Skip to main content Skip to footer

Best Practices for the Design and Installation of Thermoplastic Roofing Systems

September 18, 2022

18 • IIBEC Interface July 2022
Proper detailing of roof penetrations
is a vital part of every
completed roofing assembly. Any
penetrations through a low-slope
roof assembly could represent
potential failure points and leaks
during the life cycle of the roof. Whether the
project is new construction or reroofing, the
roof manufacturers and design professionals
develop very specific detailing procedures to
reduce the possibility of breaches occurring.
The roofing professionals who undertake the
project must be capable of meeting the expectations
of the owner, the manufacturer, and
the design team. The roofing installation crew
should be well trained and experienced in the
roof manufacturer’s recommended installation
techniques as well as the architect’s and building
enclosure consultant’s design details.
As mentioned in the first article of this
series, the intent of this series of articles is not to
explain design requirements but rather to provide
a “roofing 101” narrative on best practices.
To that end, this article describes selected issues
related to detailing roof penetrations and the
technical aspects of flashing related to drainage
in the thermoplastic roof system; the article is
not intended to provide technical specifications
for design issues such as proper sizing, waterflow,
head of water, or drain locations.
ROOF DRAINS
Roof drains and overflow drains are among
the most critical components of any internally
drained roof assembly because they are responsible
for the removal of water from the roof
system. As part of that system, the primary and
overflow drains perform independently from
each other. The primary drain is generally
located at a low point of the roof area and is in
plane with or set lower than the roof membrane
plane so as to collect the vast majority of water.
The overflow drains are generally set slightly
above the roof plane as required by local rainfall
records, building codes, and environmental
requirements.
Insulation drain sumps involve additional
considerations. The tapered sump should
have a four-sided, gradual slope (Fig. 1), and
the tapered insulation
within the drain sump
should not reduce the
minimum R-value
thickness of the roof
insulation by more
than 1 in. (25 mm).
For instance, Section
402.2.1.2 of the 2021
International Energy
Conservation Code1
indicates that “the
minimum thickness
of above-deck roof
insulation at its lowest
point, gutter edge,
roof drain or scupper,
shall not be less than
1 in. (25 mm).”
Figures 2 and 3
illustrate incorrect
tapering and flashing
of the drain sump. In
these examples of incorrect tapering and flashing,
there are several issues:
• The slope is greater than 2 in 12.
However, there should not be any vertical
transitions. Instead, the sump should
have gradual slope on all four sides.
• There are field membrane splices closer
than 9 in. (229 mm) to the drain clamping
ring. Field splices are generally not
permitted to be within 12 in. (305 mm)
of the clamping ring per the roof manufacturer
specifications; manufacturers
may have slightly different criteria for
Figure 1. Diagram of a four-sided tapered drain sump.
July 2022 IIBEC Interface • 19
this item. The force exerted on the roof
membrane from installing the drain
clamping ring can pull tension on adjacent
field seams, which could weaken
or damage the field splice. The tension
could cause wrinkles and voids in
adjacent field seams if they are in close
proximity to the drain assembly.
• The vertical surfaces of the “sump”
area are bare/exposed polyisocyanurate
(polyiso) insulation, which means
there is no insulation facer to adhere to,
resulting in loose flashing and, potentially,
damage to the polyiso insulation
from solvents in the bonding adhesive.
• A metal drain pan is installed, which
is not required by code and not recommended
by the roof manufacturer,
above the roof insulation (Fig. 3). The
metal drain pan, if specified, should be
installed against the structural deck,
not on top of the insulation assembly.
A sump pan (or sump receiver) is a
square, approximately ⅛-in.- (3-mm-)
thick, flat piece of steel (unless it is a
dual pan). It should fit the roof drain
bowl, and its purpose is to assist in
securing the drain bowl to the roof
deck. Sump pans are manufacturer specific,
so they cannot be interchanged
with other manufacturers’ roof drains.
Metal drain pans are not typically
installed in conjunction with single-ply
roof systems in many areas of US but
can be incorporated by the designer.
• The inside corner detailing at the vertical
transitions is not installed per the
manufacturers’ specifications, and the
roof contractor has not installed the
manufacturer-required unreinforced
thermoplastic flashing detail membrane.
• There are no inside or outside corner
detail flashings installed in this example.
• The primary roof drain and the overflow
drain are installed at the same
elevation. The completed overflow
drain clamping ring did not include
an overflow drain collar adapter. The
overflow drain will function the same
as a primary drain, channeling water
into the overflow drain outlets at all
times. Overflow drains are intended to
actively remove water in the event the
primary drain becomes clogged. As the
overflow drain begins to remove water
from the roof, it generally discharges
(also known as daylights) onto the
grounds of the facility, thereby providing
a visual indication that the primary
drain is not functioning properly. The
overflow drain lines are generally not
connected to the plumbing system.
• Additionally, for this particular project,
the insulation system is specified to
be adhered with foam adhesive and
is intended to receive a hail coverage
rider with the warranty. The use of
insulation fastening plates is generally
prohibited by the roof manufacturer on
projects where a hail coverage warranty
is specified because the metal attachment
plates introduce a very hard pinch
point for the roof membrane at hail
impact points.
• The insulation is cupped and loose,
and the fasteners and insulation plates
that have been installed to compensate
for inadequately adhered insulation
introduce thermal bridging to the
roof assembly. Because the metal fasteners
and plates are secured into the
metal deck, they will easily transmit
temperature differences between the
Figure 2. This photo illustrates incorrect
flashing of a drain sump with thermoplastic
roof membrane.
Figure 3. Photo showing an incorrect
drain sump configuration, improper
installation of a metal drain pan, and
foreign material adhered to drain pan.
20 • IIBEC Interface July 2022
interior and exterior, resulting in thermal
bridging and thermal loss.
• The fasteners are also penetrating
the underlying vapor barrier, which
was designed in this assembly to not
be penetrated by fasteners because
it is installed over the mechanically
attached substrate board.
DRAIN FLASHINGS
Drain flashing should be accomplished as
shown in Fig. 4. Butyl-based mastic must be
present between the drain bowl flange and the
underside of the roof membrane (see notation A
in Fig. 4). The mastic should be visible, oozing
out slightly from under the roof membrane
inside the drain bowl and clamping ring. There
should also be a discernable hump of mastic
under the roof membrane adjacent to the exterior
edge of the clamping ring. Lead or metal
drain pans are not recommended and should
not be used with thermoplastic membrane systems
above the insulation board as shown in
this case.
All bolts with washers (see notation B in
Fig. 4), as required by roof manufacturer specifications
and The NRCA Roofing Manual:
Membrane Roof Systems,2 must be in place and
must be tight enough to provide compression
of the clamping ring against the butyl mastic,
which ensures a long-term water-tight seal.
Every fastener location on the clamping ring
and threaded hole in the drain bowl must
receive a new stainless steel bolt. Stainless steel
is recommended because it is less likely to
corrode. Much like a wheel on a vehicle, every
fastener location must receive a fastener to provide
even pressure. A simple test to check the
tightness of the drain bolts is to try to spin the
washers: if the washer spins, the bolt is not tight.
The bolt assembly clamping ring must be
secured into the drain bowl. It is important
to ensure that there is no damage to the bolts,
threads, or washers and no cracks in the clamping
ring, bolts, or washers. All bolt holes in the
drain clamping ring must receive a bolt.
In reroofing scenarios, it is recommended
that existing bolts be replaced with new bolts.
It is also recommended that the new bolts and
washers are stainless steel to provide long-term
performance.
On any roofing or reroofing project, the
roofing team should ensure that the drain
ring is not cracked or broken in any way. The
clamping ring must be intact to provide constant
compression against the butyl mastic.
Damaged clamping rings must be replaced.
(You may have noticed that
I have reiterated this issue
a few times. It has been my
experience over the years that
there will be situations where
someone has attempted to
reuse a cracked clamping
ring on reroofing projects
and leaks occur.)
The drain basket should
also be intact and secured
in place into the clamping
ring. This is vital to prevent
debris from flowing into the
drain and creating a backup
or clog. Backups and clogged
drains could cause structural
overloading of the roof structure
during heavy or prolonged
rain events.
The thermoplastic roof
membrane must extend at
least ½ in. (13 mm) toward
the middle of the bowl past
the bolt protrusions of the
clamping ring (see notation
Figure 4. Example of a roof detail sheet.
Figure 5. Standard scupper detail with thermoplastic olefin/polyvinyl chloride–coated metal scupper sleeve.
C in Fig. 4). In other words, the roof membrane
must be visible inside of the clamping ring.
It is important to ensure that the drainage
hole cut in the membrane is larger than the
drainpipe but smaller than the clamping ring
bolt protrusions. There should be no cuts or
slices into the membrane that extend back
toward or under the bolts and clamping ring.
Such cuts could expand and create moisture
intrusion issues behind the clamping ring. If
such cuts are present, the clamping ring should
be removed, the roof membrane around the
outside of the drain bowl cut away, and a
target patch of new roof membrane installed
per the roof manufacturers’ specifications. The
manufacturers specify that such target patches
be of sufficient size to ensure the heat-welded
seam edges will be located a minimum of 12
in. (300 mm) from the roof drain and overflow
drain clamping rings. Then the butyl mastic
and clamping ring should be reinstalled as
described previously.
Field splices must not run though the drain
ring or the drain sump, or within 12 in. (305
mm) of the compression ring because the membrane
tension caused by tightening the compression
ring can distort or wrinkle the field
splices. (See notation D in Fig. 4; also, please
note that 12 in. [305 mm] is a typical distance; for the
project-specific distance,
see the roof manufacturers’
specifications.) If field seams
or splices should occur within
the tolerance area, cut the
membrane back and install
a target patch as described
previously.
The overflow drain
collar/dam should be at a
higher elevation than the
primary roof drain in accordance
with local requirements
(notation E in Fig. 4).
The height of the overflow
collar/dam must meet the
requirements established by
the roof drainage calculations
for head of water for
the geographic location of
the project.
During construction, reroofing, or roofing
operations, a temporary strainer cover, as
indicated by notation F in Fig. 4., should be
in place to prevent debris from entering the
drainpipes.
ROOF SCUPPERS
Another very important detail for directing
waterflow from the roof is the scupper and
overflow scupper. Figure 5 is a typical scupper
detail drawing from a roof manufacturer.
July 2022 IIBEC Interface • 21
IIBEC half page.indd 1 4/18/2022 4:07:54 PM
Figure 6. Incorrect scupper fabrication (no flange attached).
22 • IIBEC Interface July 2022
When using a metal scupper flange insert,
whether it is coated metal, bare metal (such as
galvanized or stainless steel), or prefinished
metal, the following items must be incorporated:
• The horizontal metal deck flange of
the scupper must be supported by
wood blocking to prevent the metal
flange from buckling or bowing when
fastened. Figure 6 shows a scupper
without flanges, which does not meet
the roof manufacturers’ detailing and
specification requirements.
• The wood blocking should be wider
than the metal flange to ensure that the
blocking fully supports the metal flange.
• Most roof manufacturers require a
butyl-based mastic sealant installed
between the back side of the metal
scupper flange and the membrane wall
flashing around the scupper opening to
provide a sealed gasket—much like the
seal achieved at roof drain compression
rings.
• The fasteners securing the scupper
should be installed through the
bead of the butyl mastic to provide
compression against the butyl mastic
and help seal the fastener penetrations.
• When using coated metal, the flashing
process is simplified because the flashing
membrane can be hot-air welded to
the scupper.
• If using bare or prefinished metal,
primed and self-adhered flashings
will be required.
Roof manufacturers’
requirements
can differ slightly:
whereas some manufacturers
require selfadhered
thermoplastic
flashing to be
used to strip in the
scupper flanges, other
manufacturers allow
the use of a hybrid
flashing detail using
self-adhered ethylene
propylene diene terpolymer
(EPDM)
flashings to strip in
the scupper flanges
on a thermoplastic
olefin membrane system
(Fig. 7).
• Inside the scupper
opening, once the
membrane flashings
have been installed, most roof manufacturers
will require inside corner
detailing. Refer to the individual manufacturer’s
requirements pertaining to
warranty coverage limits for field-fabricated
corner details versus premolded
corner details.
• Overflow scuppers, much like overflow
drains, should be installed at a higher
elevation on the wall based on drainage
calculation for the specific project so
that they only collect and direct water
off the roof when the primary scupper
has malfunctioned or become clogged.
GUTTER AND DOWNSPOUT SYSTEMS
Gutter systems and downspouts are another
type of high-flow water management system
incorporated into some thermoplastic roof systems.
Figure 8 shows a typical gutter detail
installation. Key considerations for these systems
include the following:
• The gutter and downspouts must be
sized, spaced, and formed to meet
the drainage calculations. The gutter
should be designed such that it captures
the water as it flows over the metal edge
flashing without overshooting the exterior
edge of the gutter.
Figure 8. Typical gutter edge detail.
Figure 7. Hybrid scupper flashing with self-adhering ethylene propylene diene terpolymer
(EPDM) white flashing over a thermoplastic roof system.
July 2022 IIBEC Interface • 23
• There must be wood blocking in place.
This blocking must be secured per the
requirements of the manufacturer, local
code, FM Global,3 and the Sheet Metal
and Air Conditioning Contractors’
National Association (SMACNA),4 and
it must be wide enough to support
the entire width of the horizontal deck
flange of the metal edge or gutter.
• The roof membrane will typically be
extended out and over the face of the
wood blocking and be fastened into
the wood blocking per the roof manufacturer’s
requirements. The metal gutter
and metal fascia are then secured
into the wood blocking in accordance
with the manufacturer, local code, FM
Global, and SMACNA requirements.
• The gutter should be sloped to drain
toward the downspouts.
• Expansion joints must be installed at
the prescribed intervals based on the
gutter size and length as well as specific
building use and design requirements.
• Gutter connections, overlaps, corners,
downspout connections, and
expansion joints must be sealed to be
watertight.
• Gutter straps and support brackets
must be securely attached, sized, and
spaced to be capable of supporting the
gutter under load.
• Downspouts must be sized, spaced,
and secured per design criteria and
specifications.
REFERENCES
1. International Code Council (ICC).
2021. International Energy Conservation
Code. Country Club Hills, IL: ICC.
2. National Roofing Contractors
Association (NRCA). 2019. The NRCA
Roofing Manual: Membrane Roof
Systems. Rosemont, IL: NRCA.
3. FM Global. 2021. Roof Loads and
Drainage. FM 1-54. Providence, RI:
FM Global.
4. Sheet Metal and Air Conditioning
Contractors’ National Association
(SMACNA). 2012. Architectural
Sheet Metal Manual. Chantily, VA:
SMACNA.
Please address reader comments to
chamaker@iibec.org, including “Letter to
Editor” in the subject line, or IIBEC, IIBEC
Interface Journal, 434 Fayetteville St., Suite
2400, Raleigh, NC.27601.
Gary Gilmore, RRO,
REWO, CIT Level I,
is director of the roof
consultant group
Lerch Bates Building
Insight, in Texas,
where he is responsible
for overseeing and
executing roofing and
building enclosure
assessments, infrared
scanning, design,
contract document
review, quality assurance
observations, and field performance testing
services. Gilmore has extensive experience working
with owners, architects, general contractors,
and trade contractors, assisting them in selecting
and installing roofing and facade systems that are
appropriate for their specific project needs with
regard to building code and energy code requirements,
building type and occupancy, and cost constraints.
He has direct experience in field installation
of roofing and cladding systems obtained
through his early career on the contractor and
manufacturer representative side of the industry.
Gary Gilmore, RRO,
REWO, CIT Level I
S P E C I A L I N T E R E S T
Photo by Marten Bjork on Unsplash
Complete So that
You Can Compete
Want to win repeat business? Consider three key traits that contractors
should exhibit to win additional jobs from clients they have previously
served, writes Zulqernain “Zulq” Malik in Construction Executive.
• Be on time and on budget. Complete your project on
time and use newer technology to review past project information.
That can help avoid “unforeseen circumstances” that, with better
tools and more attentiveness, are all too predictable.
• Quality trumps price. “Project performance includes the
quality of the finished product, which includes your compliance
record, site tidiness, and flexibility through project changes,” Malik
explains. “When it comes to excelling on these metrics, you can’t leave
anything up to chance.”
• Don’t leave clients in the dark. “Owners are putting a large
investment into these projects, which can often last for months or even years,”
observes Malik. “Diplomacy and regular communication can go a long way to delivering
peace of mind.”
Source: constructionexec.com