Skip to main content Skip to footer

Below-Grade Waterproofing Failures – Case Study

January 27, 2021

In order to highlight fundamental construction
errors, this paper reviews our
firm’s litigation-related evaluation of
below-grade waterproofing failures
at a university building in Northern
California (Figure 1). The nine-yearold
facility had experienced periodic groundwater
intrusion since original construction.1
Consider the front portion with the lowsloped
roof: this 70-ft.-long area encloses a partially
below-grade boiler room with perimeter
cast-in-place (CIP) concrete walls (beginning
20 in. below the at-grade level of the reddish
precast panels seen in Figure 2) extending down
to the concrete footings. Since original construction,
groundwater leakage had regularly
occurred at the floor-to-wall transitions (Figure
3) and, during heavy rain events, this room
repeatedly flooded over the top of the belowgrade
CIP walls (Figure 4).
A s s i s t e d
by a local geotechnical
firm,
we excavated
an OSHAcompliant2
test
hole 13 ft. down to the footings in order to assess
suspected waterproofing failures. Upon commencing
this excavation process, we exposed
a raggedy, ripped, and poorly terminated sheet
waterproofing membrane (Figure 5) applied
atop a layer of bentonite clay. “Bentonite is granulated
smectite clay that provides waterproofing
18 • IIBEC Interface January 2021
Figure 2 – A cast-in-place concrete wall encloses a 70-ft.-long
boiler room that serves the entire campus.
Figure 1 – Boiler room has perimeter cast-in-place concrete
walls (commencing below the reddish precast panels)
extending down to the concrete footings. (Whitish precast
concrete panels extend up from the red panels.)
capabilities by swelling to nearly 15 times its dry volume
when it absorbs water. In hydrated state, under
sufficient hydrostatic pressure, bentonite becomes a
water-repelling gel that will adhere to many different
materials–concrete, stone, wood.”3
Unfortunately, the lack of a counterflashed,
tightly secured termination bar (Figure 6) across
the top edge of the shot-pinned (using a powder-
actuated nail gun4) membrane had facilitated
rain- and irrigation-water flow behind
the sheet waterproofing.5 During our investigation,
we found below-grade holes (allegedly,
per the defense, caused by snails6) in vertical
January 2021 IIBEC Interface • 19
Figure 5 – Upon commencing the excavation process, a raggedy,
poorly attached, and extensively torn sheet waterproofing
membrane was exposed. (The missing section at the top of this
photo was extracted by our crew for sampling purposes.)
Figure 6 – The sheet waterproofing had been
“shot-pinned” to the reddish precast panels
without a termination bar that would
have served to prevent the membrane from
tearing loose during later backfilling. (Note
at the top of this photograph the holes in
the vertical caulking separating two of these
panels; also see Figure 7 and Figure 8. )
Figure 3 – Even during dry weather, groundwater infiltrated
the boiler room at floor-to-wall transitions. The water stains
at the lower cast-in-place wall (at left) resulted from leakage
occurring at the top of the concrete wall (see Figure 4).
Figure 4 – During rain events, water flooded down from the
top of the cast-in-place concrete wall, which commences 20
in. below grade. (The precast panels above are attached to
the cast-in-place concrete walls with steel brackets.)
Holes in vertical caulking
(also see Figure 7).
caulking at the reddish precast panels, as seen
in Figures 6–8. A test probe inserted into the
damaged caulking seen in Figure 8 extended
into the boiler room at the area of water staining
seen in Figure 4. Further, per the exemplar
“clump” seen in Figure 9, we noted that large
portions of the bentonite clay had washed out
of the system. Finally, as evidenced by Figure
10, we observed that the horizontal caulk joint
separating these two wall systems was not
bonded to the precast panels, providing yet
another route for water infiltration into the
boiler room.
As evidenced by Figure 11 (near the top
of the trench), Figure 12 (halfway down), and
Figure 13 (very near the bottom), contractor(s)
had extensively damaged the sheet waterproofing
membrane during the backfill process.
Groundwater infiltration through these
numerous breaches certainly contributed to
the ongoing leakage at the floor slab-to-wall
transition seen in Figure 3.
It also is important to note the absence
of any mechanism—such as a prefabricated
drainage composite or a backfilled layer of ¾-in.
“drain rock”—to:
• promote direct drainage down to the
footing drains at the bottom of the
trench, and
20 • IIBEC Interface January 2021
Figure 7 – (Same caulk joint seen in Figure 6.) The
defense argued that these below-grade holes were
caused by snails. At the upper hole, light from inside the
boiler room can be seen.
Figure 8 – Damaged caulking at transition between
the reddish precast panels (atop steel framing) and
underlying cast-in-place concrete wall. A probe inserted
into this hole readily extended into the boiler room at
the area of water staining seen in Figure 4.
Light inside the boiler room.
Figure 10 – The caulk joint between the two wall systems was not watertight due
to failed bonding at the precast panels.
Figure 9 – During excavation, we found this clump of bentonite
clay directly below the ripped membrane seen in Figure 8.
• to thereby relieve hydrostatic “head
pressure” against the extensively ripped
sheet membrane caused by groundwater
trapped in the poorly draining
clayish backfill.
ALLEGED SNAIL DAMAGE AT THE
VERTICAL CAULKING
As noted, the defense argued that the holes
seen in Figures 6–8 in the vertical caulking
at the reddish precast panels resulted from
post-construction consumption of the polyurethane
by snails. We observed no such snails (or
comparable polyurethane-eating gastropods)
at the site. Instead, we opined these joint failures
resulted from improper installation of the
caulking in a manner inconsistent with industry
standard ASTM C1193, Standard Guide for Use
of Joint Sealants,7
and the manufacturer’s
installation
instructions.
In particular,
we reported:
• the thickness
of the applied
caulking did not
meet the manufacturer’s
minimum
requirements,
and
• the absence of a required foam backer
rod that would have provided structural
support to this polyurethane caulking
as these precast panels thermally
expanded and contracted on a daily
basis.
In short, we opined that these holes most
likely had been caused by stretching of the
unduly thin caulking.
SUMMARY REVIEW OF
CONSTRUCTION ERRORS
During the ensuing litigation process, we
highlighted key errors by the contractor and its
subcontractors:
• Failure to terminate (or otherwise
satisfactorily counterflash) the sheet
waterproofing membrane above grade
in general accordance with industry
standards: “Membrane waterproofing
of all types . . . should terminate at least
8 in. above grade.”8
• Failure to install a continuous termination
bar at the top edge of the sheet
waterproofing, as required by the project
specifications and associated contract
documents.
• Failure to provide a backfilled layer of
¾-in. drain rock in accordance with the
project specifications and associated
contract documents.
• Failure to prevent damage to the sheet
waterproofing during the backfilling
process, in accordance with the project
specifications and associated contract
documents.
• Failure to provide a watertight seal at
the horizontal caulk joint (Figure 10) at
the transition from the reddish precast
panels to the underlying CIP concrete
wall.
• Failure (as evidenced by Figures 6–8)
at the precast panels to provide vertical
caulking conforming with industry
standard ASTM C1193 and the manufacturer’s
installation requirements.
(The defense provided no credible evidence
of attacks by snails.)
January 2021 IIBEC Interface • 21
Figure 11 – Multiple breaches in the
membrane due to damage during backfilling
were observed at all levels of the excavation.
Figure 12 – Contractor(s) severely
damaged the sheet membrane
during the backfilling process.
Figure 13 – (below) Near the bottom of the excavated trench,
breaches in the waterproofing still remained prevalent.
We opined during deposition that these egregious
construction errors should have been obvious
to a competent contractor. The case settled
prior to trial. The failed waterproofing system has
been successfully replaced with a liquid-applied
urethane elastomeric coating and associated
upgrades to the perimeter drainage.
REFERENCES
1. California’s Code of Civil Procedure
§337.15 provides a “statute of repose”
that bars actions to recover damages
for construction defects more than 10
years after substantial completion of
the work of improvement.
2. https://www.osha.gov/Publications/
OSHA3971.pdf
3. Henshell, J. The Manual of Below-Grade
Waterproofing Systems. John Wiley &
Sons, Inc., 2000: “A complex electrochemical
process promotes bentonite’s spontaneous
swelling in the presence of liquid
moisture. As a consequence of repulsive
ionic forces created between the microscopic
particles . . . by the water molecules,
the hydrated bentonite exerts an osmotic
or swelling pressure. To perform at peak
waterproofing efficiency, the bentonite
must be compressed under continuous
pressure . . . [of] at least 40 psf.”
4. A powder-actuated nail gun (e.g., a Hilti
gun) is used to attach materials to hard
substrates such as steel and concrete.
This technology is powered by a controlled
explosion of a small chemical
propellant charge, similar to the process
that discharges a firearm.
5. Henshell, J. The Manual of Below-Grade
Waterproofing Systems. John Wiley &
Sons, Inc., 2000: “Bentonite panels pose
a termination problem at grade. To
maintain the required lateral pressure,
they should be terminated 6 in. below
grade with a membrane flashing strip . . .
or metal cap flashing over the termination
joint. The flashing should extend 8
in. above grade and overlap the bentonite
by 6 in. Termination bars are the best
method for anchoring panels and sheets.”
(Note: some waterproofing system manufacturers
specify different dimensions for
these critical transitions.)
6. We observed no such snails (or comparable
polyurethane caulk-eating gastropods)
at the site.
7. ASTM C1193, Standard Guide for Use
of Joint Sealants. Conshohocken, PA.
https://www.astm.org/Standards/
C1193.htm.
8. Henshell, J. The Manual of Below-Grade
Waterproofing Systems. John Wiley &
Sons, Inc., 2000. (Also reference the 2016
updated second edition of this manual.)
22 • IIBEC Interface January 2021
Joel Agnello, AIA,
CDT, is a managing
partner at Avelar.
He is a Californialicensed
architect
with an extensive
background in architectural
services for
building design and
reconstruction, forensic
investigation, litigation
support, waterproofing
and building
enclosure consulting services, and code compliance
review.
Joel Agnello
Lonnie Haughton,
MCP, LEED AP,
CDT, is a senior partner
with Avelar, a
forensic architectural/
construction consulting
firm in Walnut
Creek, CA. (Founded
in Oakland in 1976
as Richard Avelar &
Associates, the firm
has rebranded and
relocated in 2020.)
Haughton is a California-licensed general contractor
and one of more than 900 individuals
worldwide currently certified by the International
Code Council as Master Code Professionals.
Lonnie Haughton
A federal judge in New York City has reinstated the Deferred Action for Childhood
Arrivals (DACA) program, which will allow undocumented immigrants brought to the US
as children to apply for work permits. US District Judge Nicholas G. Garaufis said he was
“fully restoring” the program, according to an article in Washington Post on December 4,
2020.1 The Trump administration attempted to end the program in September of 2017, and
in July of 2020 a memo was issued shortening work permits to one year.
As of 2014, 27.3% of construction workers were “Hispanic or Latino,” according to the
US Bureau of Labor and Statistics,2 giving the construction industry the highest share of
this occupational group. The judge’s ruling will also allow for DACA recipients, colloquially
called “Dreamers,” to receive two-year work permits, as opposed to the one-year permits
granted under the Trump administration’s rules.
The Center for American Progress estimates that the ruling could affect at least 300,000
immigrants. President-elect Joe Biden has said that he will push for “a path to citizenship” for
Dreamers and other undocumented immigrants.
1. Sacchetti, Maria. The Washington Post. 2020. https://www.washingtonpost.com/immigration/dacarestored-
dreamers/2020/12/04/37254908-367a-11eb-8d38-6aea1adb3839_story.html
2. Bureau of Labor Statistics, US Department of Labor, The Economics Daily, Hispanics and Latinos in
industries and occupations on the Internet at https://www.bls.gov/opub/ted/2015/hispanics-and-latinosin-
industries-and-occupations.htm (visited December 05, 2020).
Photo Credits: © Can Stock Photo / diego_cervo
Will DACA Revival Address
Worker Shortage?