Skip to main content Skip to footer

A Burning Question: Fire Testing of a Window Wall System With Spray Foam Insulation

November 18, 2020

A Burning Question:
Fire Testing of a Window
Wall System With
Spray Foam Insulation
Stéphane Hoffman, PEng
Morrison Hershfield Corporation
600 Stewart Street, Suite 200, Seattle, WA 98101
(206) 268-7370 | shoffman@morrisonhershfield.com
Nonpresenting Coauthor
David Kayll, PEng
No v e m b e r 9 , 1 0 , 1 2 , 1 6 , 1 7 , 1 9 , 2 0 2 0 | 2 0 2 0 I I BE C B u i l d in g E nc l o s u r e S y m p o s i u m Ho f f m a n | 2 3
ABSTRACT
SPEAKER
Stéphane Hoffman, PEng
Morrison Hershfield Corporation | Seattle, WA
With a master’s-degree-level education that combines structural engineering, building
science, and architecture, Stéphane Hoffman brings a well-balanced consulting approach to
the building enclosure, blending scientific analysis with an understanding of aesthetics considerations.
He is particularly adept at providing innovative design concepts and construction
alternatives that provide value by improving durability and increasing energy efficiency. As
a key technical leader at Morrison Hershfield, Hoffman has worked on projects throughout
North America. He leads the company’s Building Science Analytics Group, combining façade
engineering, energy modeling, and enclosure component modeling to assist teams in designing
high-performance buildings.
Nonpresenting Coauthor: David Kayll, PEng
Window wall assemblies are a popular exterior wall assembly for high-rise residential apartment buildings. These
systems are economical because of efficiencies of factory assembly and rapid installation on site. With the exception
of components deemed “minor”—including thermal breaks in the aluminum frames, sealants, etc.—window wall
assemblies are considered non-combustible and, therefore, compliant with building code requirements to limit the
vertical spread of fire. The thermal performance of window wall systems is relatively weak, limited by thermal bridging
through the frames. Thermal performance can be increased with two-component, closed-cell polyurethane foam insulation
spray-applied directly to the spandrels. However, the insulation is combustible and too large to be considered a
minor component; so, the entire assembly is often considered to be combustible. This presentation describes full-scale
fire exposure tests under CAN/ULC-S134, the equivalent to NFPA 285. The outcomes are used to assess if such walls
are combustible. The paper will also consider if the test results can be applied to other window wall assemblies and to
assess compliance with building codes in the United States, where Canadian window wall systems are often used.
2 4 | Ho f f m a n 2 0 2 0 I I BE C B u i l d in g E nc l o s u r e S y m p o s i u m | No v e m b e r 9 , 1 0 , 1 2 , 1 6 , 1 7 , 1 9 , 2 0 2 0
INTRODUCTION
The use of foam insulation as part of
building enclosures has received increased
scrutiny in recent years, and numerous
enclosure assemblies have been successfully
tested to CAN/ULC S1341 or its U.S.
counterpart, NFPA 285.2 However, most
of these assembly-specific tests have been
performed on stud-wall assemblies. The
following paper outlines the results of
testing spray-foam insulation inboard of a
unitized glazing system and demonstrates
that these assemblies can also meet the
requirements of these standards.
BACKGROUND
In recent decades, the use of unitized
glazing systems has become increasingly
common—especially for high-rise construction.
The improved quality from off-site
assembly of these manufactured systems,
along with their ease of installation and
advantage in terms of shortened onsite
construction schedules, continues to drive
the trend toward modular construction.
The opaque panels in unitized glazing systems
have traditionally been insulated with
mineral-wool insulation installed within the
aluminum frame behind a glazed spandrel,
a metal panel, or some other opaque cladding.
The interior face of the mineral wool
is typically flush with the interior frame
and finished with a foil facer or a galvanized
sheet-metal back pan.
Increasing code requirements for energy
efficiency of opaque wall assemblies has
led to the common practice of providing
an additional layer of insulation inboard of
the unitized glazing system. A recent study
by Neil et al.3 has shown the impact of the
thermal bridging through the aluminum
framing and, especially, the continuous
vertical mullions on the effectiveness of
the insulation within spandrel assemblies.
While another paper by Hoffman4 based on
the results of 3-D thermal modeling for the
Building Envelope Thermal Bridging Guide5
has outlined the limited thermal improvement
of insulating inboard of unitized glazing
systems, the practice remains common
and for some systems still provides an
improvement over insulation only within
the spandrel assembly.
In colder climates, however, the practice
of insulating inboard of the unitized
glazing systems raises the concern of condensation
on the surfaces of the glazing
system now shielded from exposure to the
interior heat source. This risk is further
increased if the assembly inboard of the
unitized glazing system is not airtight and
the interior insulation is not in continuous
intimate contact with the interior face of
the unitized glazing system. The increased
risk of condensation is especially elevated
in residential buildings, with their higher
levels of interior humidity, limited ventilation,
and, increasingly, a lack of perimeter
heating.
WHY SPRAY-FOAM INSULATION?
The application of spray foam on the
inboard face of glazing systems has been
used in recent years as one means of mitigating
the risk of condensation. The sprayfoam
insulation easily conforms to the
irregular surfaces of the unitized glazing
system, forming a monolithic, airtight, and
vapor-resistant insulation layer, significantly
reducing the potential that interior
air could come into contact with the colder
surfaces of the unitized glazing system. It
also has the secondary benefit of providing
improved acoustical performance. While
the foam insulation is typically separated
from the interior by an appropriate
layer of gypsum sheathing, concerns of
fire propagation have been raised about
its performance in the event of a fire that
breaches the glazing and leaps up the exterior
of the building. In theory, the mineral
wool insulation in the spandrel assembly
should provide adequate protection from
the flames on the exterior of the building.
However, the fact that the aluminum framing
interrupts the mineral wool insulation
has been raised as a point of concern. This
led to testing of a unitized window wall
with spray-foam insulation outlined below
for a recent high-rise residential tower
in Canada to CAN/ULC-S134, Standard
Method of Fire Test of Exterior Wall
Assemblies.
Under Canadian codes, the use of
combustible components, such as foam
insulation, in buildings required to be of
non-combustible construction, is permitted
where the building is sprinklered and the
assembly meets the requirement of CAN/
ULC-S134 on the basis that the materials
are deemed to insignificantly contribute to
fire growth and spread.
A Burning Question:
Fire Testing of a Window Wall System
With Spray Foam Insulation
No v e m b e r 9 , 1 0 , 1 2 , 1 6 , 1 7 , 1 9 , 2 0 2 0 | 2 0 2 0 I I BE C B u i l d in g E nc l o s u r e S y m p o s i u m H o f f m a n | 2 5
In recent decades, the use of
unitized glazing systems has become
increasingly common—especially
for high-rise construction.
CAN/ULC S134 VS NFPA 285
Both CAN/ULC-S134, Standard Method of Fire Test of Exterior Wall Assemblies, and NFPA 285, Standard Fire Test Method for Evaluation of Fire Propagation Characteristics of Exterior Wall Assemblies Containing Combustible Components, provide a measure of how an exterior wall assembly performs when exposed to a window fire plume under post-flashover fire conditions; however, the test apparatus, fire exposure, and acceptance criteria are significantly different.
The stated intent of CAN/ULC-S134 is to determine the comparative burning characteristics of exterior wall assemblies by evaluating the following: a) fire spread over the exterior surface; b) heat fl ow from the fi re plume to the exterior surface; and c) fire spread within the test specimen.
The CAN/ULC-S134 test standard utilizes a three-story concrete block backup wall (minimum 6 m by 10 m) with a large window opening (nominally 2.5 m by 1.4 m) centered at the ceiling of an adjacent burn chamber, with gas pipe burners distributed symmetrically throughout the chamber no higher than halfway between the floor and the bottom sill of the window opening. In CAN/ULC-S134, the gas-flow rate is linearly ramped up for 5 minutes, held at a steady state (nominally 120 g/s calibrated to achieve a specified heat flux) for 15 minutes, and then linearly decreased for a 5-minute period to 0. Flame height is observed, and heat flux measurements at 3.5 m above the window opening are observed for up to 1 hour from the start of the test.
A wall assembly successfully passes the CAN/ULC-S134 test if the visible flaming above the window opening is not more than 5 m and the average heat flux measured at 3.5 m above the window opening is not more than 35 kW/m2 for the duration of the test.
NFPA 285, Standard Fire Test Method for Evaluation of Fire Propagation Characteristics of Exterior Wall Assemblies Containing Combustible Components, evaluates the ability of exterior wall assemblies with combustible components to resist flame spread over the exterior face of the assembly, within the assembly, and at the interior surface of the curtainwall assembly to the next story, and the ability to resist lateral flame spread to adjacent compartments.
The NFPA 285 test standard utilizes a two-story test apparatus (with stacked rooms) to measure the performance of a test specimen 4.1 m wide by 5.3 m tall, with a window opening of 1.98 m by 0.76 m adjacent to the lower room. Two gas pipe burners are used in the NFPA 285 test: One is located centrally within the lower test room approximately 0.8 m from the floor, and the second burner is placed near the top edge of the window opening outside the test room. In NFPA 285, prescribed gas-flow rates for natural gas step up at five-minute intervals up to 30 minutes. Prescribed gas-flow rates for natural gas step up at five-minute intervals up to 30 minutes into the test for both the room and window burners, at which time the gas supply is shut off and observations are stopped. Flame propagation and temperature measurements are observed for the duration of the 30-minute test.
Like CAN/ULC-S134, acceptance criteria for NFPA 285 includes conditions for visual flaming (not greater than 3.05 m above the window opening or 1.52 m horizontally from the center line of the window opening). NFPA 285 does not consider heat flux as a performance measure, but considers temperature rise instead. Acceptance criteria related to temperature conditions at the external face, interior combustible components, air cavity, and within the second-story test room must be satisfied in order to pass the NFPA 285 test.
Given the variations between test apparatus, fire exposure, temperature, and
26 | Hoffman 2020 IIBEbeC BuildINg ENClosure Symposium | November 9, 10, 12, 16, 17, 19, 2020
Figure 1 – Configuration of window-wall panels.8
heat flux measurements, it is not possible to directly compare the results of the two tests. Both temperature and heat flux are indicators of the contribution of combustible components to flame spread, and it is reasonable that similar trends may be observed between the two tests with respect to flame spread at the exterior surface.
WINDOW-WALL ASSEMBLY DESCRIPTION
Window walls are different from curtainwalls in that they bear on the slab edge rather than being hung outboard of the slab edge like a traditional curtainwall system. The evolution of these traditionally residential systems is described in further detail in a paper by Torok et al.6
The as-built system documented in the test report7 is summarized here. The system tested consisted of an aluminum-
framed, center-glazed window wall. The aluminum mullions have a polyamide thermal break in line with the glazing. The outer half of the vertical mullions extends to provide an integral slab band cover. A horizontal deflection header is installed at the underside of the slab. The window wall sections are glazed with 0.080-in.-thick painted aluminum panels. Inboard of the aluminum panels there is 75 mm of mineral-
wool insulation and a 22-ga galvanized- steel back pan. Inboard of the metal back pan, a 50-mm-thick layer of medium-
density urethane spray foam was applied and covered with a layer of gypsum sheathing. The exterior joints between the window-wall panels at the vertical mullions were bedded with a silicone sealant.
CHALLENGES OF TESTING A UNITIZED GLAZING SYSTEM
When it came to undertaking CAN/ULC S134 testing of the unitized window system, there were a few challenges to overcome. The first had to do with the configuration of the panels around the specified window opening in the backup wall. The proposed assembly represented three floors of window wall panels (Figure 1). The first floor included the prescribed window opening flanked by two full-height panels. No vertical mullions extended through the window opening, nor was a horizontal mullion installed at the window head, but the slab-mounted deflection header was applied continuously across the window opening. The interior part of the deflection header was omitted due to lack of access. The two floors of panels above the window opening were broken up into three equal-width panels. As a result, the single vertical joint as required in CAN/ULC S134 was substituted for two joints approximately 825 mm to the left and right inside dimensions of the window opening. This was deemed to better represent the typical width of panels in window wall construction.
The other issues arose from the nature of the test facilities available. The few facilities available in North America have been built primarily with the intent of testing exterior-applied assemblies. Accordingly, the test facilities commonly have a non-combustible backup wall with the specified window opening to which the assemblies are installed. This was problematic because the window-wall assembly is typically installed from the interior bearing on the slab edge at the floor and is secure in a deflection header at the slab above. Furthermore, the spray-foam insulation is typically applied to the interior surface of the window-wall system after erection.
To simulate the slab edge at the typical bypass detail, mineral wool insulation was installed in lieu of concrete (Figures 2 and 3). The bituminous self-adhered membrane flashing typically installed at the slab band as part of the waterproofing of the system at the sill was omitted for this test. This detail was applied in two locations: directly above the window opening and 3 m above the window opening. This allowed the window wall to be supported on the backup
November 9, 10, 12, 16, 17, 19, 2020 | 2020 IIBEbeC BuildINg ENClosure Symposium H Hoffman | 27
Figure 2 – Window-wall detail at head of window opening.8
Figure 3 – Window-wall detail at simulated slab edge at horizontal joint.8
wall while simulating the projection of the non-combustive slab edge.
The dead weight of the window wall panels was supported on a metal bracket above the simulated slab edge. Lateral loads were accommodated using L-angle clips secured through the vertical mullions. The traditional strap anchors at the deflection header were installed, but in the absence of a concrete-slab band, were not considered adequate to restrain the panels. While the use of the additional lateral clips differed from typical installations, it is in keeping with how these window wall systems are installed when they bypass a shear wall. Since the primary purpose of the test is to assess the combustibility of the foam insulation, this was deemed by all parties to the testing to be an acceptable compromise.
Lastly, since the inside face of the window wall panels would not be accessible once they were erected on the backup wall, the spray foam had to be installed on the back side of the panels before they were erected. This led to a gap, typically less than 12 mm, in the spray-foam insulation at the vertical mullions between panels. Given that this gap could provide a channel for the propagation of the flames, it was determined that this gap would represent a more stringent test condition.
INSTRUMENTATION
The instrumentation documented in the test report7 is summarized here. Three water-cooled heat-flow transducers were installed 3.5 m above the top of the window opening: one within 0.2 m +/- 0.05 m horizontally of the centerline of the opening and the other two within 0.5 +/- 0.1 m horizontally from the first. The transducers were installed with their sensor flush with the outer face of the test assembly. In addition, thermocouples were used to monitor the temperature of the test assembly. The thermocouples were located above the opening, approximately 89 mm to the right of the vertical center line at the following intervals: 1.5 m, 2.5 m, 3.5 m, 4.5 m, and 5.5 m. At each of these locations, thermocouples were placed at the outermost surface of the test assembly—one on the outer face of each representative layer within the test assembly, and one on the base wall surface. The data acquisition system was programmed to take a reading every five seconds during the testing.
28 | Hoffman 2020 IIBEbeC BuildINg ENClosure Symposium | November 9, 10, 12, 16, 17, 19, 2020
Figure 4 – Apex of burn pattern above window opening.
Figure 5 – Exposed mineral-wool insulation above window opening.
FINDINGS
Testing was performed in accordance with the CAN/ULC-S134 test method. Once ambient conditions were met, the burners were ignited. Per the specified method, a 5-minute flame-growth period was followed by a 15-minute steady-state period and then a 5-minute ramp-down period.
The observations documented in the test report7 are summarized here. The ramp-up period was started, and within three minutes, the flames were reaching outside of the burn room. By the end of the ramp up, the deflection header was starting to buckle. Within the first 30 seconds of the steady-state period, heavy smoke was visible. At the one-minute mark, there was no visibility above 4 m, and within 2.5 minutes, there was no visibility down to 2 m. At 3.5 minutes into the test, the buckling of the window header was more pronounced, but it remained attached. By the 6.5-minute mark, flaming was visible at the center panel and left joint above the window opening. At the 8-minute mark, flaming was visible at both vertical joints above the window opening. Pieces of the metal panel started falling off after 9.5 minutes. Just before the 10-minute mark, a large piece of material from the center exterior metal panel fell off. After the 15-minute steady-burn period, panel base flaming decreased. Three minutes into the ramp-down period, flaming was still visible at the top left section above the window opening. At the end of the ramp-down period, small flaming continued. All flames self-extinguished within 45 minutes after the start of the test.
Following the test, a cone-shaped pattern was visible on the exterior metal panels. The apex of this pattern extended 2.5 m above the window opening (Figure 4). The metal skin of the exterior metal panel had fallen off, exposing the mineral-
wool insulation to a height of 1.4 m (Figure 5) above the window opening. The slab-mounted deflection header at the opening was approximately 90% consumed. The top row of exterior metal panels showed only smoke damage and slight warping of the exterior metal panels. The window wall panels were then dismantled and observed for signs of damage. The top row of window wall panels showed no damage to the spray foam layer. The next row of window wall panels immediately above the window opening showed damage. The exterior metal panels on either side of the opening showed signs of smoke damage and warping. There was some sign of charring of the spray-foam insulation at the vertical window-wall panel joint, and the aluminum vertical mullion was also damaged (Figure 6). The center panel was more damaged. The exterior metal skin was melted to a height of 1.4 m. Approximately half the thickness of the spray-foam insulation remained. There was also damage to the vertical mullion. After removal of the panels, the gypsum boards were reviewed and found to have no sign of damage.
The maximum flame spread above the window opening was 3 m. Based on the measurements, the maximum average heat flux was determined per the standard to be 20.1 kW/m², which occurred 18.7 minutes into the fire test. Based on these two findings, the assembly met the conditions of acceptance outlined in CAN/ULC-S134.
November 9, 10, 12, 16, 17, 19, 2020 | 2020 IIBEbeC BuildINg ENClosure Symposium H Hoffman | 29
Figure 6 – View of localized charring of spray foam at vertical above-window opening.
CONCLUSION
The results of this test demonstrate that, despite some challenges in adapting the erection of the window wall assembly to accommodate the requirements of standards and the nature of the test facility, spray-foam insulation applied to the interior face of a residential window wall system with an exterior aluminum spandrel panel and a metal back pan insulated with mineral wool can comply with the requirements of CAN/ULC-S134. The nature of this standard is that it is assembly-specific and any significant changes of materials or dimensions would require its own testing.
The biggest variable is the configuration of the window-wall frames that can vary significantly from manufacturer to manufacturer, as do the specific details at the deflection header and the slab bypass. In particular, window-wall systems which bear on the slab edge are different from curtainwall systems that are hung outboard of the slab edge with fire staffing and a smoke seal between the slab and the spandrel panel. While the result of the window-wall test can provide insight on the potential performance of curtainwalls with spray-foam insulation, further testing will be required to demonstrate performance.
Likewise, while the variations outlined between CAN/ULC-S134 and NFPA 285 do not allow for a direct correlation of the results, both temperature and heat flux are indicators of the contribution of combustible components to flame spread. Therefore, while a separate test to demonstrate performance to NFPA 285 would be required, it is reasonable to assume that similar trends would be observed with respect to flame spread at the exterior surface and further that the assembly would have a reasonable chance of meeting the temperature rise criteria stipulated by that standard.
REFERENCES
1. CAN/ULC-S134-2013. Standard Method of Fire Test of Exterior Wall Assemblies. Underwriters Laboratories of Canada. Ottawa, ON. August 2013.
2. NFPA 285-2019, Standard Fire Test Method for Evaluation of Fire Propagation Characteristics of Exterior Wall Assemblies Containing Combustible Components. National Fire Protection Association. 2019.
3. Norris, N., L.D. Carbary, S. Yee, P. Roppel, and P. Ciantar. “The Reality of Quantifying Curtain Wall Spandrel Thermal Performance: 2D, 3D and Hotbox Testing.” Proceedings of the Fourth Building Enclosure Science and Technology Conference. National Institute of Building Sciences. 2015.
4. Hoffman, S. P. “Energy Code Implications for Spandrel Design: Quantifying and Mitigating the Impact of Thermal Bridging.” Proceedings of the Façade Tectonics 2016 World Congress. Façade Tectonics Institute. 2016.
5. Morrison Hershfield Ltd., Building Envelope Thermal Bridging Guide. BC Hydro. 2014.
6. Torok, G. R., and Y.J.A. Chiasson. “Canadian Window Wall: Design Challenges and Opportunities.” Proceedings of the Façade Tectonics 2016 World Congress. Façade Tectonics Institute. 2016.
7. Burgos, V. M., and M. Dey. “Fire Test Report 10344740SAT-001.” Intertek. 2018.
8. 8000 Series Mock-up Drawings for CA-ULC S-134. BV Glazing. 2018.
30 | Hoffman 2020 IIBEbeC BuildINg ENClosure Symposium | November 9, 10, 12, 16, 17, 19, 2020