Skip to main content Skip to footer

The Hidden Risks of Green Buildings: Why Building Problems are Likely in Hot, Humid Climates

May 15, 2009

The great irony of building green
is that the very concepts
intended to enhance a building’s
performance over its
entire lifetime are many of the
same things that make a building
highly susceptible to moisture and mold
problems during its first few years of operation.
While green buildings have many positive
benefits, there is also strong evidence to
suggest a direct correlation between new
products/innovative design and building
failures. Simply put, departing from the
“tried and true” often means increasing the
risk of building failure.
Two strong characteristics of most green
buildings are: 1) the use of innovative, locally-
produced products and 2) the implementation
of new design,
construction, and
operation approaches
that are intended
to reduce energy
usage and be environmentally
sound.
The accompanying
graphic (see Ta –
ble 1) summarizes
some of the differences
between green
buildings and the
concepts the au –
thors have found in
lower-risk buildings.
For example,
lower-risk buildings
do not exceed in –
dustry guidelines on
mechanically introduced outside air but,
instead, emphasize humidity control (especially
in hot, humid climates). Green buildings,
on the other hand, reward the introduction
of more outside air than current
industry standards, which can lead to in –
door humidity problems and mold growth.
Green building environmental goals are
typically organized around a set of nationally
accepted benchmark guidelines such as
those of LEED® (Leadership in Energy and
Environmental Design), which is the guideline
established by the United States Green
Building Council (USGBC). LEED® certification
is a checklist and point system of recommended
practices in which achieving
various point levels can certify the building
as having achieved silver, gold, or platinum
status. These practices involve such issues
as efficient water and energy use, the reuse
of waste materials, and the use of renewable
and regionally produced products.1
The overall goal of these new materials
and procedures is to achieve a structure
with reduced negative environmental
impact — both during construction and
throughout the building’s life. The intent of
building green is unquestionably noble and
good, and should be aggressively pursued.
However, because of the dramatic change
that this will present to the design and construction
industry, its implementation will
present new risks that are likely to be both
technical and legal in nature.
Some of the legal risks are fairly obvious,
such as the risk of not meeting a building
owner’s expectation of achieving a certain
level of LEED® certification (i.e., implied
Table 1
A U G U S T 2009 I N T E R FA C E • 1 9
GREEN BUILDINGS VS. LOWER-RISK BUILDINGS
GREEN BUILDINGS LOWER-RISK BUILDINGS
Add additional outside air (>ASHRAE by 30+%). Minimize outside air (do not exceed ASHRAE
guidelines).
Emphasize energy conservation. Emphasize dehumidification.
Stress VOC reduction. Minimize VOC concern.
• Emphasize exhaust (>5 Paschals). • Very tight control of exhaust.
• Building flush-out. • Reject building flush-out.
Stress new, innovative materials. Stress proven materials.
Stress carbohydrate-based materials. Stress hydrocarbon-based materials.
Stress extra envelope thermal insulation. Stress drying potential of envelope (walls and
roof).
or even written warranties). Other risks are
more obscure, such as:
• The failure of new products to meet
their promoted performance levels,
which is more likely with new materials
compared to proven materials
found in traditional buildings.
• Accepting the higher standard of
care that a green building might present.
What is currently considered
“best practices” may now become
the new expected “standard of care.”
• Failing to recognize (or prepare for)
the unknowns in cost and schedule
impacts that a green building might
present.
It is even unclear if a LEED®-certified
building can be built under a design/build
method without the construction team
assuming huge amounts of unknown risks
because of the vague definition of what is
considered “green.”
The building industry has been historically
conservative, relying on time-proven
construction materials and methods. The
introduction of new materials and methods
has not always proven to be successful and
sometimes has resulted in notable building
failures, especially those related to moisture
intrusion and mold contamination. Many of
the time-tested materials found in lowerrisk
buildings are hydrocarbon based. The
long-term efficacies and performance levels
are unproven for some of the new carbohydrate-
based materials being promoted for
green buildings.
The proliferation of new products and
innovative building approaches related to
green development is challenging the design
and construction community in such a dramatic
fashion. These changes virtually
guarantee an increase in building failures
and lawsuits. Past experience indicates that
many of these failures will be predictable,
and some are likely to be catastrophic.2
EXAMPLES OF TECHNICAL RISKS FOR
CONTRACTORS & DESIGNERS
Moisture intrusion, whether bulk water
intrusion through the building envelope or
a relative humidity increase due to the heating,
ventilating, and air conditioning (HVAC)
system, results in a large percentage of construction
claims in the United States.
Moisture intrusion not only results in building
deterioration but also has been linked to
occupant comfort and health issues, especially
in those buildings that become contaminated
with mold.3 Sustainable building
practices, some of which are part of the
LEED® accreditation process, can increase
the potential for moisture intrusion if not
carefully considered and implemented.
Examples include:
• Vegetated roofs, which are more
risky than conventional roofs (due to
the constantly wet conditions) and
must be carefully designed, constructed,
and monitored after construction.
• Improved energy performance
through increased insulation and
the use of new materials, which may
change the dewpoint location in
walls, resulting in damaging condensation
and a reduced drying
potential for wall assemblies. Lowerrisk
buildings emphasize the drying
potential of the envelope over in –
creased insulation. While it is desirable
to increase insulation for energy
savings, the designer must also
evaluate moisture impacts.
• Reuse of existing buildings or recycled
components, which may not
provide optimum water-shedding
performance in new configurations
or may not be readily integrated to
the adjacent new materials.
• Use of new green construction materials
that have not been field tested
over time. The designer needs to
assess new materials and their risks
compared to traditional materials
found in lower-risk buildings.
• Increased ventilation to meet indoor
air quality (IAQ) goals that may
unintentionally result in increased
interior humidity levels in hot,
humid climates. The designer must
consider the increased energy load
(and cost) and HVAC equipment sizing
required to properly dehumidify
a building when exceeding the minimum
outside air requirements recommended
by the American Society
of Heating, Refrigerating, and Airconditioning
Engineers (ASHRAE).
• Building startup procedures, such
as “building flush-out,” which could
result in increased humidity levels
and mold growth. Lower-risk buildings
rely almost exclusively on
source control (which is also a
green-building goal) rather than
relying on “flush-out” and increased
building exhaust. Building “flushout”
along with building “bake-out”
were concepts developed in the late
1980s by the indoor air quality
industry, which often caused more
problems than it solved.
New green construction materials are
entering the market at a staggering rate.
Because many of these products help to
achieve multiple LEED® credits, designers
working on green buildings are eager to
specify these materials. The risk to contractors
is that many of these new items are not
time-tested, and designers often do not
have the time to fully research their efficacy.
If the new product fails, it may be difficult
to determine if it is a design error, an
installation error, or a product defect.
Additionally, general contractors must rely
on subcontractors to install new materials
that they are inexperienced in installing.
Some of the expandable foam insulation
products are examples of green materials
that pose increased risks. The water ab –
sorption properties of these insulation
materials can be quite different than what
designers expect with traditional insulation.
Additionally, some of the carbohydratebased
foam insulation materials may retain
more water than traditional hydrocarbonbased
foam insulation. Increased absorption
of water into the insulation could negatively
affect the wall performance. This is not to
say that such materials should not be used;
however, their properties need to be recognized
and accommodated in the design.
The amount of ventilation (outdoor air)
necessary for occupant health and comfort
has been debated for decades. Although
there are sound arguments on both sides of
the debate, the emphasis on increasing ventilation
to achieve LEED® environmental
quality credits has increased the incentive
to add more outdoor air to a building
through its HVAC system (a minimum of
30% more outside air above ASHRAE recommended
minimums is required to obtain
a LEED® credit for ventilation).1
Increased ventilation is especially risky
in the southeastern U.S., where outdoor relative
humidity levels are elevated for a good
part of the year. Experience in the South –
east, as well as other areas of the country
with humid summers, has shown a direct
correlation between the number of moisture
problems and increased ventilation rates.
To effectively minimize the risk of moisture
problems while increasing ventilation,
designers may need to increase the complexity
and capacity of the HVAC components
and control systems to achieve proper
dehumidification. This adds to contractor
risk, since complex systems historically fail
20 • I N T E R FA C E A U G U S T 2009
more often than simple systems. Addi –
tionally, the complexity of the system operation
can result in unintended pressurization
relationships where local depressurization
causes humid outdoor air to be drawn
into interstitial building cavities, causing
condensation and mold growth.4
Building owners, designers, and contractors
all assume more risk when they
deal with complex and possibly untried
technologies not generally found in traditional
buildings. Pinpointing whether the
problem is design- or construction-related
may be very difficult after problems have
already occurred.5
Building startup procedures to meet
LEED® credits include a credit flush-out of
indoor containments using increased outdoor
air, either at the end of construction or
during the initial occupancy period. The
intent is to remove pollutants from offgassing
of volatile organic compounds
(VOCs) from new materials. The amount of
air needed to meet the flush-out requirements
places a building at increased risk
because of the amount of moisture introduced
with the increased outdoor air.
LEED® requirements are that a minimum of
14,000 cubic ft per sq ft of floor area is
required for flush-out. This presents multiple
problems: most HVAC systems are not
designed to dehumidify that amount of outdoor
air, which, in a 100,000-sq-ft building,
is 1,400,000 cubic ft of outside air. De –
pending on outside conditions at the time of
the flush-out, as much as 240,000 gallons
of water can be added to a 100,000-sq-ft
building. This added moisture will be
absorbed into building materials, finishes,
and furnishings, increasing the risk of mold
growth.6
Most specifications put the general contractor
in charge of the flush-out, including
controlling relative humidity levels during
flush-out. If the system is not designed to
handle such loads, the contractor is faced
with a difficult challenge that may require
the addition of a temporary and extremely
costly dehumidification system. Lower-risk
buildings tend to avoid flush-out.
CONCLUSIONS
“There’s one sure way to kill an idea:
Sue it to death.”
— Quote from ENR, July 2008
What is the greatest risk to the green
building movement? It’s likely not the in –
creased costs associated with green buildings—
it’s more likely green buildings that
don’t perform up to expectations and, in some
cases, may experience significant failures.
The increased costs of litigation and
insurance that could result from underperforming
green buildings will be absorbed by
designers (in a highly competitive marketplace),
but in most cases, it will be passed
on to building owners. These increased costs,
along with the negative publicity on failed
green buildings, could dramatically in –
fluence building owners not to build green.
Only recently has the marketplace
begun to recognize the various contractual,
legal, and technical risks that are inherent
in green buildings. A growing number of
experts have suggested that the first two
steps to improved green building risk management
are to 1) recognize the unique risks
for green buildings; and 2) develop a set of
guidelines that merge the unique regional
challenges with green building guidelines,
recognizing the lessons learned in lowerrisk
buildings.
The design and construction community
must not assume that if one builds green,
then one will be building regionally correct
or even lower-risk buildings. Until the gaps
between lower-risk buildings and green
buildings are addressed, the design community
would be advised to prioritize the
lessons of lower risk-buildings already
learned from the waterproofing, humidity
control, and building forensics community.
Without these priorities, poorly functioning
green buildings are the likely result, and
this could be the ultimate killer for the
green building movement, especially in
demanding climates.
In our opinion, the solution to wellperforming,
lower-risk green buildings is at
least threefold:
• Development of a set of climate
design criteria that integrate (and
prioritize) climate-specific criteria
with current green building practices.
Best practices for moisture
control must take priority over green
building practices.
• Development of a detailed green
building risk management plan that
provides guidelines for the design
and construction team from concept
through the one-year warranty period.
These guidelines would incorporate
the best ideas of green building
specialists, moisture control specialists,
construction attorneys, and
insurance companies.
See What it Takes to Get Involved
www.rci-online.org/document-competition.html
RCI, Inc. 800-828-1902
2010 DOCUMENT COMPETITION
New – No Entry Fee
This year, there is no entry fee for the 2010 RCI Document Competition.
􀀲􀁓􀁈􀁑􀀃􀁗􀁒􀀃􀁄􀁏􀁏􀀃􀀳􀁕􀁒􀁉􀁈􀁖􀁖􀁌􀁒􀁑􀁄􀁏􀀏􀀃􀀳􀁕􀁒􀁉􀁈􀁖􀁖􀁌􀁒􀁑􀁄􀁏􀀃􀀤􀁉􀂿􀁏􀁌􀁄􀁗􀁈􀀏􀀃􀁄􀁑􀁇􀀃􀀴􀁘􀁄􀁏􀁌􀁗􀁜􀀃􀀤􀁖􀁖􀁘􀁕􀁄􀁑􀁆􀁈􀀃􀀲􀁅􀁖􀁈􀁕􀁙􀁈􀁕􀀃
􀁐􀁈􀁐􀁅􀁈􀁕􀁖􀀏􀀃􀁗􀁋􀁈􀀃􀁆􀁒􀁐􀁓􀁈􀁗􀁌􀁗􀁌􀁒􀁑􀀃􀁇􀁈􀁄􀁇􀁏􀁌􀁑􀁈􀀃􀁉􀁒􀁕􀀃􀁈􀁑􀁗􀁕􀁌􀁈􀁖􀀃􀁌􀁖􀀃􀀱􀁒􀁙􀁈􀁐􀁅􀁈􀁕􀀃􀀖􀀓􀀏􀀃􀀕􀀓􀀓􀀜􀀑
In addition to the traditional winners’ plaques and Interface 􀁓􀁘􀁅􀁏􀁌􀁆􀁌􀁗􀁜􀀏􀀃􀁗􀁋􀁈􀀃
􀀧􀁒􀁆􀁘􀁐􀁈􀁑􀁗􀀃􀀦􀁒􀁐􀁓􀁈􀁗􀁌􀁗􀁌􀁒􀁑􀀃􀀦􀁒􀁐􀁐􀁌􀁗􀁗􀁈􀁈􀀃􀁚􀁌􀁏􀁏􀀃􀁄􀁚􀁄􀁕􀁇􀀃􀁆􀁄􀁖􀁋􀀃􀁙􀁒􀁘􀁆􀁋􀁈􀁕􀁖􀀃􀁗􀁒􀀃
nine winners in three categories:
LARGE PROJECT | SMALL PROJECT | REPORT
1st􀀃􀀳􀁏􀁄􀁆􀁈􀀃􀁚􀁌􀁑􀁑􀁈􀁕􀁖􀀃􀀑􀀑􀀑􀀑􀀑􀀑􀀑􀀑􀀑􀀃 􀀖􀀓􀀓􀀃􀀵􀀦􀀬􀀃􀀧􀁒􀁏􀁏􀁄􀁕􀁖
2nd Place winners ……… 150 RCI Dollars
􀀖rd Place winners ……… 50 RCI Dollars
􀀵􀀦􀀬􀀃􀀧􀁒􀁏􀁏􀁄􀁕􀁖􀀃􀁚􀁌􀁏􀁏􀀃􀁅􀁈􀀃􀁕􀁈􀁇􀁈􀁈􀁐􀁄􀁅􀁏􀁈􀀃􀁉􀁒􀁕􀀃􀁄􀁑􀁜􀀃􀁓􀁕􀁒􀁇􀁘􀁆􀁗􀀃􀁒􀁕􀀃􀁖􀁈􀁕􀁙􀁌􀁆􀁈􀀃􀁓􀁕􀁒􀁙􀁌􀁇􀁈􀁇􀀃􀁅􀁜􀀃􀀵􀀦􀀬􀀃􀁒􀁕􀀃􀁗􀁋􀁈􀀃􀀵􀀦􀀬􀀃􀀩􀁒􀁘􀁑􀁇􀁄-
􀁗􀁌􀁒􀁑􀀑􀀃􀀵􀀦􀀬􀀃􀀧􀁒􀁏􀁏􀁄􀁕􀁖􀀃􀁄􀁕􀁈􀀃􀁕􀁈􀁇􀁈􀁈􀁐􀁄􀁅􀁏􀁈􀀃􀁅􀁜􀀃􀁗􀁋􀁈􀀃􀁄􀁚􀁄􀁕􀁇􀀃􀁚􀁌􀁑􀁑􀁈􀁕􀀃􀁒􀁕􀀃􀁅􀁜􀀃􀁄􀁑􀁜􀁒􀁑􀁈􀀃􀁖􀁓􀁈􀁆􀁌􀂿􀁆􀁄􀁏􀁏􀁜􀀃􀁇􀁈􀁖􀁌􀁊􀁑􀁄􀁗􀁈􀁇􀀃
􀁅􀁜􀀃􀁗􀁋􀁈􀀃􀁄􀁚􀁄􀁕􀁇􀀃􀁚􀁌􀁑􀁑􀁈􀁕􀀑􀀃􀀸􀁖􀁈􀀃􀁜􀁒􀁘􀁕􀀃􀁚􀁌􀁑􀁑􀁌􀁑􀁊􀁖􀀃􀁉􀁒􀁕􀀃􀁜􀁒􀁘􀁕􀁖􀁈􀁏􀁉􀀃􀁒􀁕􀀃􀁗􀁒􀀃􀁋􀁈􀁏􀁓􀀃􀁄􀀃􀁉􀁕􀁌􀁈􀁑􀁇􀀃􀁒􀁕􀀃􀁆􀁒􀁏􀁏􀁈􀁄􀁊􀁘􀁈􀀃􀁅􀁘􀁜􀀃􀁄􀀃
􀁕􀁈􀁉􀁈􀁕􀁈􀁑􀁆􀁈􀀃􀁅􀁒􀁒􀁎􀀃􀁒􀁕􀀃􀁄􀁗􀁗􀁈􀁑􀁇􀀃􀁄􀀃􀁖􀁈􀁐􀁌􀁑􀁄􀁕􀀑􀀃
􀀃
􀀃 􀀃
􀀃
DOC
CUMENT COM
MPETITION
N
A U G U S T 2009 I N T E R FA C E • 2 1
Apply the lessons learned from past
building successes and failures and make
green building concepts subservient to
these past lessons.
REFERENCES
1. U.S. Green Building Council.
www.usgbc.org.
2. J. David Odom, Richard Scott, and
George H. DuBose, The Hidden
Risks of Green Buildings: Avoiding
Moisture and Mold Problems,
Washington, DC: National Council
of Architectural Registration Boards
(NCARB), 2007.
3. U.S. Environmental Protection
Agency, Office of Air and Radiation,
Indoor Environments Division, Mold
Remediation in Schools and Commer
cial Buildings, Washington, DC:
EPA, March 2001.
4. J. David Odom and George H.
DuBose, Mold and Moisture Pre ven –
tion, Washington, DC: National
Council of Architectural Registration
Boards (NCARB), 2005.
5. LEED® for New Construction. U.S.
Green Building Council. www.usgbc.org
/DisplayPage.aspx?CMSPageID=220.
6. Stewart Brand, How Buildings
Learn: What Happens After They’re
Built, New York: Viking, 1994.
22 • I N T E R FA C E A U G U S T 2009
George DuBose is a general contractor with a mechanical
engineering degree. He is also a building forensics expert and
vice president of Building Consulting Services with Liberty
Building Forensics Group®. He has authored over 15 technical
articles and coauthored three manuals on moisture-related
indoor air quality problems and building commissioning.
George DuBose
David Odom is a building forensics expert and vice president
with Liberty Building Forensics Group® in Orlando, FL. He
has authored over 50 articles and three manuals on moisture
and construction. In 1998, he was named Indoor Air Quality
Person of the Year by IAQ Publications, and in 1999, he was
recognized as one of the 50 Most Influential People in the
indoor air quality field by the same magazine.
David Odom
Richard Scott is a senior forensic architect registered with the
AIA, specializing in moisture and mold problems with Liberty
Building Forensics Group®. He has coauthored two monographs
on mold prevention.
Richard Scott
Liberty Building Forensics Group, LLC (www.libertybuilding.com) specializes
in forensic building investigations and expert witness/litigation support.
The National Nuclear Security Administration (NNSA)
announced the completion of a construction project at NNSA’s
Nevada test site more than two years ahead of schedule and at
only 20% of the original cost estimate. NNSA officials have made
it a priority to promote project management best practices
throughout the nuclear security enterprise.
During a ceremony honoring the accomplishment, NNSA
Principal Assistant Deputy Administrator for Military Application
Brig. General Garrett Harencak applauded the project managers
at the Device Assembly Facility (DAF) for saving U.S. taxpayers
$7.8 million. “To fix the issue as quickly as they did while saving
taxpayers nearly 80% of the original price tag is a major accomplishment
and is the latest example of the excellent project management
skills employed across the nuclear security enterprise.”
The DAF is a collection of more than 30 individual steelreinforced
concrete buildings connected by a rectangular common
corridor. The entire complex is covered by compacted earth
and spans an area of 100,000 sq ft. The operational buildings in
the DAF include five assembly cells, four high bays, and three
assembly bays. Five staging bunkers provide space for staging
nuclear components and high explosives. One of the safety features
of the DAF is its compacted earth overlay (cut-and-cover
construction) roof system. Besides weather protection, the DAF
roof provides for the filtration of escaping gases should there be
an accident involving high explosives inside DAF.
Over time, the porosity of the roof enabled water to infiltrate
the building, causing unexpected maintenance expenses and
industrial safety issues. In the summer of 2008, NNSA initiated
a project under its Roof Asset Management Program to address
the problem and awarded a contract to Building Technology
Associates (BTA). The project was originally projected at a cost of
$10 million, with an estimated completion date of September
2011. The project was completed in June at a cost of $2.2 million.
The program streamlines the management of its roofs by
implementing a single multisite construction activity – a program
that in the past would have required multiple projects.
Engineers came up with a waterproof membrane structure to
cover the entire area of the DAF roof. The engineered membrane
structure allows for the gas filtration safety system to work as
designed yet prevent water from filtering into the facility. Using
this material allowed the project to be completed more quickly
and at a substantial savings.
NNSA Praises BTA Roof Project Managers for Cost Savings