Skip to main content Skip to footer

Risks of Roofing Over Concrete Decks

May 15, 2014

Over the years, the construction
industry has been aware
of moisture issues from
freshly placed concrete, as
well as the ability of concrete
to absorb and hold great
amounts of water. Over time, this water may
migrate into the roof system, saturating
the insulation and cover boards, causing
adhered systems to become disbonded, or
increasing the risk of corrosion to metal
components. Many articles have been written
discussing the issues of moisture and
concrete. These articles identify some of the
reasons and issues related to the moisture
in concrete, and why problems appear to be
more prevalent than in the past, such as
eliminating vapor retarders (especially ones
that are adhered to the concrete deck) and
the practice of keeping concrete forms in
place, which are typically sheet-metal form
decks.
The most common ways excess water in
concrete is generated include:
• Mixing and pouring new concrete
decks/slabs
• Interior finish work, including:
— Water-based construction materials,
such as paint, plaster, and
drywall application
— Heating the interior with propane
or oil burners
• Concrete decks exposed to standing
water from various sources, such as:
— Exposure to long-term leakage
into existing roofs
— Rain or snow
— Other sources
CONCRETE AND WATER
Concrete is a combination of cement,
aggregate (fine and coarse), and water, typically
proportioned about 10-15% cement,
60-75% aggregate, and 15-20% water.
Studies have shown that from the original
mix, there will be from 0.9 to 2.6 quarts
(0.85 to 2.5 l) of excess water per square foot
of concrete surface present in a one-monthold,
6-in.-thick concrete roof deck. This does
not include possible water from rain, snow,
or a curing process.
This excess
water may migrate
into a roof system
that is applied after
the concrete has
cured to sufficient
strength to support
construction traffic,
which generally has
been accepted as
28 days for normalweight
structural
concrete. In reality,
the time to cure
will vary, possibly
as short as 7 to 14
days, depending on
the required design
function of the concrete
and the mix design. With this large
amount of free water available, it must
be noted that cure time (generically 28±
days) does not mean the concrete is dry.
“Cured” simply means it has reached adequate
structural strength. Depending on the
concrete mix or formula, it may take up to
three months under ideal drying conditions
and significantly longer without ideal drying
conditions for a normal-weight structural
concrete deck to dry sufficiently to allow for
a finish product such as flooring or a roofing
system to be installed.
In addition to normal-weight structural
concrete (NWSC), there is more lightweight
2 0 • I n t e r f a c e J u l y 2 0 1 4
Photo 1 – Micrograph of lightweight concrete with expanded shale
aggregate (compliments of SGH).
structural concrete (LWSC) being specified
and installed. The differences between the
two structural concretes are the “in-place
density” and the type of aggregate used.
LWSC has a density between 90 and 115
lb./ft.3 (1440 to 1840 Kg/m3), and NWSC
has a density range of 140 to 150 lb./ft.3
(2240 to 2400 Kg/m3). NWSC aggregate is
typically a combination of fine and coarse
aggregate, including sand, natural gravel,
and crushed stone. The industry is starting
to see more recycled aggregates, such as
construction demolition and waste, as a
partial replacement for natural aggregates.
The LWSC can achieve the low “in-place”
densities by using a lightweight porous
aggregate containing air voids. The most
common aggregates used in LWSC are
expanded shale slate, slag, or clay. The
materials are processed at very high temperature
(2000ºF) in a rotary kiln. These
aggregates have a textured surface, a network
of internal pores, and absorb relatively
large amounts of water (Photo 1).
The lightweight aggregate must be saturated
before mixing, or it will pull water
from the mix, which will make it too stiff to
place. This process increases the water-tocement
ratio, causing issues with the final
concrete product. To put it into perspective,
the LWSC aggregate can absorb 5 to 25% of
its mass with water. The Portland Cement
Association (PCA) Engineering Bulletin 119
states the dry down time for LWSC is many
months more than NWSC. To achieve a
75% relative humidity for NWSC, it will take
approximately three months. To achieve the
same 75% relative humidity for LWSC, it
will take twice as long—almost six months,
according to testing noted in the PCA bulletin.
The test was conducted with an 8-in.
(20-cm) slab that had both its top and bottom
sides exposed to air to dry. Consider
that if a roof membrane is installed over
the top surface, and the bottom surface is
a steel form deck (as is very common), the
ability of the concrete to dry will be severely
affected. In reality, the ideal laboratory
conditions for drying the LWSC will never
be achieved during six months of field conditions.
Factors that are driving the increased
use of LWSC include lower overall building
costs, as well as environmental and sustainability
claims. LWSC is typically more
expensive than the NWSC when looked at
on a unit-cost basis. The overall cost saving
achieved by using LWSC, however, is due to
a number of factors, but, most importantly,
that the lower density reduces the dead
loads.
As an example, comparing a 145-pcf
concrete slab to a 115-pcf one, the reduction
in density provides a weight savings of
approximately 20% in the concrete. Thinner
slabs of LWSC can achieve the same fire
ratings as NWSC. The dead-load reductions
allow reduction of the structural framing.
Concrete with lightweight aggregate is
being touted as a sustainable alternative
to NWSC due to savings on materials. With
lower dead loads, there is a reduction in the
concrete thickness, which helps reduce the
reinforcement and concrete for the foundations.
It will also reduce the structural
members such as columns, beams, and
girders. Transportation costs are less, as
lighter weight and less mass are shipped.
CONSTRUCTION-GENERATED
MOISTURE
Various construction activities, such
as newly poured concrete floor slabs and
water-based construction materials (including
paint, plaster, and drywall application,
among others) generate and contribute to
the accumulation of moisture within an
enclosed building space. Additional moisture
is generated when propane- or oilburning
heaters are used to condition the
interior of the building. This heating of the
interior may help to dry the new construction
materials or allow for interior finish
work to be done.
To put this moisture accumulation into
perspective, a 4-in.- (10-cm-) thick concrete
floor slab generates approximately 1 ton of
water for every 1,000 sq. ft. of finished concrete.
For every gallon of oil burned, 1 gallon
of water is produced; and a 200-lb. tank of
propane produces 30 gallons of water. All of
this moisture produced and trapped in an
enclosed space affects the roofing system.
Should these conditions exist, the project
designer and/or the construction manager/
general contractor must take steps to properly
vent the moisture out of the enclosed
space to prevent it from migrating into the
roof assembly. A well-designed air barrier
system that is sealed at all penetrations and
perimeters can minimize moisture-laden air
from leaking into the roof system.
J u l y 2 0 1 4 I n t e r f a c e • 2 1
800-255-4255 • www.r-guard.com
Superior Fluid Applied
Air Barrier System
• Instantly waterproof and air-tight
• Bonds to wet or dry surfaces
• For strip-and-reclad or new construction
• Sustainable — lasts for the life of the building
RCI July Ad.indd 1 6/12/2014 5:21:38 PM
WATER ABSORBED INTO CONCRETE
Water sitting on a deck—as precipitation
on new decks or through long-term leakage
into existing systems being reroofed—will
typically be absorbed into the concrete. The
top surface may appear dry, giving a false
sense that a roof system can be installed.
After the installation of the roof membrane,
the moisture within the concrete will
migrate into the roof system. The rate of the
water migration will depend on the local climate
and the conditions (temperature) within
the building. The migration of the water
out of the concrete will be greater than the
moisture vapor passing through the roof
membrane. The moisture condenses when
it reaches the cold membrane surface. The
accumulation of water within the assembly
may affect moisture-sensitive products
such as adhesives, paper-faced insulation
boards, gypsum, perlite, and fiberboards.
VENTED DECKS
The Steel Deck Institute (SDI) issued
a position statement in November of 2008
commenting on the use of vented composite
steel floor deck forms to quicken the drying
time of a poured concrete slab. The document
notes that vented steel decks have traditionally
been used to allow for the excess
mix water to drain when an LWIC deck was
poured. The paper states that the LWIC
should not be confused with LWSC.
The SDI cautions designers about the
use of vented decks for drying out concrete
as noted:
While some deck manufacturers
have the ability to provide slots
in the composite deck to assist in
venting, it should be noted that
the current research and testing on
composite steel floor deck does not
extend to vented products. While it
is known that the inclusion of slots
has little effect on the strength of
the steel deck, the effect on draining
mix water through the bottom of the
deck on the properties of the cured
concrete and the bond to the concrete
is unknown. Specifiers should
proceed with caution when requiring
slots in this application.
The steel deck acts as a vapor
barrier, preventing diffusion of water
vapor out from the bottom of the
slab. Some publications (Joseph W.
Lstiburek, “Concrete Floor Problems,”
ASHRAE Journal, Jan. 2008; and
“Sealing Vapor Barrier Penetrations,”
Concrete Construction Magazine, July
2005) note that the amount of diffusion
is directly proportional to the
open area in the vapor barrier (Fick’s
Law). For example, providing a hypothetical
1.5% open area will increase
the diffusion of water vapor by 1.5%,
an inconsequential amount.
The document states when pouring concrete
floors on steel decking, the specifiers
should consider the conditions to be the
same as pouring concrete on grade with a
vapor barrier, for drying purposes. Designers
should be concerned about this statement,
as the permeability of steel is substantially
less than a poly vapor barrier. The SDI suggests
others means for controlling the water
content, thus improving drying time, such as
minimizing the water content, using water
reducers, controlling drying temperatures
and relative humidity, and providing protection
from external moisture sources. In reality,
the finish contractor—be it for flooring
or roofing—has very little control through
any means in reducing the excess moisture.
DETERMINING MOISTURE CONTENT
A main issue our industry has regarding
water and moisture in concrete is that there
is not a good, practical, consistent, and viable
test to determine the moisture content of
a concrete roof deck. We must also be aware
that when measuring the relative humidity
in a concrete slab, there is currently no
reasonable method of associating measured
relative humidity levels to the actual moisture
content.
The plastic film test (ASTM D4263,
Standard Test Method for Indicating Moisture
in Concrete by the Plastic Sheet Method)
is no longer considered a good, valid test,
especially with LWSC. The National Roofing
Contractors Association (NRCA) issued an
Industry Issue Update titled Moisture in
Lightweight Structural Concrete Roof Decks
stating this method is unreliable. The NRCA
notes the difficulty in achieving an airtight
seal between the film and the concrete deck.
It also states that if the temperatures on
both the top and the bottom of the concrete
slab are not nearly identical, the pressure
difference can result in a false “dry” result.
This is also true for the calcium chloride
test (ASTM F1869). Independent testing has
shown these test methods often give misleading
results.
2 2 • I n t e r f a c e J u l y 2 0 1 4
Figure 1 – Dates for the new concrete roof deck pours for Case
Study 1.
Figure 2 – Dates for the installation of the self-adhered vapor
barrier, Case Study 1.
The flooring industry, which also has
concerns with moisture in concrete, uses a
moisture probe test (ASTM F2170, Standard
Test Method for Determining Humidity in
Concrete Floor Slab Using In-Situ Probes) to
determine if the moisture in the concrete
slab has reached a level at which the flooring
material can be adhered. This test uses
probes that are set into cores at different
depths of the concrete slab and sealed for
72 hours. This test works relatively well for
flooring due to the more consistent indoor
temperatures and humidity. For concrete
slabs that are exposed to the weather, such
as roof decks, the temperature and humidity
will vary, which will affect the readings
from the probes. The conditioning section
for ASTM F2170 states:
9.1 Concrete floor slabs shall be at
service temperature, and the occupied
air space above the floor slab shall be
at service temperature and service
relative humidity for at least 48 hours
before making relative humidity measurements
in the concrete slab.
Based on the conditioning statement,
this test is not viable for concrete slabs
exposed to the weather.
Furthermore, even if the amount of
moisture could be measured easily and
accurately in-situ, the industry has not
determined or defined what the acceptable
moisture content in concrete decks is for
the installation of a roofing system.
CASE STUDY 1
This new construction project in the
Northeast U.S. involved approximately 450
squares, with
three floors of
newly poured,
6-in.-thick concrete
deck. Slope
was built into
the deck with
the ridgeline running south to north in
the middle of the field and drains set along
the east and west walls. The walls were
tilt-up concrete panels with the tops of the
walls approximately 4.5 ft. above the deck
elevation, and overflow scuppers cut into
the panels by each drain. The roof system
consists of:
• An adhered thermoplastic PVC singleply
roof membrane
• Primed glass-faced gypsum board,
0.5 in. thick
• Two layers (1.5- and 2.0-in.) glassfaced
isocyanurate insulation
• Self-adhered vapor barrier and primer
• Poured concrete deck into a nonventing
metal pan
• Low-rise urethane foam adhesive
adhering all layers of board as well
as to the adhered vapor barrier
The roof deck was poured in four sections
on December 16, 29, and 30, 2011;
and January 25, 2012 (Figure 1).
The air temperature on the days of the
pours ranged from 3º to 33ºF. With interior
finish work already in progress, the
general contractor (GC) pushed the roofing
contractor to dry-in the building as quickly
as possible. The vapor barrier was installed
over three days (January 10 and 16, and
February 7, 2012), when the temperature
ranged between 7º and 43ºF (within the
acceptable temperature installation range
for the vapor barrier). (See Figure 2.) The
roofing project reports state that the concrete
was visibly dry and the GC, roofing
contractor, and FM Global representative
witnessed and accepted the adhesion testing
of the vapor barrier to the concrete
deck. According to the project records, on
the south section of the roof, the initial concrete
pour was exposed for 25 days, and the
north sections were open for 12 to 18 days.
On January 25, the roofing contractor
began installing the roof system along the
ridgeline, filling in the middle area of the
roof and leaving approximately 20 ft. along
the perimeter open.
On February 15, blisters were seen
under the adhered vapor barrier. Test cuts
showed moisture and standing water on the
deck (Photos 2, 3, 4, and 5). An additional
12 test cuts were done on February 23,
with nine test cuts showing moisture and
standing water between the vapor barrier
and the concrete deck (Figure 3). At this
point, the project was shut down, and accusations
and blame for the presence of the
water started, followed by claims that the
products and/or the workmanship were at
fault. The GC refused to share the construction
documents, specifically for the concrete
floor and roof deck applications. He did
state that the concrete was a “normalweight
structural concrete.”
J u l y 2 0 1 4 I n t e r f a c e • 2 3
Photo 2 – Moisture between the concrete
and self-adhered vapor barrier.
Photo 3 – Removal of adhered vapor
barrier from primed concrete deck.
The self-adhered vapor barrier sheeting was removed from the
entire 20-ft.-wide perimeter on February 23. The exposed deck was
left to surface-dry (Photo 6). On March 5, pull testing was done on
new self-adhered vapor barrier to the primed deck. The first test
failed within the urethane adhesive foam due to inadequate cure
time. The other five assemblies all showed very good pulls, with
the readings between 645 and 1,185 pound force—well above the
calculated design uplift load of 28 psf for the wind uplift pressure.
During this site visit, the GC did acknowledge that the interior of the
building was heated to a constant 70º to 75ºF temperature to allow
the intumescent paint to dry.
Figure 3 – Field-testing of the self-adhered
vapor barrier, Case Study 1.
2 4 • I n t e r f a c e J u l y 2 0 1 4
Photo 5 – Primer coming off the concrete deck.
Photo 6 – Roofing removed
from the perimeter.
Photo 4 – Moisture on the deck;
minimal primer.
It was subsequently determined that
high moisture content in the concrete roof
deck and the initial cold temperatures
inside and out caused a slow cure and
slower drying of the concrete. When the GC
heated the interior of the structure to 70º to
75ºF while the outside temperatures were
averaging in the mid-20ºF range, a strong
moisture drive up into the roofing vapor
barrier had been created. The moisture
drive was so great that the diffused water
that accumulated on the deck lifted the barrier
sheet off of the concrete. Typically, the
adhesion of the vapor barrier to concrete is
well above 500 psf, indicating the moisture
drive was substantial.
Concern was expressed for the water
still in the concrete deck and how it might
affect the roof system or appear as leaks in
the building. Due to the lack of test methods,
we do not know if the remaining water
is great enough to potentially affect the roof
system. The probability of the water in the
concrete entering the building is minimal,
as the steel form will prevent downward
drying, and any vents or small holes will
typically plug and stop water from draining
from the concrete.
The roof system was completed as specified
with the inclusion of sealing all of the
through-deck penetrations, as well as along
the walls. Two mechanically fastened batten
bars, at 4 and 8 ft. from the perimeter, were
installed with a cover strip welded over the
top. The roofing contractor has monitored
this project for the past two years, reporting
no issues.
This case study is a classic example of
an expedited construction schedule with
pressure to dry-in the building so the interior
work could be done during the coldest
months of the year. While it was never
determined what type of structural concrete
was poured for the roof deck, the fact that
it was poured over a steel pan, with outside
temperatures predominately below freezing,
caused the drying time to be considerably
slower. Pressure to dry-in the building by
installing the adhered vapor barrier shortly
after the pours, due to construction schedules,
sealed the excess moisture in the
concrete. To compound the issue, the interior
of the building was heated to very high
temperatures, which created an even greater
vapor drive than what would normally
be seen. Once all the factors were brought
together, it was obvious that the schedule
for the building had not been realistic; more
time should have been scheduled to allow
the concrete to dry.
CASE STUDY 2
Located in the Mid-Atlantic region, this
office building was built in 2007/08 and is
approximately 150 ft. high with a roof area
of approximately 340 squares. The walls
are precast concrete with formed window
openings. The roof deck is a poured-in-place
8-in.-thick structural concrete deck. It is flat,
with no slope to drains. There are four drains
equally spaced along the two lengths of the
roof. The parapets vary in height from almost
flush to the roof level to approximately
4 ft. high. There are two penthouses and
mechanical equipment in the center of the
roof surrounded by an EIFS windscreen. The
roof system consists of:
• An adhered thermoplastic (PVC)
single-ply membrane
• Four-inch base layer with tapered
polyisocyanurate insulation
• Concrete deck
• Low-rise urethane foam adhering
the layers of insulation to each other
as well as to the deck
The roof installation was uneventful up
until 95-98% of completion. On a Friday
J u l y 2 0 1 4 I n t e r f a c e • 2 7
ISSUE SUBJECT SUBMISSION DEADLINE
October 2014 Roofing failures July 15, 2014
November 2014 Traditional materials August 15, 2014
December 2014 Codes and standards September 15, 2014
January 2015 Expansion joint systems October 15, 2014
February 2015 Liquid-applied membranes November 14, 2014
March 2015 Extreme weather December 15, 2014
Publish in Interface
Interface journal is seeking submissions for the following issues. Optimum article size is 2,000
to 3,000 words, containing five to ten graphics. Articles may serve commercial interests but
should not promote specific products. Articles on subjects that do not fit any given theme may be
submitted at any time.
Submit articles or questions to Executive Editor Kristen Ammerman at 800-828-1902
or kammerman@rci-online.org.
Sample Nuclear Moisture Lab Field
Number Gauge Weight Moisture Observation
Reading Content
1 8 0.44 2.2% All components dry
2 12 0.69 4.6% Bottom layers of insulation damp
3 16 9.78 56.8% Bottom layers of insulation wet
Table 1
afternoon in early summer, a decision was
made to test the water-cooling system for
the building, which had valves on the roof.
It was also thought this would offer a good
opportunity to conduct a flood test on the
roofing system. Unfortunately, the flashings
were not 100% complete, the drains had not
been sealed and clamped, and the roofing
contractor was not informed of the flood
test. When work resumed Monday morning,
it was discovered there had been numerous
leaks into the interior.
The construction team brought in a
consultant to determine the extent of the
water intrusion into the roof system. The
consultant scanned the roof using nuclear
radioisotopic thermalization, based on 10-ft.
grids. Readings were recorded and the data
studied for where to extract the samples,
based on low, intermediate, and high readings.
The samples were identified, removed,
bagged, and brought to a lab for evaluation
for water content. See Table 1.
It was determined that approximately
75% of the roof was dry, 15% damp, and
10% wet. This survey noted the water infiltration
occurred at the drains and where the
flashing details along the penthouse were
not completed. Concern was noted that
while the majority of the roof appeared to
be dry, over time, the trapped water would
vaporize on hot days and migrate through
the system. The vapor could then condense
on cooler nights and during colder temperatures,
reverting back to a liquid.
The construction team identified areas
of the roof to be replaced (approximately
one-third of the total area), which was done
during the late summer and early fall of
2008 (Figure 4). It appears that most of
the areas identified as wet/damp from the
nuclear scan were replaced (heavy black
lines on Roof Plan 4). Project records indicate
not all of the identified damp/wet
areas were replaced, primarily at the west
end of the building. At the completion of
the rework, 11 test cuts were done by a
third party to determine the condition of
the roof assembly; the cuts are designated
by the orange dots on Roof Plan 5. Based
on the report, all test cuts indicated the
roof system layers and concrete deck to be
dry, including the west end of the building
where there was no product replacement
(Figure 5).
The building owner noticed a few leaks
in late 2011, and upon investigating the roof,
noticed the membrane billowing and insulation
displaced at the west end. The owner
2 8 • I n t e r f a c e J u l y 2 0 1 4
Figure 4 – Initial area of moisture in the roof system and replacement (Case Study 2).
Figure 5 – Test cuts indicating all areas of the roof to appear to be dry (Case Study 2).
2008 Investigation 2012 Investigation
Sample Nuclear scan Moisture Unadhered membrane
(dry/damp/wet) (yes/no) (yes/no)
1 Wet No Yes
2 Dry Yes No
3 Damp Yes Yes
4 Dry Yes Yes
5 Dry No Yes
6 Wet Yes No
7 Wet Yes No
8 Wet No No
9 Wet Yes No
10 Wet No No
Table 2
contacted a contractor who repaired the
leaks, repositioned the insulation, and added
paver ballast to hold the system in place.
Upon notification of the roof issues,
the roof system supplier arranged for an
investigation with a roof consulting firm
that had not been involved with the project.
After review of the previous reports, which
included the “water test,” the nuclear moisture
scan, and the test cuts, the roof system
supplier and consultant identified where
test cuts would be taken.
Ten cuts were performed with the locations
determined by the 2008 nuclear scan
where the original results would be compared
to the present day. Sample 1 from
the 2012 investigation, which showed dry
conditions, matched the test cut from 2008;
however, Sample 3 from the 2012 investigation
showed wet conditions, whereas the
2008 test cut had been dry. These cuts were
taken from the west end of the building,
where the system had become unadhered.
The findings show that the moisture conditions
had changed for 50% of the test cuts.
See Table 2.
The area where the roof system was
replaced with new insulation and membrane
had three areas that showed wet
conditions (Samples 6, 7, and 9). The roof
system was thoroughly checked to see if
there were any breaches or possible entry
points for the water, and none was found
(Figure 6).
Excess water/moisture caused the
issues with this roof installation and performance.
A major contributor to the problems
was the water from the flood test. The ponding
water from the flood test that entered
J u l y 2 0 1 4 I n t e r f a c e • 2 9
American Hydrotech, Inc. 303 East Ohio | Chicago, IL 60611 | 800.877.6125 | www.hydrotechusa.com
© 2013 Monolithic Membrane 6125 is a registered trademark of American Hydrotech, Inc.
Monolithic Membrane 6125, the original rubberized
asphalt membrane, has been entrusted with keeping
high profile structures across the country and around
the globe watertight for 50 years. More than 2
billion square feet of membrane is still performing
today as it did the day it was installed.
50 YEARS OF PROVEN PERFORMANCE – MONOLITHIC MEMBRANE 6125®
RCI-50-Half-Horiztonal.indd 1 12/11/2012 5:15:41 PM
Figure 6 – Field evaluation with test cuts indicating the movement of the moisture within the
system at Case Study 2.
the roof system was able to move between the roofing components
and along the concrete deck, aided by hydrostatic pressure
(Photos 7, 8, 9, and 10). After the water test, the water in the
system has to travel around the insulation boards as well as the
ribbons of urethane adhesive. The adhesive ribbons that were on
the concrete deck most likely trapped some of the water in the
U-shaped application pattern. The records indicate there were
areas where the insulation was not removed and replaced for up
to three months. It is also unknown if all of the wet or damp insulation
was replaced. Comparing the nuclear scan results with the
2012 test cuts that were taken in the designated replacement
zone (Samples 6, 7, and 9), these test cuts should have been dry.
An unanswered question: Is the original insulation still in place
(which can explain the results), or was it replaced and moisture
migrated toward these areas? With the wet insulation and
water in contact with the concrete deck for up to three months,
a portion of this excess water soaked into the concrete deck.
In addition,
with the wet
components
and water on
the deck, this
slowed down
and probably
stopped
the natural
drying and
removal of the
excess water
in the concrete
deck.
During the
replacement
phase, the
concrete deck
most likely
was exposed
for, at best, a
few hours—
not enough
time to allow
3 0 • I n t e r f a c e J u l y 2 0 1 4
Photo 7 – Moisture underneath
the bottom layer of iso.
Photo 8 – Moisture on
concrete deck.
Photo 9 – Moisture between the layers of boards.
Photo 10 – Moisture between the layers of iso.
for any drying of the concrete.
Case Study 2 highlights the potential
consequences of allowing water to remain
within a roof system installed over a concrete
deck. The long time between the flood
test and removal and replacement of wet
components allowed the water to move
through the system, as well as be absorbed
into the concrete. While this case study
may be severe, we can learn from this
event not only that there is an issue with
excess concrete mix water, but also that a
concrete deck exposed to the elements will
absorb some of the water and, if not properly
addressed, will affect the roof system
at some point and most likely well after the
“wetting” event occurred.
CONCLUSION
Moisture and concrete decks will continue
to be an issue for the roofing industry,
with accelerated construction schedules,
the increased frequency of adhering insulation
directly to concrete decks in ribbons
of adhesive, leaving the metal pan/forms in
place, etc. In some sense, we may see more
issues, as there are perceived energy savings
when the LWSC is used.
As noted above, there is currently no
acceptable test method to determine the
moisture content or relative humidity of a
concrete deck that is exposed to the weather.
Greg Doelp and Stephen Condren, engineers
at Simpson Gumpertz & Heger who
have documented the issues and resulting
roofing-related problems with moisture
entrapped in concrete roof decks, noted:
While it might be helpful to have a
field test method that could quickly
and accurately measure the moisture
content in a concrete roof deck,
such a test method will only confirm
that concrete roof decks contain too
much water. Drying of wet concrete
roof decks is a long-term process.
Roofing systems installed over concrete
decks need to be designed to
accommodate the moisture within
the roof decks. This usually involves
inclusion of a vapor retarder within
the system.
The 28-day “cure” time commonly referenced
with structural concrete is the period
for developing the design compressive
strength of the concrete and has no correlation
with the moisture content or concrete
“drying.” Concrete develops strength by curing
that is a chemical process, not through
the loss of water by drying. The cure time
should never be used as a basis for when a
roof system may be installed.
The Portland Cement Association has
done research that shows it takes up
to three months to reach a 75% relative
humidity level with NWSC, and twice as
long with LWSC. The test was done in a laboratory
setting, with constant temperature
and humidity levels, all sides of the concrete
exposed, and without any additional moisture
(the latter often occurs in the field).
Factor in that more roof decks are being
poured onto a steel pan, and the inward
drying for all practical purposes is eliminated,
even if vented steel decks are used, as
the SDI states in its position paper.
The NRCA is seeing an increase in the
number of claims associated with moisture
in concrete and the use of LWSC. The solutions
for repairing damaged assemblies will
J u l y 2 0 1 4 I n t e r f a c e • 3 1
At your own pace,
on your own time, at your fingertips …
Roof Drainage Design
Roof System Thermal and
Moisture Design
Roofing Basics
Roofing Technology
and Science I
Roofing Technology
and Science II
Rooftop Quality Assurance
Wind Design for
Low-Slope Roofs – Part I:
Understanding ASCE 7-10
Wind Load Calculations
Wind Design for
Low-Slope Roofs – Part II: FM
Global Guidelines and Best
Practice Considerations
www.rci-e-learning.org
Online Educational Programs
be expensive, regardless of whether one or
all parties of the project participate.
Designers of projects that include concrete
decks—either new pours or existing
slabs—should strongly consider including
in their roofing specifications an adequate,
bonded vapor barrier on the top side of
the deck to prevent any water that may be
retained in the concrete from migrating into
the roofing system and condensing over
time. Consideration should also be given to
minimize the use of organic materials and/
or moisture-sensitive products within roofing
systems.
Although surface dryness can generally
easily be determined, the remaining free
moisture that is within the concrete slab
cannot readily be assessed. Until such time
as a viable moisture test method is found,
the decision of when a concrete deck may be
roofed should include the project designer,
the general contractor, the concrete contractor,
and their suppliers, as they will have
more knowledge of the concrete mix and
moisture release rates. The designer and
GC should also have the best knowledge
of the potential water/moisture migration
and potential vapor pressures, based on
the concrete specifications and the project
environment, including the building microclimate,
such as heated interior, additional
high-moisture interior components, and
other factors that may affect the moisture
drive out of the concrete. This design and
management group should communicate
with the roofing specifier and roofing contractor
when they can safely proceed with
the installation of the roof assembly.
EDITOR’S NOTE: RCI is currently developing
a technical advisory on LWSC construction.
When it is completed, it will be posted to the
RCI website.
ACKNOWLEDGEMENTS
Micrograph (Photo 1) of lightweight
concrete with expanded aggregate,
from “Is Lightweight Concrete All
Wet?” in Structure, a joint publication
of NCSEA, CASE, and SEI,
published 1/2013; by David Martin,
Alec Zimmer, Michael Bolduc, and
Emily Hopps
“Venting of Composite Steel Floor Deck,”
the Steel Deck Institute position
paper, November 2008
William Wolf, “Designing with Lightweight
Concrete,” Structure, April
2008
Mark Graham, “Moisture in Lightweight
Structural Concrete Roof Decks,”
NRCA Industry Issue Update
Stephen Condren, Joseph Pinon, and
Paul Scheiner, “What You Can’t See
Can Hurt You,” Professional Roofing,
August 2012
Comments from Stephen Phillips, legal
counsel for the NRCA
3 2 • I n t e r f a c e J u l y 2 0 1 4
Joe Schwetz is
the Director of
Technical Service
for Sika Sarnafil,
a division of Sika
Corp., Canton, MA.
He has a degree in
architectural engineering
from SUNY
and has worked in
the roofing industry
for over 25
years in various research and development,
technical, and managerial capacities.
Schwetz is active in various technical
standard and code development bodies,
including SPRI and SIGDERS, and chairs the
ASTM committee on PVC roofing. He is also
the membership secretary for ASTM E60
Committee on Sustainability.
Joe Schwetz
The fifth annual survey performed by the Building Information Modeling (BIM) committee of the Structural Engineering
Institute (SEI) and the Council of American Structural Engineers (CASE) shows that two-thirds of the 20,000 firms polled who
responded said they are using BIM, compared
with one-third in 2008.
The majority is not sharing its structural
BIMs with contractors due to liability
concerns. Most respondents use BIM
for steel structures, with 10% using it on
cast-in-place concrete structures.
The majority stated that BIM training
was either “horrible,” “nonexistent,” or
only “moderately effective.” The deliverable
remains 2-D drawings in the form
of a PDF, not model-based delivery. A
seamless, back-and-forth link between
the structural analysis model and the
BIM is not yet occurring, most engineers
agreed.
— ENR
BIM Use Is Growing