Skip to main content Skip to footer

Interface of Construction Documents and Submittals for Roofing

May 11, 2020

30 • IIBEC InterfaceCEMay 2020
Figure 1 – Case Study 1 – Proper fastening.
Project submittals are a key piece
of the construction process that
sometimes are minimized in
importance, rubber stamped, or
not reviewed by staff with adequate
knowledge of the material(
s) and its application by both design
and construction consultants. Submittals
contain the information provided by the
contractor to the design professional for
approval of equipment, materials, and
installation details before they are utilized
at the project site. Submittals can be given
in varying formats, such as shop drawings,
product data, and material samples.
The agreement documents contain provisions
for the information the contractor
is required to submit to the design professional
for review or to correct misunderstandings.
The most commonly used
documents by design professionals for
detailing submittal requirements are
the American Institute of Architects’
(AIA’s) A201, “General Conditions
of the Contract for Construction,”
and the Engineers Joint Contract
Document Committee’s (EJCDC’s)
C-700, “Standard General Conditions
of the Contract” for designbid-
build projects.
For design-build projects,
the document used is AIA’s A141,
“Standard Form of Agreement Between
Owner and Design-Builder.”
Paragraph 6.17.C.1 of EJCDC C-700
requires that shop drawings include
information such as “quantities, dimensions,
specified performance and design
criteria, and similar data.” Section 3.12.1 of
AIA’s A201 defines shop drawings as “drawings,
diagrams, schedules, and other data
specially prepared for the work.”
These documents include a broad
“catch-all” provision allowing the design
professional to request any other additional
information necessary to adequately verify
that the equipment or material included in
a submittal meets the intent of the contract.
The EJCDC C-700 document says,
“Engineer’s review and approval will not
extend to means, methods, techniques,
sequences, or procedures of construction”
(except where a particular means, method,
technique, sequence, or procedure of construction
is specifically and expressly called
for by the contract documents) “or to safety
precautions or programs incident thereto.
…The review and approval of a separate
item as such will not indicate approval of
the assembly in which the item functions.”
The AIA A141 design-build document
notes for submittals that “the Design-
Builder represents to the owner that it has
(1) reviewed and approved them, (2) determined
and verified materials, field measurements,
and field construction criteria
related thereto or will do so and (3) checked
and coordinated the information contained
within such Submittals with the requirements
of the Work and of the Design-Build
Documents.”
It is not unusual during the submittal
phase that an inadequate amount of
information is provided to the design professional
for review. Another issue that can
occur during the submittal phase is that
the submittal review process is done by staff
that are not familiar with the intricacies of
the project requirements. This can lead to
inadequate or missing information to show
that the project requirements are being met.
The third-party consultant can either be
under contract with the design-build general
contractor or with the building owner. In the
case of the design-build general contractor,
the intent is to provide independent review
of the roof construction operations to verify
the roof membrane manufacturer’s requirements—
as well as applicable building code
requirements—are met. The building owner
can also hire a third-party consultant to
review the construction process to supplement
the design professional’s duties for construction
phase services and provide another
set of knowledgeable eyes on the project.
The following two case studies describe
where a project consultant was engaged
as a third-party consultant for submittal
review and construction observation for the
building enclosure elements. They illustrate
the importance of critical review of submittals
for proper conformance of the design
intent by the design professional.
CASE STUDY #1
A design-build contractor employed the
project consultant to review submittals and
perform periodic observation of the roof
assembly installation being performed by a
local subcontractor. The building itself was
an office/storage area with approximately
18,422 m2 (198,400 sq. ft.) of roof area.
The roof assembly consisted of structurally
sloped metal deck, a layer of 50-mm-
(2-in.-) thick polyisocyanurate (iso), and
a second layer of 48-mm- (1.9-in.-) thick
iso. See Figure 1 for insulation installation.
A 1-mm- (45-mil-) thick thermoplastic
polyolefin (TPO) membrane
was installed using the heat induction
method.
The heat induction process
used metal plates coated with a
TPO resin with fasteners penetrating
the insulation. Fasteners were
placed in a pattern to provide the
required wind uplift resistance for
the assembly. The fastener pattern
was designed so that no more than 914
mm (36 in.) was between any two fasteners.
The overlying TPO membrane sheet
was then welded to each of those plates.
A special induction heater, placed
over each attachment plate in turn, heated
the plate for five seconds. A weighted magnet
was placed above the plate for approximately
20 seconds, and the membrane
and plate became welded together. The
seams of the membrane sheets were then
heat-welded together as is done with a TPO
membrane. See Figure 2.
The submittal provided to the thirdparty
consultant included a comprehensive
list of technical information sheets of all the
materials to be utilized for the project from
the roof membrane and insulation manufacturer
(a single entity). The submittal
was noted by the designer of record (DOR)
as “reviewed for design intent only,” and
the following was stamped on the submittal:
“Reviewed for general compliance. Not
reviewed for performance or compliance
with any codes/energy standards/testing
standards.” Even though the statement
Ma y 2 0 2 0 I I B E C I n t e r f a ce • 3 1
It is not
unusual during
the submittal phase
that an inadequate
amount of information
is provided to the
design professional
for review.
notes “not reviewed for compliance with any codes,” the DOR’s professional duty is that the documents must comply with applicable building and energy codes.
The third-party consultant also analyzed the roof membrane/insulation manufacturer’s system installation information. This information neither appeared to have been requested by the DOR from the roofing contractor, nor provided to the DOR in the submittal process. The third-party consultant’s review of the membrane/
insulation manufacturer’s system installation information indicated the fastener density for the 1.2- x 2.4-m (4- x 8-ft.) specified board insulation should be six fasteners in the field of the roof, 10 in the perimeter, and 16 for corner areas. Neither the plan set nor submittal documents contained any information about the board insulation fastening density or requirements for wind uplift performance. These criteria are noted in the building code to be included in the design documents.
A pre-construction meeting was not scheduled or conducted for the project. The third-party consultant was notified that the roofing operation had started, and the consultant arrived on site to discover the roofing contractor was only installing six fasteners for the 1.2- x 2.4-m (4- x 8-ft.) insulation boards in the corner and perimeter areas. A call from the third-party consultant to the roofing contractor’s project superintendent relayed that this fastener density was not per the manufacturer’s specifications. The contractor proceeded to contact the local manufacturer’s representative to independently verify the fastener density for the project and then began installing the fasteners as recommended.
CASE STUDY #2
This project involved a third-party consultant review of a five-story residential living/retail space facility. Services included review of design documents and submittals, performance of periodic observation of the roof assembly installation, a penetration firestop inspection, water testing of select aluminum storefront sections, and air and water testing of selected vinyl windows.
During review of the design documents, the third-party consultant noted the following specification:
Mechanically fastened insulation: Install each layer of insulation and secure to deck using mechanical fasteners specifically designed and sized for fastening specified board-type roof insulation to deck type.
1. Fasten insulation according to requirements in Factory Mutual Global’s (FMG’s) “Approval Guide” for the specified windstorm resistance classification. [No specific windstorm resistance classification per FMG was noted in the design documents.] 2. Fasten insulation to resist uplift pressure at corners, perimeter, and field of roof.
The third-party consultant noted in the review letter, “The project is not insured by FMG; recommend change to conform to the current International Building Code (IBC) and American Society of Civil Engineers (ASCE) 07, Minimum Design Loads and Associated Criteria for Buildings and Other Structures, requirements for wind classification.”
The consultant added, “Revise fastening of insulation to meet current IBC and ASCE guidelines for attachment, especially since
32 • IIBEC InterfaceCE May 2020
Figure 2 – Case Study 1 – Heat induction welding.
roof height is over 18 m (60 ft.). Recommend provide fastening pattern for insulation fastening based on wind uplift calculations for roof at field, perimeter, and corners.” (See Figures 3 and 4.)
During construction, the third-party consultant reviewed submittals for the roof assembly. The building code for the project was the 2012 IBC. The building occupancy classification group was noted as R-2 (III-A) for the area covered by the roof assembly per the code summary on the plans.
The submittal for the roof assembly was provided to the third-party consultant four days before construction was scheduled to start. It was also given to the local roofing subcontractor and reviewed by the general contractor and DOR. Dated June 13, 2018, the DOR’s feedback said, “Reviewed exceptions noted” and “refer to comments throughout.” Actual roof installation started July 3, 2018. The third-party consultant’s post-review response included:
Roofing X-section shows new ethylene propylene diene monomer (EPDM) directly over oriented strand board (OSB) deck. Revise to include new 13-mm- (½-in.-)
thick insulation board to meet UL [Underwriters Laboratories] Class B rating per building code per “third-party consultant” e-mail dated 7-3-18. [It] should provide fastener spacing/layout for insulation board to decking also for IBC/ASCE wind uplift requirements. Tapered insulation information for parking garages do [sic] not provide any information for insulation adhesive bead spacing to be used for field, perimeter, and corner areas.
May 2020 IIBEC InterfaceCE • 33
Figure 3 – Case Study 2 – No insulation over OSB decking.
Figure 4 – Case Study 2 – No insulation.
A similar comment was not on the submittal from the DOR. The detail in the submittal showed the installation of a single-
ply EPDM membrane directly over OSB decking. The roof decking is over an attic space with batt insulation in the cavity to provide the code-required thermal resistance value.
The third-party consultant tried to contact the general contractor’s project superintendent by phone and left a voice message that the roof assembly needed to meet UL’s fire rating classification (Class B) per the building code. The consultant also traveled to the site the same day to inform him of the situation. The project superintendent noted the roofing subcontractor had already started installation work but indicated he would get confirmation from the DOR on the third-party consultant’s assessment and on what needed to be done to meet a UL rating. Later that day, the DOR agreed with the third-party consultant’s assessment.
The manufacturer’s list of approved insulation for an adhered 1.5-mm (60-mil) EPDM for a Class B roof assembly rating, according to the American National Standards Institute’s ANSI/UL 790, Standard for Standard Test Methods for Fire Tests of Roof Coverings, has these three listings:
• Minimum 48-mm (1.9-in.) layer of the EPDM manufacturer’s iso high-density composite,
• Minimum 35-mm (1.4-in.) layer of any UL-classified EPDM manufacturer’s iso insulation, and
• Minimum 25-mm (1-in.) layer of EPDM manufacturer’s iso combustible deck insulation.
The number of listings meeting the UL Class A rating includes 15 systems. The installation system agreed upon was 6.4-mm- (1/4-in.-) thick gypsum-based insulation over OSB. This system is listed in the membrane manufacturer’s UL Class A listing for combustible decks. The insulation board was to be attached with 16 fasteners per 1.2- x 2.4-m (4- x 8-ft.) board. The number of fasteners also met the wind uplift requirements for the roof system and wind zone area.
CONCLUSION
These two case studies showcase the importance of timely and thorough submittal review. Lack of proper review can lead to installations not meeting the design intent and, possibly, building code requirements. Submittals are a key part of the construction process and need to be addressed accordingly.
Darrell L. Smith is a project engineer in the Facilities Division of Terracon Consultants, Inc. and is based in Des Moines, IA. Smith has more than 30 years of experience in the building enclosure consulting industry. He specializes in project design, peer review of construction documents, building enclosure testing, quality assurance, and forensic investigations. Smith can be reached at darrell.smith@terracon.com.
Darrell L. Smith
34 • IIBEC InterfaceCE May 2020This brand-new edition is available only in digital format.Visit iibec.org/hub to purchase and download your copy.IIBEC Manual of Practice – 3rd EditionOrder your copy today!Price:Member: $349 Nonmember: $429