Innovative Facade Repair Solutions: 3-D Laser Scanning and Project Team Collaboration

May 15, 2013

Innovative Façade Repair Solutions:
3-D Laser Scanning and Project
Team Collaboration
Matthew Kutzler, PE, CDT
Facility Engineering Associates
12701 Fair Lakes Circle, Suite 101, Fairfax, VA 22033
Phone: 703-591-4855 • Fax: 703-591-4855 • E-mail: matt.kutzler@feapc.com
2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3 K u t z l e r • 1 8 7
Abstract
Design and implementation of building repairs can present challenges when dealing
with existing conditions. Access difficulties, time and budget constraints, etc. hinder observation
and understanding of conditions. This session will share project-related experiences
that led to innovative approaches in two specific instances. Participants will learn how 3-D
laser scanning technology was used to render models of elevation planes for detection of
brick movement in consideration of retrofit masonry ties. The speaker will also explore the
collaborative team process used to address an atypical brick-support and flashing issue that
was a persistent source of water infiltration.
Speaker
Matthew Kutzler, PE, CDT — Facility Engineering Associates – Fairfax, VA
Matth ew Kutz ler is a project manager who has participated in over 200 projects
while at Facility Engineering Associates in Fairfax, VA. His experience with existing facilities
includes evaluation and repair of waterproofing, masonry and stucco building enclosures,
balconies, roofing systems, parking garages, and asphalt and concrete pavements. His primary
focus has been working with property managers and owners to develop and implement
repair and maintenance plans that make sense for the life cycle of each facility. Kutzler has
authored several articles related to construction contract administration, façade and parking
garage maintenance and restoration, and hazardous materials testing.
1 8 8 • K u t z l e r 2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3
Have you ever passed by a building
and wondered, “How was that ever constructed?”
Your mind wanders through all
of the planning and coordination, equipment
and materials, labor force, and leadership
required to accomplish this feat. You
stand in awe at the architectural elements
and detailing or sheer magnitude of size. If
you’re like me, these thoughts have crossed
your mind many times.
Inevitably, all of those structures will
need some sort of repair, restoration, and
maintenance as they move through their
service lives and materials deteriorate. Now
think about another question: How often
have you wondered how a building will be
accessed for repairs? A busy sidewalk shut
down for overhead work? A large cooling
tower replaced on the roof? I’m guessing
this isn’t thought about nearly as much as
original construction accomplishments.
Restoration contractors and consultants
are routinely challenged with these questions.
The presence of finishes, access difficulties,
time and budget constraints, etc. all
hinder observations and understanding of
potential repair conditions of existing buildings.
In order to overcome these hurdles,
all members of a project team must work
in unison. Owners, property managers,
contractors, consultants, and others have
specific roles that overlap in many areas. No
ideas on how to accomplish goals should be
off the table.
A recent repair project performed at an
urban office building highlighted the use
of an atypical assessment approach (threedimensional
laser scanning technology) and
the importance of project team collaboration
in addressing a challenging throughwall
flashing repair.
Just the (Background ) Facts
In keeping with several other metropolitan
areas and jurisdictions, Philadelphia
had adopted an ordinance for scheduled
façade inspections to be performed by a
Pennsylvania-licensed professional engineer
or registered architect.
The intent was
to document building
wall components
that were in need of repair or potentially
unsafe conditions, what those conditions
were, and how/when they should be
addressed to consider the building façade
to be in “safe” condition.
Based on the specified ordinance schedule
and age of the building, the façade
had to be inspected and commented upon
no later than the end of June 2012. To
comply with the ordinance, it was thought
that a building façade assessment could
be performed and recommended repairs
completed prior to the specified deadline—a
plan that building owners were determined
to follow.
The aforementioned property was a
20-story commercial office building that
was constructed in 1970 in the center city
of Philadelphia (see Photo 1). The rectangular
structure consisted of a concrete frameand-
brick veneer at each of the four elevations.
Vertical mechanical chases of alternating
depths projected outward from the
building, creating a recessed appearance at
narrow window bays between chases (Photo
2). The building was uniform throughout its
height, terminating at its peak with a wall
around the perimeter that sloped toward
Innovative Façade Repair Solutions:
3-D Laser Scanning and Project
Team Collaboration
2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3 K u t z l e r • 1 8 9
Photo 1 – Typical façade overview of subject building.
Photo 2 – Top of mechanical chase
projections and sloped wall.
the main roof. There was a large mechanical
penthouse near the center of the roof.
We Need to Add Wall Ties
Throughout the Façade ?
According to original construction drawings,
corrugated galvanized metal ties were
to be installed every three to four brick
courses vertically. The specified horizontal
spacing was unclear at window bays
but was to be one tie into each side of the
projections (two at the front of the larger
projections).
In the early 1990s, a repair project was
undertaken to address various conditions
related to deterioration and water infiltration.
During this project, large areas of brick
were removed at the top of the mechanical
chases. Photographic documentation and
past reporting indicated that wall ties were
largely absent at areas where brick was
removed. While ties were installed at these
repair areas, no additional ties appear to
have been installed elsewhere.
There was speculation from past consultants
that a perceived lack of wall ties
necessitated widespread installation of retrofit
masonry ties. Based on the height
of the building and a perimeter length
approaching 400 linear feet, performing
such repairs would be costly, disruptive,
and time-consuming. As a result, one of the
central goals to the façade assessment was
to assess the potential need for additional
masonry ties; but what was the best way to
accomplish this?
When Is Enough Enough ?
Façade assessments can include a variety
of aspects such as past document
review, visual observations, and exploratory
openings. Visual observations are typically
performed from swing stages or other lifts,
terraces or balconies, roofs, and surrounding
grounds—perhaps with binoculars.
These methods all have two things in common:
human observation and perception.
Two people viewing the same conditions
can have differing opinions on what they’ve
seen, based on past experience or knowledge,
not to mention weather conditions,
fatigue, etc. Without a definitive way to
measure or calculate a deficiency, there is
the potential for human error.
Another aspect to consider is the level
of assessment performed. How many swingstage
drops or exploratory openings are
appropriate? At what point can an assessor
be comfortable with his or her findings?
Conditions can vary widely, and what is
observed in one area may not necessarily be
the same condition present at another.
In the case of assessing the state of
masonry ties at the subject building, visual
observations from the ground, roof, and
several swing-stage drops were performed to
gain an initial understanding of conditions.
The masonry elements and mortar joints
were generally in fair condition. Evidence
of bulging or other movement of the brick
veneer was not observed below the top floor.
However, it appeared that the brick veneer
at mechanical chase projections had shifted
outward at the top floor in some locations.
The movement was minimal in this area,
but visually apparent.
Exploratory openings indicated a lack of
brick ties, but the openings were quite small
compared to the overall façade area. A bore
scope was able to indicate that some ties
were employed, but use of the instrument
was difficult due to mortar droppings within
the cavity, which is common in masonry
walls.
Considering the age and service life of
the building, observed conditions, and no
reports of falling brick, initial indications
were that the apparent lack of ties had
not adversely affected the brick façade.
However, there was enough information to
show that ties were likely needed in select
areas. Determining which areas were candidates
for retrofit masonry ties would be
the challenge.
The Technology of the
Future
It was apparent that visual observations
alone would not be sufficient for the project
requirements related to masonry wall ties.
While an educated estimate could be provided
for the number of wall ties to be installed,
it had the potential to be somewhat or
even largely inaccurate, and the owner’s
budget could be exceeded. This wouldn’t
be confirmed until the project had already
started and a swing stage was erected at
each façade drop. Also, the construction
schedule could be adversely affected with
an unexpected increase in quantity, leading
to unhappy tenants and extended closure of
facility areas and public sidewalks. Finally,
the contractor would have little to
no direction as to where to install
the ties; it would ultimately be
left, in large part, to his judgment.
Accessing all areas of the
façade during the assessment
phase did not make sense financially,
as it would cost far more
to refine the number of expected
ties than it would to actually
install them. Even with unparalleled
access, the quantity of ties
would be subjective, based on the
assessor’s opinion. A finite, quantitative
assessment was sought
to alleviate these possible issues.
1 9 0 • K u t z l e r 2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3
Photo 3 – Typical scanner
set up on tripod.
Photo 4 – Typical
scanner keypad and
display screen.
The answer was found in three-dimensional
laser scanning.
Laser scanning involves the gathering
of millions of data points from the surface
under consideration (the brick façade) in
order to manifest the data into lines and
planes for documentation of as-built conditions.
The process is similar to traditional
surveying, with a laser-scanning device taking
the place of the theodolite.
Using traditional surveyors’ methods,
a baseline of reference is established. This
baseline (or control) can be the sidewalk at
the base of the building, a nearby benchmark,
or another set point that will have a
high likelihood of remaining fixed for future
scans. The baseline is linked to a global
positioning system (GPS), so that all points
are linked to the global reference. Once the
baseline is set, the scanning device is set
up on a tripod, attached to a computer, and
takes a 360-degree view of the items around
it (Photos 3 and 4). Everything is captured,
including trees, pedestrians, cars, and even
steam in the air. After data acquisition is
complete, the usable point data must be
sorted from the noise. The device measures
the “time of flight” of the laser from the time
it leaves the device to the time it bounces off
of a surface. With the speed of light being a
known constant, the time of flight is then
converted to a distance; that distance is
then referenced to the baseline and, in turn,
given a GPS position for every point on the
surface. Accuracy of the scan will depend
on line of sight, angle of incidence, and the
density of the scan.
The electronic data output can be
catered for the desired use, such as production
of a highly detailed elevation drawing in
CAD, and is accurate within a thousandth
of a foot. The data can be used for comparative
analysis from year to year to look for
trends in movement. Some scanners even
have the ability to link high-resolution digital
photographs to the point cloud data.
In the case of the subject building, the
scanning was used to establish a uniform
plane at each elevation. Once a base plane
was established, limits could be placed on
the point data to determine their location
relative to the plane. For example, an analysis
could be performed to identify any point
that is more than ½ inch away from the
base plane. These points, gathered together,
would represent brick movement away from
the building and a possible area where retrofit
masonry wall ties should be installed
(Photo 5).
With this data in hand, locations where
brick movement had occurred were identified
on elevation drawings and included
in the construction documents for repair.
Detailing related to spacing for retrofit
masonry ties was also included, providing
clear direction to the contractor as to
where the ties should be installed. Ties
were not unilaterally installed everywhere at
unneeded locations, and a contracted quantity
of ties was established that was largely
adhered to during the course of work.
It should be noted that the laser scanning
was not intended to be a replacement
for professional engineering judgment, but
rather supplemental to it. Several areas of
potential concern were identified during the
scanning and were subsequently reviewed
in conjunction with the contractor during
the project. Repairs were intelligently, not
blindly, performed at these areas.
Laser scanning provides a safe and
effective way for gathering repeatable data
for future comparisons. Beyond the façade
repair project, the point data could be used
as a baseline for movement detection in
the future. When a follow-up assessment
is required to fulfill the local façade ordinance
in five years, scanning can again be
performed to assess increased movement at
previously identified areas or new deviations
at others.
While there are added costs associated
with laser scanning, these could be offset in
reduced up-front assessment fees through
less required staging and fewer professional
hours. In addition, as future repairs are
recommended, the point data comparisons
could result in more accurate construction
documents, concentrated repairs where
needed, and cost savings to the owner in
avoiding unnecessary repairs and possible
change orders.
How Does Water Always Find
a Way in ?
While the issue related to masonry ties
had been resolved, a second challenge awaited
with the waterproofing detail at the
top of the building. The mechanical chase
projections that extended the height of the
building were terminated with waterproofing
membrane and precast concrete caps. A
2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3 K u t z l e r • 1 9 1
Photo 5 – Drawing provided to contractor (left) depicting retrofit tie installation
locations (superimposed on original building elevation drawing). Scan image (right)
showing variation from analysis plane. The circled area is just one example of
locations that were out of plane and then transposed to the bid documents.
sloped brick parapet wall extended from the
caps toward the penthouse at the main roof.
A wood wall was constructed on the backside
of the sloped wall, creating a triangularshaped
cavity around the perimeter of the
main roof. A shelf angle supported the sloped
brick at the bottom of the inclined surface.
Over time, water infiltration and efflorescence
issues arose at the top floor of the
building. As part of the aforementioned repair
project performed in the early 1990s, the
lower eight brick courses of the sloped wall
were removed above the shelf angle to install
through-wall flashings. Flashing was also
installed at a five-sided brick wall where the
sloped wall transitioned to the vertical façade.
Weep tubes were installed at this lower flashing.
A similar detail was employed at projections,
with the flashing extending below the
setting bed and precast concrete caps.
Follow-up repairs were completed in
2000 at the north elevation only and consisted
of masonry work at the sloped wall
and further repairs at the precast caps.
A similar scope of planned repairs was
slated for the south elevation, but it was
later deemed unnecessary and canceled.
However, water and efflorescence issues
continued to plague the top floor.
Information Just Out of
Reach
Due to the configuration of the building
and projected areas, access to the sloped
wall proved difficult. The swing stage was
several feet away from the area in question,
and observations were limited to visual
only, not exploratory. Even if this area could
have been accessed effectively, the swing
stage was positioned nearly 270 feet in the
air above crowded urban streets and an
adjacent school. Removal of brick in a sufficient
quantity for observation under these
conditions could potentially be unsafe without
overhead protection or closure of areas
below, which was an undesirable scenario
for the assessment. Putting these measures
in place could result in double or triple the
cost of the assessment.
Based on detail drawings available from
original construction and past repairs, it
appeared that sufficient information was
available to specify waterproofing details to
address ongoing water infiltration. The past
scope of work was used as a starting point,
as it appeared to be reasonably effective at
the north elevation, though some issues
remained.
Both the former and new designs called
for removal and replacement of through-wall
flashing at the base of the sloped wall, both
on the steel angle and directly below at the
five-sided transition brick. Several improvements
in the design were made (Photo 6).
Cell vents replaced weep tubes (which had
frequently clogged), and were spaced at a
greater frequency. A stainless steel flashing
with a drip edge was specified for the transition
brick in an effort to keep water away
from the brick face below and address the
presently unsupported, sagging condition of
the membrane flashing within the brick cavity.
Lastly, the shelf angle at the base of the
sloped wall was tilted back such that any
water traveling down the flashing behind
the wall was effectively trapped at the lowest
point of the angle. Holes were to be drilled
into the base of the shelf angle to allow
moisture behind the brick veneer to follow
the new flashing down to the stainless steel
termination below.
Constructability was of some concern,
though previous repairs were completed in
a similar setting. While multiple flashing
sections and terminations were not ideal
(including sealing each hole in the angle),
options appeared limited due to existing
conditions.
1 9 2 • K u t z l e r 2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3
Photo 6 – Through-wall flashing detail at base of sloped wall.
Two Heads Are Better Than
One
As design gave way to bidding, contracting,
and preconstruction activities, the time
had come to put the specified detail
into practice. Work began at the
initial swing-stage drops, and the
contractor naturally had questions
related to work as points were clarified
and expectations set in the field.
The repairs proceeded through
a mock-up process but at a slowerthan-
desired pace due to a few issues
(Photo 7). To maintain support for
the sloped brick face above, throughwall
flashing was being installed in
short runs. The condition of the
shelf angles was slightly worse than
anticipated, with some loss of cross
section, necessitating removal of
several angle sections for replacement.
The lintels that could remain
were cleaned, primed, and painted in
place, but drilling of holes for water
to pass through was difficult for the
crew to achieve under the circumstances.
Though the specified detail could
be achieved, it became apparent
that improvements could be made to
speed production and create a better
end result with fewer points of water entry.
Collaboration with the contractor was going
to be important for an effective solution.
Working as a team, an exchange of
ideas led to several changes in the
flashing approach and creation of a
new mock-up. Since several angles
required removal for replacement, a
method to support the brick above
was required. After removal of three
courses of brick and the existing
flashing and angle, the contractor
placed small, temporary steel angles
at the bottom of the remaining brick,
which were in turn supported with
clips fabricated to slide onto the
shelf angle fasteners and abut the
temporary angle above (Photo 8). The
steel angle could now more easily be
prepared, primed, and painted at the
roof rather than in place.
With removal of the shelf angles,
it became apparent that a one-piece
flashing could be installed at the
base of the sloped wall and extended
below the five-sided brick and precast
caps at the top of the mechanical
chase projections (Photo 9). This
was more ideal than the detailed
two-piece flashing. Doing so also
removed the need for holes in the
bottom of the shelf angles and the
associated waterproofing that would need to
be performed at each opening. The amount
of termination detailing was substantially
2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3 K u t z l e r • 1 9 3
Photo 7 – Conditions at the base of the sloped wall created difficulties in addressing
lintels and installing new through-wall flashing.
Photo 8 – Sloped brick supported with temporary steel and fabricated clips at angle
fasteners.
reduced, minimizing future risk for
waterproofing failures.
Installing the through-wall
flashing behind the shelf angles as
opposed to over top maintained the
previous dam condition, as water
traveling down the flashing would
encounter the top of the steel and
eventually settle at the low point
of the tilted angle. To address this,
an offset was created between the
flashing and angles by placing two
washers on the fasteners prior to
reinstallation of the angles. The
minimal space could accommodate
water flow behind the angle but
was slender enough to prevent
angle rotation.
End of the Road
Despite the issues encountered
related to retrofit masonry ties and
installation of an effective waterproofing
detail at a problematic area, the project was
completed successfully (Photo 10). Threedimensional
laser scanning led to a costeffective
effort for concentrated installation
of retrofit masonry ties, and project team
collaboration enhanced a difficult waterproofing
detail while improving efficiency
of installation. The project was completed
in October of 2011, and there has been no
reported water infiltration or the return of
efflorescence at the areas addressed.
1 9 4 • K u t z l e r 2 8 t h R C I I n t e r n a t i o n a l C o n v e n t i o n a n d T r a d e S h o w • M a rc h 1 4 – 1 9 , 2 0 1 3
Photo 9 – Revised through-wall flashing
detail following collaboration with
contractor.
Photo 10 – Completed appearance
at sloped wall, five-sided brick,
and capstone. Contrast with soiled,
unrepaired appearance below.