Skip to main content Skip to footer

Precast Concrete Construction: From Pitfalls to High Performance

May 15, 2016

3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 H u b b s • 4 3
Precast Concrete Construction:
From Pitfalls to High Performance
Brian Hubbs, PEng, and Eric Guetter, EIT
RDH Building Engineering Ltd.
224 West 8th Avenue, Vancouver, BC V5Y 1N5
Phone: 604-873-1181 • Fax: 604-873-0933 • E-mail: brian@rdh.com
Abstract
Over the past few decades, the use of glass and glazing on our high-rise buildings has
increased dramatically. More recently, as a result of increased industry recognition of the
importance of energy efficiency, the trend is towards more energy-efficient glazing systems.
However, there are instances of implementation of new technology that have resulted in premature
and costly failures. Several case studies will be used to show and explain the variety
of problems that can occur with glass and glazing after installation. We will offer designers
risk reduction recommendations to avoid the most common causes of failures.
Speaker
Brian Hubbs, PEng — RDH Building Engineering Ltd.
Brian Hubbs has over 20 years’ experience as a consultant practicing exclusively in
the field of building science. Recognized by his peers as being a practical building science
engineer and researcher who consistently delivers innovative solutions, Brian has a unique
blend of theoretical and hands-on knowledge gained from completing hundreds of building
enclosure investigations and rehabilitation projects, as well as from design consulting and
construction review of building enclosures for new buildings.
4 4 • Hu b b s 3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6
3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 H u b b s • 4 5
ABSTRACT
Precast concrete has long been an
established architectural cladding system
for buildings of all sizes and shapes.
Precast concrete allows for unique architectural
shapes and textures and has a
long track record of good durability and
performance. In recent years, most cladding
systems have evolved to be more
energy-efficient through the integration of
high-performance air barriers, rain screen
moisture management design, and thermal
breaks at anchors for continuous insulation.
However, conventional precast has
remained virtually unchanged in the past
50 years. The high cost, coupled with relatively
poor thermal, air, and water leakage
performance, often makes conventional
precast uncompetitive when compared to
modern cladding systems.
By changing the sequence of construction,
it is possible to create high-performance
and energy-efficient rain screen systems
using conventional precast panels;
however, this increases the overall cost.
Advances in precast ties and anchors allow
insulated precast sandwich panels to be
made and installed like a window wall
system on high-rise buildings. At the same
time, advances in forming technology make
the addition of custom patterns and textures
cost-effective. These panels can be
installed quickly, have continuous insulation,
and incorporate rain screen cladding
design and detailing. With attention to the
economics of precast at the design stage, it
is possible to install these complete systems
at a cost that is less than most other cladding
and window assemblies.
Through a number of case studies, the
author will discuss shortcomings, failures,
successes, and lessons learned when dealing
with precast concrete cladding systems,
as well as insight for potential future
improvements.
INTRODUCTION
In order to understand the basic science
behind the performance of concrete
as a building envelope material, five distinct
types of concrete wall assemblies
have been identified for comparison in this
paper: cast-in-place concrete, precast concrete
cladding, tilt-up concrete panels, thinshell
sandwich panels, and true rain screen
precast panels. With the exception of the
true rain screen panels, all of the concrete
wall assemblies listed above are considered
mass walls.
Rain Penetration Control Strategy
The rain penetration control strategy
of a mass wall is to absorb any rainwater
that penetrates the face and store the water
until it is able to dry. To have an effective
system, the mass wall must be able to store
enough water so that it will always be able
to dry before the water reaches the inside
of the wall and infiltrates into the interior
space. Factors affecting the rain penetration
performance of mass walls include storage
capacity, exterior finish, joint detailing,
crack control, and amount of wetting.
Thermal Performance
Thermal performance of conventional
mass concrete walls is typically not ideal.
In concrete buildings, slabs act as large
thermal bridges at each floor. This can
lead to high energy costs, cold spots inside
the building, and increased condensation
potential. The one benefit of mass walls
in regard to thermal
performance is
their large thermal
mass, which means
a large amount of
energy is required
to change the temperature.
Once the
mass wall is at a
desired temperature,
it will stay relatively
consistent,
even when other
elements around it
are changing more
rapidly; and as a
result, heating and
cooling requirements
can be significantly
decreased
by exposing the thermal mass to the conditioned
space (as seen in Figure 1).
In practice, this means that concrete
mass walls that have a substantial portion
of their mass inside the insulation layer
(such as sandwich panels) can expect up to
a 7% increase in energy savings compared
to conventional precast systems.
Cast-In-Place Concrete
Cast-in-place concrete walls use the
mass wall rain penetration strategy of
absorbing water until it is given a chance to
dry. Since this concrete is integral with the
building structure, it is likely to crack when
the building undergoes movements as a
result of settlement, thermal expansion and
contraction, and live and/or environmental
loads throughout its life. As a result, joint
and crack control is critical to successful
performance. In standard cast-in-place
concrete walls, all of the thermal mass
is outside the insulation, and any water
penetration to the interior of the building
is unable to drain back to the exterior of
the building. Water infiltration through
cast-in-place concrete enclosures is a common
occurrence at cracks, tie holes, and
interfaces with other enclosure systems
(Figure 2).
Precast Concrete Construction:
From Pitfalls to High Performance
Figure 1 – Energy savings due to thermal mass effect (City of
Vancouver Passive Design Toolkit).1
Precast Concrete Cladding
Conventional precast concrete cladding
utilizes a mass wall rain penetration control
strategy with a heavy emphasis placed
on joints between panels. Since the panels
are mounted onto the main structure of
the building rather than being an integral
structural component, they can be attached
using anchors that are able to
move and rack independently
of the building. As a result, it is
less likely that panels will experience
uncontrolled cracking.
The thermal mass for this wall
system is also on the exterior,
unconditioned face.
Tilt-Up Concrete Panels
Tilt-up concrete panels also
use the mass wall rain penetration
control strategy. The use of
sandwich panels with insulation
between two layers of concrete
is common in tilt-up applications.
This allows for half of
the thermal mass to be inside
the conditioned space, leading
to more efficient-energy performance,
while the interior concrete
wythe serves as an interior
vapor retarder.
Performance Enhancers for
Face-Sealed Precast
It is common for builders to
install performance enhancers
in conjunction with face-sealed
precast to promote
drainage within
the wall. During
numerous investigations,
the author
has observed metal
drainage gutters in
the capillary break
between the back of
the precast panel and
the metal studs to
direct water ingress
back to the exterior
at window heads and
though joints, sometimes
incorporating
unconventional construction
materials
as shown in Figure 3.
While this gutter
system can be effective
in promoting drainage, it is not the best
solution to the problem of leakage at joints
and cracks. Often, high humidity, created
by drainage water or leakage around the
gutter system, will cause damage to the
interior finishes and result in costly rehabilitation
work.
Precast Joints
Joints between precast panels are crucial
in order to maintain a waterproof and airtight
system. Since sealants inevitably will fail over
time, it is recommended to use two stage
joints for redundancy. The interior sealant
joint is the air and moisture barrier, which
is continuous down the entire height of the
wall. The exterior sealant joint is the watershedding
surface. To make the two stage joint
systems work effectively, periodic gaps in the
primary face seal, in conjunction with ramping
of the top of the joint, should be provided
for drainage and venting (Figure 4).
Ramping of the joint at the base of the
wall is also required to ensure that water
is not directed straight downwards into the
building.
Current State of Precast
The lack of redundancy for water penetration
resistance, combined with the thermal
bridging and weight, often make precast
a less desirable choice when compared
with high-performance exterior insulated
rain screen systems such as masonry or
metal panel. Interfaces between precast
panels and other building enclosure elements
are also often difficult to detail and
4 6 • Hu b b s 3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6
Figure 2 – Water penetration at crack in concrete (Homeowner
Protection Office, BC Housing).2
Figure 3 – Unconventional construction methods for wall assembly drainage.
require a lot of attention in design and
construction. To solve these issues with
conventional precast, it is useful to look at
other enclosure systems used in high-rise
construction to see if there is a more efficient
method of installing precast in today’s
high-rise buildings.
Mass-storage rain control can only hold
so much water before it passes through, or
even worse, finds its way inside through a
crack. Therefore, in order to make precast
concrete a viable wall system in today’s
high-rise construction industry, it is desirable
to use a redundant, drained system
that easily interfaces with modern window
and curtain wall systems.
The following case studies will showcase
the author’s experience assisting in the
evolution of several unconventional precast
concrete cladding systems. Lessons learned
in the case studies were used to develop a
model precast system that is economical,
fast to install, and aesthetically variable.
Case Study 1
Rain Screen Precast Outside
and in Sequence
The first precast, concrete-clad building
discussed in this paper is a 32-story,
multiunit residential building in Portland,
Oregon. The design called for concrete
framing with post-tension slabs, aluminum
window wall, and precast concrete cladding,
which was to be installed like unitized curtain
wall, where precast concrete panels are
stacked as individual units and supported
at each floor line (Figure 5).
The three fundamental requirements for
the precast concrete panel system were exterior
insulation, self-adhered weather barrier,
and the ability to act as a rain screen
wall system. To achieve these requirements,
the precast panels incorporated a selfadhered
air/moisture/
vapor weather barrier
membrane over exterior
sheathing and insulation
on the exterior. Drainage
for the weather barrier
was to be provided by
through-wall flashing
at each floor line and
by ramping of two stage
joints between panels.
Originally, a conventional
inside-to-outside construction
sequence was
planned, which involves
installing the layers of the wall assembly
sequentially, starting with the studs and
moving outwards to the exterior finish.
However, constructability and cost issues
made it necessary to build the wall system
from outside to inside. This reversal of
sequence required a prefabricated, panelized,
interior wall assembly (Figure 6) and
bolted connections for mounting the precast
panels in order to avoid welding near the
self-adhered membrane.
Although continuity of thermal, water,
vapor, and air barriers was achievable
with this inside-out panelized approach,
blind sealing at the interior was required
to ensure this continuity. As a result,
significant quality assurance and control
(QA/QC) efforts were required, resulting in
a slower and more costly installation than
was originally anticipated by the construction
team.
Case Study 2
Precast Sandwich Panels on High-Rise,
Installed Like Curtain Wall
Case Study 2 is a high-rise building
in Seattle, Washington, where the desired
masonry finish was achieved by casting the
thin brick into the face of the precast sandwich
panels (Figure 7).
3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 H u b b s • 4 7
Figure 5 – Installation of
precast concrete panel.
Figure 6 – Typical
prefabricated wall assembly.
Figure 4 – Panel sealant joint layout.
The precast panel-to-slab edge details
were based on curtain wall detailing with
some minor modifications. The thickness
of a precast sandwich panel allowed for the
interior concrete wythe to sit on the slab
below, reducing the required anchor size.
Silicone sealant and extrusions ramping
downwards overtop of spray foam were used
as through-wall flashing and at the panel
head and sill for the interior air seal.
Corner and slab details required premanufactured
flashing boots (Figure 8) and
Dow 123 preformed silicone extrusions to
maintain a continuous air and water seal
around the entire perimeter of the building.
Some of the more difficult interfaces,
such as the jamb conditions between precast
panel and curtain wall, had to be
worked out in the field rather than in the
design stage, which is to
be expected when working
with a completely
new system. Regular QA/
QC testing was necessary
to check air and
moisture seals and was
crucial in discovering
areas that needed attention.
Overall, the cladding
system was found
to be quick to install and
economical by
the design and
construction
team.
Case Study 3
Rain Screen Precast – Proper
Sequence
The third case study is a threestory
hospital building in Sechelt,
BC, which featured large precast
panels. The wall design (as suggested
by the author) was precast
concrete over mineral wool
over self-adhered membrane; however,
this design was changed
during construction. Instead,
spray-applied polyurethane foam
(SPF) was used as the insulation,
air barrier, and water barrier,
instead of mineral wool and selfadhered
membrane.
Even though the potential
for cracking of
foam and compatibility
issues with welding
were raised, the plan,
moving into the construction
phase, was to
proceed with SPF.
Following the proper
enclosure construction
sequence of building
interior to exterior,
the precast concrete
cladding was the last
wall component put
onto the building. The
panels were attached
to anchors protruding
from the edge of the
slabs and welded into
place (Figure 9). Joints
in the panels were sealed with silicone sealant
and allowed to vent and drain at the
bottom of the wall.
While installation of the precast cladding
was performed without issues, ultimately
the SPF created difficulties. Erection
of the precast panels and welding of precast
panel anchors damaged the foam, and
natural shrinkage of the foam resulted in
it pulling away from metal girts and window
frames, creating discontinuities in the
air and moisture barrier. Because of this,
4 8 • Hu b b s 3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6
Figure 7 – Precast sandwich panels with brick face.
Figure 8 – Typical premanufactured corner flashing boot.
Figure 9 – Installation of
precast panels over spray foam.
multiple repairs were necessary to maintain
a continuous air and water barrier. This
precast system was relatively costly due to
the complex panel shapes, but was easy to
install and is expected to perform well in its
highly exposed marine environment.
Case Studies 4 and 5
Precast Sandwich Panels on High-Rise
Installed Like Window Wall
The final two case studies discussed
in this paper represent a culmination of
the author’s knowledge of innovation in
precast concrete cladding systems, borrowing
successes and lessons learned from
past projects. The highlighted project at
the University of British Columbia (Figure
10) is a high-rise university residence with
unique and challenging design requirements,
including the following: effective
R-15 insulation cladding, textured concrete
cladding with randomly shifting panels and
colors, high-performance air and moisture
management strategy, similar installation
cost to window wall ($40-50/sq. ft.), short
construction schedule, durable lifecycle,
and LEED Gold status.
This set of requirements was unattainable
with conventional precast systems in
this region. In order to achieve the design
requirements, the team had to rethink the
way precast cladding is designed, manufactured,
and installed. To meet the project
requirements, insulated precast sandwich
panels were utilized. The fundamental idea
behind the precast system designed for
this project was to make the precast panels
act, interface, and look like the adjacent
window wall units. This allows the window
wall mounting angle to be run continuously
around the perimeter of the building and
allow for substitution of window wall units
and precast panels at desired locations.
While mock-ups are recommended and
required in nearly every new construction
project, with an entirely new system being
developed for this building, concept mockups
were even more important than usual.
Through-wall flashing details for the panels
were modelled in 3-D and then mocked-up
using metal flashing, silicone, and foilfaced,
self-adhered membrane to select the
preferred method (Figure 11).
For the connection device to hold the
two precast wythes of the sandwich panel
together, metal, carbon fiber, and fiber
composite ties were considered. Ultimately,
fiberglass composite ties were chosen due to
their superior energy efficiency (Figure 12).
Since these precast panels act as a
screened wall assembly with no drain space,
a concern was raised about the need for a
drain mat. Heat and moisture transiency
analysis software (WUFI) was used to show
that the panels would have no issues with
drainage; however, the insulation panels
were grooved to promote additional drainage,
which satisfied all parties. Extruded
polystyrene (XPS) insulation at a thickness
of 3 inches
was selected as the
insulating material,
providing an effective
R-value of 16.
With the enclosure
design substantially
completed,
the next phase
was fabrication
of these unique precast concrete panels
(Figure 13). The first step in this process
is to prepare the formwork for the required
panel dimensions. Next, the exterior wythe
steel mesh is placed, and concrete is poured
to the required thickness of 3 inches. An
XPS board with ties on both sides is then
placed onto the plastic concrete and vibrated
into place, and vertical concrete returns
are poured monolithically with the exterior
wythe.
3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 H u b b s • 4 9
Figure 10 – University of British Columbia Ponderosa building concept.3
Figure 11 – 3-D model and mock-up of through-wall flashing detail.
Figure 12 – Thermal images of buildings using different
concrete ties (left to right: metal, carbon fiber, and fiberglass
composite).
The interior wythe is prepared with a galvanized
mesh and mounting embeds before the
concrete is placed to complete the sandwich
panel. Completed panels are then steam cured
in accordance with the Canadian Standards
Association, and once stripped from the form,
can be sealed. However, the author advises
against sealing precast concrete in the factory,
as the concrete should be sealed in-situ after
fully curing and pressure washing.
The installation of these precast sandwich
panels (Figures 14 and 15) was straightforward,
with larger mounting angles installed over the
window wall angle.
Two mounting angles corresponded to the
location of two embeds on the bottom of the
interior wythe, and the panels were easily
dropped into place. Quality assurance smoke
testing during construction revealed
that mounting bolts were not airtight
and required sealant around the
head. The interior only required paint
finishing, providing construction cost
savings along with life cycle cost savings,
due to the durability of concrete
rather than drywall in a university
residence setting.
Many lessons were learned
throughout the duration of the project.
Since the details for panels and
window wall are so similar, it is feasible
and even beneficial to have one
contractor install all of the building-
5 0 • Hu b b s 3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6
Figure 13 – Fabrication sequence of precast
sandwich panel.
Figure 14 – 3-D rendering of precast panel
and window wall installation process.
Figure 15 – Installation
photos of precast panels.
critical sealant and membrane seals, as was
the case for this project. Speed of assembly
was found to be very rapid, and crews were
able to install 20 to 25 panels per day using
portable cranes and temporary outriggers.
Installing precast sandwich panels
like window-wall is a new concept for the
precast manufacturers involved; therefore,
training and education is required for
both manufacturers and installers. Parties
involved must be aware of the intricacies
of the system in order to accurately provide
a bid and minimize potentially troubling
disconnects in knowledge. A specialized
structural engineer
should be used for
analysis due to the
unique nature of
the work and to
prevent expensive,
ultra-conservative designs. The completed
project is shown in Figure 16.
The N ext S tep – W indow
Wall -Style P recast S andwich
Panels
Based on the successes and the exposure
gained from working on the buildings
at the University of British Columbia, the
author was approached by another architect
looking to use the same style of panel
in order to achieve a bamboo-like cladding
pattern (Figure 17).
This project will have sandwich panels
of different sizes and nonuniform width
running in front of the window wall units.
The building design initially had over 30
different panel sizes. In the previous project,
it was discovered that one of the largest
cost factors is the number of distinct
panel sizes. Curve analysis and rendering
software (RHINO)5 was used to optimize the
panel layout to 17 unique panels while still
meeting the required look (Figure 18).
The overall cost of the precast concrete
sandwich panel system was less than
the conventional window wall ($50/sq. ft.),
which was one of the primary design objectives.
The use of precast concrete sandwich
panels installed like window wall (Figure 19)
met all of the design parameters for this
building and allowed it to be completed on
time and on budget.
Overall Building
Thermal Val ues
Using insulated precast concrete sandwich
panels is an economic, easy-to-install,
and thermally efficient solution for the
3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6 H u b b s • 5 1
Figure 16 – Completed University of British Columbia residence building.
Figure 17 – Orchard
Commons rendering.4
Figure 18 – RHINO panel optimization.
building envelope. However, when analyzing
a building for thermal performance, the
building as a whole must be evaluated. Due
to the inverse addition of R-values, the component
with the lowest R-value in a system
will have a dominant effect on the overall
effective building R-value, even if it exists
at a relatively low percentage of building
surface. In practice, windows will always
be the most vulnerable areas in a building’s
thermal performance, and improving
these assemblies will greatly increase the
overall performance. The comparison of an
R-2 window wall to an R-6 window wall is
shown in Figure 20. This graphically shows
the dominant effect that windows have
on the effective thermal resistance of the
building and reinforces the drive for better
windows on our buildings.
REFERENCES
1. http://vancouver.ca/files/cov/passive-
design-large-buildings.pdf
2. https://hpo.bc.ca/files/download/
BuilderInsight/BI3.pdf
3. http://www.srlindustries.ca/images/
UBC-Ponderosa.jpg
4. http://vantagecollege.ubc.ca/
orchard-commons
5. https://www.rhino3d.com/features
5 2 • Hu b b s 3 1 s t RC I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h ow • Ma rc h 1 0 – 1 5 , 2 0 1 6
Figure 19 –
In-progress precast
panel installation.
Figure 20 – R-2 vs. R-6 windows’ impact on overall building R-values.