Skip to main content Skip to footer

Screw The Deck And The Welds

May 15, 2007

Steel roof deck can be secured
to structural bar joists using
“puddle” welds, powder-actuated
pins, pneumatically driven
pins, or self-drilling
screws. It is not unusual to
find that the consistency of deck-to-joist
welding is poor. Some welds, by some
welders, are good. Some would argue, however,
that most welds are inferior. Although
many welders can join plate, beams, angles,
etc., satisfactorily, they just cannot weld
steel deck correctly. The basic problem is
that it is difficult to weld relatively thin steel
decking (e.g., 22 gauge is 0.0295 inches
thick) to the top chord angle of a steel joist
(which may be ±0.25 inches thick). This
applies to certified welders as well as noncertified
welders. The quality
of the weld is a function
of the condition of rods, the
type of rods being used, and
most importantly – the
delivery amperage.
At the intersection and
lap of four pieces of deck
(which occurs at each corner
at each end of each
piece of deck), weld fusion
is seldom optimum. To get a
good weld, the welder must
compress all four pieces of
the deck at the same time
snugly to the joist or beam.
This is to eliminate any gap
between individual pieces of
deck or between the bottommost
piece of deck and
the joist or beam. Failure to
do this every time results in a gap and,
thus, a deficient weld.
On almost every project, the inspector
observes some welds that “appear” sound
one day but that will have sheared off a
week later. One can actually hear welds failing
on a deck in the early morning as the
sun heats the deck up and it expands,
shearing a deficient weld. If this can happen
within only a few days of installation, it can
happen over the life of the deck as well. This
affects the integrity of the roof deck, the
bracing system, and the roofing system
above the deck.
“Blow-through” or “burn-through” of
welds has always been a problem with arc
welding on a steel deck. Blow-through
occurs when the electrode burns through
the deck to air, not to a structural member.
When this happens, the conscientious
welder moves over a few inches and tries
again. If the weld hits steel that time, the
job is done. If not, the electrode is moved
over a few more inches and tried again. This
leaves one or more burn holes in the deck
that must be coated.
All welds should be wire-brush-cleaned
and painted before the roof is installed. All
burn-throughs should also be painted and
then, in some fashion, sealed or covered.
Some designers/specifiers call for pieces of
duct tape to be placed over the holes. That
is not a very effective repair, as the tape will
soon lose adhesion and peel off. Few techniques
are better, other than maybe selfadhering
foil tape.
Generally, the burnholes
are left. Now we all
know that roofs never leak,
but God forbid, if they do,
that the water runs the
flutes of the deck and then
drips into the building at
every blow-through down
slope of the leak point. The
same can occur with a
screw if it is extracted; however,
the hole is smaller,
and there seems to be a
tendency for screw applicators
to strike a line to stay
on steel. Many inspectors or
observers just haven’t seen
too many “iron workers” do
that.
Welding galvanized deck
Photo 1 – Burn-through in the top flange of the deck that was not repaired. breaches the galvanizing at
44 • I N T E R FA C E OC T O B E R 2007
the most crucial point, the point of attachment.
The spot painting is seldom as good
as the galvanizing. This is probably the
most important concern one can have. If
the welder goes back and wire brushes the
slag from the weld and applies a proper
coating, the labor cost of the deck installation
can nearly double.
Screwing the deck may be a better
option for securement for several reasons,
including the following.
With minimal training, a laborer can
properly and consistently install screws
using relatively inexpensive equipment.
Welders seem to think installing screws is a
little beneath them and want to do “what
they’ve always done,” which is to weld.
Screws are either a “go” or a “no-go”
installation. There is little chance of a deficiently
installed screw being overlooked.
The most likely deficiency that may get
overlooked is where the screw is in place
and flush with the top of the deck but
where it never penetrated the upper
chord of the joist. For that reason, the
inspector should test some screws at random.
A socket on a long speed-handle,
ratchet, or pull-bar makes this an easier
task.
The same screw gun may be used to
install the side lap fasteners and the joist-
Photo 2 – Missing weld at critical
juncture of four pieces of deck that
was repaired with screws. The
leftmost weld has sheared or failed.
Photo 3 – Really poor-quality weld with blowthrough
on right side; second attempt was
successful, though it is not painted yet.
􀀲􀁑􀁏􀁌􀁑􀁈 􀀨􀁇􀁘􀁆􀁄􀁗􀁌􀁒􀁑􀁄􀁏 􀀳􀁕􀁒􀁊􀁕􀁄􀁐􀁖
􀀤􀁗􀀃􀁜􀁒􀁘􀁕􀀃􀁒􀁚􀁑􀀃􀁓􀁄􀁆􀁈􀀏􀀃
􀁒􀁑􀀃􀁜􀁒􀁘􀁕􀀃􀁒􀁚􀁑􀀃􀁗􀁌􀁐􀁈􀀏􀀃􀁄􀁗􀀃􀁜􀁒􀁘􀁕􀀃􀂿􀁑􀁊􀁈􀁕􀁗􀁌􀁓􀁖􀀃􀀑􀀑􀀑
􀁚􀁚􀁚􀀑􀁕􀁆􀁌􀀐􀁈􀀐􀁏􀁈􀁄􀁕􀁑􀁌􀁑􀁊􀀑􀁒􀁕􀁊
OC T O B E R 2007 I N T E R FA C E • 4 5
Photo 4 – Broken weld at toe of upper
piece of deck (piece on left).
to-deck screws, so there is no need for extra
equipment. The torque settings do have to
be adjusted between installing the two types
of screws, but that requires only a click on
the screw gun.
It is important for the installer to use a
quality screw to fasten the deck. Some manufacturers
are better than others and produce
consistently high-quality screws, while
some do not.
Most specifications call for deck-to-joist
screws to be self-drilling No. 12 – 24 x 1-
1/4-inch long.
That consistency is often lacking in
specs regarding the side-lap fasteners.
Some say the side laps should be made with
No. 10 screws, and others, No. 12 screws. A
No. 10 screw is more easily over-driven and,
as a result, requires a lot of drop-back and
correction work. This may or may not take
place. The pitch of the screw thread is critical
for proper engagement of side-lap
screws. If the pitch is too fine, the screw can
be more easily overdriven, galling or stripping
the threads. Most experienced specifiers
require No. 12 – 24 x 3/4-inch long
screws for side laps (or for that matter,
whenever sheet metal is attached to sheet
metal and strength is important).
Another benefit of securement using
screws is that work can progress in lessthan-
ideal weather, as long as the screw
guns are properly grounded and provided
with a ground-fault interrupter. An option
in inclement weather is to use battery-powered
screw guns, but many installers have
found these guns discharge rather quickly
under such loading.
For these reasons, many experienced
consultants and engineers advocate the use
of screws for both deck-to-joist and sidelaps
and recommend that the specs not be
changed to allow welding.
Check the deck installation closely and
bring deficiencies observed immediately to
the attention of the construction team.
Screw the deck, don’t weld it!
Richard (“Dick”) Canon is a registered professional engineer
in seven states and was one of the inaugural recipients of the
Registered Roof Consultant classification in 1988. Dick
became a Fellow of the Institute in 1987 and received the second
Herbert Busching Award from RCI in 1996. Dick and his
wife Connie celebrated their 40th anniversary recently. The
couple started Canon Consulting & Engineering Co., Inc. in
1983 and have their office in Moore, SC. Dick has been a
speaker/presenter at many of RCI’s conventions and symposia.
He has a driven interest in wind- and drainage-related issues and is a manufacturer
of a negative pressure (uplift) chamber that is quickly becoming a standard in the
industry for high-pressure tests. Dick says among his most rewarding and fulfilling
experiences have been serving as first vice president of RCI in 1983 and 1984 and president
of RCI in 1985 and 1986.
Richard (“Dick”) Canon, FRCI, RRC, PE
􀀥􀁘􀁌􀁏􀁇􀁌􀁑􀁊 􀀨􀁑􀁙􀁈􀁏􀁒􀁓􀁈
􀀷􀁈􀁆􀁋􀁑􀁒􀁏􀁒􀁊􀁜
􀀱􀁒􀁙􀁈􀁐􀁅􀁈􀁕 􀀛􀀐􀀜􀀏 􀀕􀀓􀀓􀀚
􀀥􀁒􀁖􀁗􀁒􀁑􀀏 􀀰􀀤
􀀶􀁜􀁐􀁓􀁒􀁖􀁌􀁘􀁐 􀀕􀀓􀀓􀀚
􀀛􀀓􀀓􀀐􀀛􀀕􀀛􀀐􀀔􀀜􀀓􀀕
􀁚􀁚􀁚􀀑􀁕􀁆􀁌􀀐􀁒􀁑􀁏􀁌􀁑􀁈􀀑􀁒􀁕􀁊􀀒􀁖􀁜􀁐􀁓􀁒􀁖􀁌􀁘􀁐􀀑􀁋􀁗􀁐􀁏
46 • I N T E R FA C E OC T O B E R 2007