How to Give Owners What They Want Through Performance Specifications

May 25, 2021

There are numerous sources of
potential building enclosure
failures. These failures have
caused building repairs and
litigations to become a billiondollar
annual industry and
are one of the main reasons why the industry
needs performance specifications. This article will
explain building owners’ directives and discuss
properly executing the project requirements as
part of the performance specifications.1 Clear,
concise, correct, and complete performance specifications
help mitigate risk for all parties involved.
BUILDING AN UNDERSTANDING
The reality of a project outcome is typically
different from what an owner expects
due to budget, time, and other constraints. So
how can the design team, building enclosure
consultants, and commissioners minimize the
gap between owner expectation and reality?
Just because it looks good on paper, and just
because we specify it, does not necessarily
mean the contractor can build it and meet the
owner’s performance expectation. We must ask
ourselves several questions:
• How do we guide the contractors so
that they can succeed?
• Are design professionals giving the
construction team designs that work?
• Are designers specifying assemblies
and systems that have been tested?
• Are the specified materials compatible?
• Should more direction be provided
so contractors are not missing critical
components as part of their sequencing?
• Are we directing the construction team
on how to control the performance of
the building and even how to control
their quality assurance and quality control
during construction?
As design professionals, we must clearly
define what the owner expects in “Division
One” of the project manual so the contractor
clearly understands the design intent and can
fully envision the building enclosure performance
as defined by the owner’s expectations.
If the design is not clear, the contractor may
not understand it, and may construct it differently
than expected. We need to take the entire
building enclosure system into consideration
and comprehensively describe not only assemblies
of components, but the system as a whole.
Methods to clearly define the project requirements
often begin with concise performance
specifications.
The scope of the Building Enclosure
Performance Requirements includes quality
assurance and quality control (QA/QC)2
covering all materials and systems comprising
the building enclosure. This section includes
specific requirements for project management,
coordination between the trades, scheduling
and sequencing of the work, preconstruction
and preinstallation meetings, inspections, tests,
and related actions (including reports) performed
by contractor, manufacturer, and independent
third-party consultants.
Let us look at some of the challenges that
often lead to building enclosure failures and
how we can help prevent them.
BUILDING ENCLOSURE FAILURES/
CHALLENGES
Legal fees, rework, and all the forensics
involved in investigating building failures
account for billions spent in the construction
industry annually. Over 90% of these failures
occur in 1% of the enclosure.3 These failures are
related to issues typically observed at penetrations,
fenestrations, roof-to-wall transitions, and
dissimilar material transitions, most of which

could have been avoided by requiring the construction
team to: construct mock-ups, conduct
performance testing, conduct preconstruction
and preinstallation meetings, document the
verification and validation of installed assemblies,
and implement construction QA/QC.
These requirements can be defined in both Part
One – General and Part Three – Execution, as
part of Section 01 83 16 – Building Enclosure
Performance Requirements Specification.
Quality Assurance and Quality Control
QA and QC processes, in the form of testing
and construction observations throughout
the entire construction process, play an
important role in ensuring that the project
requirements are met. It is crucial to consider
how the construction manager (CM) and/or
general contractor (GC) are managing the construction
observations and installation inspections
of the various enclosure trades. Are the
installing trades educated on the installation
processes and following the manufacturer’s
requirements? Who is observing the installation
of the building components and how
they transition? These are items that the contractor
needs to build into its QA/QC program.
In addition, onsite observation by the
manufacturer, and installation inspections by
a third-party consultant or building enclosure
commissioner are also critical items that the
contractor should incorporate as part of their
QA/QC process. Walk-throughs, systems testing,
and verification of installations should be
conducted during the construction phase to
ensure performance criteria are met. It should
be noted that the stated protocols can also be
defined in Section 01 83 16 to ensure these
risk management steps are carried out during
construction.
QA/QC should be clearly defined within
Section 01 45 00, “Quality Requirements;” however,
additional enhanced QA/QC should be
clearly defined in Section 01 83 16, “Building
Enclosure Performance Requirements” as they
relate to the building enclosure. Most CMs and
GCs have their own QA program, but no two QA
programs are created equal. To meet the defined
owner’s performance expectations for a given
project, the design team should include provisions
in the project manual to clearly outline the
QA/QC protocol to be followed as part of the
construction phase and explain the required collaboration
throughout the construction phase
to include and involve a third-party consultant
and/or building enclosure commissioning protocol
paid for by the owner. Simply said, if it is
specified, it is contractually understood that the
CM/GC is required to follow the defined quality
of construction in order to attain the given building
enclosure performance.
Designing to Code (or Not)
When designs, building codes, and the
owners’ requirements are in conflict, how are
these conflicts resolved? We need to educate
owners and help them understand the conflict
resolution process. Keep in mind that a code
contains the bare minimum requirements for
structures. We should be aiming higher than
what the code is offering us if we truly want
high-performance structures.
Water and Air Management
Water intrusion and air leakage4,5 are
issues that frequently lead to project callbacks.
Designers should understand the effects of
water intrusion and air leakage on the performance
of a building as a whole. The contractor
should implement the provisions in the specifications
to minimize the risk of these two
phenomena during construction, and for the
life-cycle performance of the structure. With
large projects, various trades, and different
product technologies and systems, installation
deficiencies can wreak havoc on projects and
get missed. So how are we controlling risks? Are
we giving sufficient drawing details to go along
with our performance specifications? We need
to make sure that the trades understand exactly
what is expected of them. We can test to ensure
that we do not have air leakage or water intrusion;
we should require it in the specification.
Environmental hazards and site conditions, of
course, are inevitable, but water management
during construction is something that the contractor
is really in control of. We should be
making sure that we give installers the precise
details and transitions they are going to be
encountering in the field in the project documents,
along with providing the proper information
in the specifications so that the installer
understands the performance expectation of
the specified systems. By dictating clear expectations,
we can mitigate the chance of moisture
intrusion and air leakage within our buildings
after construction.
Lack of Skilled Labor and Training
There is a huge labor shortage right now.6
We do not have as many skilled laborers in
construction, and many in the workforce are
retiring. Due to the speed of construction, labor
shortage, and turnover, the industry is challenged
with adequately training the younger
May 2021 IIBEC Interface • 37
Durability,
Sustainability,
Energy Effi ciency
Your GUARD Against Energy Loss
Insulated Concrete Solutions
for Wall Assemblies
ProGUARD® DP Insulated Concrete Board
A unique wall sheathing that provides
Continuous Insulation value consisting of
Util-A-Crete® Concrete Backerboard
laminated to rigid insulation with
specially designed drainage planes to
allow moisture to escape.
– Meets or Exceeds Energy Codes
– NFPA 285 Approved Wall Assembly
– ASTM E119 1-Hour Fire Approved Assembly
– Signifi cant Labor Savings Achieved
– Durable, Ready-to-Finish Substrate
WallGUARD® Concrete Faced
Insulated Perimeter Wall Panels
A “one step” Continuous Insulation panel
that protects foundations, slab edges,
rim joists and parapet walls by
combining rigid insulation laminated to
a latex-modifi ed c oncrete facing.
– Reduces Energy Loss
– Long-term High Insulation Value
– Above and Below Grade Approved
– Durable, Impact Resistant Substrate
800.544.7398 tclear.com
tclear_ad.indd 1 3/9/2021 10:15:04 AM
generation as they enter the workforce. We need
to focus on continually educating tradespeople
to give them the tools and knowledge they need
to do proper installations. If not addressed, this
can lead to poor quality of work and deficient
installation of the building components. To
complicate matters, manufacturers are coming
out with new products all the time. These new
products may not necessarily be something
contractors or tradespeople are experienced
in, or have had time to train in. It is difficult
for installers to keep up with the new products
and systems available or specified. Maybe
product manufacturers have shifted how to
install system components or the sequencing
of components. By specifying manufacturer
participation at preconstruction and preinstallation
meetings, we can help ease that burden;
by requiring manufacturers to follow up with
manufacturer audits during the installation
phases, and inspecting the work along the way,
installation deficiencies can be minimized.
Lack of Coordination
Between the contractor, tradespeople, architects,
consultants, and engineers, there can be a
large disconnect in the coordination of a project.
We must ask ourselves, “Is there enough collaboration
going on so that we are mitigating
the risks by looking at the design as a whole,
not just one piece at a time?” The CM or GC is
responsible for construction sequencing, and all
subcontractors need to be cognizant of which
trades are going to follow up behind them. What
are those trades doing to an already installed or
maybe already inspected system? For example,
additional penetrations to an existing air-barrier
membrane that was tested and approved could
severely damage the integrity of the air barrier.
So how is the contractor managing those potential
risks? This process should be outlined in the
performance specification, and the contractor
should include coordination protocols on the
agenda for discussion of coordination expectations
during the preconstruction and preinstallation
meetings.
HOW DO PERFORMANCE
SPECIFICATIONS HELP?
The only way that we can resolve water
intrusion, air leakage, construction deficiencies,
and even poor quality control, is by providing
and following specifications that effectively
describe performance and clearly translate the
owner’s project requirements into a low-risk
and leak-free building. So how can we accomplish
this within the specifications?
The Owner’s Project Requirements
The owner’s project requirements (OPR)
should be a product of collaboration between
the owner and the architect of record. The
OPR clearly defines the requirements of a project
and the expectations of how the building
will be used and operated, and should include
project goals, measurable performance criteria,
cost considerations, benchmarks, success criteria,
and supporting information.7 Defining
what the owner wants will determine exactly
what the QA will be. We need to provide
specifications that define the performance and
functionality of the building and ensure that
all technical requirements are being met. This
communication reduces risk for the owner and
everybody else, including the designer, specifier,
contractor, and installing trades, for the
lifecycle of the building—not just during construction.
So, these are the “Four Cs”8 that we are
after: Clear, Concise, Correct, and Complete.
Performance specifications should embody the
Four Cs. From there, we must look at the actual
execution of the OPR and the coordination of
design intent to construction execution. Does
the owner want construction observations?
Does the owner want a third-party inspector?
Will the owner hire their own third party?
What is required of the contractor? Will testing
be required to meet the performance specified?
All those components need to be documented.
In addition, what does the maintenance
protocol look like for the owner? Will the
owner, for example, be taking mechanical systems
offline during non-peak hours, such as
at a school? And if so, are there provisions
available so that that the designed enclosure
is not compromised, and does not prematurely
fail because of these set points? Are there
test requirements, such as a whole-building air
leakage test to ensure the mechanical system is
functioning properly in conjunction with the
building enclosure? Is the contractor required
to test the systems for both peak hours and nonpeak
hours to ensure the performance of the
mechanical system and the building enclosure
will work as designed?
The building enclosure performance specification
should provide all enhanced QC and
testing required to meet the desired performance
the owner is seeking. By understanding
how the owner will use and operate the building,
the architect can clearly define the requirements
of a project, and provide a basis of design
which is clear, concise, correct, and complete.
This project-specific building enclosure specification
will serve to guide the contractor to
construct a building which will meet the owner’s
expectation for the lifecycle of the structure
and its system components.
Communicating Building Codes
We need to make sure that we are following
current codes adopted by the local authorities
having jurisdiction for the location of the
project. But because local codes are the bare
minimum, we should strive to exceed those
requirements. The International Building Code
38 • IIBEC Interface May 2021
If it is specified, it is contractually
understood that the CM/GC is
required to follow the defined quality
of construction in order to attain the
given building enclosure performance.
(IBC) dictates that “the supporting documentation
shall fully describe the exterior wall
system, which was tested, where applicable, as
well as the test procedure used.”9
According to “code,” manufacturer’s specifications
and installation instructions are also
part of what should be included in the project
manual. We should clearly outline and explain
that all manufacturers’ requirements for testing
will need to be followed to ensure that the
installation is done properly. By interpretation
of code, a tested exterior wall system should be
described, as well as the testing procedure used.
Because we do not engineer wall systems that
have been tested for water intrusion and/or air
leakage, we must require the contractor to test
the wall systems to ensure the performance the
owner is seeking.
The architect of record should clearly define
any enhanced measures required to meet the
desired performance as defined by the OPR.
Any enhanced performance testing required
to attain the design intent and the desired performance
should be considered, identified, and
included in the performance specification. The
key is to provide a comprehensive specification
so that construction can be verified to ensure
we are getting the specific performance that is
in the OPR.
Quality and Testing Requirements
QA and QC of the building enclosure can
reduce many of the risks resulting in lawsuits
and insurance claims10 in the construction
industry due to water intrusion. Clearly specified
quality requirements and performance
testing also help the contractor by reducing
rework.11
Within the quality requirements, the design
and construction teams’ responsibilities should
be clearly defined in the specification. Who
is going to manage performance testing and
installation inspections/observations? Who is
going to do the lab and in-field testing and
when? Are they doing mock-ups? What defines
“failure?” If there is a “failure” in the testing,
who is going to conduct the retesting, and who
is responsible for the cost of retesting? What are
the repairs and modifications needed to correct
the “failure” identified? How is the contractor
documenting their “lessons learned” and
communicating the results to the other trades?
Lessons learned from the construction and performance
testing of a mock-up are paramount
in mitigating risks on a project. Requiring the
contractor to include these protocols as part
of their QA/QC program is a very beneficial
aspect of the specification.
The specifications can also identify transitions
that need to be observed by the contractor
and how often they should be witnessed.
Connections to be reviewed include:
• below-slab barriers, penetrations, and
terminations;
• foundation wall penetrations and transitions;
• walls and windows or doors, and other
openings;
• adjacent wall systems;
• walls and roof;
• walls and decks;
• walls, floors, and roofs across construction,
control, and expansion joints;
• penetrations at all walls, floors, and
roofs with systems functioning as the
primary weather barrier; and
• walls and roofs over conditioned space.
Each environmental separator, including
the substrates and transitions from below
grade, the superstructure, and the exterior
building enclosure, should be inspected regularly
to verify quality. The contractor should
May 2021 IIBEC Interface • 39
Available As:
Secure Smart PDF Format or
Printed Edition
“This monograph has been
written as a textbook to
serve all three disciplines—architecture, plumbing engineering,
and structural engineering,” said Dr. Mehta. “We have learned a
great deal since the 2003 publication and have incorporated
it into this book.”
IIBEC Member
IIBEC Nonmember
Order your copy today at iibec.org!
$59.00 USD
$79.00 USD
$75.00 USD
$95.00 USD
Digital Print
Authors:
Stephen Patterson, RRC, PE
Madan Mehta, PE, PhD
be required to observe and document construction
and installation at these junctures at
10%/50%/100% completion, at a minimum.
The contractor should document all observations
as part of their QA/QC protocol. The
report should include details of the components
or systems found to be non-compliant with the
drawings and specifications or with the manufacturers’
installation specifications. It should
also denote adjustments or alterations required
to correct the system operation and should
identify which trade is responsible for making
the corrective changes. This report is a living
document that should be regularly updated to
reflect the progress on the building enclosure
components and systems, and all items noted
as a deficiency should be corrected and closed
prior to covering the condition and prior to
substantial completion of the project.
The construction quality assurance process
should always be defined in the project manual.
By incorporating risk mitigation, the design
team can aid in reducing the owner’s risk, and
in turn, everyone’s risk.
PRECONSTRUCTION AND
PREINSTALLATION MEETINGS
Preconstruction (precon) and preinstallation
(preinstall) meetings should not be confused,
one with the other, or skipped. The
specification can detail which parties should
be present for which meetings and provide an
example agenda of what those meetings should
address.
Preconstruction Meeting
The building enclosure precon meeting
is, in essence, an opportunity for all parties
to sit down and talk about the construction
before it even happens. The design team, construction
team (including the leads for all the
installing enclosure trades if known at the time
of the meeting), and the owner should attend.
Manufacturers should also be present because
the team is covering everything from the design
that is on paper and trying to figure out exactly
how it is going to be constructed. Sequencing,
compatibility, cure times, manufacturing lead
time, testing, mock-ups, and the like, all need to
be taken into consideration, as these factors can
affect the project schedule. Discussing those
items during the precon meeting with every
trade is going to help identify potential problems
and minimize risk for all the parties.
The precon meeting should be held on
site and prior to the submittal of the shop
drawings, after the product selection has been
completed so that the manufacturer can attend.
The contractor’s responsibility is to organize
the precon meeting with all trades involved in
the whole building’s enclosure barrier systems
to discuss where each trade begins and ends;
the responsibility and sequence of installation
of all the air- and weathertight joints; and
junctures and transitions between materials,
products, and assemblies of products specified.
It offers the opportunity to go through every
single step of the construction process and
discuss the specific sequencing, compatibility
concerns, and testing requirements, and
promotes collaboration and project ownership
with the installing trades. Can a given installer
apply the specified products/systems onto the
substrate as designed? Are there dissimilar or
incompatible materials? And if there is a change
that needs to be made, then that is the time for
the design professional to be made aware of the
concerns, and ensure that the shop drawings
and the resubmittals, if any, can reflect what has
been discussed.
The contractor should hold this meeting once
they have conducted a constructability review12
to identify sequencing for construction, and the
meeting should be scheduled such to bring in
40 • IIBEC Interface May 2021
Photo by Sharon McCutcheon on Unsplash
the building enclosure trades when their area
of construction will be covered. The purpose of
this meeting is to simulate construction from the
ground up and to review the construction documents
for constructability concerns, sequencing,
and review of transition details—the “by others”
transitions—between systems.
Why should the design team go to the
extent of specifying a preconstruction meeting?
Simply put, not all contractors conduct precon
meetings, and this process will minimize the
owner’s risks and aid in ensuring that the performance
of the constructed building will meet
the owner’s expected performance.
Preinstallation Meeting
The preinstall meeting should happen
about two weeks prior to the actual installation.
This is the time to fill in the gaps and make
sure that everything is covered. If there were
any missing trades during the precon meeting,
that can be noted and then addressed at the
preinstallation meeting. Completeness of the
submittals is the goal. Remember, if you do not
specify something, it may not happen.
Industry standards suggest that several
meetings may be conducted throughout the
construction phase as construction progresses.
Preinstall meetings give the construction team a
chance to discuss installation to ensure the transitions
happen per the shop drawings and meet
the owner’s project expectations. Every preinstall
meeting offers the opportunity to eliminate
or minimize mistakes during construction that
could result in rework. Below grade, above grade,
and roofing meetings can be conducted at different
times of construction depending on the size
of a project. Keep in mind that the preinstallation
meeting(s) serves as the contractor’s QC point
and provides an opportunity for the building
enclosure trades to review the substrate and
project conditions, and to discuss lessons learned
prior to commencing work. This meeting should
include all trades who will be part of the construction
team to make sure that the quality of
the installation can be provided in accordance
with the performance specification. As part of
this meeting, submittals of shop drawings should
be reviewed to verify they reflect what was discussed
in the precon meeting. The specification
should require the contractor to include that the
lead installer(s) for each trade should attend the
meeting related to their scope of work. The success
of this meeting is largely dependent on the
installing trades being included in the meeting.
To ensure that all trades are included, the
specification can even go to the extent of requiring
that each person in attendance sign off that
they have been at the preinstallation meeting
and have observed the condition of the building
prior to installation of the components. For
example, a waterproofing installer must look at
the substrate and confirm that they are ready to
conduct the installation and ensure a weathertight
installation can be accomplished by accepting
the substrate. If conditions are not such that
the installer can guarantee a weathertight installation
can be accomplished, they should let their
contractor know what repairs are needed prior to
returning and commencing work.
CONCLUSION
With so many complicated factors and competing
needs through the duration of a commercial
construction project, a cohesive team
and clear, concise, correct, and complete performance
specifications are a must to reduce the
risk for all stakeholders. Remember that specifications
are part of a legal document that carries
legal ramifications. Identify the OPRs and
desired performance, and specify the expected
performance once, in the right place within the
project manual.
Specify what should be covered at the preconstruction
and preinstallation meetings and
clearly define when these meetings should be
held. Define the expectations for a QA/QC
plan for the construction team. Outlining the
sequencing, testing, and QA/QC requirements
during the preconstruction and preinstallation
meetings will minimize many of the design and
application challenges contractors are faced with
during construction. Have a plan, and execute
that plan in the building enclosure performance
specification, and require this plan be followed
in the field.
Together, we can create leak-free buildings,
but it is through performance specification that
we can aid in this process by clearly detailing
the expectations and responsibilities for each
team.
REFERENCES
1. Building Enclosure Performance
Specifications should be defined in
Section 01 83 16 – “Building Enclosure
Performance Requirements.” This
section is used to define the required
performance of the building enclosure
as a whole and should be in accordance
with the OPR for the building
enclosure. The specification is intended
to incorporate all enhanced performance
not noted in other related
sections of building enclosure components
as required to attain a whole
building enclosure enhanced to meet
the owner’s needs. This section should
not duplicate what is specified in other
sections. Construction Specifications
Institute. Alexandria, VA. https://www.
csiresources.org/.
2. According to CSI, quality assurance
“refers to the procedures for guarding
against defects and deficiencies
before and during the execution of
the work,” and quality control “refers
to the procedures for evaluating completed
activities and elements of the
design for conformance with the
requirements.” Patrick Reicher, REWC,
REWO, SE, CCS, CCCA and Jacob
Arnold, CDT. “Specification Strategies
for Field Testing Success.” Proceedings
of the Building Envelope Technology
Symposium. IIBEC. Raleigh, NC.
November 16-17, 2018. https://iibec.
org/wp-content/uploads/2018-bes-reicher-
arnold.pdf.
3. The 90%/1% Principle: As much as 90
percent of all water intrusion problems
occur within 1% of the total building
or structure exterior surface area. The
99% Principle: Approximately 99% of
waterproofing leaks are attributable to
causes other than material or system
failures. Michael T. Kubal. Construction
Waterproofing Handbook. The McGraw
Hill Companies Inc. 2000.
4. By putting assemblies, penetrations,
and transitions to the test during
construction, water intrusion and air
leakage can be rectified during construction
and avoided. Sarah K. Flock,
CDT, AIA, and Andrew Dunlap,
AIA, CDT, LEED AP, NCARB. “Put
Penetrations to the Test: The Effect
of Cladding Attachments on Air and
Water Barriers.” Construction Specifier.
Construction Specifications Institute.
Alexandria, VA. July 12, 2018.
5. S. Molleti, A. Baskaran, P. Beaulieu,
D. Ban Reenen. “Air Intrusion and
Its Impact on Energy Performance of
Roofing Assemblies.” Proceedings of
The First International Conference on
Building Energy and Environment. July
13, 2008. National Research Council
Canada. https://nrc-publications.
canada.ca/eng/view/object/?id=b2ea29c1-
afcb-4778-a286-1b4b39be0c84.
6. The Associated General Contractors
called for measures to rebuild the
workforce in 2018 because 80% of
contractors reported difficulty finding
qualified craft workers to hire.
“Eighty Percent of Contractors Report
May 2021 IIBEC Interface • 41
Difficulty Finding Qualified Craft
Workers to Hire as Association Calls
for Measures to Rebuild Workforce.”
Associated General Contractors.
August 29, 2018. https://www.agc.org/
news/2018/08/29/eighty-percent-contractors-
report-difficulty-finding-qualified-
craft-workers-hire-0.
7. Owner’s Project Requirements (OPR)
definition. ASHRAE/ANSI/IES
Standard 202, Commissioning Process
for Buildings and Systems. ASHRAE.
Peachtree Corners, GA. 2018. https://
www.techstreet.com/ashrae/standards/
ashrae-202-2018?product_
id=2025517#product.
8. CSI’s Four Cs for specifications are
as follows. Clear: Use proper grammar
and simple sentence construction
to avoid ambiguity. Concise:
Eliminate unnecessary words, but not
at the expense of clarity, correctness,
or completeness. Correct: Present
information accurately and precisely.
Carefully select words that convey
exact meanings. Complete: Do not
leave out important information. “4 Cs
To Improve Construction Document
Communication.” Construction
Specifications Institute. Alexandria,
VA. https://www.csiresources.org/.
9. Construction documents for all buildings
shall describe the exterior wall
envelope in sufficient detail to determine
compliance with this code. The
construction documents shall provide
details of the exterior wall envelope as
required, including flashing, intersections
with dissimilar materials, corners,
end details, control joints, intersections
at roof, eaves or parapets, means
of drainage, water-resistive membrane,
and details around openings. The construction
documents shall include manufacturer’s
installation instructions that
provide supporting documentation that
the proposed penetration and opening
details described in the construction
documents maintain the weather resistance
of the exterior wall envelope. The
supporting documentation shall fully
describe the exterior wall system that
was tested, where applicable, as well as
the test procedure used. International
Building Code 2018: [A] 107.2.4 “Exterior
Wall Envelope.” International Code
Council. August 2017. https://codes.
iccsafe.org/content/IBC2018/chapter-
1-scope-and-administration.
10. Zurich US construction property data
for losses occurring between 1/1/2007
and 12/31/2016 show that nearly 50%
of all builders risk claims resulted from
some form of weather or escape-ofwater
event. This includes damage
from events such as rainstorms, snow,
flooding, and hurricanes. Zurich states
that water intrusion issues on a project
are not limited to the builders risk
policy, and water intrusion-related
issues can also lead to claims under
general liability, professional liability
and environmental liability policies
well after project completion, with the
majority of construction defect claims
being water-related. Construction
Defects Claims Data. Zurich Insurance
Group. Schaumburg, Illinois. https://
www.zurichna.com/-/media/project/
zwp/zna/docs/kh/const/water-intrusion-
mitigation-program-for-construction-
fs.pdf.
11. Around 30% of the work performed
by construction companies is actually
rework. Mohammad Miri and Mahsa
Khaksefidi. “Cost Management in
Construction Projects: Rework and Its
Effects.” Mediterranean Journal of Social
Sciences. December 2015. Doi:10.5901/
mjss.2015.v6n6s6p209.
12. “An independent and structured review
of construction bid documents by construction
professionals to make certain
that the work requirements are clear, the
documents are coordinated, and that
they assist the contractor in bidding, construction,
and project administration to
result in reduced impacts to the project.”
Although constructability reviews
are conducted during the design phase,
the awarded contractor should conduct
a constructability review to identify
sequencing scope prior to conducting
a preconstruction meeting. Stephen
R. Pettee, PE, CCM. “Constructability
Reviews—an Introduction.” Construction
Management Association of
America. Vienna, VA. June 2012. https://
www.cmaanet.org/sites/default/files/
resource/Constructiblity%20Reviews.
pdf.
42 • IIBEC Interface May 2021
Melissa Payne,
BECxP, CxA+BE,
CDT, joined Tremco’s
Building Envelope
Solutions Team in
November 2018.
Prior to joining
Tremco, she provided
building enclosure
commissioning, consulting,
and forensic
investigations at
Miller, P.C. Payne
possesses a strong
foundation in industry standards, BECxP, building
science, performance testing, and building
enclosure construction. Her consulting and commissioning
experience, forensic work, and manufacturer
involvement give her an encompassing
perspective of the construction industry.
Payne maintains high involvement in the
design and construction industry as a guest speaker
at Drury University School of Architecture. She
is a member of ISO on ISO/TC 163 and serves
on IIBEC’s Building Enclosure Commissioning
Certification Committee.
Melissa Payne,
BECxP, CxA+BE, CDT
Define the expectations for a QA/QC
plan for the construction team. Outlining
the sequencing, testing, and QA/QC
requirements during the preconstruction
and preinstallation meetings will
minimize many of the design and
application challenges contractors are
faced with during construction.