTURE
CONTROL
Parking structures often experience
internal sources of moisture
that must be managed. A
prevalent source of moisture is
excessive humidity in unconditioned
structures. Underground
parking structures have coderequired
mechanical ventilation
systems to expel vehicle combustion
gases. Local code may define
ventilation in air changes per
hour, CFM per square foot, or
CFM per operating vehicle.1
Whatever the condition, volumes
of fresh, unconditioned air enter
these structures. Warm, moist air
contacting large,
cold concrete surfaces
produces
large quantities of
c o n d e n s a t i o n .
This phenomenon
can propagate itself
for extended
periods of time,
depending on conditions.
Condensation
moisture must be
managed. It may
be prudent to
detail membrane
transitions similar
to exterior applications
by using
appropriate sheet metal flashings.
Prolonged exposure to moisture
will deteriorate expansion joint
terminations, traffic- bearing
membrane terminations, and
other critical sealing components.
In addition, sheet metal and related
redundant flashings can provide
additional protection at slabto-
wall transitions where movement
may disturb membranes
and coatings.
Vehicles are a source of moisture.
In northern climates, vehicles
are often covered in road salt
and snow. De-icing materials
often contain a variety of chloride.
Chloride ion contamination is a
significant cause of deterioration
in parking structures and will be
discussed later. Over a season, a
parking structure full of vehicles
covered with salt and snow creates
tremendous exposure to
chloride ion contamination. The
condition is exacerbated with the
application of ice-melting materials
to maintain slip-resistant surfaces.
In coastal regions, saltwater
dripping from vehicles presents
another source of chloride
ion contamination.
Vehicles discharge a variety of
liquid substances. Automotive air
conditioning systems are similar
to building HVAC systems.
Condensate from automotive systems
contains the same copper
ions as HVAC systems and may
interact with less noble metallic
surfaces. While anti-freeze and oil
typically do not cause moisture
concerns, they can penetrate
unprotected concrete and cause
adhesion or contamination problems
during future repair work.
These materials can also damage
prefabricated joint systems and
sealant joints. Engines create volumes
of water vapor during combustion.
This warm, moist air is
another source for condensation
on cool concrete surfaces.
Maintenance activities, particularly
pressure washing and
cleaning, provide large quantities
of moisture, sometimes complicated
by humid conditions. Faulty
plumbing systems may also contribute
large sources of moisture
to the structure.
CAUSES OF COMMON
MOISTURE-RELATED
CONCRETE DETERIORATION
Corrosion of reinforcement in
concrete is a significant cause of
moisture-related concrete deterioration
in parking structures.
“Corrosion-induced deterioration
is the most dominant and aggressive
form of deterioration of parking
structures located in the
northern climactic region.”2
Proceeedings of the RCI 21st International Convention Gernetzke and Maki – 107
Reinforcing steel in new or
uncontaminated concrete does
not corrode because a passivating
layer of protective oxide forms on
the steel during the cement
hydration process. The presence
of calcium hydroxide in concrete
creates a high pH environment of
12 to 13. The presence of chloride
ion contaminant reduces the high
pH of concrete and will initiate the
corrosion process once the contamination
reaches the reinforcing
steel. If the pH falls below 11.5,
the passivating layer on the steel
will become unstable and can lead
to corrosion.3,4
Concrete is a porous material.
Concrete pores have a diameter
ranging from 15-1000 Angstroms.
The diameter of a chloride ion is
less than two Angstroms. One
angstrom is equivalent to ten millionths
of a millimeter.5 Trafficbearing
membranes and clear
water repellants provide a measure
of protection but cannot stop
chloride ion contamination. Slab
areas with poor drainage or
standing water exacerbate contamination.
Older structures are more
susceptible to chloride ion contamination.
Structures built prior to
the mid 1980s do not benefit from
air entraining admixtures, corrosion
inhibiting additives, or crack
reduction techniques. Prior to
1977 the minimum concrete cover
over reinforcement was 3/4-inch.
This minimal concrete cover provides
optimal conditions for rapid
chloride ion saturation and subsequent
corrosion. Today, ACI
362 requires a minimum of two
inches of cover.6
“Corrosion of a metal is an
electro-chemical process that
requires an oxidizing agent, moisture,
and electron flow within a
metal; a series of chemical reactions
takes place on and adjacent
to the surface of the metal.”7 This
electrochemical process requires
an anode, a cathode, an electrolyte,
and a return circuit. The
anode is the point where corrosion
occurs by migration of ions
into the electrolyte; the cathode is
the point where electrons are consumed
and no corrosion occurs.
The electrolyte (water-based solution)
carries ions capable of conducting
current. The return circuit
is usually the steel reinforcement
itself.8
Rust is a byproduct of the corrosion
process. The rust from the
reinforcement occupies a volume
greater (2.5 times or more) than
the steel itself. This expansion
causes stress in the surrounding
concrete resulting in cracking.
Once the concrete is cracked,
electrolyte, oxygen, and chloride
have a direct path to the steel,
further accelerating the corrosion
process. This cracking then develops
into delamination and eventual
spalling of the concrete.9
REPAIR TECHNIQUES
1. Horizontal Surface Spall
Repair
Horizontal surface spalling is
the predominant deterioration
mechanism in underground parking
structures. Even when protected
by traffic-bearing membranes,
these surfaces are still
susceptible to corrosion activities.
In order to perform these repairs,
an accurate delamination survey
must be conducted. During this
survey, it is important to remember
the markings will be a guide
for sawing. It is very difficult to
saw a radius or elaborate shapes
into concrete. Angles should be
kept (as close as possible) to 90
degrees or larger. Tight angles
often break off during the repair
process, creating unnecessary
work. For detailed information,
refer to the International Concrete
Repair Institute (ICRI) “Guide for
Surface Preparation for the Repair
of Deteriorated Concrete Resulting
from Reinforcing Steel Corrosion,”
Guide No. 03730.
Prior to beginning any spall
repair, it is critical to determine
the effects of the repairs to the
integrity of the structure. Buried
electrical conduits, prestressing
or post-tensioning tendons must
also be located prior to work.
Disrupting these items with a saw
or other means can create an
imminent safety threat.
The perimeter of the spall
must be cut, typically with a con-
Gernetzke and Maki – 108 Proceeedings of the RCI 21st International Convention
crete saw. It is desirable for the
depth of cut to be greater than
1/2-inch as long as the reinforcement
is not cut. After saw cuts
have been made to define the
perimeter, removal of the deteriorated
concrete above the corroded
reinforcement can begin.
Concrete removal should be limited
to 15-lb. chipping hammers or
smaller. Larger hammers often do
more damage than good.
Occasionally, larger hammers can
be used in certain situations by
trained technicians.
After initial removals have
been completed, the reinforcement-
to-concrete bond and the
condition of the concrete in the
vicinity of the rebar should be
checked. After the initial removal,
if the concrete is in good condition
and the rebar is well bonded, further
removal is unnecessary. The
rebar-to-concrete bond is checked
by lightly tapping the rebar with a
hammer. Heavy blows to exposed
rebar will de-bond the rebar,
requiring further repair. If lightly
striking the rebar with a hammer
produces a ping-type noise without
vibration, the bond is acceptable.
If striking the rebar produces
a thud and is accompanied
by vibration of the bar, the rebar
is not bonded, requiring further
removal and undercutting.
Concrete removal and undercutting
must be completed until both
ends of the exposed bar are wellbonded
to surrounding concrete.
Undercutting of reinforcement
steel should provide a minimum
of 3/4-inch clearance around the
bar or 1/4-inch larger than the
largest aggregate in repair material,
whichever is greater. A good
rule of thumb is a hand should be
able to be wrapped around all
portions of the exposed bar. This
will ensure there is sufficient
clearance for cleaning and preparation
of the bar. Any reinforcement
that is loose shall be
secured in place by tying to other
secured bars or by approved
methods, as directed by the structural
engineer.
Once the rebar has been
exposed and prepared, all heavy
corrosion and scale should be
removed by media blasting. An
oil-free abrasive blast is the preferred
method. By changing the
angle of the blast, all portions of
the bar can be addressed, either
by direct contact with the abrasive
or by rebounding the abrasive
off the concrete substrate. The
concrete substrate should also be
blasted to ensure laitance and
other foreign matter is removed.
This blast will help to achieve adequate
bond between repair (patch)
material and existing concrete.
If a rebar has a loss of significant
cross-section, the structural
engineer should be consulted.
There are multiple methods to
repair deteriorated rebar. The
structural engineer should determine
the most appropriate and
effective method for the repair.
Also, the corrosion specialist
should determine if epoxy or other
treatments should be applied to
the rebar. Rebar treatment will
depend on existing conditions and
future corrosion protection or mitigation
methods.
Once the removal, undercutting,
cleaning, and repair process
has been completed, the concrete
excavation needs to be final
checked for remaining spall conditions.
The structural engineer
should select the appropriate
repair (patch) material to be used.
Material considerations should
include time to cure, temperature,
size of repair, ease of use, return
to service time requirements, and
possible future cathodic protection
or mitigation efforts.
2. Vertical and Overhead Spall
Repair
Vertical and overhead spall
repair is similar in principle to
horizontal spall repair, with differences
being location of the repair
and techniques used to perform
the repair. Removal, undercutting,
cleaning, and repair requirements
are still the same. Repair
(patch) material and its placement
technique will dictate the preparation
required. Vertical and overhead
spall repairs often require
different material than horizontal
repairs.
For all repairs, care must be
taken to follow the manufacturer’s
instructions for bonding
methods and placement methods.
Corrosion Mitigation and
Cathodic Protection Systems
There are multiple methods to
mitigate or reduce corrosion activity;
their effectiveness is relatively
short-term. The two commonly
accepted methods are chlorideion
extraction and re-alkalization.
These methods are similar but
deliver different results. Both are
intended to return passivity to the
steel reinforcement. Both will
allow future contamination and
may require additional treatments.
Chloride ion extraction is
achieved by applying a conductive
media and electric current to the
slab. Re-alkalization is similar to
chloride ion extraction in that an
electric field is applied to the slab.
Re-alkalization also introduces an
alkaline electrolyte to the concrete.
The combination of the
applied electric field and the electrolyte
results in higher pH levels
and returns the reinforcement
steel to a passive condition.
For nearly-permanent results,
cathodic protection (CP) method is
“in concept, the only method
which will effectively stop the corrosion
of embedded reinforcement
in chloride contaminated
slabs…”10 Simply, CP introduces
electric current into the slab to be
protected.
Currently, CP installations are
limited to conventional, mildlyreinforced
concrete structures.
With caution, CP has been applied
Proceeedings of the RCI 21st International Convention Gernetzke and Maki – 109
in limited applications to
prestressed and post-tensioned
structures. These
structures present potential
hydrogen ion development,
causing embrittlement
and failure of highstrength
prestressing steel
and post-tension tendons.
EXPANSION JOINTS
The Construction Waterproofing
Handbook
claims the 90%/1% principle
of water intrusion: “As
much as 90% of all water
intrusion problems occur
within 1% of the total
building or structure exterior
surface area.”11 Expansion
joints are the epitome
of this principle. Waterproofing
expansion joints
are the most difficult,
expensive, and important
detail preventing longterm
moisture infiltration
into an underground parking
structure.
1. Vertical Joints
Vertical expansion joint leakage
is a primary moisture path
into an underground parking
structure. These joint systems are
often subject to intense hydrostatic
pressures, seismic movements,
building movement induced by
thermal expansion and contraction
and vehicular influences,
positive- and negative-side chemical
contamination, and vandalism.
Below-grade vertical expansion
joint repair and remediation
is difficult. A typical short-term
solution is epoxy injection of the
joint. Epoxy injection does not
allow for joint movement;12 however,
chemical grout injection can
provide some protection in movement
joints and is sometimes an
alternative to costly full-depth
joint excavation and repair.
Chemical grout injection requires
detailed cleaning and preparation
to remove mineral deposits and
other contaminants in order to be
effective. The grout injection
process can also cause additional
cracking if blind-side concrete or
joint conditions are deteriorated.
Full-depth excavation and
joint repair can provide assured,
long-term results, but this
method is expensive and can be
very disruptive. Depending on
conditions and depth of the joint,
these repairs can exceed $2000
per linear foot of joint. The primary
expense is the excavation and
shoring required to expose these
joints. Depending on the depth of
excavation, piling, lagging, and
related shoring items must be
designed by a registered professional
engineer (OSHA 29 CFR
1926.652). Shoring systems must
allow for adequate access to the
entire joint. This includes a minimum
of five feet on either side of
the joint to allow assessment of
the concrete as well as enough
area to tie-in to existing waterproofing
systems.
Dewatering responsibilities
must also be delineated prior to
the excavation. These excavations
can very easily fill with water,
exposing the under-construction
joint to premature water exposure
as well as deteriorating shoring
and piling systems. These excavations
are also defined as confined
spaces. Adequate protective measures,
such as harnesses, safety
lines, and ventilators, must be
used by anybody entering the
excavation.
Once the excavation and
shoring have been completed, the
existing joint system is removed
and the surface prepared for the
new joint. The preparation work
must be inspected prior to the
new joint system being installed.
The inspection should include a
thorough sounding (hammer-tapping)
to determine if any concrete
spalling or deterioration has
occurred. If spalling or other dete-
Gernetzke and Maki – 110 Proceeedings of the RCI 21st International Convention
Dewatering responsibilities must be delineated prior to start of work.
Note the ladder in the water.
rioration is observed, the area
must be repaired and restored to
its original condition. The primary
concern is the restoration of a
smooth and even surface condition
to allow the new joint system
to bond to the surface. Irregular,
cracked, or deteriorated surfaces
will cause joint failure.
Given the cost of these
repairs, redundant joint systems
are preferred. Each layer of the
membrane used should be
secured to the substrate independently
to secure against differential
movement and increased
hydrostatic pressures. For expansion
joints, the joint system
selected must also be able to transition
from vertical to horizontal
at the top of the joint. After the
joint system is installed, a bentonite,
clay-backed HDPE sheet
can be secured over the joint to
protect the joint as well as provide
additional waterproofing capabilities.
The HDPE sheet should be
considered as minimum to protect
the joint during the back-fill
process. Protection mat, drainage
board, XPS insulation, and other
means and methods can and
should be used to protect the new
joint from damage during back-fill
and finish grading.
The joint can be installed continuously
or by lifts as the excavation
is back-filled. Depending on
conditions, the back-fill material
and drainage systems must be
selected to (if possible) minimize
hydrostatic pressure on the new
joint. Back-fill materials can
range from course sand to clear
stone, pea gravel, or slurry fill. If
slurry fill is used, “half-bag” or
“diggable” slurry should be used.
Slurry with more Portland cement
content will be very difficult, if not
impossible, to excavate if any
future joint work or surface work
in the vicinity needs to occur.
Even with a half-bag mix, the concrete
cream will rise to the surface
and may create a nearly impenetrable
surface. During the backfill
process, the
shoring system
may be cut
down or removed
as necessary.
2. Horizontal
Joints
Below-grade
horizontal expansion
joints
are common
sources of water
i n f i l t r a t i o n .
Though not as
expensive to
repair as belowgrade
vertical
joints, horizontal
expansion joints require the
same care and attention.
Waterproofing manufacturers
specify joint details to be used
during the replacement of waterproofing
systems.
Below-grade horizontal expansion
joints are often located on
plaza-deck type systems. These
joints are often covered with overburden,
or can have asphaltic
concrete pavement applied directly
to them. Care must be taken
during the removal of the overburden,
as any existing joint integrity
will be lost during the removal
process. This is a critical consideration
if waterproofing over finished
spaces, pedestrian tunnels,
etc. Many do not consider parking
structures critical spaces, but
repainting vehicles damaged by
debris carried through open construction
joints is an expensive
and embarrassing proposition. In
addition, an open horizontal joint
can allow quantities of water into
a parking structure greater than
the available floor drain capacity
of the structure. Parking structure
floor drains are often restricted
or clogged with sand and
debris, or vehicle tires obscure
them. Vehicles should not be
allowed to park under joints during
construction.
3. Traffic-Bearing Joints
Traffic-bearing expansion
joints receive tremendous abuse
in a parking structure. These systems
must withstand UV exposure,
chemical exposure, vehicular
traffic, traffic-induced deflection
across joints, snow plowing
and removal operations, vandalism,
seismic movement, and other
deleterious influences. In addition,
these joint systems must
often be aesthetically pleasing
and meet accessibility requirements.
When detailing a new expansion
joint or a remedial application,
a primary consideration
must be the potential movement
of the joint. The structure must be
analyzed by a structural engineer
to predict movement. Possible
movement includes expansion
and contraction, sheer stress, and
differential movement unrelated
to thermal expansion and contraction.
Joint termination must often
accommodate the following conditions:
floor joints, wall-to-floor
joints, building-to-floor joints,
intersections with curbs, intersections
with columns, joints at
ramps, ramp-to-floor joints, intersections
of two or more joints,
changes in direction, and joint
Proceeedings of the RCI 21st International Convention Gernetzke and Maki – 111
terminations.13
Joint systems must
not create trip hazards.
Depending on individual
situations, joints
may have to be ADAcompliant.
These joints must
perform flawlessly
through the entire lifespan
of the system.
This continuous performance
can be assured
with a bi-annual
inspection and maintenance
program. This
program should be
included or added to
the required warranty
for the joint. Trafficbearing
expansion joint
system warranties are
void if maintenance is
not performed and
documented on a regular
basis.
Manufacturers’ warranties
must be carefully considered for
traffic-bearing joints. As previously
stated, consider movement
analysis by a structural engineer
in the design. This information,
including a worst-case movement
scenario, must be included in bid
documents. If building movement
exceeds the limits set by the engineer,
joint warranties are typically
voided.
Traffic-bearing joint warranty
considerations should include
“joint and several” warranties and
approved installer programs.
Joint and several warranties bind
the manufacturer and the contractor
for the life of the warranty.
If either party to the warranty
defaults or becomes unresponsive,
the other party becomes
responsible for the warranty.
Joint manufacturers that do not
have approved or licensed
installer programs should be further
scrutinized. These joint systems
require skilled, experienced
technicians to ensure proper
installation.
There are 11 main types of
expansion joint systems.14 They
are: sealant, T-joint, expanding
foam, hydrophobic expansion
seals, sheet, bellows, preformed
rubber, combination rubber and
metal, vertical, heavy-duty metal,
and below-grade applications.
Only T-joint systems, pre-formed
rubber systems, combination rubber
and metal systems, and
heavy-duty metal systems are
appropriate for use as trafficbearing
expansion joint systems.
Systems should be carefully chosen
based on its inherent
strengths and weaknesses.
The most popular and durable
traffic-bearing expansion joint
systems used in parking structures
are classified as pre-formed
rubber and combination rubber
and metal. These systems consist
of a pre-formed rubber gland,
mounting flanges, and elastomeric
concrete nosing set into blockouts
on either side of the joint.
The pre-formed rubber glands
consist of different profiles to
allow for different joint movements
and ADA requirements, if
necessary. These glands are typically
manufactured with a chemical-
resistant thermoplastic elastomeric
(TPE) material. TPE materials
can be heat-welded and have
similar properties to other thermoplastics,
such TPO and PVC
roofing membranes.
The joint glands are attached
to perforated flanges. Flanges are
set into the block-out area and
secured with elastomeric concrete.
The perforations in the
flanges provide an improved
mechanical connection of the
gland to the structure. The elastomeric
concrete provides the
mechanical connection to the
structure as well as providing protection
for the gland from vehicular
traffic and snow-removal operations.
Attention must be directed
to the particular manufacturer’s
material being used. Some manufacturer’s
elastomeric concrete is
not UV-stable and requires a
coating after installation.
Gernetzke and Maki – 112 Proceeedings of the RCI 21st International Convention
Localized failure of a pre-formed, traffic-bearing expansion joint. Photo
shows components of joint system.
Depending on the material, this
coating can deteriorate, causing
deterioration of the elastomeric
concrete.
As with any waterproofing
system, preparation is essential
for long-term performance of traffic-
bearing joint systems. Blockouts
to receive the joint gland
must be prepared exactly as
required by the manufacturer’s
installation instructions. This
often includes sounding of the
concrete to inspect for spalling or
other concrete deficiencies, concrete
repairs, and media blasting
of the block-out surfaces. Blockout
surfaces must be true and
level. If not, the joint gland may
pivot on uneven surfaces and create
a ratcheting action under flexural
movements, leading to adhesive
or cohesive cracking of the
elastomeric concrete nosing material.
Traffic-bearing expansion
joint systems are available with
manufacturers’ transition details.
As with all expansion joint systems,
transition details are the
Achilles heel to these systems.
Consult a manufacturer’s representative
during the design
process to ensure the correct
specification of joint transition
details and materials.
CONSTRUCTION AND PHASE
JOINTS
Construction joints (often
referred to as “cold joints”), phase
joints, and control joints often are
sources of water infiltration.
During initial construction, water
stops are often specified at these
critical locations. If the water
stops are actually installed during
initial construction, they frequently
are poorly installed or
damaged during concrete formwork
and placement.
During the leak investigation,
assessment, or design phase of a
remedial waterproofing project, a
careful review of as-built drawings
should be conducted to determine
the presence of known construction,
control, or phase
joints. Typically, control joints
should be located 30 feet apart
or closer. These control joints
are designed to crack during
plastic concrete shrinkage and
settlement. They are not
intended for movement other
than settlement. A cracked
control joint with a poorly
installed water stop is an ideal
moisture infiltration source.
“Cold joints” are often not
indicated on as-built drawings.
Due to the inherent weakness
of these joints, they can crack
more easily than the surrounding
concrete and allow
moisture infiltration. To aggravate
matters, water stops are
often not included in these
joints. Depending on original
construction methods used,
these joints can traverse entire
lengths of below-grade walls. If
a cold joint crack is detected
from the interior, a determination
must be made if there is
movement of the joint. This helps
to determine a course of action.
Depending on the importance of
the interior space, epoxy injection
or chemical grout injection should
be attempted as a first course of
action. If injection systems do not
perform adequately or if the joint
cannot be accessed from the interior,
excavation and external
repair may be the only course of
action.
Horizontal cold joints can be a
source of water infiltration.
WATERPROOFING REPAIR
AND REHABILITATION
Perhaps the most familiar
parking structure repair for WCs
is waterproofing repair and rehabilitation.
Many parking structures
are contained below-grade,
with the exception of entrance
doors and ramps. Typically, the
overburden consists of pea gravel,
filter fabric, clayey fills, and top
soil. Overburden like this is used
Proceeedings of the RCI 21st International Convention Gernetzke and Maki – 113
Water stop that migrated up into the concrete slab during the initial
pour. Concrete at corner of expansion joint subsequently
spalled, causing joint leakage.
to retain moisture to support
plant growth.
All structures should
have analysis conducted
by a structural engineer to
determine load capacities
with and without overburden
in place. Knowledge of
capacity by excavation,
landscape, and paving
contractors assists them
to formulate means and
methods during rehabilitation
Free-draining stratum
atop waterproofing systems
is the key component
to maximized life-expectancy.
For this, protection
mat, drainage board, insulation,
and, of course,
overburden, must be considered.
These materials
must provide, at a minimum,
exemplary protection
to the primary waterproofing
membrane,
including during construction
and back-fill. Drainage layers,
insulation, root barriers, and
other items are placed in the system
to perform specific tasks and
can also provide protection to the
primary membrane.
CONCLUSION
The effect of moisture infiltration
into underground parking
structures is complex business.
There are numerous components
that typify the moisture-protection
system of the structure.
Additionally, there are dynamics
that require foresight and ingenuity
if one endeavors to thwart
long-term maintenance investment
or expensive repair for the
owner’s benefit. The subject presents
its advantages for the expertise
of the waterproofing consultant.
The principles of moisture
migration are consistent. Consulting
owners of these structures
with the utmost confidence,
whether providing peer review or
providing positive conclusion to
remedial activity, is possible with
the materials and methods that
exist. If a waterproofing consultant
is not comfortable undertaking
consultancy individually,
underground parking structure
repair is ideal for a team
approach. For many, it is a natural
progression.
FOOTNOTES
1. International Building
Code, 2003. Section 406.4.2,
Ventilation.
2. Anthony P. Chrest et. al.,
Parking Structures, Third
Edition.
3. Causes, Evaluation, and
Repair of Cracks in Concrete
Structures. ACI International
ACI 224.1R-93.
4. Chrest.
5. Design and Control of
Concrete Mixtures, Twelfth
Edition. Portland Cement
Association.
6. American Concrete Institute,
ACI 362.
7. Guide for Making a Condition
Survey of Concrete in
Service. ACI International.
ACI 201.2R-92.
8. Chrest.
9. Causes, Evaluation, and
Repair of Cracks in
Concrete Structures.
10. Chrest.
11. Michael T. Kubal, Construction
Waterproofing Handbook.
12. Ibid.
13. Ibid.
14. Ibid.
Gernetzke and Maki – 114 Proceeedings of the RCI 21st International Convention
Localized failure of a pre-formed, traffic-bearing expansion joint. Photo
shows components of joint system.