Skip to main content Skip to footer

Keeping Great Performances “Under Cover” at the Kennedy Center

September 1, 1998

Keeping Great Performances “Under Cover” at the Kennedy Center

Required: Hie Best Materials and a Well-Orchestrated Effort to Apply Them
By Swen E. Swenson III, CSI
AS THE JOHN F. KENNEDY CENTER FOR THE
Performing Arts in Washington, D.C. was celebrating its
25th anniversary, work was beginning to replace the
entire roof of the nation’s most visible showcase for music,
theater and dance. It was a project that would require sensi¬
tivity to the very special nature of this facility as well as close
coordination among several organizations.
Those organizations included the architectural firm, the
general contractor, the roofing contractor, the manufacturer
of the roofing system, the U.S. Army Corps of Engineers, and
the Kennedy Center management itself. All agreed on one
thing: They did not want to repeat the process again anytime
in the near future.
The right roofing system
So the starting point was to select the appropriate roofing
system. After an exhaustive analysis of six possible roofing
technologies, the Chicago-based architectural firm of Wiss,
Janney, Elstner Associates, Inc. (WJE) selected coal tar builtup
roofing (BUR). They specified a four-ply coal tar built up
roofing system over insulation with a top flood coat of coal
tar and aggregate surfacing. Larry Meyers, the architectural
firm’s consultant on this project put it succinctly: “I wanted
to be able to retire without having to worry about this roof
again.”
For a level or low-sloped roof, coal tar has two important
characteristics that make it inherently superior to other commonly-
used materials. First, coal tar’s tight molecular structure
gives it naturally superior resistance to water, air and water
vapor penetration. And secondly, a coal tar roof is “self-heal¬
ing” due to a property known as “cold flow.” That simply
means that hairline cracks that may develop due to changes in
temperature will periodically fill in as the temperature rises
and the coal tar reaches its “cold flow” point. This process will
occur over the life of the roof.
The built-up aspect of the roofing system specified by WJE
called for four plies of organic felt saturated with coal tar.
“We wanted a four-ply built-up system,” Meyers explained,
“for the redundancy, and thus additional layers of confi¬
dence— if you will— that it would give us.”
The roofing contractor, Prospect Waterproofing Company,
a Sterling, Va. -based firm specializing in built-up roofing
installations, chose a system from Koppers Industries
(Pittsburgh, PA).
The biggest initial challenge: being invisible.
The biggest challenge, from a project management perspec¬
tive, was presented by the nature of the Kennedy Center
itself. Not only does the Kennedy Center host worldrenowned
performers and performances, but it also boasts an
audience that on any given day might include dignitaries and
heads of state from the U.S. and around the world.
The Kennedy Center is also the nation’s busiest center for
the arts, presenting more than 2,800 performances each year
for audiences approaching 2 million people. Activity at the
facility, from major performances to classes, is virtually con¬
stant. The Kennedy Center houses six theaters and several
major public spaces ranging from the Hall of Nations to
rooftop restaurants, to a 24,720 square foot Grand Foyer with
a 63-foot high ceiling. This architectural gem is also situated
Day or ni^ht, the Kennedy Center is the nation’s busiest center for the arts.
16 • Interface September 1998
next door to one of the world’s most exclusive urban apart¬
ment complexes, the Watergate.
Thus, two things were understood by everyone involved in
the project: The work must be invisible to patrons and neigh¬
bors, and it must not interfere with any of the Kennedy
Center’s performances or other activities.
“A pretty good lesson in cooperation”
Roofing is not necessarily clean, quiet or odorless work. So
the first challenge, identified by the Kennedy Center’s Vice
President of Facilities, Clifton Jeter, was to set up a system of
communications and procedures between Prospect and the
Kennedy Center’s staff to schedule work to avoid interfering
with the almost continuous flow of performances and activi¬
ties.
Phase One began in June of 1996 with the removal of the
old roof right down to the concrete deck. But because the
existing roof already had numerous active leaks, this had to
be done in manageable sections and would require the imme¬
diate application of a temporary, watertight covering.
Prospect and WJE jointly decided on the application of twoply
vapor retarder directly onto the concrete as it was uncov¬
ered. Not only would the two-ply vapor retarder provide tem¬
porary roofing as demolition continued, but it would be left
in place as a permanent vapor barrier under succeeding layers
of insulation and the built-up coal tar roof in Phase Two.
An external elevator was installed outside the south end of
the Kennedy Center, where there were no adjacent buildings.
That elevator was used throughout the project to carry crews,
material, equipment and debris unseen by patrons or neigh¬
bors.
Initially, to avoid interference with performances, Prospect
worked only at night. But they soon realized that the frequen¬
cy of thunderstorms and rain showers was much higher at
night, increasing the risk of leakage as sections of roof were
uncovered. Work then shifted to early morning hours, usually
beginning before 7 a.m. but often needing to conclude by
early afternoon to accommodate matinee performances.
Once work shifted to daylight hours, Kennedy Center staff
and Prospect established a communications system and plan¬
ning schedule that allowed Prospect to plan manageable
breaks in the work around scheduled performances. The sys¬
tem permitted emergency communications in case of unantic¬
ipated problems. Prospect generally planned its work to con¬
clude at least several hours before any performance. They also
provided a supervisor whose job it was to remain on-site and
in communication both with Kennedy Center staff and
Prospect staff throughout the performance.
“As far as our patrons were concerned, no construction was
underway,” explained Jeter. “That’s quite an accomplishment,
when you consider the amount of work that was actually
being done directly overhead. It was a pretty good lesson in
cooperation for all of us,” he added.
Fumes—an even bigger challenge
Working unseen and unheard. Scheduling work around per¬
formances and activities. Ensuring that no work shift ended
with a totally uncovered section of roof. Planning clean-up to
make sure that no equipment or debris were visible. These
challenges were all manageable through close coordination
and good communications. However, the odor of asphalt or
coal tar fumes was another challenge entirely. It was one that
required more than good management.
“Initially,” explained Jeter, “we coordinated to ensure that
the appropriate intake vents were closed as the kettles were
moved about on the roof.” That, however, did not solve the
problem of disturbing nearby residents, particularly those liv¬
ing at the Watergate.
The solution developed by Prospect and WJE was to
acquire an FRS-6000® Fume Recovery System. This unique
piece of technology (for which Koppers is national sales
agent) is manufactured by Aercology, Inc. (Old Saybrook,
CT) and distributed by NTE, Inc. (Boardman, OH). The FRS-
6000 is a portable unit that consists of a hood, plenum and
propane-powered blowers to recover fumes from tar and
asphalt kettles and then “clean” them by pulling them through
a series of filters and media. The system not only removes
fumes and particulates (down to 0.3 microns), but it also
removes gases, vapors and, most important to the Kennedy
Center’s neighbors, odors. Its use virtually eliminated the pos¬
sibility that neighbors or passers by could detect the presence
of coal tar or asphalt fumes.
According to James Newcomer, Prospect’s project manager
on the Kennedy Center job, workers eventually had two ket¬
tles in continuous use— one for coal tar and the other for
asphalt. (The asphalt was used to attach the insulation and
flashings and during demolition as the temporary roof). They
were able to connect one FRS 6000 system to recover fumes
at both kettles and at the points where coal tar or asphalt
were placed into luggers for distribution to roofing areas.
Out of sight (and of smell) is not out of mind.
Just under the 140,000-plus square foot main roof, but hid¬
den from view from within, was a system of pans, hoses and
pumps that was catching and draining away water that would
continuously work its way through the old roof during, and
for some time after, rain storms or rapid snow melts.
All agreed that two serious problems had diminished the
performance of the old roof: its flatness and inadequate
drainage.
In addition, there are two areas of the main roof that are
unique: Directly over several small theaters that are in con¬
stant use, are floating acoustic “slabs” to protect those theaters
from airplane noise. These slabs are actually areas of concrete
roof poured directly on top of insulation. It was believed that
the slabs might already have absorbed water.
These three challenges— flatness, poor drainage and the
possibility that the acoustic slabs might have absorbed
water— would require joint creative solutions.
Flatness and poor drainage—creative solution
number one.
According to Meyers, the architects’ initial challenges were
how to design enough slope into the roof to allow proper
September 1998 Interface • 17
All phases of the job can be viewed in the photograph at the left. At the bottom (south end) is the external elevator that was used throughout the job. The
south third of roof shows bare concrete slab and a section of the installed vapor barrier. The rectangular area on the east (right) side of the middle section
contains the acoustic slabs that were left in place under the concrete in a creative solution that avoided the additional work of removing concrete deck. New
2-ply, insulation board, built-up roofing and gravel top coat were installed over the concrete, leaving the old insulation undisturbed. The tan areas on the
north end of the building show finished roof with top coat of tar and river gravel. The photograph at the right shows the completed roof. Installation took
19 months.
drainage, and then how to direct that water and control run¬
off to within D C. code limitations.
“We knew from the outset,” explained Meyers, “that a lot of
ponding had occurred over the years and that had con¬
tributed to the active leaks in the old roof.” The original roof
simply did not have enough drains. In fact, Prospect’s
Newcomer said he could actually see the algae blooms in dry
weather. “Those are created only when water stands for
extremely long periods of time.”
Putting slope into the new roof presented its own special
aesthetic and physical challenges. According to Meyers, the
old roof had a top surfacing of white marble chips, which
actually carried forward the white appearance of the Italian
marble on the building’s facade. Now the architects were call¬
ing for a river gravel top surfacing to eliminate the potential
of piercing the top ply presented by the sharpness of marble
chips. And they were faced with the need to create elevation
to facilitate drainage and accommodate base flashings.
WJE’s solution was to design a modification that increased
the height of the parapet wall around the entire perimeter of
the main roof by eight inches to maintain the design intent of
the original sight line. They specified marble to match the
blocks in the original facade. “We were able to show the
client that we could change the wall height enough to accom¬
modate necessary drainage without significantly changing the
building’s original ground-level site lines,” Meyers explained.
“And we believed that the river gravel would lighten over
time, providing visual continuity in more elevated views from
across the river or from the Watergate.”
But getting marble to match was another challenge.
According to Douglas Winger, project manager for Rockville,
MD-based Grunley Construction Company, Inc. (the general
contractor), the original marble was Carrera Ultisimo, found
only in the Carrera Mountains of Italy. After some research,
Pagliaro Brothers Stone Contractors were not only able to
locate the marble, but the original quarry from which it was
cut.
Grunley then raised the parapet walls using marble mined
from the original quarry and then reinstalled the original mar¬
ble coving atop the parapet wall.
The additional eight inches enabled the architects to design
in about 1/4-inch per foot of slope and create a more than
adequate system of 63 drains. The slope was executed via a
system of “crickets,” or peaks and valleys to catch water and
carry it to the 63 drains. Over the initial vapor retarder, and
directly beneath the four-ply built-up coal tar roof, was iso¬
cyanurate insulation with a one-inch thick overlay board. The
system of crickets and valleys was created by varying the
thickness of the isocyanurate from two inches to 12 inches.
And the additional eight inches of elevation around the exter¬
nal wall allowed for the necessary additional insulation and
base flashing.
Runoff was then controlled to within code limits through
the use of “flow preventers” at all 63 drainage points.
“Having standing water at these points for a few hours
when necessary will present no problem because of the builtup
coal tar roof,” explained Newcomer.
“As we completed sections, you could literally see them
drain like sink bowls,” Newcomer added. “And you could
watch the catch pans under the roof dry up.”
18 • Interface September 1998
Creative solution number two: the
acoustical slabs.
The floating acoustic slabs presented a differ¬
ent kind of problem. While the ponding and
leakage could be seen, the condition of these
slabs, because they were installed directly under
poured concrete, could not.
“It was the Koppers people who first
expressed concern that we may have moisture
in the acoustic slabs,” recalled Newcomer. After
discussions among Grunley, the architects and
the U.S. Army Corps of Engineers, it was
decided to undertake a “fairly major” redesign
in midstream to effectively isolate the acousti¬
cal areas— physically and drainage-wise— so
they could be replaced much more easily if
necessary in the future.
The solution involved surrounding both areas
with a low, double masonry wall (like a room
divider). Batt insulation was specified between
the double walls, and they were to be capped
by roll roofing (See Figure i). Then, as a backup,
Prospect was asked to mechanically fasten the
first layer of insulation to the slab prior to
installing additional layers of insulation and
finally the built-up roof itself.
“It was agreed by all that we couldn’t and
shouldn’t disturb the slabs,” explained Meyers.
“I could fax drawings back and forth to Koppers
technical people and get some quick resolutions
to this and several other problems and issues.”
“It was a group effort,” was Larry Meyer’s
conclusion— one that required good communi¬
cation among all entities involved in the job.
YV7TC Wiss, Janney, Elstner Associates, Inc.
W J L 29 N. Wacker Drive, Chicago, Illinois 60606-3203
MADE BY
SGN
SHEET NUMBER
SK-1
KENNEDY CENTER FOR PERFORMING ARTS
ACOUSTIC SLAB REDESIGN
CHECKED BY
LRM PROJECT NUMBER
960246
DATE
5/17/96
NEW WOOD BLOCKING SK- 11 A2.1 5
SLOPE ANNECWH OCROENCDR ETTO E COMNACSROENTREY
BATT INSULATION
STRUCTURAL SLAB
2 PLY TEMP ROOE
EXTG. ACOUSTIC SLAB
SECTION AT ACOUSTIC SLAB
SCALE (A)
sA.NsD.
EIXNISSUTLIANTGI ONF IBERGLASS
OFLNO O4D PCLOYA TR OAONFDI NGG RAVEL
CCOAUPN TERFLASHING
ITNASPUELRAETDI ONI SWOC/Y A1N”U RTAHTIEC K OVERLAY BOARDS
R9O0O FLIB.N G FELT OR ROLLED
SCALE ® 12
SCALE OF INCHES
^6 0 6
SCALE @ O’ –
SCALE OF INCHES
NOTES ON DIMENSIONS:
24
12
+ 1′ —7″ AT EISENHOWER THEATER
+ 1’-3 3/4” AT OPERA HOUSE
Figure t
Last December, just the week before
Christmas, another well-coordinated group, the Joffrey Ballet
of Chicago, performed its Nutcracker to full houses over a
six-day run at the Kennedy Center. Not a person in the audi¬
ence was aware that a well-orchestrated team of engineers,
architects, builders and roofers had worked since June of 1996
to ensure that the management and board of the nation’s pre¬
mier performance facility would not have to think about the
roof again at least until the grandchildren of the Joffrey’s
dancers were starting their careers.
Swen E. Swenson III, tvho is currently National Sales Manager
of Koppers Industries Commercial Roofing Department, has held a variety
of positions with the company over the past 28 years. He has served as
Architectural Manager, District Manager, Regional Manager of
Commercial Roofing and Product Manager for Roof Maintenance
Products. He has held membership in CSI since 1977, and is a past Board
Member of the Single Ply Roofing Institute (SPRIf Mr. Swenson also
serves as a Municipal Planning Commissioner for the Borough of Leetsdale,
PA, near Pittsburgh.
Interested in advertising in
Just call 1 -800-828-1 902.
September 1998 Interface • 19