Hurricane Coastline: Lessons Learned During Sliding Glass Door Replacement and Concrete Balcony Repairs

May 15, 2016

3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 W y l i e • 1 0 1
Hurricane Coastline:
Lessons Learned During Sliding Glass Door
Replacement and Concrete Balcony Repairs
John C. Wylie, EI
Construction Science and Engineering, Inc.
218 East Main St., Westminster, South Carolina 29693
Phone: 864-647-1065 • Fax: 864-647-1076 • E-mail: john_wylie@constructionscience.org
Abstract
During an initial investigation of a 12-story condominium building, general conditions
of the sliding-glass doors and concrete balconies revealed that they were in various states of
deterioration and corrosion such that sliding-glass door replacement and concrete balcony
repairs were considered to be necessary. The ongoing multiphase project also included new
structural framing, new exterior cladding, concrete balcony re-sloping, and new waterproofing.
The new sliding glass doors were water-tested in accordance with industry standards.
However, unforeseen obstacles were experienced during the repair project and water testing
that revealed the need for additional engineering and waterproofing research.
Speaker
John C. Wylie, EI — Construction Science and Engineering, Inc.
John C. Wylie provides engineering services to the professional staff at Construction
Science and Engineering, Inc. (CSE), primarily in the areas of deficient construction, structural
analysis, and collapse and damage investigations. He provides investigations and
engineering analyses of various types of building components in high-wind environments,
including roof coverings and exterior wall claddings. Wylie was the project engineer for the
sliding-glass door replacement and concrete balcony repair project described herein, and
was directly involved in all aspects of the project.
1 0 2 • Wy l i e 3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6
INTRODUCTION
Coastal environments are considered
some of the harshest conditions to which
a building can be subjected. Over time,
the combination of salt, humidity, and
wind can significantly decrease the service
life of important building envelope components.
For example, aluminum-framed
sliding glass doors exposed to these coastal
conditions are prone to have a decrease in
serviceable life. Even though typical maintenance
will prolong the longevity of such
building envelope components, it can be
expected that these components will have to
be replaced at some point.
Since the early 1980s, a 12-story oceanfront
condominium building has been subjected
to the harsh coastal environment of
South Carolina. During a preliminary investigation
of the building, general conditions
of the aluminum-framed sliding glass doors
and exterior concrete balconies revealed
that they were in various states of deterioration
and corrosion such that sliding glass
door replacement and concrete balcony
repairs was considered necessary.
The ongoing multi-phase project included
the removal and replacement of all of
the sliding glass door units, installation
of new light-gauge metal framing, repairs
and resloping to the concrete balconies,
installation of new waterproofing on the
concrete balconies, and installation of new
stucco cladding. Additionally, several of the
new sliding glass doors were water-tested
in accordance with industry standards.
Unforeseen obstacles were experienced during
the project that revealed the need for
additional engineering and waterproofing
research. This paper will present this as a
case study, discussing the technical highlights
of the first phase of this project and
identifying the issues experienced during
the building project.
PRELIMINARY INVESTIGATION
The subject property includes two oceanfront
condominium buildings. The Phase 1
building was constructed in 1986 and is
12 stories high, while the Phase 2 building
was constructed shortly after and is nine
stories high. Both of the buildings are supported
by reinforced concrete foundations.
The structural skeleton of the buildings is
constructed with elevated reinforced concrete
slabs and reinforced concrete columns.
The exterior walls of both buildings
include light-gauge steel infill framing that
is covered by a combination of conventional
stucco and brick veneer. The roofs of the
buildings are low-slope configurations that
are covered with a single-ply membrane.
Preliminary investigation of the subject
property began with the Phase 1 building.
This building is divided into two sections:
the condominium units on the oceanfront
elevation, and the hotel units. Each floor
on the condominium side consists of three
individual units that include an exterior
cantilevered reinforced concrete balcony on
the oceanfront elevation (see Figure 1). With
the exception of the south elevation units,
each unit has two sliding glass door units,
which provide access to the exterior balcony
from the living room and master bedroom
areas. The south elevation units have an
additional smaller cantilevered reinforced
concrete balcony accessed from a bedroom
area (see Figure 2). Each floor on the hotel
Hurricane Coastline:
Lessons Learned During Sliding Glass Door
Replacement and Concrete Balcony Repairs
3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 W y l i e • 1 0 3
Figure 1 – Oceanfront elevation.
side consists of eight individual units with a
sliding glass door unit leading to a concrete
balcony.
During the preliminary investigation of
the Phase 1 building, the sliding glass doors
and exterior concrete balconies’ assessment
revealed that they were in various states of
deterioration and corrosion. Specifically, the
sliding glass door units were observed to
show signs of distress and limited remaining
service life due to the extent of gaps in
the framing components (see Figure 3), the
extent of gasket failure between the framing
and glazing components (see Figure 4), and
compromised waterproofing conditions.
The extent of corrosion observed on the
framing components of the sliding glass
doors varied significantly. Additionally, evi-
1 0 4 • Wy l i e 3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6
Figure 2 – South-facing elevation.
Figure 3 – Extent of gaps
in framing components.
dence of modifications, repairs, and physical
damage was observed on the framing
components. Figure 5 and Figure 6 show
significant corrosion and deterioration of
the framing components at the bottom of
the operable slider and sliding glass door
threshold.
The concrete surface of the exterior
balconies was observed to be spalling adjacent
to several of the sliding glass door
units. Additionally, localized areas of concrete
cracking and/or delamination were
observed.
RECOMMENDED SCOPE OF REPAIR
Based on the preliminary investigation
of the Phase 1 building, it was evident
that the sliding glass door units were at
the end of their
service life, and
repairs were necessary.
The recommended
scope
of repair included
the complete
removal and
replacement of
the sliding glass
door units and
localized repair to the exterior concrete
balconies. The repair would include the
removal and installation of new light-gauge
metal framing, corrective sloping of the exterior
concrete balconies to drain, installation
of a new waterproofing membrane on the
exterior concrete balconies, and the localized
installation of new stucco cladding.
Additionally, approximately 10% of the new
sliding glass doors would be subjected to
water penetration testing.
Several factors were considered when
deciding how the repair project would be
broken down between the Phase 1 and
Phase 2 buildings. Since neither the Phase
1 nor the Phase 2 building could be completely
closed during repairs, the repair
project would be divided into three phases.
The first and second phases would consist
of repairs to the condominium units and
hotel units, respectively, on the Phase 1
building. The third phase would consist of
repairs to the Phase 2 building. Repairs
would be performed three floors at a time
during the winter season to minimize fulltime
resident disturbance and financial
impact. As repairs are currently ongoing,
this paper will focus on the first phase of
the repair project.
3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 W y l i e • 1 0 5
Figure 6 – Significant corrosion and
deterioration of framing components.
Figure 5 – Significant corrosion and
deterioration of framing components.
Figure 4 – Extent of gasket failure between framing and glazing components.
REPAIR DESIGN AND DETAILING
The design of the Phase 1 building was
based on the applicable building code at
the time of original construction. Since that
time, the building codes have continued
to progress and change due to construction
practices and engineering research.
Therefore, the design for the first phase of
the repair project would be based on the
2012 International Building Code (2012
IBC), code-referenced standards, and manufacturers’
installation instructions.
Since the original sliding glass door
units were being replaced, the engineering
design consisted of coordination between
the project engineer, sliding glass door
manufacturer, and general contractor. The
project engineers provided the sliding glass
door manufacturer with the code-prescribed
wind pressures that the new sliding glass
doors would have to resist. Additionally,
the project engineers also provided details
to the general contractor regarding the
new light-gauge metal framing, which was
installed to transfer the code-prescribed
wind pressures from the sliding glass doors
to the reinforced concrete slabs.
The original sliding glass door units
in the condominiums consisted of a combination
of two fixed/one operable door
(i.e., OXO configuration) and one fixed/
one operable door (i.e., OX configuration).
Additionally, the original sliding glass doors
were non-full height (i.e., not slab-to-slab)
at an opening size of 10 x 8 ft.
During design discussions with the
homeowners’ association, it was decided
that the new oceanfront sliding glass doors
would be full height (i.e., slab-to-slab), and
the remaining sliding glass doors would be
the original size of the existing sliding glass
doors. The opening size for the new fullheight
sliding glass doors was 10 x 10 ft.
Changes to the original-size oceanfront
sliding glass doors consisted of simply
designing the vertical jambs along each
sliding glass door since the new sliding
glass door would be anchored directly to
the reinforced concrete slab at the top and
bottom. A new light-gauge metal header was
also designed for the new sliding glass doors
that would remain at the original size (i.e.,
non-full height).
The concrete adjacent to several of
the original sliding glass door units was
observed to be spalling and cracked. The
project engineers worked with the general
contractors to come up with a design that
incorporated a new waterproofing membrane
with the new sliding glass doors.
Many of the original sliding glass door
thresholds were installed on shallow concrete
curbs or on the surface of the original
concrete balconies. This original design/
detail was considered undesirable due to
the vulnerability of water intrusion around
the sliding glass door. Therefore, a new
raised concrete curb would be constructed
that would incorporate the new waterproofing
membrane and provide support for the
new sliding glass door. Figure 7 illustrates
the new concrete curb and waterproofing
details.
As shown above in Figure 7, a new concrete
curb would be constructed to support
the new sliding glass doors. A cant strip was
installed at the transition from the horizontal
concrete balcony surface to the vertical
concrete curb surface. The waterproofing
membrane was installed on the concrete
balcony surface and continued onto the
concrete curb.
As previously stated, approximately 10%
of the new sliding glass doors were subjected
to water penetration testing. It should
be noted that the new sliding glass doors
were not tested for air resistance. The water
penetration testing would be performed in
general accordance with ASTM E-1105,
Field Determination of Water Penetration
of Installed Exterior Windows, Skylights,
Doors, and Curtain Walls, by Uniform or
Cycle Static Air Pressure Difference and
1 0 6 • Wy l i e 3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6
Figure 7 – Concrete curb and new waterproofing detail.
AAMA 502, Voluntary Specification for Field
Testing of Windows and Sliding Glass Doors.
Specifically, the new sliding glass doors
would be subjected to a uniform air pressure
for a duration of 15 minutes.
REPAIR CONSTRUCTION
Due to the location and functionality
of the Phase 1 building, the coordination
and execution of the first phase of the
repair project would be performed during
the winter months. Additionally, since all
12 floors could not be completely closed at
the same time, the first phase was broken
down into four groups of three floors; each
group included nine condominium units.
Repairs would commence at the top group
(12th floor through 10th floor) and continue
forward with each group section (9th floor
through 7th floor, 6th floor through 4th
floor, and 3rd floor through 1st floor) until
completion. In order to complete the repair
project on schedule, each floor group had
to be completed within three to four weeks.
The work to be completed for each floor
group included the following:
• G rinding of concrete balconies
• R emoval of existing sliding glass
doors and components
• R epair of concrete balconies
• I nstallation of new concrete curb
• I nstallation of new light-gauge metal
framing
• I nstallation of new exterior stucco
cladding
• I nstallation of new sliding glass
doors and waterproofing
• I f applicable, water penetration testing
of new sliding glass doors
• Cleaning of condominium units to
preconstruction conditions
Grinding and Repair of Concrete
Balconies
The repair project began with the grinding
and repair of the exterior concrete balconies.
Unlike current building codes and
standards, the applicable building code
at the time of original construction did
not provide exterior concrete balcony slope
requirements. Though drainage scuppers
were installed at the outboard edge of
the balconies, evidence of water ponding
was observed on the balconies. For new
construction, accepted industry standards
and typical waterproofing manufacturer’s
installation instructions require a minimum
1/8-in.-per-ft. slope-to-drain for balconies
over a nonhabitable space. The repair project
did not specify the installation of a new
overlayment to provide adequate slope for
drainage purposes, and the concrete balconies
were ground in localized areas to assist
with drainage. Additionally, since carpet
was installed on the concrete balconies of
several condominium units, grinding would
remove any glue or impurities that otherwise
would not allow the new waterproofing
membrane to properly adhere to the concrete
balconies.
Localized areas adjacent to several of the
sliding glass door locations required repair.
The majority of issues adjacent to the sliding
glass door locations consisted of spalling
and cracking of the concrete balcony from
long-term water intrusion. In a few localized
areas, the steel rebar was observed to be
corroded; therefore, the exposed steel rebar
was ground and treated with a corrosion
inhibitor to prevent any further deterioration.
After loose or broken pieces of concrete
were removed from the spalled and cracked
areas, a concrete rehabilitation repair mortar
was used to patch the areas and provide
a uniform and sloped surface (see Figure 8).
Installation of New Concrete Curb
Following the concrete balcony grinding
and repair work, a new concrete curb was
poured. Additionally, the new concrete curb
3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 W y l i e • 1 0 7
Figure 8 – Repaired concrete balcony surface.
would allow the installation of the
cant strip to provide proper integration
of the new waterproofing
membrane (see Figure 7). When
the concrete curb had properly
cured, a urethane waterproofing
membrane was installed from the
top surface of the concrete balcony
and past the interior face of
where the new sliding glass door
would be installed.
Installation of New Light-
Gauge Metal Framing
The new sliding glass doors
and metal framing were designed
to resist the 2012 IBC wind loads.
The new metal framing (i.e.,
jambs and headers) for the sliding glass
doors consisted of 18 light-gauge metal
studs and tracks. For example, the design
pressure rating for the sliding glass doors
at the twelfth floor was DP 100. Therefore,
after the new sliding glass doors received
the code-prescribed 100-psf wind pressure,
the new metal framing has to transfer that
load to the adjacent reinforced concrete
slabs.
Due to the large wind pressures, the
metal framing (i.e., jambs and headers) of
the new sliding glass door units would consist
of several framing members. The fullheight
metal framing configuration is shown
in Figure 9, while the non-full-height metal
framing configuration is shown in Figure 10.
For example, the metal built-up jamb
framing at the 12th floor consisted of two
studs and two tracks. Likewise, the builtup
header framing consisted of three jambs
and three tracks. A structural metal connector
was installed to attach the built-up
jamb framing to the reinforced concrete
slabs. A similar-type connector was used for
the attachment of the built-up header to the
built-up jamb framing.
Once the metal framing was complete
and the concrete curb was properly
cured, the sliding glass door units could
be installed. Before the sliding glass door
units were installed, the door subcontractor
had to install a metal subheader and subsill.
Due to the large code-prescribed wind
pressures, the subheader and subsill act
as a stiffener to allow proper load transfer
from the sliding glass door to the reinforced
concrete slabs and metal framing. The new
sliding glass doors are simply “snapped”
into the subheader and subsill, which are
connected to the reinforced concrete slabs
(for the full-height units) and metal built-up
header (for the non-full-height units). Figure
10 shows a non-full-height opening (on
right) and full-height opening (on left) with
the subheader and subsill installed.
Installation of New Sliding Glass Doors
and Waterproofing Membrane
The final stage in the repair project
was the installation of the new sliding
glass doors and waterproofing membrane.
The new sliding glass doors were simply
“snapped” into the subheader and subsill.
Additionally, the jambs of the sliding glass
doors were attached to the metal built-up
jambs. The new sliding glass doors were
properly sealed with engineered sealant
joints around the perimeter. Lastly, the
liquid-applied waterproofing membrane was
1 0 8 • Wy l i e 3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6
Figure 9 – Full-height
metal framing.
Figure 10 – Non-fullheight
metal framing.
installed. The waterproofing membrane consisted
of small aggregate that provides slip
resistance and keeps the concrete balcony
surface cooler.
WATER PENETRATION TESTING
Due to the magnitude of the repair project,
it was imperative that the new sliding
glass doors be tested in place to replicate
the harsh coastal environment. As the subject
building is located on a hurricane-prone
coastline, the new sliding glass doors would
very likely be subject to hurricane-force
wind speeds and wind-driven rain during
its serviceable life. One of the best ways to
subject the new sliding glass doors to these
conditions is to perform an in-situ water
penetration test to simulate these conditions.
During the repair project, ten new sliding
glass doors were water-tested. The
water penetration testing was performed
in accordance with ASTM E-1105, Field
Determination of Water Penetration of
Installed Exterior Windows, Skylights, Doors,
and Curtain Walls, by Uniform or Cycle Static
Air Pressure Difference, and AAMA 502,
Voluntary Specification for Field Testing of
Windows and Sliding Glass Doors.
To simulate a high wind-driven rain
event, the laws of thermodynamics are used
to draw exterior air and water toward the
interior. Specifically, since pressure will
always flow from high pressure to low pressure,
an internal vacuum (i.e., low pressure)
is created to force air from the exterior (i.e.,
high pressure) toward the interior. The simplest
way to create this condition is to construct
a frame around the interior perimeter
of the sliding glass door and install a
vacuum to draw the air out (see Figure 11).
This method simulates a pressure differential
by equilibrating the interior air pressure
to a high-wind event. Additionally, a grid
of water spray nozzles was constructed on
the exterior side of the sliding glass doors
to simulate rain (see Figure 12). The combination
of the spray nozzles and interior
pressures created the conditions of a high
wind-driven rain event.
The interior chamber used during the
repair project was constructed from structural
wood framing and sealed with duct
tape to prevent any air leakage. Clear
heavy-duty plastic was installed on the interior
face of the chamber to allow for water
penetration observations.
The water
spray rack was
constructed from
PVC pipe and copper
spray nozzles.
Based on the abovereferenced
industry
standards, the new
sliding glass doors
would be subjected
to a constant water
spray of 5.0 gallons
per feet squared
per hour (gal./ft2/h)
and a static vacuum
air pressure for 15
minutes. The static
vacuum air pressure
was based on
the design pressure
rating of the sliding
glass doors. Therefore, the static vacuum
air pressure at the 12th floor for a DP 100
sliding glass door is 1.92 inches of water
column, or ten pounds per square foot (10
psf).
THE UNFORESEEN OBSTACLES
DURING REPAIRS
In a perfect construction world, all of the
contracting trades would work in harmony
and construct an effortless structure with
no imperfections or issues. However, in the
real world, whether it is new construction
or repair of an existing structure, this is
never the case, and technical issues will
arise. During the course of the repair project,
several technical issues and unforeseen
3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 W y l i e • 1 0 9
Figure 12 – Water penetration
test spray rack.
Figure 11 – Water penetration test chamber.
obstacles were experienced that required
additional engineering and drew on the
expertise of the project engineers.
Light-Gauge Metal Framing
Modifications
With any type of construction, it is
always good practice to “measure twice, cut
once.” During the preconstruction phase of
the repair project, all of the existing sliding
glass doors were field-measured for exact
dimensions. On paper, it seemed the new
sliding glass doors would fit into the existing
openings. However, as the repair project
progressed, it became evident that several
structural reinforced concrete columns were
not in the exact location as depicted on the
original construction plans.
The depth of the new sliding glass doors
increased from approximately four inches to
six inches, but the length of the new sliding
glass doors remained the same. Additionally,
the number of light-gauge metal framing
members increased at the jambs and headers
of the new sliding glass doors. Though it
appeared on the original construction plans
that new built-up jambs would fit into the
existing openings, this was not the case at
several locations. Specifically, due to the
location of the existing structural column,
the built-up jambs had to be redesigned or
completely omitted.
At some locations, we were able to omit
the built-up jambs because the existing
structural column was close enough such
that the new sliding glass door could be
directly attached. At locations with headers,
the connection hardware could still be used;
however, the fasteners had to be changed to
be compatible with the reinforced concrete
columns (see Figure 13).
At other locations, the required number
of light-gauge metal framing members
would not fit between the location of the new
sliding glass door and existing reinforced
concrete column. At these locations, only
a few framing members that would fit the
new sliding glass doors were then attached
directly to the existing reinforced concrete
column. The fasteners used were driven
though the few metal framing members,
with the metal framing members acting as a
filler between the new sliding glass door and
existing reinforced concrete column.
Issues During Water Testing
Water penetration testing is a method to
observe whether or not a fenestration product
(i.e., windows or doors) was properly
installed to prevent water from entering the
building. However, if a fenestration product
does fail (i.e., allows water intrusion), then
the water leak must be traced back to its
origin to determine a proper repair.
During the water penetration testing
for the repair project, ten new sliding glass
doors were tested over the duration of the
repair project as groups of floors were completed.
Unfortunately, three of the ten sliding
glass doors failed the water penetration
testing.
During the first water penetration test,
water appeared at the wall-to-floor intersection,
adjacent to the right jamb of the sliding
1 1 0 • Wy l i e 3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6
Figure 13 – Header attached directly to reinforced concrete column.
Figure 14 – Void in sealant joint.
glass door. The observed water intrusion
was caused by a crack/void in the exterior
stucco cladding in the same area as the
failed location. It should be noted that the
new sliding glass door was not isolated from
the exterior cladding. Since the intent was
to test the installation of the sliding glass
door only, subsequent water penetration
testing would involve isolating the sliding
glass door with clear plastic.
Of the remaining sliding glass doors
to be tested, two additional sliding glass
doors failed during water penetration testing.
The failure mechanism of both sliding
glass doors was observed to be similar.
Specifically, water was observed to come up
and over the back dam of the threshold at
the intersection of the fixed panel and operable
panel (i.e., sliding door). The operable
door was removed so that the area where
the water penetration was observed could
be inspected. Upon inspection, a pinhole
void in the field-applied concealed sealant
joint was observed at the intersection (see
Figure 14).
It was determined that the sealant had
not had sufficient time to set prior to normal
construction traffic pressure being applied
to the threshold. It should be noted that
unlike the water penetration testing, the
pressure differential from the exterior to the
interior and volume of water experienced
during a high wind-driven rain event (i.e.,
hurricane) are not constant over an extended
duration. Therefore, the author believes
that it would be very unlikely that the failed
sliding glass doors would fail under a high
wind-driven rain event.
Issues With Waterproofing Membrane
The repairs to the cantilevered exterior
concrete balconies consisted of localized
repairs and grinding of the surface to assist
with drainage. After the localized repairs
and grinding were completed, a new waterproofing
membrane was installed to protect
the concrete balconies and assist with
keeping water from entering the interior of
the subject building. The new waterproofing
membrane installed on the exterior
concrete balconies was a two-part waterbased
epoxy primer/sealer that included
an aggregate textured finish. The textured
finish provided a slip-resistant surface and
additional cooling during hot, sunny days.
The new waterproofing membrane is marketed
to be insensitive to humid conditions,
therefore making it a suitable product in a
coastal environment. Since
the repair project was being
performed during the winter
months, the environmental
conditions had to be suitable
before the new waterproofing
membrane could be installed
(i.e., minimum temperatures,
excess moisture conditions,
proper curing). However, a
few issues occurred during
the installation of the new
waterproofing membranes
that had to be corrected.
The installation schedule
of the waterproofing membrane
was modified several
times during the repair project because
of weather. Due to the timing of subsequent
weather events, curing problems
in the waterproofing membrane occurred.
Specifically, the localized areas of the waterproofing
membrane did not have adequate
time to properly cure from temperature and
rain events. Therefore, many of the concrete
balconies were recoated with a finishing
layer to provide a uniform product.
Several months after the installation of
the new waterproofing membrane, small
voids or pinholes were observed at localized
areas on the finishing layer of several
the concrete balconies. The initial prognosis
was that either moisture off-gassing or
pockets left from dislodged aggregate particles
caused the imperfections (see Figure
15).
After further investigation among the
project engineers, general contractor,
and manufacturer representative, it was
observed that the small voids did not penetrate
through the base layer of the waterproofing
membrane. Though the likely cause
of the small voids may be from off-gassing
(from excess moisture), the base layer of the
waterproofing membrane was not damaged.
LESSONS LEARNED DURING
REPAIR PROJECT
Regardless of the type or size of the
construction project, there are always takeaways
that can be applied to the next one.
This repair project was no different. Several
takeaways are being implemented into the
next phases of the repair project, and others
are being improved. Though there were
several technical issues identified during
the repair project, there were other lessons
learned from a construction administration
viewpoint. Many of the key lessons learned
during the first phase of this repair project
are outlined below.
Technical Lessons
• Perform a more comprehensive
survey to verify existing conditions.
During our preliminary investigation,
a comprehensive survey
was performed of the existing conditions
for the sliding glass doors and
concrete balconies, but not of other
items, such as the location of reinforced
concrete columns. The verification
of the reinforced concrete
column may have saved some time
and engineering during the course of
the repair project.
• Be able to adjust and redesign
engineering components during
repairs. On paper, it appeared that
there would not be an issue with
the new light-gauge metal framing.
However, when the issue with
the reinforced concrete column
was encountered, the repair project
could not be stopped to come up
with a solution. Therefore, the project
engineers had to rapidly come
up with an adequate solution that
would not delay the repair project.
• Identify and correct water intrusion
during water penetration
testing. Having a new sliding glass
door fail the first water penetration
test may have been expected.
Conversely, having two additional
sliding glass doors fail was definitely
not expected. After each failed water
penetration test, we were able to
identify the cause and determine if a
3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 W y l i e • 1 1 1
Figure 15 – Small voids in waterproofing membrane.
repair was considered necessary.
• Investigate potential issues with
the new waterproofing membrane.
Several issues were experienced—
either during the repair project or
after completion. After correctly identifying
the problem, whether from
curing issues or post-installation
voids in finishing layer, we relied
upon research and experience to
determine if repairs were required.
• Work with the general contractor.
When general contractors work
on similar projects over time, they
figure out what products and methods
work best for them. This repair
project was no different. After the
initial project plans were sent out,
the general contractor requested a
few minor changes to the connection
hardware. Therefore, the project
engineers researched and reviewed
the requests to determine if those
products could be used.
Construction Administration Lessons
• Work with homeowners. Though
the majority of the condominium
units at the subject property were
rented out to vacationers during peak
months, there are some residents
who live at the subject property fulltime.
These people had to be temporary
relocated until repairs were
completed in the units. Fortunately,
the subject property is large enough
such that those people could be easily
relocated. Additionally, those fulltime
residents were able to observe
the progression and completion of
repairs.
• Work with homeowners, again.
Though the majority of the homeowners
were in favor of the repair
project, some homeowners were not.
Therefore, the project engineers,
homeowners’ association, and project
management worked with those
individuals to come up with acceptable
solutions.
• Coordinate with all the different
parties. Due to all of the parties
involved and the rapid pace of
the repair project, weekly conference
calls were started to keep everyone
informed and to discuss any potential
issues. Though at times there
were not many items to discuss, the
conference calls became especially
convenient during periods when
scheduling water penetration testing
and to keep all parties informed.
• Share project information. Early
on in the repair project, much of the
project information was being shared
via email with all parties. However,
this process became cumbersome
and difficult due to the volume of
project information that was being
shared. Therefore, a project website
was setup in the virtual “cloud”
that would allow all of the parties to
access the project information.
CONCLUSIONS
Through the duration of the first phase
of a multi-phase repair project, several
unforeseen technical obstacles and construction
administration issues were experienced
that required additional engineering,
research, and problem-solving. Since the
repair project is located on a hurricaneprone
coastline, the products used had to
withstand the harsh environmental conditions
over a long period of time, in addition
to the wind pressures produced during
hurricanes. It was proven during the repair
project that not everything on paper goes
according to plan. Ultimately, having the
ability and experience to adjust and redesign
components in a short amount of time
was crucial to keep the project progressing.
The lessons learned during the repair project
have been valuable in that many aspects
can be used for the remaining phases of the
project and for future projects. The ability to
work with different parties (i.e., engineers,
contractors, management, and homeowners)
is critical with regard to sharing project
information, problem-solving, and meeting
project deadlines while attaining appropriate
customer satisfaction.