Electric Heating Systems for Combatting Icing Problems on Metal Roofs

January 31, 1999

Electric Heating Systems For
Combatting Icing Problems
On Metal Roofs

By James Buska, Wayne Tobiasson, Alan Greatorex and William Fyall
ICICLES AND ICE DAMS MAY DEVELOP ON METAL ROOFS THAT DRAIN TO COLD EAVES. MELTWATER
that backs up behind such icings may leak into buildings, causing serious damage. Large icings are also a safety hazard.
Electric heating systems may be needed to provide a path for meltwater to drain safely off such roofs.
Fifteen different electric heating systems were evaluated during five winters on several buildings with severe icing problems
at Fort Drum, NY. All of these buildings had standing seam metal roofs and inadequate attic ventilation. The heating systems
installed in their valleys had various power outputs, layouts, and attachment methods. Most heaters were attached mechanically
or adhesively on top of the metal roofing, but some were installed under it. When too much heat was generated in a valley,
excess meltwater was produced and icing problems increased if the fascia was not well heated. Several techniques for heating
fascias were evaluated. Heater attachment with a special silicone adhesive and low-profile perforated stainless steel clips
worked well. Mechanical fasteners also worked well. Plastic clips attached with epoxy did not survive. Heaters placed under
the metal roofing also worked well but were difficult to install. It was also determined that snow guards are needed to prevent
heater damage by moving snow and formation of icicles on overhanging snow which bypasses the best of heating systems.
Introduction
The most effective way to reduce icings and ice dams on
metal roofs is to cool the underside of its surface with outside
air resulting in a “cold” ventilated roof. Paine1 states that
“roofs should not have to depend on an energy supply to
work properly.” We agree with that statement since most
new buildings can be designed so that their roofs do not
need electrical heating systems to function properly in cold
climates. However, there are situations when electric heaters
can be used to solve localized icing problems anticipated on
new roofs and chronic icing problems on existing buildings.
Although minor icings can be caused by daytime solar
melting of snow on a roof and nighttime refreezing of that
meltwater, building beat is the primary cause of ice dams and icicles on
warm roofs that drain to cold eaves2’3. Adding insulation to reduce
heat loss from occupied spaces and heat-producing equipment
in attics will help, but ventilation is still the key to a
“cold” roof.
Meltwater produced from melting snow on a “warm” roof
above heated portions of a building may freeze at cold eaves
producing icicles and ice dams there. Meltwater that backs
up behind an ice dam may leak into the building, causing
serious damage and possible loss of occupancy. Some warm
roofs can produce very large ice dams and icicles which are
also a safety hazard (see Figure 1). Electric heating systems do
not prevent icings from occurring. They prevent ponding
behind icings by providing a path through the ice for meltwater
to drain safely off such roofs. This greatly reduces the
size of the icing and the risk of roof leaks.
Standing seams on metal roofs direct the flow of snow,
ice and meltwater directly downslope along the seams. That
flow pattern is complicated by valleys and obstructions (e.g.,
vents, dormers, and snow guards). Standing seams are in the
way of most traditional heater layouts. Zigzagged loops of
electric heaters must either go up and over each standing
seam or be placed on the flat panel between them.
Generally, holes should not be drilled in metal roofs for
mechanical attachment of electric heaters. Adhesive attachment
to metal roofing is difficult. Creeping and sliding snow
Figure 1. Severe, problematic icings and ice dams along eaves of a dining
facility at Fort Drum in upstate New York.
January 1999 Interface • 13
and ice removes anything not well attached.
When using electric heaters, meltwater from the warm roof
above and that produced by the heater must be kept from freezing
on lower portions of the roof. This is difficult to do since these conductive
metal surfaces are exposed to cold air and wind. Icings on
building walls and on walkways or parking areas below also need to
be prevented.
Types of Electric Heaters
Henry4 provides a summary of the various types of electric
heaters, listing some of their advantages and disadvantages. Electric
resistance heaters are available for 110 and 220 volt systems in a
variety of heat outputs. Most constant wattage heaters cannot be
overlapped, since they will burn out at the hot spot created. Mineral –
insulated, constant-wattage heaters are available with metal sheathing.
They are quite durable, but since they are custom-made to
length, they are rather expensive. Plastic-sheathed, constant-wattage
heaters are also available. Some must be custom-made, but others can
be cut to length in set increments. Plastic-sheathed, self-regulating
heaters can be cut to any length and can be overlapped without creating
problems. They are generally more expensive than plasticsheathed,
constant-wattage heaters.
The authors chose to use 110 volt plastic-sheathed, self-regulating
electric heaters with outputs from 10 to 66 watts per meter (3 to
20 W/ft). The ability to safely overlap such heaters and their ability
to be cut to any length were important attributes. Ground fault interrupters
were used on all circuits.
Icing Problems at Fort Drum
Many new standing seam metal roofs at Fort Drum, near
Watertown, NY, suffered from severe icing and leakage problems
(Figure 1). The authors determined the primary cause to be excessive
attic heat3 and developed natural and mechanical attic ventilation
improvements that solved most of these problems.
Several new buildings contained significant heat-producing
mechanical equipment in their attics. The authors were concerned
that these roofs would be difficult to keep cool by improving attic
ventilation only and that they might require electric heaters in their
valleys. Many valleys were also difficult to drain, due to a parapet
wall ending at their lower ends. Figure 2 shows an icing at a typical
valley-parapet intersection (shown in Figure 3) that constricts the flow
of snow, ice, and meltwater. Many roof leaks occur here (even in the
summer) since it is a difficult place to waterproof. The authors
worked with Public Works personnel at Fort Drum to develop and
test ways of heating these constricted valleys to provide a meltwater
flow path through the icings there.
Figure 2. Large ice dams and icicles form where the gahle parapet
ends at the bottom of valleys.
Figure 3. System with single heater loop in valley. Inset shows
heater runs on the fascia and drip edge at this location.
Figure 4. System with multiple heater runs in the valley, behind
the parapet and on several standing seams. Inset shows heater runs
at its fascia and drip edge.
Electric Heaters Installed for the Winter of 1991-’92
The authors chose six similar buildings with 27° (6:12) roof slopes and the same solar aspect to test the electric heater systems.
The gable parapet at the front of these buildings constricted a valley at each end (Figure 2). An electric heater was
installed in the left valley on each building and the adjacent unheated right valley was used as a control. The structural standing
seam metal roof on these buildings had flat-topped standing seams. The 20-mm- (0.8-in.-) wide, 51-mm- (2-in.-) high
seams were spaced 0.5 m (20 in.) apart. Power consumption and air and roof surface temperatures were recorded using dataloggers.
Periodic photos were obtained by the authors and Public Works personnel.
Six heating systems were installed by a contractor from Dec. 30, 1991 to Jan. 4, 1992. They had various power outputs,
layouts and attachment methods as summarized in Table d (Note: power outputs are defined in Note 1 on Table 1). The authors
14 • Interface January 1999
Table t. Electric heaters installed during winter 4991-92.
Building # 10110 10120 10130 10210 10220 10230
Heater located above or below metal roofing Above Below in
Valley
Above on
Fascia
Above Above Above Above
Power Output (see Note 1) Medium High Medium Medium Medium Low Medium
Heater Layout (see Note 2):
Number of heater loops in valley
Number of heater runs behind parapet
Number of heater loops up and over seams
2
2
13
Note
3
012
1
0
0
100
122
122
Heater length, m.
(Heater length, ft.)
46.9
(154.0)
34.6
(113.7)
13.5
(44.3)
12.9
(42.3)
12.8
(42.1)
22.9
(75.0)
22.4
(73.4)
Avg. heater wattage (if measured) from 3/3-4/8/92 907 1649 273 263 316 468
Average watts per meter
(Average watts per foot)
19.3
(5.9)
47.4
(14.5)
20.2
(6.2)
20.4
(6.2)
13.8
(4.2)
20.9
(6.4)
Plastic mounts adhered with epoxy
(Number failed – see Note 4)
44
(17)
36
(25)
10
(4)
30
(30)
18
(16)
60
(52)
Angle clips adhered with silicone (Number failed –
see Note 4)
3
(1)
24 42
(1)
Heater adhered with silicone only 10
Stainless steel loop clamp mechanically attached
(Number failed – see Note 4)
87 1 2 2 5 5
(1)
Notes
1. Manufacturer’s power output ratings for self-regulating electrical heaters were:
High: 65.6 W/m (20 W/ft) on an insulated metal pipe at 10 degrees C (50 degrees F)
Medium: 32.8 W/m (10 W/ft) in ice at O’C (32’F) or 16.4 W/m (5 W/ft) in air at O’C (32’F)
Low; 9.8 W/m (3 W/ft) on an insulated metal pipe at 10’C (50‘F).
2. All heater layouts also had a single run of heater either under or on the drip edge at the base of the fascia.
3. There were four runs of heater under the metal roofing in this valley (two runs in the metal decking flutes on the parapet side of the valley and two
runs [i.e., one loop] covered with insulation under the metal decking on the eaves side of the valley).
4. The number of attachment failures is given in parentheses below the total number of attachments (e.g., “(17)” means that 17 plastic mounts
failed). If there is nothing in parenthesis, nothing failed.
chose to demonstrate a range of electric heating systems from
little heat to what was expected would be too much heat (this
was the amount the industry was recommending at the time).
Figure 3 shows a system with only a single loop of heater in the
valley, two heater runs on the fascia, and a heated drip edge.
Figure 4 shows a system with multiple heater runs in the valley,
on the standing seams approaching the valley, behind the
parapet, on the standing seams at the eaves, on the fascia and
on the drip edge. Another high-powered system is shown in
Figure 5 where most of the heater was installed below the
metal roofing. Two runs of high output heater were placed in
the flutes of the metal decking supporting that valley (left side
of Figure 5). On the other side of that valley, a loop of highoutput
heater was run down and back up under the insulation
shown strapped to the bottom of the metal decking. These
heaters ran about 7.6 meters (25 ft) up the valley. The area
behind the parapet, and the fascia and eaves were heated with
medium-output heater adhesively attached to the outer surface
of the metal roofing. All six systems had a run of heater along
the drip edge similar to the one shown in Figure 6 and vertical
runs of heater on the fascia with drip loops provided at their
lower end.
Figure 7 shows the four attachment methods used to secure
the electric heaters to the metal roof and fascia. Small, commercially-
available 25-mm- (1 in.-) square black nylon mounts
adhered with epoxy were used to reduce the visual impact of
the heaters at all fascias (Figures 6 and 7a). Heaters were
attached to these mounts with black nylon cable ties. Black
nylon cable ties are UV resistant, whereas white cable ties are
not. Larger perforated stainless steel angle clips were adhered
with a neutral-curing silicone adhesive (Figure 7h) that pro-
Figure 5. System with high output heater installed below the metal roof in
a valley.
Figure 6. Typical attachment of nylon mounts to fascia with epoxy.
Angle clips on the roof itself are attached with neutral-curing silicone.
Note horizontal heater all along drip edge.
January 1999 Interface • 15
duces methyl alcohol as a by-product
of curing rather than acetic
acid, which is corrosive. Even
though our metal roofs had a polyvinylidene
fluoride (“Kynar”) coating,
there are cut edges and
scratches that would rust when
exposed to acid-curing silicones.
Neutral-curing silicones are used
extensively by the electronics
industry, but the silicones used by
the construction industry are of the
acid-curing variety. Neutral-curing
silicones are much more expensive
than acid-curing silicones. Silicone
adhesives are flexible, which is an
advantage since the metal panels
flex with diurnal and seasonal temperature
changes and roof traffic.
During application, this neutralcuring
silicone flowed slowly and
evenly when pressed between the
clip or mount and the metal roof
and had sufficient uncured stiffness
Figure 7. Heater attachments: (a) epoxy adhered plastic mount, (b) angle clip adhered with neutral-curing
silicone, (cj beater adhered with silicone only and (d) mechanically attached stainless steel loop clamp high
on the standing seam.
Figure 8. Heaters provide melt paths through snow and ice for
meltwater to drain off the roof. Some ice was removed to expose
these paths for this photo.
to hold the fastener in place until it cured. Silicones like the “hardware
store” acid-curing variety flow out too fast and leave air bubbles
or gaps. Metal roof surfaces were cleaned with isopropyl alcohol and
allowed to dry before adhesive attachments were made. Tooling was
not done for any adhesively-applied fastener.
The angle clips were made from perforated 0.95-mm thick (20
gauge) stainless steel with 6 mm (1/4-in.) diameter holes on 10-mm
(3/8-in.) staggered centers. The surface that was adhered to the metal
roof was about 50 by 100 mm (2 by 4 in.). The heating cable was
held in place by two cable ties through the upstanding perforated leg
of each angle clip (.Figure 7b). The simplest adhesive method used to
fasten the heater was to place it in puddles of the special silicone
(Figure 7c). The authors didn’t have high hopes for this method but
felt it should be tested. The mechanical fasteners consisted of commercially-
available stainless steel loop clamps with extruded rubber
cushions. These loop clamps were attached high on the standing
seams with stainless steel bolts (Figure 7d). The holes
drilled through the seams for these bolts were sealed
with silicone. On the fascia and under the eaves, the
loop clamps were fastened with stainless steel selfdrilling
screws.
Thermostatic control was provided for all systems
so their heaters energized when the outside air temperature
was below 4.4°C (40°F). The authors chose
this setting to ensure that the system was on when
icing conditions were occurring. A setting of 0°C
(32°F) was not used since the controllers were not
very accurate and they were not located where the
problematic icings would occur. The controllers were
located under the eaves on the north side of each
building. They were checked after installation to
ensure proper operation
Figure 9. (a) Large icicle created by a high-powered valley heater and (b) three days
later, its remnant hanging from the displaced (but still operating) heater.
16 * Interface January 1999
Table 2. Electric beaters installed during winter of 1992-93.
Building Number 10110 10120 10130 10210 10220 10230 10150 (See Notel)
Valley (NE, NW, SE, SW) SW SW SW SW SW SW SW NW NE SE
Heater located above or below metal
roofing
Below.
ocfts
Note 2
Below.
OvAJ
Note 2
Above Above.
S@6
Note 3
Above Inbox
below
gutter
Above.
See
Note 3
Above.
See
Note 3
Above On
Drip
Edge
Below.
See
Note 4
Power output (See Note 5) Medium Medium Medium Medium Low High Medium Medium Medium High Medium
Heater Layout (See Note 6):
Number of heater runs in valley
Number of heater runs behind parapet.
Number of heater runs on fascia.
217
219
208
2
0
20
22
2
See
Note
7
226
22
12
222
See
Note
8
1
0
10
Heater length, m.
(Heather length, ft.)
16.6
(54.5)
16.5
(54.0)
13.0
(42.8)
19.5
(64.0)
11.3
(37.0)
2.4
(8.0)
11.9
(39.0)
14.7
(48.2)
10.0
(32.8)
3.0
(9.7)
8.0
262
Average heater wattage from Nov. 21,
1992 to April 26,1993
270 296 308 386 287 291 295 411 148
Average watts per meter
(Average watts per foot)
162
(4.9)
18.0
(5.5)
23.6
(7.2)
19.8
(6.0)
20.9
(6-4)
24.5
(7.5)
20.1
(6.1)
31.8
0-7)
18.5
(5.7)
Percent of time that heaters were on
from 11/21/92 to 4/26/93
82 86 87 74 86 87 93 93 93
Angle clips adhered with neutralcuring
silicone (See Note 9)
18
white
20
white
3
gray
Plastic mounts adhered with gray
neutral-curing silicone
21
Stainless steel loop clamp
mechanically attached
5 5 1 3 2 1
Dome dips adhered with gray neutralcuring
silicone (Number failed – See
Note 10)
17 21
(5 ties)
16
(2 ties)
Cable ties through drip edge (Number
failed – See Note 10)
5 13
(2)
Butterfly clips mechanically fastened 17 6 9 15
Channel clips adhered with gray
neutral-curing silicone
12
Tunnel clips adhered with gray
neutral-curing silicone
9
Cable ties through water diverters 5 9 2 3
Notes:
1. Dining Facility with severe icing problems. All other buildings are Headquarters Buildings with icing problems concentrated at their constricted valleys.
2. Valley heater runs were placed below the metal roofing in the downslope oriented flutes of the valley metal decking. The plywood sheathing behind the fascia
metal was routed out, the heater laid in these channels and carefully stapled in place. Upper loops from the heater fascia runs were held tight to the sloped metal
roofing near the end of the parapet by aluminum tape and strapping to the metal decking.
3. Heaters on the fascias of these buildings were looped over butterfly clips mechanically attached to the metal fascia and then covered with a false fascia,
either closed at the top (Buildings 10150 NW and 10210) or open at the top like a chimney (Building 10230).
4. The single run of valley heater was placed below the metal roofing. The plywood behind the fascia metal was rotten and had to be replaced. The heater runs
were looped over butterfly clips mechanically attached to the new piece of plywood installed at the fascia.
5. Manufacturers’ power output ratings for self-regulating electric heaters are as in Table 1 ..Note 1.
6. All heater layouts had a single run of heater under the drip edge at the base of the fascia except for the gutter layout on Building 10220. Water diverters were
used to keep meltwater flowing over heated areas only.
7. A gutter was installed near the top of the fascia and a high power heater was placed within a box under the gutter to keep it warm.
8. There was only room for two runs of heater on the fascia between the first standing seam and the parapet. Meltwater coming down this valley had a very narrow
drainage path. A single run of high power heater was placed under the drip edge at this valley.
9. The angle clips on Buildings 10130 and 10220 were adhered during the winter of 1991-92 with a white-colored neutral-curing silicone. The angle clips in the
northeast valley on Building 10150 were adhered with a gray-colored high-strength neutral-curing silicone.
10. The number of attachment failures is given in parenthesis below the number of attachments (five ties means that five cable ties broke). If there is nothing in
parenthesis, nothing failed.
Findings After the First Winter
All six electric heater systems provided melt paths
through the ice dams in their valleys and prevented ponding
from occurring there (Figure s). In most cases, this greatly
reduced the size of the icings and the risk of roof leaks. Roof
leaks were reported under control valleys that winter but not
under the heated valleys.
The weak link on all six electric heater systems was that
not enough heat had been provided at their fascias and drip
edges. Our systems did not prevent ice from forming on
either side of heaters placed on the fascia. Ice accumulated
there resulting in large icicles and icings hanging from the
fascia and drip edge (Figure 9a). When those icicles broke free,
they pulled the heater off the fascia and drip edge. Some icicles
hung from the heaters as they melted free (Figure 9b). This
damaged the plastic sheathing on those heaters as they were
pulled through the well-secured mechanical fasteners.
January 1999 Interface • 17
Figure to. Heater attachments adhered with high-strength, neutral-curing silicone are: (a) dome,
(b) channel, and (c) tunnel clips. The commercially-available butterfly clip (d) was mechanically
attached with rivets or screws.
The weakest attachment method was the nylon mounts
adhered with epoxy. By the end of the winter, 73 percent of
them had failed (Table 1) and heaters were hanging down
from all six test valleys. Some of the epoxy failed adhesively
at the nylon mount, but most failed at the coated metal roof.
The mechanically-attached loop clamps worked quite well
and can be used wherever holes can be accepted. One mechanical
loop clamp failed when a large icicle with a fascia
heater embedded in it fell off the roof, pulling that clamp out
of the weak soffit screening. The adhesively-attached perforated
angle clips also worked well. Sliding snow and ice bent
them over, but most remained in place. Two failed adhesively
when sliding snow and ice from the roofs above took them
out. A lower profile clip may have survived. None of the silicone
puddles holding a heater loop on the roof behind a
parapet failed. Their success was related to three angle clips
(one which failed due to sliding snow) on the same heater
loop that provided most of the resistance.
Electric heaters placed under the metal roofing of one valley
(Figure 5) kept a wide, clear melt path down the valley.
However, the 1649 watts provided in that valley (Table 1) was
too much and it melted more snow than was necessary. That
extra meltwater refroze on cold portions of the fascia and created
a large, dangerous icicle (Figure 9a), even when no icings
were forming on the control valley. The authors concluded
that too much heat was provided in all valleys. Meltwater was
produced by the heaters even when it was too cold outside
for the warm roofs of these buildings to be producing meltwater.
The low output heater used on one roof provided enough
heat to create a melt path through the ice dam and to avoid
ponding there.
The authors found that meltwater rarely flows off the roof
along the heater. It flows along the cold edges of the melt
path and under any ice near those edges. If the meltwater was
not directed where it was intended to go, it refroze on the
fascia, which was undesirable.
Electric Heaters
Installed for the Winter
of 1992-’93
Based on the findings from the previous
winter, the authors tested alternative
methods of adhesively attaching heaters,
better methods of heating the fascia, and
ways to direct meltwater down the fascia
to a heated drip edge and then away from
the walls below. Valley heater runs were
shortened to reduce their contribution to
the meltwater produced on the roof.
Additionally, methods of placing heaters
under the metal roofing were investigated
further.
The authors installed nine heating systems
from Oct. 21 to Nov. 20, 1992. They
had various power outputs, layouts and
attachment methods as summarized in Table
2 (Note: power outputs are defined in Note
1 on Table 1). New heater systems replaced
all or portions of the six systems used in 1991-’92. New systems
were installed in three constricted valleys of a dining
facility with its fourth valley used as a control. Roof slopes on
the dining facility were 18° or 4:12. Thermostatic control for
all systems was the same as that used during the previous winter
(i.e., “off” when it was warmer than 4.4°C (40°F) outside).
Air and roof surface temperatures and power consumption
were again measured using dataloggers. Periodic photos were
taken by the authors and Public Works personnel.
Stainless steel loop clamps fastened with screws were
again used to fasten heaters to fascias and soffits. An even
higher-strength, neutral-curing silicone was used for all adhesive
attachments. Its gray color more closely matched the
color of these metal roofs. The heater on one fascia was
attached with this silicone using the same black nylon mounts
which had previously failed when adhered with epoxy. After .
four winters, none of them had failed. Figure io shows the four
new attachment methods used in 1992 to secure electric
heaters to the metal roof and fascia. Three new perforated
stainless steel clips were designed and built for attachment
with the higher-strength, neutral-curing silicone. The authors
called one the “dome” clip (Figure toa), as it has a 25-mm- (1
in.-) diameter, 6-mm- (1/4 in.-) high dome in the center of a
flat, 66 by 89-mm (2.6 by 3.5-in.) perforated plate made from
the same material as the angle clips used the previous year.
The other two clips were made from perforated 1-mm-thick
(20-gauge) stainless steel with 5-mm- (3/16 in.-) diameter
holes on 6-mm (1/4 in.) staggered centers. One clip was bent
into a channel shape with walls sticking up 16 mm (5/8 in.)
on both sides of the channel where the heater was placed
(Figure lob). The other clip was bent into a 5-mm- (3/16 in.-)
high, 13-mm- (1/2 in.-) wide tunnel that just fit over the electric
heater (Figure 10c). The bottom of both clips was about 76
mm (3 in.) square. The surface adhered to the metal roof on
both clips was somewhat less, as silicone was not placed
18 • Interface January 1999
under the heater.
During installation of the tunnel clips, adhesive was applied to them,
they were placed over the heater, and the assembly temporally held in
place with tape until the adhesive cured. All other adhesively-applied
clips and mounts could be placed on the metal roof and the adhesive
allowed to cure before the heater was attached to them with one or two
black nylon cable ties. The last attachment method shown in Figure tod,
the butterfly clip, is a commercially-available soft steel clip used to secure
heaters to asphalt shingled roofs. The authors used it to loop heaters up
and down across the face of fascias. The butterfly clips were attached
with screws or rivets, depending on the fascia material.
Heater loops installed under the metal roofing were sometimes taped
in place with aluminum foil tape. The authors used a variety of methods
to secure heaters as the situation demanded (e.g., duct tape, tucking the
heater behind parapet flashing, and cable ties to secure heater loops to
each other).
To keep meltwater from reaching cold portions of the metal roof (fascias
in particular), water diverters of aluminum angles were made. Drip
edge extensions were made from metal roofing to “kick” water further
away from the building. Cable ties were used to secure heaters to water
diverters on the sloped metal roofs and to drip edges or drip edge extensions
at the base of fascias.
Two valley heaters were reattached to some of the remaining angle
clips that had been adhered with white silicone the previous winter. Other
valley heaters were adhesively secured with channel, dome or tunnel clips
using the high-strength gray silicone after the roof surface was cleaned as
mentioned before. Three valley heaters were placed below the metal roofing,
either in the downslope-oriented flutes of the metal decking directly
below or between the metal roofing and another layer of metal valley
flashing placed over the cross-slope-oriented metal decking on the dining
facility. It was quite easy to feed the heater down the flutes of the metal
decking, but very hard to place it between the metal surfaces in the valley
of the dining facility.
For aesthetic and thermal efficiency reasons, some heaters were placed
behind the metal fascia. On two buildings, plywood sheathing behind the
metal fascia was routed out and the heater carefully stapled in these channels
(Figure it). Upper loops from the heater’s fascia runs were held tightly
to the sloped metal roofing. The end of the heater ran horizontally at the
bottom of the fascia to warm the drip edge. When the metal roofing was
replaced, these two buildings had all their heaters located below the metal
roofing. This was difficult to do but it was tried for the aesthetic, mainteFigure
11. Heater laid in channels routed in the plywood
sheathing behind the fascia metal.
Figure 12. Heater looped over butterfly clips mechanically
attached to fascia.
Figure 13. False closed-top fascia installed over heater
shown in Figure 12. Note heated vertical baffles (water
diverters) at each end.
nance and thermal efficiency benefits gained.
Heater runs on the fascias of three buildings were looped over butterfly
clips mechanically attached to the metal fascia (Figure 12) and then covered
with a false fascia, either closed at the top as shown in Figure 13
(Buildings 10150 NW and 10210) or open at the top like a chimney (Building 10230). Installation of heaters and false fascias
was much easier than placing heaters behind existing fascias. False fascias also allow for easier access if repairs are necessary.
Heated water diverters were used on all roofs to direct meltwater flow over the heated fascia and drip edge. A diverter is
shown at each end of the false fascia in Figure 13. Diverters were able to prevent icings just beyond heated portions of fascias.
A small gutter (open at one end) was installed near the top of the fascia on one building, and a high-power heater was
placed within a box under the gutter to keep it warm. This assembly was relatively easy to construct and install. It redirected
meltwater away from the cold fascia but looked out of place on this building.
Findings After the Second Winter (1992-’93)
All nine electric heater systems provided meltwater paths at the lower ends of their valleys. However, on the dining facility
with its very hot attic, meltwater froze all along the unheated eaves, creating large ice dams and icicles (similar to those in
Figure 1) that encroached upon the heated meltwater paths down the valleys. Meltwater that left the roof at the heated valleys
dripped onto the encroaching icicles, causing them to grow much larger. This resulted in a massive icing that descended from
January 1999 Interface • 19
the eaves to the ground at the southeast valley of the
dining facility even though the heated path at that valley
remained open essentially all the time. The dining
facilities needed heaters all along their eaves, not just
in their valleys, or they needed much improved attic
ventilation.
There were no adhesive failures of any clip or
mount during the second winter. The only failures
were several broken cable ties, mostly on dome clips
on the dining facility which experienced severe icing.
Electric heaters installed under the metal roof
worked well, as did all false fascia systems. False fascias
that are closed at the top worked better than the open
“chimney” type and were also more robust. Figure 44
shows a typical comparison of heated and unheated
(control) valleys on a test building. The eaves below
the unheated valley are encased in a massive icing. The
eaves below the heated valley are clear of ice. The icefree
fascia was the heated false fascia with a closed top,
shown in Figure 13. The gutter design also worked fine
but did not fit the aesthetic look required for these buildings.
The exposed fascia heater looked unattractive {Figure
15), but it also performed well. The ability of all of the
heater systems to prevent icicles suffered when snow and ice
overhung the heaters as shown in Figure 15. The overhangs
were created by creep of snow and ice extending beyond
the fascia 0.3m (a foot) or more. Meltwater tended to flow
within and on the underside of these overhangs instead of
over the heated path down the fascia. This bypassed the
heating system and created dangerously large icings. These
observations convinced us that snow guards are needed to
hold snow in place to protect the heaters.
Further Findings
Attic ventilation improvements recommended by
CRREL were completed on the dining facility (Building
10150) during the summer of 1993. The following winter,
the three electric heater systems on that roof were able to
cope with the greatly reduced rate of meltwater production
from the much cooler roof. Large icicles and ice dams did not
form all along the eaves as in the past. This clearly illustrates
how effectively a “cold” ventilated roof can reduce icings and
ice dams, at times obviating the need for electrical heaters.
The three valley heaters on this roof have been left on to provide
comparisons with unheated valleys of nearby dining
facilities now having improved attic ventilation. Those studies
suggest that electric heaters are no longer needed in any of
these valleys.
Snow guards were added to several electric heater systems
over the next two winters3’5’6 All nine heating systems and
their snow guards were maintained and studied every year
through the winter of 1995-’96 (i.e., three more winters). All
externally-attached heaters at Fort Drum required some repair
after each winter. Sliding snow and ice was the main problem.
Snow guards were effective in reducing damage to heaters.
However, maintenance and contractor personnel also caused
damage when fixing roof leaks or climbing up on the roof
over the heaters. Heaters installed under the metal roofing
Figure 44. Comparison of heated and unheated valleys at Building 10210 on Feb.
22, 1993: (a) Heated valley and heated false fascia clear of ice. (h) Adjacent
unheated valley and fascia encased in ice.
Figure 15. Icings forming on a creeping, overhanging mass of snow and ice,
bypass the heated fascia on this building. Note exposed heaters at near end of
fascia.
required no repairs.
The dome clip attachment method continued to suffer
from broken cable ties which had to be replaced often. The
angle, channel, and tunnel clips provided better mechanical
support and resisted downslope movement of the heater, even
when a cable tie broke. These perforated clips let the silicone
adhesive squeeze through their perforations as shown in
Figures 10a, 10b and 10c. This allowed the adhesive to cure better
and provided some mechanical connection between the
adhesive and clip.
The leaky valley-parapet intersections on the test buildings
all required repairs to stop leaks. They were patched
with roofing cement, special coatings, and rubber (EPDM)
membranes. The heaters were inadvertently embedded in
roofing cement, which is not acceptable (the authors pulled
them out). If a heater was in the way of maintenance work, it
was removed and replaced after the leak was fixed. White
cable ties and ordinary “hardware store” acid-curing silicone
were used to reattach the heaters. None of these replacements
lasted more than two winters. The leaky valley-parapet inter-