Building Envelope Commissioning

May 15, 2013

Building Envelope Commissioning
Karim P. Allana, RRC, RWC, PE
Allana Buick & Bers, Inc.
990 Commercial Street, Palo Alto, CA 94303
Phone: 650-543-5638 • Fax: 650-354-8828 • E-mail: karim@abbae.com
2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3 A l l a n a • 1 1 5
Abstract
Building envelope commissioning yields significant life cycle capital and operational
cost savings in new buildings; retro building envelope commissioning greatly reduces future
operating costs in older buildings. Through a case study, the presenter will show how to
implement this powerful method to lead, plan, schedule, manage documentation, and coordinate
the process. Building envelope commissioning meets owner requirements by confirming
building envelope system and assembly functionality, durability, constructability, design
and installation quality, and interoperability.
Speaker
Karim P. Allana, RRC, RWC, PE — Allana Buick & Bers, Inc. – Palo Alto, CA
Karim P. Allana , PE , RR C, RWC, is CEO /senior principal of Allana Buick & Bers, Inc.
With more than 25 years’ experience in construction engineering, forensic investigation, and
design, his firm specializes in exterior cladding of all types, curtain walls, roofing, windows,
and waterproofing. It is his firm’s mission to improve how exterior assemblies can be successfully
designed and constructed, even under extreme conditions. His firm’s commitment
to the building exterior enclosure commissioning process, from investigation of conditions
through design and construction monitoring services, is the basis of this session, providing
both practical and engineering data.
1 1 6 • A l l a n a 2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3
INTRODUCTION
Commissioning is the systematic process
that facilitates the communication,
coordination, testing, and verification
required to deliver building systems in
accordance with the intended design.
Commissioning as a construction practice
was started by the American Society of
Heating, Refrigerating and Air-Conditioning
Engineers (ASHRAE) at its founding and
initially associated with mechanical systems.
However, the program has since been adapted
to include all major building systems. The
basic commissioning methodology can be
applied to building enclosure systems, claddings,
and components, including:
• R oofing systems
• E xterior walls
• Window walls, curtain walls, and
storefronts
• E xterior doors and windows
• Sealants, joints, and flashings
• P laza decks and podiums
• P lanters
• Foundation systems
• Below-grade walls
Building envelope commissioning
(BECx) can yield significant life cycle cost
savings in new buildings. Similarly, retrocommissioning
(RCx) can offer greatly
reduced operating costs in older buildings.
One of the most common sources of
building failures is the building envelope.
When applied systematically, BECx can significantly
reduce the risk of water infiltration,
improve facility operation and maintenance,
reduce capital costs during the
first year of operation, and reduce the life
cycle costs of the facility for the life of the
building.
Commissioning is a comprehensive
design and construction/repair process
that is woven into a construction project,
not as an expensive, stand-alone process,
but one that is fully integrated into the project
delivery. It is common for construction
commissioning to be considered on its own;
however, for maximum savings, it should
be planned for all design and construction
phases. A commissioning program implemented
only after construction commences
will be less effective than commissioning
that begins during the schematic phase.
Construction projects are complicated,
involving many trades that, in many cases,
work independently. A commissioning program
that employs design reviews and construction
validation protocols can minimize
building performance issues and offer the
owner an assurance of receiving an end
project that will perform as intended, specified,
designed, and, of course, paid for.
Commissioning is generally conducted
by a third party under contract with the
project owner. The third party acts as the
owner’s representative and provides objective
development of programming goals,
objectives, and recommendations. In some
cases, a project commissioning process is
prescribed directly to the project’s designer
and consultant team members instead of
under a third-party commissioning authority.
The intent, in these cases, is to have the
designer verify that the owner’s objectives
are defined ahead of the design process,
that the objectives are met, and to provide
quality assurance during construction.
If a third party is utilized, the owner
or owner’s representative will select the
commissioning agent directly. The agent
will lead the commissioning process in
cooperation with the designers and contractors,
with the owner’s interest as first
priority. The commissioning agent should
be licensed to practice engineering or architecture
in the state where the project is
located. The commissioning agent should
also be an expert in the systems being commissioned.
HISTORY OF BUILDING
COMMISSIONING
Historically, ASHRAE was the leader in
building commissioning, focusing originally
on mechanical systems and building operations.
In the last ten years, the National
Institute of Building Sciences (NIBS); the
United States Green Building Council
(USGBC), through the Leadership in Energy
and Environmental Design (LEE D) process;
various state governing agencies; and
recently—ASTM have added exterior enclosure
commissioning as a crucial component
of the design and construction process.
• 1982 – ASHRAE begins work on
commissioning guidelines.
• 1989 – Publication of the first
ASHRAE guideline on commissioning
mechanical systems (updated in
1996).
• 2005 – Latest ASHRAE guideline on
the commissioning process for the
whole building.
• 2006 – First publication of NIBS
exterior enclosure technical requirements
for the commissioning process.
• 2011 – California Green Building
Standards Code, including commissioning,
codified into Title 24.
• 2012 – Latest publication of NIBS
exterior enclosure technical requirements
for the commissioning process.
• 2012 – ASTM International and NIBS
announce their agreement to collaborate
on developing a buildingenclosure
commissioning process
that the organizations said would
facilitate improved building enclosure
design and commissioning programs.
As part of the agreement,
NIBS Guideline 3 will be developed
and published as an ASTM standard
guide by ASTM Subcommittee
E06.55 on Building Enclosure
Performance (part of ASTM Committee
E06 on Performance of Buildings).
NIBS is a nonprofit, nongovernmental
organization that brings together represen-
Building Envelope Commissioning
2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3 A l l a n a • 1 1 7
tatives of government, building sciences
industry professionals, various labor and
consumer interests, and regulatory agencies.
A key focus of NIBS is identifying
and resolving problems in building science
and technology toward improving the
built environment. NIBS Guideline 3-2012,
Building Enclosure Commissioning Process
(BECx), describes the specific applications
of the BECx process more generally than
ASHRAE Guideline 0-2005. The procedures,
methods, and documentation requirements
in this guideline describe the application
of the commissioning process to building
enclosure systems for each building delivery
phase, from predesign through owner occupancy
and operation.
BUILDING ENVELOPE
COMMISSIONING OBJECTIVES
AND BENEFITS
Many building owners have benefited
from the ASHRAE commissioning process,
which has been in existence for decades.
Currently, the building industry, NIBS,
and USGBC have extended the benefits of
commissioning by defining a process that
includes exterior enclosures.
The commissioning process allows owners
to clearly define their goals and objectives
that are often not well understood by
design professionals. For example, developers
and owners often have competing
goals in the areas of cost savings and highperformance
building enclosures. Traditionally,
the outcome is “value engineering”
by specifying cheaper materials and systems.
Through the commissioning process,
owners, contractors, and design professionals
collaborate to think outside the box by
analyzing not only the cost of enclosure systems
but also how each solution will impact
scheduling, long-term maintenance, and
longevity factors that very often have overarching
effects on the cost of construction
and long-term ownership of the building.
Collaboration during the commissioning
process significantly improves system
selection to better meet many of the owner’s
objectives, such as longer-lasting systems,
reduced maintenance costs, energy efficiency,
and remaining within budget without
sacrificing quality of construction.
The BECx process aims to confirm that
the building will fulfill the functional and
performance requirements of the owner,
occupants, and operators.
Typically, the BECx process focuses on:
• Heat/air flow
• Noise/acoustics
• Thermal comfort
• Visual comfort
• Fire protection
• L ight management
• R ain penetration control
• Moisture management
• Structural performance
• Durability – increased systems life
• R eliability
• Aesthetics
• Value
• Constructability
• Maintainability
• Sustainability
• R educed energy costs
• Carbon footprint reduction
The main objectives of commissioning
are:
• Document the owner’s requirements
to improve the quality of design
deliverables.
• Verify that systems and assemblies
perform according to the owner’s
requirements as stated in the owner’s
project requirements (OPR ).
• Memorialize the design requirements
in a basis-of-design (BOD) letter.
• Confirm that proper verification is
provided to the owner before, during,
and after construction.
• Verify that operating staff are trained
in proper operation of the facility.
The commissioning process can cost
2-4% of construction, depending on the
project size and complexity. While many
owners may give high priority to reducing
up-front costs, the commissioning process
can be invaluable and pay for itself in the
long term. Many owners have spent millions
and invested years of effort in repairing
construction defects in buildings improperly
designed or constructed, or on expensive
modifications to improve building performance
after initial construction. The longterm
effects of poor design and construction
include inferior energy efficiency, high
operating and maintenance costs, frequent
replacement of components, lower reliability,
water intrusion, and side effects of poor
indoor air quality, such as mold. Building
enclosure commissioning can mitigate these
risks and offer the owner an array of benefits,
including:
• R educed risk of leaks, disruption,
lawsuits, loss of rents, and remedial
construction
• R educed long-term operating costs:
Operating costs can represent up to
80% of the total cost of a building
over its lifetime. In a study on building
commissioning from the U.S.
General Services Administration
on Building Commissioning, they
state that “operating costs for commissioned
buildings are reported at
8-20% lower than those of a comparable
noncommissioned building.”
• Fewer project delays: Coordination
and scheduling programs integrated
in project management enable
contractors to sequence work more
efficiently, thus expediting construction.
Common issues can be proactively
identified, and resolutions can
be implemented to allow the project
to remain on its critical path.
• E xpedited projects may be completed
sooner by early identification
and resolution of issues. For revenue
properties, owners can generate
rental revenue earlier, reducing
the substantial costs of carrying
construction money, loans, etc.
• Minimal design impacts: The qualified
commissioning agent reviews the
design and submittals to identify
design issues. Recommending alterations
during the design phase is much
more cost-effective than field-directed
revisions and reduces change orders
and construction delays.
• Quality assurance during construction:
Specialized quality assurance
protocols on behalf of the owner to
observe critical building envelope
components during construction will
help validate that the construction
is performed in accordance with the
design intent. Construction of building
envelope systems is extraordinarily
complex; quality-assurance
protocols enable the commissioning
agent to address many unanticipated
conditions before they can cause
cost overruns and delays.
• Comprehensive documentation of
the construction process: When the
commissioning process is integrated
throughout the design-and-construction
process, valuable information
is collected that will assist the
owner with future building operation
1 1 8 • A l l a n a 2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3
and maintenance. The
commissioning process
provides facilities
staff with detailed
information on how
the building systems
were designed and
constructed.
Currently there is no
direct method to calculate or
quantify anticipated payback
that can be achieved utilizing
BECx. Since every project
has its own objectives and
construction obstacles, there
is no definitive savings percentage
that can be used in
project budgeting. Currently,
it is known that commissioning
can cost 2-4% of construction
and that abovementioned
studies state that operating costs
for commissioned buildings can be between
8 and 20% lower than those of comparable
noncommissioned buildings.
BUILDING ENVELOPE
COMMISSIONING DEFINED
Current guidelines and documentation
for commissioning include ASHRAE guideline
0-2005, which defines the commissioning
process for both ASHRAE technical
volumes for HVAC&R and NIBS guidelines
for roofing, lighting, fire/life safety, interiors,
envelopes, and plumbing. This paper
focuses on ASHRAE guideline 0-2005 and
NIBS guideline 3-2012, exterior enclosure
technical requirements.
Per ASHRAE and NIBS, the building
commissioning process is:
• A quality-oriented way of achieving,
verifying, and documenting that the
performance of facilities, systems,
and assemblies meets owner-defined
objectives from concept to operations
and maintenance
• A system by which owners, architectural
programmers, designers, contractors,
and operations and maintenance
personnel are fully accountable
for the quality of their work
NIBS defines exterior enclosure as containing
“all systems separating the interior
environment from the exterior, including
exterior walls, fenestration, and roofing and
roof openings, below-grade perimeter walls,
and the slab-on-grade or crawlspace.” (See
Figure 1.)
BUILDING ENVELOPE
COMMISSIONING PROCESS
The basic abbreviated BECx process follows
these steps:
• Initiate conceptual predesign consulting
with the team.
• P repare an OPR list.
• P repare a BOD report.
• Conduct design peer review at determined
design stages.
• Supervise mock-up construction
and testing, carrying forward any
lessons learned.
• Devise performance-testing standards.
• P rovide construction period commissioning,
including inspection and
testing.
• Develop a commissioning report.
The following sections provide details of
the BECx process
A. Develop a Building Envelope Scope of
Work
In the commissioning process, the first
step is to determine the extent of the process
to be implemented and the budget. The
BECx process can include a very wide range
of services, with a correspondingly wideranging
budget. If you don’t receive a clear
Scope of Work from the owner or owner’s
representative, the BECx agent will need
to develop the scope of services by asking
numerous detailed questions to obtain an
in-depth sense of the owner’s needs and
concerns. The commissioning agent can
also question the owner about how issues
such as maintenance and operating costs
will impact return on investment (RO I) and
capitalization rates for resale, as well as a
payback period for system upgrades. It is
very important to understand the owner’s
project goals before developing the commissioning
scope.
The project budget should include the
cost of the commissioning process. Funds
allocated for commissioning can usually be
recouped from savings achieved through
fewer change orders during construction,
improved building performance, and reduced
risk of future system failure. At the very
beginning of the project, the commissioning
process (Figure 2) needs to be established by
all of the team stakeholders as an important
part of the project process.
B. Predesign Phase
The OPR is developed and defined during
the Predesign Phase. This phase is critical,
since the OPR creates the foundation
for the design, construction, occupancy,
and operation of the facility, and is the basis
for the commissioning plan and schedule.
Each item of the OPR will include welldefined
parameters for performance and
acceptance, plus the project goals, measurable
performance criteria, cost considerations,
bench-marks, success criteria, and
2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3 A l l a n a • 1 1 9
Figure 1
supporting information.
According to NIBS, during the preliminary
schematic design stage, “Emphasis
should be on the impact on budget and
schedule required for commissioning of
various enclosure options. Each building
enclosure system has specific tests and
tools available for qualitative and/or quantitative
analysis of
performance, with
varying degrees of
certainty” (NIBS
Guideline 3-2012 –
5.1.1.)
During the
Predesign Phase,
the commissioning
plan is developed to
address the OPR .
The commissioning
plan identifies processes
and procedures
and includes
a schedule of commissioning
activities,
team member
responsibilities,
documentation requirements,
communication
and
reporting protocols,
and evaluation procedures.
The commissioning
plan
is a “living document”
that is continually
updated
during the life of a
project. During the
Predesign Phase,
the commissioning
plan focuses on
defining the scope
of the commissioning
process for the
design phase.
The following
predesign commissioning
objectives
must be met for
any project:
• A s c e r t a i n
the owner’s
f i n a n c i a l
and building
perf
o r m a n c e
goals.
• P ropose building enclosure systems
and assemblies that match their
intended use.
• Determine if the building enclosure
meets the climate conditions.
• Ascertain that the building enclosure
meets the heating and cooling
needs and the owner’s life cycle
expectations.
• Confirm that the selected systems
meet owner’s budget requirements.
See Figure 3.
C. Design Phase
During the Design Phase, the OPR is
1 2 0 • A l l a n a 2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3
Figure 2 – Flowchart for commissioning process.
translated into construction documents. A
document called the Basis of Design Report
(BDR) is created to provide a narrative
description of the systems and assemblies
that fulfills the OPR .
In this phase, the building envelopecommissioning
agent reviews the design professional’s
submittals. This is an extremely
important step in ensuring that the OPR
is being met and that the design intent is
accurately and thoroughly documented to
remove ambiguities from the building envelope
design. During this “peer review,” the
BECx agent reviews documents at specific
points of the Design Phase, typically during
the design development and construction
document phases of the project.
According to NIBS, during the design
development stage: “DD Phase Project Team
Commissioning is a crucial phase in the
design/commissioning process, as the concept
of the building is well-enough established
to allow resolution of the building
enclosure design against highly defined and
precise owners’ criteria. In this phase, more
detailed drawings, large-scale wall sections,
elevations and details, and preliminary
specifications for the building enclosure
systems are developed in support of the
schematic design concept and BOD. The
OPR is updated to reflect ongoing decisions.
The Design Development Documents are
verified against the OPR .” (NIBS Guideline
3-2012 – 5.2.1.)
The review includes all building envelope
system plans, details, and specifications
for general conformance with material
manufacturers’ requirements and industry
standards. The review should also address
interoperability between systems and coordination
among disciplines.
NIBS outlines additional design development
technical reviews including, but not
limited to:
• “Review the design development documents
for comparison of building
enclosure assemblies and details,
required testing, and typical details
for interfacing continuity. Details
to be reviewed should include but
are not limited to: Typical details
for roof-to-wall, foundation-to-wall,
fenestration, wall-to-floor, wall-tocolumn,
wall-to-floor penetrations,
and other features that are common
or highly repeated for the various
enclosure assembly layering
options.” (NIBS Guideline 3-2012 –
5.2.4.4.)
• “Review the initial development of
typical plans and details for interface
of the various enclosure systems.
Both constructability and the
design continuity for air, water, thermal,
and vapor control layer interfacing
details are to be evaluated.
The DD documents should clearly
identify the extent of each control
layer. At each interface between systems
(i.e., window-to-wall, wall-tofoundation,
wall-to-roof), verify continuity
and compatibility of control
layers and performance. The design
review report should advise the
project team on technical matters;
provide recommendations for the
development of details, systems, and
assemblies; and review documents
for completion and coordination.”
(NIBS Guideline 3-2012 – 5.2.4.5.)
The design phase also includes:
• Update the Commissioning Plan with
processes and procedures for the
Construction Phase, as well as the
Occupancy and Operations Phase.
• Define and develop commissioning
processes to be included in the
construction documents, including
quality-assurance and quality-control
procedures. Commissioning processes
are defined in the Division 1
to Division 16 specification sections
and include processes for documentation,
training, testing, and installation
of systems and assemblies.
• Develop construction checklists of
equipment/assembly verification,
preinstallation checks, and installation
checks. These checklists are
used to verify that the equipment
and materials specified and submitted
are what is actually delivered to
the site, and that the condition of
the equipment/materials has been
examined before installation. The
installation section of the checklist
verifies that the specified testing has
been completed and confirms proper
installation of systems.
• Develop a systems manual to contain
the information needed to
operate and maintain systems and
assemblies. The systems manual
2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3 A l l a n a • 1 2 1
Figure 3 – Where predesign consulting occurs.
should additionally serve as the
source of information about any
updates and changes to systems
and assemblies as they occur during
the Construction, Occupancy,
and Operations phases. Contractor
contribution requirements for the
systems manual should be clearly
stated in the construction documents.
D. Construction Phase
In the Construction Phase, the BECx
agent confirms that the systems and assemblies
have been installed, inspected, tested,
and placed in service in a manner that
meets the OPR .
Construction Phase commissioning services
include the review of submittals, shop
drawings, mock-ups, and sample construction
to confirm that the submitted materials
meet the project specifications; and testing
to confirm performance.
Various field-testing protocols are recommended
in the NIBS Guideline. They
include, but are not limited to:
• “Conduct additional field testing as
required if failures occur during the
laboratory mock-up, field mock-up,
or the field tests performed during
the construction phase. Additional
testing may also be needed if substitutions
of materials and systems
are accepted during the construction
submittal phase.” (NIBS Guideline
3-2012 – 6.1.2.)
• “Conduct field review of the aesthetics
and performance of mock-up(s).
Review the unique interface conditions
with differing materials to
verify they meet the design intent
and will provide the performance levels
and functionality of the building
enclosure as specified in the contract
documents. Mock-ups construction
and testing must be scheduled with
float time allowed for the remediation
of unforeseen issues by way of
iterative repair submittals and field
performance testing of the mock-up
repairs prior to actual construction.”
(NIBS Guideline 3-2012 – 6.1.3.)
During the construction phase, the
BECx agent will review field mock-ups
focusing on general and unique interface
conditions to verify that they meet the
design intent and will provide the system
performance as specified in the OPR .
The BECx agent witnesses the system
testing procedures that were documented
in the design phase. The agent completes
periodic site visits, particularly during critical
events, and documents all observations.
The commissioning agent maintains an
open issues log to track any items noted
during the observation that require corrective
action.
CASE STUDY
The following case study highlights the
detailed steps required to plan, schedule,
lead, coordinate, and manage the documentation
for a successful building envelope
commissioning. The building envelope
consultant becomes involved early in the
design process, providing consultation, peer
review, and design services; designing and
supervising mock-up construction; testing;
and creating project constructability
manuals. The purpose of this process is to
confirm that the building envelope system
and assembly will meet the OPR in terms of
their functionality, durability, constructability,
quality of design and installation, and
interoperability.
A. Case Project Overview
• 1,800+ for-rent residential units to
be built in phases
• Four wood-framed levels over concrete
podium
• R apidly changing design and a fastpaced
construction process
• The following commissioning process
was followed:
— Met with the owner early on to
understand the OPR
— Developed a BOD letter
— Suggested assemblies to meet
the owner’s budget goals
— Modified the design of assemblies
to expedite construction
— E mployed design development
phase documents to establish
final pricing and budgeting
— P repared a construction quality
assurance program that included
observations and testing protocols
• The following building envelope systems
were commissioned:
— Below-grade waterproofing
— L andscaping planter waterproofing
— P edestrian bridges/catwalks
— P odium waterproofing
— P rivate-deck waterproofing
— E xterior wall assembly
— Windows
— Doors
— R oofs
B. Predesign Phase
The OPR :
• Build and hold property for life.
• Build and operate a sustainable,
maintainable property.
• R educe construction defects and
risk of leaks and failure.
• Maintain fastest possible construction
pace; bring every unit to “revenue
status” as soon as possible.
• E nclose the building as soon as possible.
• Use a small number of suppliers and
manufacturers.
See Figure 4.
Basis of design
The following formalized system selections
and specifications were approved by
the owner:
• R oofing systems – low-slope and
steep-slope
• P odium and pedestrian deck waterproofing
systems
• Below-grade foundation perimeter
wall systems
• Foundation footing and slab systems
• E xterior wall systems
See Figure 5.
C. Design Phase
Budget review
Construction details were developed
with a goal of obtaining actual budget numbers
before the start of construction. During
the budget review phase, the owner received
conflicting information about pricing of the
recommended roof system. The contractor
told the owner that cold-applied polyurethane
cost less than $6 per sq. ft., whereas
hot-applied rubberized asphalt would cost
more than $11 per sq. ft. The owner hesitated
to approve the system as recommended
and decided to use the cheaper but inferior
system recommended by the contractor.
However, after researching the issue, it
was discovered that the subcontractor had
quoted a higher price for the recommended
system because he was inexperienced and
1 2 2 • A l l a n a 2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3
unequipped for this installation type and ultimately
did not want to install the system. Upon hearing
this explanation, the owner was persuaded of the
long-term benefits of the system. A request for bids
from local waterproofing contractors yielded pricing
for the recommended hot-applied rubberized asphalt
process similar to the cold-applied process, and the
owner agreed to a return to hot-applied rubberized
asphalt.
Structural Changes
The original structural design called for spread
footings and slab-on-grade foundation. A specific
waterproofing method for this type of foundation
requires that the waterproofing be applied in stages,
with specific curing periods. It is a very complex
process, both in phasing and in waterproofing; and
some portions of these systems cannot be waterproofed.
Complexity = lengthier construction = increased
general conditions + overhead = more $.
To fast-track construction scheduling, a mat
slab with sodium bentonite system rather than with
spread footings was used to allow faster building and
waterproofing of the foundation.
D. Construction Phase
The following construction commissioning steps
were implemented:
• P erformance mock-up(s)
• Visual mock-up(s)
• Material testing
• Continuous/part-time inspection
• System testing
• Field review and observation
• Compliance testing
• Wind uplift and wind load
testing
• Seismic testing
• Vibration testing
• Membrane adhesion performance
testing
See Figure 6.
Mock-ups
To verify the OPR and BOD, a
mock-up was used for waterproofing
and building various assemblies. The
mock-up provided valuable information
whenever a need arose to resolve
issues by alternative methods.
The mock-up was built by the
trades as a stand-alone mock-up that
included most of the typical details.
The mock-up used the specified materials
in order to simulate actual proj-
2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3 A l l a n a • 1 2 3
Figure 4 – Where the OPR is developed.
Figure 5 – Where the BOD is developed.
ect conditions. It allowed the team to review
how difficult transitions and turns would
be constructed. Testing for compliance was
conducted on the mock-up and set the level
of standard of care and performance. The
construction crews used the mock-up in
reviewing and adopting best construction
practices.
The mock-up stage yielded the following
lessons:
• The mock-up supported the evolution
of designs.
• The mock-up created a baseline for
rapid, ongoing resolution of installation
issues.
• The mock-up enabled chemical compatibility
testing and adhesion testing.
• It resolved dimension issues.
• The size of the mock-up limited the
conditions that could be tested and
created tight working areas.
• The mock-up is not a panacea for
resolving every issue.
See Figures 7 and 8.
Benefits Realized From the
Commissioning Process
• 1,800 fully occupied units represent
approximately $4-$5 million
in monthly revenue. The commissioning
process helped expedite the
project and realize occupied unit
revenues sooner.
• The commissioning process led to
many system selections that saved
installation time. Time = money.
• Standardizing the waterproofing
systems reduced the complexity of
installation.
• The building was made weathertight
faster, reducing the risk of
weather damage.
• Strategic system selection resulted
in faster construction sequencing.
CONCLUSION
Commissioning is a systematic quality
assurance process that becomes part of
the construction process during the early
design stages and continues throughout
the construction phases. Commissioning
protocols can be applied to any building
system and should be especially considered
for building envelope systems. The goals
of commissioning are to 1) identify and
mitigate issues early to allow the project to
remain on schedule, and 2) provide a building
that meets the owner’s performance
requirements.
1 2 4 • A l l a n a 2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3
Figure 6 – Where construction commissioning happens.
Figure sources
• All photos and
details used were
by Allana Buick &
Bers.
• Flowcharts were
based on those
found in NIBS
Guideline 3-2012,
Building Enclosure
Commissioning Process
BECx.
2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3 A l l a n a • 1 2 5
Figure 7 – Image of actual
mock-up constructed.
Figure 8 – Where the mock-up was built.