By Stefan Nespoli, PEng

Setting the Stage of Uncertainty
Consider a nine-story high-rise multi-unit residential property constructed circa 1990 with a failing concrete brick façade. Due to areas of brick cracking and walls out of plumb, the owner had originally engaged a contractor to perform retrofit helical brick tie installation. For a variety of reasons—including escalating costs—the work was halted with only about 25% of the work complete.
Among our challenges would be confirming the extent and sufficiency of repair work already completed, and developing and implementing an effective retrofit solution for the fa&cceil;ade. These challenges needed to be addressed in an environment of relative uncertainty, as is the case with existing buildings. The focus of this article will be on the design and implementation of repairs, including those related to concealed conditions.
Challenge 1: Lateral Support – Brick Ties
Several original construction deficiencies related to the lateral support systems were uncovered during our initial investigation, including improperly installed and failed brick ties at steel stud backup walls and inconsistent brick tie spacing at cast-in-place concrete backup.
Wall areas with steel stud backup were designed with wire-and-plate-style ties (also referred to as unit ties). These ties consist of a steel plate connected to the steel stud backup, with a slotted connection protruding through the exterior sheathing to accommodate the wire tie, which is embedded in mortar (Figure 1). The existing tie spacing was 16 in. horizontally by 24 in. vertically. The horizontal spacing is consistent with interior metal stud spacing.
At over 50% of the locations reviewed, wire ties were installed backwards, relying only on the back-turned leg of the tie to provide lateral support (Figure 2). Furthermore, we uncovered disconnected plate connections at steel stud backups (Figure 3) at 12% of interior test openings performed.
Lateral support would be re-established with new stainless steel retrofit helical brick ties at both steel stud and concrete backup. These ties are installed by first pre-drilling a pilot hole through the mortar joint and backup (Figure 5), then drilling the helical tie through the mortar joint and into the backup structure (Figure 6). A small mortar joint repair to conceal the tie completes the installation. Suitability of this application was established through pullout testing throughout the installation process to ensure adequate lateral support at the façade.
Challenge 2: Brick Support at Shelf Angles
In addition to the lateral support concerns, our review uncovered issues related to excessive brick overhang at shelf angles. Steel shelf angles are installed at building floor slab edges. Each angle supports one story of the brick façade, and there should be engineered joints—a gap between the angle and brick sealed with a flexible sealant—at the top of each brick panel to accommodate movement. In many areas, bricks had been installed beyond the toe of the shelf angle so far that the engineered joint was instead filled with mortar to provide support to the brick above. Of course, this use of mortar also facilitated load transfer to the shelf angles below, resulting in possible overloading concerns. It’s important to note that the brick installation was an original construction defect, and that we did not observe major signs of structural distress that would indicate immediate safety concerns or risk of sudden movement.
Full exposure of all shelf angles to check overhang would have been unduly costly. Instead, we performed localized openings at shelf angle toes to measure overhang (Figure 7). We observed some locations where the shelf angle was providing inadequate support, and some locations where the shelf angle was providing no support at all (Figure 8).
Where repairs were required, shelf angles were extended and reinforced in place with welded steel extension and stiffener plates, custom-sized based on the repair location and existing overhang (Figure 9). Stiffener plate spacing was designed to accommodate existing brick coursing. Repaired shelf angles were then waterproofed, and bricks were reinstated (Figure 10).
Challenge 3: Shelf Angle Securement
During repair implementation, we uncovered a previously unforeseen condition related to shelf angle securement. At cast-in-place concrete backup wall areas, shelf angles were secured to the structure with T-slot bolts and washers/nuts. This method of shelf angle securement was not uncovered during the limited initial review, nor was it identified on the original construction drawings provided. As a result, we did not expect to uncover these bolted connections while conducting repairs.
Consistent with the workmanship from original building construction previously described, the shelf angles appeared to have been crudely modified on site during installation to accommodate bolt locations and masonry coursing. These modifications required repair, since they resulted in bolt slots that were oversized or too close to the edges of the shelf angle.
At areas with oversized bolt slots, the existing washers were not making full contact with the shelf angle around the bolt slots (Figure 11). ortunately, we were able to back off the existing nuts to provide a new, larger washer (Figure 12).
Don’t Forget About the Owner
Existing buildings are all unique in design, construction, and performance. Owners are also unique and require a customized approach and accommodations to ensure smooth project delivery. In this case, the owner included multiple non-specialist stakeholders with a high level of interest in project cost and progress.
Perhaps this should be Challenge 4: Owner Communication and Involvement. Despite identifying creative, minimally invasive, safe solutions and opportunities for cost savings in design, unforeseen concealed conditions and uncertain repair quantities resulted in cost forecast fluctuation throughout repair implementation. Owner communication involved development of non-technical short-form reporting and multiple meetings and presentations to educate the ownership group on required repairs.
Existing buildings are not always beautiful in design or architecture, but there can be an elegance in design and project implementation that will often define project success, as it did here.
Stefan Nespoli, PEng, is a project manager with Edison Engineers Inc., based in Ontario, Canada. He has a technical background in construction, contract administration, engineering design, and technical reporting for existing buildings. His experience covers all typical aspects of building enclosure repairs, structural restoration, and capital planning. Nespoli’s focus remains on working with clients to develop and implement repair strategies that align with their objectives and financial constraints.
I learned a great deal about how lateral supports are of the utmost importance when using bricks as main material for your building exterior. I assume that residential building owners want to maintain the cleanliness of their building’s exterior to attract more future tenants. If I was in the business, I’ll consider hiring a tuckpointing service to check if the bricks’ exterior is still intact and to check if we need to replace them soon.