Skip to main content Skip to footer

The Atrium on Commonwealth – Roof Replacement / Garage Repairs / Facade Reclad

About the Submission

Title: The Atrium on Commonwealth – Roof Replacement / Garage Repairs / Facade Reclad

Award Category: Building Enclosure

Project Address/Location

1079 Commonwealth Ave
Suite 2320, SGH
Boston, MA 02215
United States

Submitted By: Christopher Grey

Company Info

Simpson Gumpertz & Heger

800 BOYLSTON ST
Suite 2320, SGH
BOSTON, Massachusetts 02199
United States

7742307410

[email protected]

Project Description and Background: The Atrium on Commonwealth Avenue is a 4-story, concrete building constructed in the early 20th Century as home to the Packard Motor Car Company in Boston. The building served this original purpose for decades until car showrooms began moving into less-expensive and less-crowded suburban regions during the mid-20th Century. The Packard building was converted to residential apartments during that transition, serving as one of the early examples of many adaptive reuse projects in Boston. The facade underwent a renovation in the 1980s with EIFS overcladding, and after that point, it remained unchanged for decades. Our work began in 2019 with an initial condition assessment and make-safe work, and our efforts grew into parking garage and roof replacement projects, followed by a $50,000,000+ multi-year, phased reclad project coordinated with an interior gut renovation that required a coordinated effort between many firms involved throughout the project. SGH acted as the prime consultant for the project, managing several sub-consultants through the assessment, design, and construction phases. Challenges throughout the project included working with an undocumented existing building with limited existing drawings, working with and managing the lidar scanning data for holding control working points, meeting current energy code standards in Massachusetts without reducing occupied space and encroaching on property lines, significant unforeseen conditions that required additional structural repairs, coordinating with occupied commercial spaces at the first floor, which remained occupied during construction, and coordinating across many firms contractually engaged by different parties including an owner/contractor arrangement.

Scope: The project spans between 2019 and 2024+ and involved the following scope: -2019-2020 - Condition Assessment: The building owner requested that SGH perform a condition assessment of the garage, facade, balconies, and roofing to develop rehabilitation options to extend the useful life of the building. Our objective was to document the condition of the garage, facade, balconies, roofing systems, and pool structures to identify deterioration and distress, and to prepare and evaluate alternatives to repair current deterioration and extend the useful life of the structure. As part of our assessment work, we also performed make-safe work across the enclosure, removing any fall hazards present, and shoring any unsafe conditions observed at the time of the assessment. We performed a field investigation that consisted of a visual, infrared, and hands-on assessment of the enclosure and structural components, including exploratory openings and concrete testing, including petrographic examination, chloride content testing, and carbonation testing. -2020-2021 - Option Evaluations: We developed rehabilitation alternatives for the Owner that included localized repairs, a full building reclad, or a new building. We then worked with the Owner and local contractors to review these options, provide order-of-magnitude pricing estimates, and assist the Owner in selecting an option and a phasing approach. As part of this phase, we provided a deliverable to the Owner in the form of a matrix that identifies the various materials, system performance, weights, NFPA triggers, insulation options, service life expectancy, comparative costs, glazing costs, and notes regarding constructability of the various systems. -2020-2021 - Roof Replacement and Garage Repairs: We performed design, bidding, and construction administration services for roof replacement and garage repairs. -2021-2024+-Facade Reclad: We performed design, bidding, and construction administration services for the facade recladding. SGH was the prime consultant, and we engaged the services of a local Architect to provide aesthetic design services and coordinated with the interior design architect and mechanical engineer, who were engaged directly with the building Owner, who was also acting as the General Contractor. The project utilized a design-assist approach with a local enclosure contractor to identify potential cost-saving measures and procure long lead time products early. Throughout construction administration, there were significant unforeseen conditions throughout the building that required re-designs of both the base structure and the new enclosure systems. The project was separated into three phases, the first of which was completed mid-2024, Phase 2 is ongoing through 2025, and Phase 3 is in the contract award phase for 2026.

Solution: Roof Replacement: Remove and replace the existing low-sloped membrane roof systems with a new single-ply PVC membrane roofing system, including a self-adhered vapor retarder, rigid insulation, and cover board. Mechanical systems were also replaced in kind, and we worked with the mechanical engineer to raise the new units to provide higher flashing heights. A roof anchor fall protection and facade access system was installed at locations where the structure allowed it. At roof edge and parapet conditions where the roof would interface with the future reclad, we detailed the roofing to tie into the existing walls and reconstructed new code-compliant parapets that provided us the ability to not disrupt the new roof during the future reclad. Garage Repairs: Garage repairs generally consisted of localized concrete repairs and the installation of a new vehicular traffic-bearing coating system on the trafficable elements and an acrylic coating on all other surfaces in the garages. Typical concrete repairs across the garage included topside, underside, and full-depth slab reconstruction at elevated parking deck beams and slabs, full-depth slab-on-grade reconstruction, concrete slab on metal deck reconstruction, and localized spall and crack repairs on concrete structural elements. Supplemental steel reinforcement was required at localized areas where concrete repairs were executed, including the installation of mechanical couplers and sacrificial galvanic anodes. Facade Reclad: The facade reclad included the removal of the existing enclosure systems, which included EIFS, brick veneer, miscellaneous structural steel elements, punched windows back to the cast-in-place concrete structural frame, and reconstructing a new enclosure. The new enclosure consisted of light gage metal framing, gypsum sheathing, a self-adhered air, vapor, and water barrier, exterior insulation, and composite metal panels. Fenestrations generally included punched windows fabricated with a flanged curtain wall system and sliding and terrace doors that led to balconies that were resurfaced with a new pedestrian-bearing coating system and outfitted with new railing systems. New louvers were glazed into the punched curtain wall assemblies, which allowed the team to re-direct mechanical vents to the louvers instead of requiring additional penetrations through the walls. A new main entry was designed, including a new canopy and aluminum framed storefront systems across the first-floor commercial spaces, which remained occupied during construction. Challenges included working with an undocumented existing building with limited existing drawings, working with and managing the lidar scanning data for holding control working points, meeting current energy code standards in Massachusetts without reducing occupied space and encroaching on property lines, significant unforeseen conditions that required additional structural repairs, coordinating with occupied commercial spaces at the first floor, which remained occupied during construction, and coordinating across many firms contractually engaged by different parties including an owner/contractor arrangement.

Value: Due to the size of this project, a single consultant cannot be credited. SGH was the prime consultant, but all consultants needed to work collaboratively with each other, the Owner, and the contractors to execute this complex project. SGH, having in-house enclosure and structural engineering services, was able to handle the project issues collaboratively through all phases of the project to identify, discuss, present options, and execute the work together. At the onset of the project in the condition assessment phase, our role was to assist with making the structure and enclosure systems safe as the primary goal and then present options for repairs. While a reclad was the likely approach at the onset of our work, we made sure that we vetted other options that the Owner could consider and guided the discussion with the pros and cons for each of those options for their consideration. Once the direction for repairs was selected, SGH acted as the prime consultant for the project, and we engaged the services of a local design architect and landscape architect for aesthetic design and decisions while SGH developed the drawings and specified the technical performance requirements of the project. We also engaged with a local lidar scanning company to assist with documenting the existing building components throughout the design phase to assist with developing working points. Mechanical and interior design were engaged directly through the Owner; however, we collaborated closely with those groups through the design and construction phases.

Project Team Info

The Hamilton Company

Steve Weinig

39 Brighton Ave
Suite 2320, SGH
Boston, MA 02134
United States

617.783.0039 ext.1274

[email protected]

Building Enclosure Consultant Company Info

Simpson Gumpertz & Heger

Christopher Grey

800 BOYLSTON ST
Suite 2320, SGH
BOSTON, Massachusetts 02199
United States

7742307410

[email protected]

Contractor Company Info

Hamilton Construction Management Corp

Steve Weinig

39 Brighton Avenue
Boston, MA 02134
United States

617.783.0039 ext.1274

[email protected]

Architect Company Info

Margulies Perruzzi

Nathan Turner

308 Congress St
Boston, MA 02210
United States

617.226.4136

[email protected]

Project Images

Image File 1:

Image File 2:

Image File 3:

Additional Info: This project required a large team from SGH including the following Team Members. Enclosures: Jeff Ceruti, P.E. (Cognizant Senior Principal) Christopher Grey, P.E. (Associate Principal) Matthew Colturi, P.E. CPHC (Senior Consulting Engineer) Structural: John M. Porter, P.E. (Principal) Nathan Boutin, P.E. (Senior Project Manager) Other SGH Members: Ali Yalaz Ahmed O.A. Ba Wazir Michael Barone Syed Najeeb Husseini Brett Holland Matthew Oostdyk Zachary Lozon Will Bergendahl

Documents

Document File 1:

View Document Here

Document File 2:

View Document Here

Document File 3:

View Document Here

Videos

Video Link 1:

View Video Here