Skip to main content Skip to footer

Analysis of a Roof Failure

March 31, 2008

Analysis of a Roof Failure

 

John Wells, RRO
Wells Klein Consulting
Victoria, BC, Canada
ABSTRACT
This paper looks at the investigative process of the failure of a single-ply roof on a new
high-end, high-rise condominium building. The failure resulted in major damage
claims for the insurance company and a replacement roof on a building less than six
months old. The initial failure appeared to be wind-related, but a more complete
investigation proved that components of the roof had actually failed prior to the wind
events that drew attention to and emphasized the failure. The investigation pointed
out fundamental problems with the roof design and the building envelope design, all
of which were exacerbated by poor workmanship by the roofing contractor and per¬
haps pressures from the developer to “value engineer” the building process.
SPEAKER
John Wells is the senior partner and president of Wells Klein Consulting Group Inc.,
a British Columbia, Canada-based company that specializes in providing solutions to
roofing, waterproofing, and related building envelope problems for commercial and
institutional building owners throughout British Columbia and Western Canada.
Prior to starting his consulting practice in early 1992, John gained international
recognition for his work as technical manager of the Roofing Contractors Association
of B.C., a position he held until the fall of 1991. John has authored technical manu¬
als, published technical columns and articles in trade magazines, and has been a
guest lecturer and speaker at universities, technical societies, and national conven¬
tions.
Wells was the founding president of the British Columbia Building Envelope Council
and was an elected director for ten years. John joined RCI in 1997 and earned the
RRO certification in 1998.
Contact Information: Phone – 250-658-3143; E-mail -jwells@wellsconsult.com
Wells – 184 Proceedings of the RCI 23rd International Convention

 

 

Analysis of a Roof Failure

 

INTRODUCTION
In this paper, we will review
the investigative process of the
premature failure of a new single¬
ply roof on a high-end, high-rise
condominium building in Victoria,
BC, Canada. Once again we
learned that “things ain’t always
what they seem to be!”
The roof failure resulted in
interior water damage claims well
in excess of $150,000 to an insur¬
ance company and the necessity
of a replacement roof (projected
cost in excess of $100,000) on a
high-end condominium building
that was less than six months old.
We will lead the reader
through the investigative process¬
es that led to our conclusions on
this failure as we review informa¬
tion and gather clues leading to a
perhaps startling conclusion. It
was not the conclusion that many
wanted to hear.
Wells Klein Consulting Group’s
main work is in the investigation,
remediation, and replacement of
roofs, due diligence inspections,
roof condition assessments, roof¬
top quality control, maintenance
planning, and inspections, etc.
Forensic investigation projects
don’t come along very often, but
are a favorite of our business.
Our practice is mostly com¬
mercial, institutional, and indus¬
trial buildings with only a smat¬
tering of residential condominium
work and virtually no single-fami¬
ly construction. We operate pri¬
marily in southwestern British
Columbia in the Vancouver area,
and on Vancouver Island. WKGCI
and its predecessor company,
J.W. Wells Consulting Inc., has
been in practice for 16 years.
Figure 1 – The roof had failed after only six months in service.
British Columbia is a very so¬
phisticated roofing market, given
the influence of the Roofing Con¬
tractors Association of BC. The
climate varies from coastal to se¬
vere. Lots of rain and wind are
common in winter months on the
South Coast area, where we oper¬
ate. Unlike other parts of Canada
or even the interior of BC, winters
in southwestern coastal BC are
pretty much snow-free. For those
unfamiliar with our geography,
think Seattle, because we are only
80 miles (130 km) northwest of
the Emerald City.
For the purposes of this paper,
we are focusing on Victoria, BC,
the capital city of British Colum¬
bia. Victoria is located on the
southern tip of Vancouver Island,
the largest of British Columbia’s
6,500 islands. It is a community
often chosen for its temperate cli¬
mate, natural beauty, recreational
sites, and superior economic
opportunities. According to the
2006 census, about 380,000 peo¬
ple make their home in the
greater Victoria area.
Located in a sub-Mediterran¬
ean zone, Victorians enjoy some of
the most moderate weather in all
of Canada. Victoria boasts an
average of 2,183 hours of sun¬
shine yearly, and an eight-month,
frost-free season. Average annual
rainfall is only 26.2 in (65.6 cm),
compared to some 48 in (121.9
cm) for Vancouver and 37 in (94
cm) for Seattle.
Victoria, however, can be a
windy place. The real stormy sea¬
son of late October through
January usually produces a num-
Proceedimjs of the RCI 23rd International Convention Wells – 185
ber of wind events with storms
often exceeding 50 mph (80 kph).
Wind gusts of up to 65 mph (100
kph) are not unusual, and occa¬
sional gusts to 75 mph (120 kph)
or more are not uncommon.
Storm wind direction is southeast
to west.
THE FACTS MA’AM,
JUST THE FACTS
The subject building is a
brand new, 11-story, high-end
residential condominium, of rein¬
forced concrete structure. The
penthouse portion has a curved,
cast-in-place, concrete roof deck
shaped similarly to an airfoil or
aircraft wing. We are advised this
was an architectural feature
rather than an attempt to provide
a spoiler effect to keep the build¬
ing firmly on the ground!
There are two main roof areas.
Only the failed roof area on the
airfoil is addressed in any detail in
this paper.
The roof plan of the building is
shown in Figure 2. The drain loca¬
tions are highlighted. A section
view of the upper roof portion fol¬
lows in Figure 3.
THE PRELIMINARY
REVIEW AND CLUES
Figure 2 – Drains shown in white circles or arrows.
We received the first call on Figure 3 – Section of the upper roof.
the project on January 9, 2006,
from an insurance company
adjuster in Victoria. We were told
briefly that a roof had failed
(“blown off’ was the term) due to
wind and were we interested and
qualified to perform an investiga¬
tion and provide a report. The
adjuster said he had been told the
roof membrane was single-ply
TPO (thermoplastic polyolefin)
and asked if we knew anything
about that material. We advised in
the affirmative and our bona fides
were supplied and a written
instruction to proceed was quick¬
ly issued.
We were advised in the initial
phone discussions that the roof
had partially “blown off “ the
building a few days previously,
that water ingress and damage
had occurred, and that a contrac¬
tor had supplied and installed a
number of concrete pavers as bal¬
last to hold the loose roof mem¬
brane in place.
Following are some excerpted
sections from our preliminary
report (italicized within quotation
marks).
Our first impression in driving
up to the property was that it was
a very exposed location to all pre¬
vailing storm winds. It is close to
the Victoria “Inner Harbor” area, a
prime location. We observed a
very unique feature on the roof.
The top of the penthouse looks
like an airplane wing, an airfoil, in
fact. This feature, with its atten¬
dant possibilities, was not lost on
the writer, a former pilot.
“We attended this property
on January 10, 2006, in
order to perform a prelimi¬
nary assessment on the
condition of the roofs on
this building. You advised
that subsequent to recent
windstorms, portions of
Wells – 186 Proceedings of the RCI 23rd International Convention
the roof, specifically the
curved or “airfoil” section,
had suffered damage. ”
“Weather conditions during
our preliminary review
were showers, breezy,
with a temperature of 9°C
(48°F). Steady rain settled
in as we left the site at
about 3:00 p.m.
“Prior to accessing the roof,
we viewed a partial set of
reduced architectural draw¬
ings. Project specifications
and other information such
as roofing warranties were
not available. The property
manager also advised that
the roof problems were first
noticed or reported on or
about Jan. 1, 2006.
Also prior to accessing the
roof, we were shown some of the
suites where water damage had
taken place. The points of water
entry into the building were drain
holes in the concrete (the roof
deck) slab above the suites. We
were advised that the “drains had
been pulled out of the deck pene¬
trations and allowed water in¬
gress.” We observed interior dam¬
age was severe and that drying
and repairs were still underway.
The interior damage was
extensive, indicating a significant
volume of water had entered the
building. All the flooring, hard¬
wood, and carpet for three floors
was being removed for replace¬
ment, and the lower portions of
walls (both wood and drywall)
were wet. The suites are valued
from $700,000 to over a million
dollars.
We were able to access loca¬
tions underneath the deck and
took photographs of the partially
repaired drains. It had been re¬
ported that the drains had been
pulled out of the deck, tearing the
membrane. Figure 4 shows one of
the drains on the east side of the
deck.
Figure 4 – One of the drains on the east side of the deck.
One of the things we observed
was the difference between the
size of the drain line and the size
of the chase. We also observed
that other chases or holes in the
concrete for penetrations were all
significantly larger than the pene¬
tration would require.
Our preliminary look at the
drawings showed the lower or
main roof was a 2-ply, SBS, modified-
bitumen assembly over poly¬
isocyanurate insulation. The air¬
foil roof was originally specified as
a TPO membrane, fully adhered to
a treated gypsum-board overlay,
adhered with a well known poly¬
urethane adhesive to 4 in (200
mm) board-stock polyisocyanu¬
rate insulation adhered to a con¬
crete deck with the same well
known polyurethane adhesive.
We were advised that the TPO
assembly had been installed by a
roofer subcontracted to the prime
roofing contractor.
We then accessed the airfoil
roof and were quite frankly (par¬
don the expression) “blown away”
by what we saw. Photos 5 and 6
may help to explain why.
We counted well over 150
pavers, at 160 kilos (100 lbs) a
piece, that had been brought up
to hold the roof membrane in
place!
Back, briefly, to our report:
“The complete assembly is
no longer “fully adhered”
but is now completely
loose and only held on the
building by concrete pav¬
ers (installed as emer¬
gency ballast) and a
perimeter fixation bar from
the original installation.
We were advised (by the
property manager) that the
pavers move during wind
events and this may repre¬
sent an extreme safety
hazard if a paver fell from
the roof level.
“Subsequent to our site
visit, another windstorm
occurred on January 12,
and we were advised
again by Mr. Ennis that
the pavers were moving
and becoming displaced
by membrane movement
in the wind.”
Proceedings oj the RCI 23rd International Convention Wells – 187
Figures 5 and 6 – Over 150 pavers of 100 pounds each held the roof membrane in place.
In fact, we observed that es¬
sentially none of the membrane
was adhered.
“We observe that the insu¬
lation has moved around
and p’iled up’ under the
membrane.
“Water entry into the
suites took place at the
locations of cast drain
penetrations through the
concrete deck. The cast
drains were likely ‘pulled
out’ of these locations by
the membrane billowing
and luffing in severe wind
conditions.
“We advise it seems
unlikely that the drains
were ever mechanically
fastened to the deck, but
more likely, the cast iron
drain flanges were just
placed on top of the insul¬
ation without adequate
mechanical fixation. No
clamping rings were evi¬
dent. Downpipes were at¬
tached with MJ-type cou¬
plings, which apparently
failed when the drains
were pulled and moved
upward and water entry
took place. ”
Our Preliminary Opinions
“The roof membrane, how¬
ever, [was] intact at the
time of our preliminary
review (due to the tensile
strength of the membrane)
and water entry was
through the concrete deck
subsequent to the failure
of the membrane at the
drain connection.
“The roof membrane is in
danger of blowing off the
building and is held in
place by the concrete
pavers. These pavers may
represent an extreme
health and safety hazard,
should one or more fall
from the roof in high wind
conditions. The pavers
also represent a danger to
the membrane proper from
abrasion or physical pene¬
tration. We observed some
broken pavers with sharp,
pointed corners on the
roof.
“If the membrane is pene¬
trated, further severe
water ingress may be
expected.
“The exact failure mode
cannot be established
without further investiga¬
tion and calculation. The
membrane must be cut
open and the membrane,
insulation, and roof deck
examined for clues.
“We suspect there were
deficiencies, both in the
application of the insula¬
tion to the deck, and of the
membrane to the insula¬
tion. Viewing the compo¬
nents after opening the
system would confirm (or
deny) our suspicions. ”
In fact, the only things that
had held this roof on the building
(prior to the paver installation)
were the perimeter fixation bars.
The whole membrane would flap
or flutter in the breezes, and that
was the force that pulled the
improperly attached roof drains in
place.
Wind Conditions
As previously mentioned,
windy conditions are not uncom¬
mon in Victoria, especially during
winter. I note, however, that this
winter had not been particularly
windy up to the point of our pre¬
liminary investigation. Winds of
40 to 50 kmh (25 to 31 mph) are
commonplace year round. My
idea of a “wind event” is only when
the wind exceeds at least 70 kmh
Wells – 188 Proceedings of the R CI 23rd International Convention
(44 mph) . A wind chart of Canada
is pretty self explanatory, with
Victoria highlighted with a red
star in the 100 mph (160 kph)
coastal zone.
“A review of recent wind
conditions in Victoria Har¬
bor since December 1,
2005, is attached. I have
only included the days
when gusts exceeded 35
kmh. We note that wind
conditions at the building
site are likely exacerbated
by shape, height, and
exposure.
“It would appear from the
property manager’s re¬
marks that the major prob¬
lems took place in a wind
event on December 29.
Harbor gusts that day
were recorded as high as
50 kmh (30 mph). Another
wind event with one gust
at 48 kmh was recorded on
January 1, 2006.
We noted a more prolonged
wind event on January 7,
2006, and another, more
severe event on January
12. Records are attached”. 1
None of these events is out of
the ordinary, and would normally
be no cause for problem or alarm.
“Our initial or preliminary
opinion of the reasons for
the failure of this roof sys¬
tem includes poor or im¬
proper workmanship of
the membrane assembly
(primarily the insulation
and membrane adhe¬
sive), improper installa¬
tion of the roof drains,
coupled with the possibil¬
ity of under or inadequate
roof-system design for the
conditions.
“Further and much exten¬
sive investigation is re¬
quired to confirm our
opinions. ”
And there it was for the first
“go round” – some suspicions and
opinions based on initial observa¬
tions and experience.
The Destructive Testing
On January 21, we were invit¬
ed back to observe cut testing of
the roof. We also viewed copies of
more drawings and the original
specifications.
It became quickly apparent
that there had been some “value
engineering” in that the original
specifications, poor as they may
have been, had been changed or
not followed.
Our inspectors’ observations
recorded this day include:
“Airfoil roof area is/ was
.060 TPO fully bonded
with bonding adhesive to
3.2- in x 4-ft x 4-ft board
stock polyisocyanurate in¬
sulation adhered to con¬
crete deck with foam poly¬
urethane adhesive in rib¬
bons at +/- 9 in oc.
“At each end of the roof,
the backslope from the 5 ft
perimeter band to the
drain line was installed
using plywood and fram¬
ing instead of the concrete
shown on the drawings.
There are 3 +/-25-mm (1-
in) diameter holes to drain
from under the wood
backslope to the exterior.
Water was draining from
those at the bottom of the
roof.
“Most of the south half of
the roof and some of the
north half has had all of
the insulation moved
around and piled up
under the membrane. ”
The Key Clues
“A 2 ft x 4 ft section near
the ridge on the north¬
west quadrant was
opened.
“About 1/3 of the insula¬
tion facer was attached to
the membrane. Over the
rest of the area, the facer
sheared parallel to the
membrane, resulting in
facer being attached to
Figure 7 – About 15% of the insulation facer was attached to
the membrane, complete with a thin layer of insulation. The
remainder of the membrane had the top half of the insulation
facer attached.
The attachments referred to are from the original report, not this presentation paper.
Proceedings of the RCI 23rd International Convention Wells – 189
Figures 8 through 11 – A total of 480 pavers kept the membrane on the roof; some had been
flipped off the roof by flapping membrane, falling over 100 feet to the ground.
both the membrane and
the insulation. The portion
of the facer still attached
to the insulation ap¬
peared to be well ad¬
hered. The facer attached
to the membrane had
been set in a full bed of
bonding adhesive.
“The insulation facer on
top of the insulation was
wet.
“The joint between the
insulation panels was irr¬
egular and about 3/8-in
wide maximum.
“When the insulation was
removed, this cut test was
over the edge of a faced
gypsum board panel. Or¬
iginal spec called for the
faced gypsum, board to be
installed on top of the in¬
sulation. Faced gypsum
board that was installed
was on the concrete deck,
contrary to the specifica¬
tions. The requirement for
faced gypsum board was
deleted on the first day of
installation (according to
the roofer) after a few
rows of faced gypsum
board had been installed.
“The insulation was ad¬
hered to the faced gyp¬
sum board and the con¬
crete with beads of ure¬
thane adhesive at about 8-
in centers. In some areas
of the glue bead, it is obvi¬
ous that the insulation
was well adhered, and irv
others, that there was no
contact between the glue
bead and the insulation.
“At the interface between
the faced gypsum board
and the uneven concrete
deck, there is a gap of up
to about 5/8-in under the
insulation.
“The insulation facer on
the bottom of the insula¬
tion and the concrete deck
was dry.”
Three other locations cut open
exhibited similar conditions.
Wells – 190 Proceedings of the RCI 23rd International Convention
“A third 2-ft x 4-ft opening
was cut in the membrane
where the insulation had
been shuffled, leaving the
concrete deck exposed
under the membrane.
“About 15% of the insula¬
tionfacer was attached to
the membrane, complete
with a thin layer of insu¬
lation. The remainder of
the membrane had the
‘top half of the insulation
facer attached. ” (See
Figure 7.)
“The adhesive ribbons se¬
curing the insulation to
the rough concrete deck
were spaced at intervals
varying from 8 into 14 in.
Some of the ribbons had
parts of the insulation
facer attached; other sec¬
tions had been in contact
with the insulation; and
still others had never
been in contact with the
insulation. ”
The concrete deck was diy
and had a very rough and uneven
surface.
“Another (fourth) opening
was made at the south
edge of the insulated roof
area. The 2 2×6 wood
blocking was in place
(although the roofer had
said that some of this
block had come away
from the deck). The 2-3/8-
in barbed metal plates
securing the perimeter
RPF strip were still
installed in the wood
blocking and had the rem¬
nants of TPO membrane
under them. The mem¬
brane had torn out from
under the metal plates.
“There was bonding ad¬
hesive on the concrete
upstand (parapet) to the
perimeter band, but no
membrane attached.”
Figure 12 – The concrete deck, had humps and hollows of more
than an inch.
We had not been retained to
consult; only to investigate and
report. It was subsequently decid¬
ed (by others) to try to do a tem¬
porary repair on the roof as the
weather was unlikely to cooperate
for months. The “roof’ was now
not leaking as long as it stayed on
the building. Additional pavers
(now 480!) were brought up and
then an elaborate system of steel
cables anchored at the perimeter
was installed to keep the pavers
on the roof. Some had been
flipped off the roof by the flapping
membrane, falling over 100 feet
below. Some balcony railings were
damaged, but, thankfully, no
injuries had occurred to humans.
See Figures 8 through 11.
Most of the clues are in. But
you may have noticed one partic¬
ular thing that has not been iden¬
tified or mentioned. This paper
may have been available, and you
may have read it prior to my pre¬
sentation!
Here’s another clue. Figure 12
is a picture of the concrete deck to
which the assembly was installed.
This photo was taken after the
failed assembly had been removed
for replacement roofing.
The concrete deck is far from
level. In fact, a straight edge
would reveal humps and hollows
of more than 25 mm (1 in). Some
of the adhesive strips are undis¬
turbed, due to the rigid insulation
boards spanning hollows and
never coming in contact with the
adhesive. There is still, however,
one very important clue that we
haven’t mentioned yet!
A review and comment on
observations
“Observation #10 – About
1/3 of the insulation facer
was attached to the mem¬
brane. Over the rest of the
area, the facer sheared or
failed in cohesion parallel
to the membrane and
insulation. The portion of
the facer still adhered to
the insulation appeared to
be well adhered. The facer
attached to the membrane
had been set in a full bed
of bonding adhesive.
“The insulation facer on
top of the insulation was
Proceedings of the RCI 23rd International Convention Wells – 191
wet. The joint between the
insulation panels was
irregular and about 3/8 in
maximum. ”
Photo 13 was actually taken
six months after the failure. This
material is being removed for the
installation of a replacement roof.
Note the insulation facer is fairly
well adhered to the back of the
TPO membrane. The facer is wet
or even saturated with water. At
this time, the odor of the facer
was quite significant, as well!
The wet or damp insulation
facer is of considerable concern
and would be a contributing fac¬
tor in the failure due to the
decreased intra-laminar strength
of the facer. The facer is a glassreinforced
saturated paper and
the strength would be significant¬
ly reduced by moisture. We con¬
sidered that the source of mois¬
ture might have been water
ingress when the drains failed.
Upon further investigation and
consideration of the configura¬
tion, this was discounted. The
likely source of moisture would be
from condensation of moist air
from within the building itself,
with the airflow uninhibited by
the lack of an air barrier or air
seal at the deck-level penetrations
and exacerbated by the stack
effect of the 11 -story building.
Warm, moist air could flow up
into the roofing assembly at the
drain locations as well as other
unsealed penetrations. We ob¬
served significant air gaps around
drains and other visible roof pen¬
etrations in our site visit of Jan¬
uary 10. We did not observe any
requirement or mention of an air
seal or vapor retarder at the deck
level in the project specifications,
section 07530. In my opinion, the
lack of an air seal at the deck
would be considered a fundamen¬
tal roof design issue as well as an
installation issue that contributed
significantly to the failure.
Observation #10 continued:
“When the insulation was
removed, this cut test was
over the edge of a faced
gypsum board panel. The
specifications called for the
faced gypsum board to be
installed over the insula¬
tion. The faced gypsum
board, which was in¬
stalled, was on the con¬
crete deck under the insu¬
lation, contrary to the spec¬
ifications.
“This was deleted on the
first day of installation (ac¬
cording to the roofer), after
a few rows of the Dens
Deck had been installed.”
OPINION
The specification actually calls
for the faced gypsum board to be
installed over the insulation, not
under. In my opinion, this (over)
was the proper installation, as the
faced gypsum board then provides
protection to the insulation layer
beneath the membrane from foot
traffic and increases the mechan¬
ical resistance of the assembly.
The polyisocyanurate insulation
is quite friable under point loads
and the friability contributes a
void under the membrane at that
location. I note the faced gypsum
board has little resistance to
moisture vapor drive and would
allow the diffusion of air upward
to the insulation and membrane.
We were not advised why the
roofer began putting the faced
gypsum board under the insula¬
tion and we were not privy to any
written change orders allowing
the elimination of the faced gyp¬
sum board. In Canada, this is
often referred to as “value engi¬
neering” or expediency or some
other reference to cheapening
building assemblies. This, in my
opinion, is an installation issue
that contributed to the failure.
Please note we are not criticizing
the faced gypsum board itself. It
did not contribute to the failure.
Further Observations
The insulation was adhered to
the concrete deck with ribbons of
urethane adhesive at about 8-in
centers. In some areas of the
application, it is obvious that the
insulation was adhered; and in
many others, that there was no
contact between the adhesive rib¬
bon and the insulation.
At the interface between the
insulation (or faced gypsum board
in some locations) and the con¬
crete deck, there is a gap of about
5/8 inch under the insulation –
all due to spanning between high
points.
The insulation facer on the
bottom of the insulation and the
concrete deck were dry.
The adhesive ribbons securing
the insulation to the rough con¬
crete deck were spaced at inter¬
vals varying from 8 in to 14 in.
Some of the glue beads had parts
of the insulation facer attached;
other sections had been in contact
with the insulation, and still oth¬
ers had never been in contact with
the insulation.
Opinion
The observation that “there
was no contact between the adhe¬
sive ribbon and the insulation”
indicates that portions (we sus¬
pected significant portions, much
later confirmed) of the roof assem¬
bly were never or were poorly
adhered at best. Irregularities in
the deck level, in conjunction with
the rigid insulation boards (which
in themselves are not always flat
and tend to “cup”), coupled with
the failure of the contractor to
“walk in or weigh down the insu¬
lation boards into the adhesive
(until the adhesive is cured),”
would all contribute to this situa¬
tion. This, in our opinion, was an
installation issue, which also con¬
tributed significantly to the failure
of the assembly. This would at
Wells – 192 Proceedings of the RCI 23rd International Convention
least partially explain why the
insulation was able to move
around and “pile up” under the
membrane. There was an adhe¬
sion failure, both at the mem¬
brane level and the deck level, so
the insulation could move under
when the membrane flapped or
fluttered in the wind.
Lastly, in our preliminary
report, we advised, “It seems
unlikely that the drains were ever
fastened to the deck, but, more
like the drain flanges, were likely
placed on top of the insulation
without adequate mechanical fix¬
ation. Downpipes were attached
with MJ-type couplings, which
apparently failed when the drains
were pulled and moved upward by
wind; and, subsequently, water
entry took place.”
This suspicion was verbally
confirmed in our site visit of
January 21. Although not a pri¬
mary failure mechanism, in our
opinion, this would have provided
an additional, larger channel for
more air to get into the assembly,
and was also the primary point for
water ingress into the building.
What Happened Here?
The “top” or “airfoil” roof is a
single-ply TPO membrane. The
system is designed as an insulat¬
ed assembly and was designed to
be installed “fully adhered.” We
observed a complete system fail¬
ure on this roof, although the
membrane integrity proper was
still essentially intact.
The complete assembly was
no longer “fully adhered,” but was
now completely loose and only
held on the building by concrete
pavers (installed as emergency
ballast) and a perimeter fixation
bar from the original installation.
Subsequently, a system of steel
cables was installed to hold the
pavers and membrane on the roof.
We observed that the insula¬
tion had moved around and “piled
up” under the membrane.
Water entry into the suites
took place at the locations of cast
drain penetrations through the
concrete deck. The cast drains
were likely “pulled out” of these
locations by the membrane bil¬
lowing and “luffing” in severe
wind conditions.
OUR CONCLUSIONS
We confirmed a total system
failure of the fully adhered TPO
roof section. The roof would have
to be removed and replaced at
some time in the very near future.
The assembly was not, in our
opinion, “repairable,”
The roof membrane integrity,
however, was still intact at the
time of our preliminary and sub¬
sequent reviews (due to the tensile
strength of the membrane), and
water entry was through the con¬
crete deck subsequent to the fail¬
ure at the drain connection.
The roof membrane was in
danger of blowing right off the
building and was held in place by
the concrete pavers and a system
of steel restraining cables.
Subsequent to our first visit,
an elaborate system of steel
cables was installed over the
membrane and pavers as a tem¬
porary measure to hold the roof
membrane in place. We under¬
stand the assembly was to have
been eventually removed and
replaced in the summer of 2006.
We advised our concern for
the adequacy of the design. The
roof is an airfoil shape, 12 stories
high, in an exposed building loca¬
tion, and is subject to significant
wind loading. The specifications
only contained one minor refer¬
ence to wind design. We believe no
wind engineering was ever done in
the design stages. As mentioned
earlier, there seem to have been
no requirements in the specifica¬
tion for an air/vapor seal at the
deck level. We advised that the
membrane manufacturers’ speci¬
fications often call for certain
components like an air barrier or
a very specific roof assembly,
depending on the use and design
of the building; but none was
used.
We were not able to view any
project correspondence that
approved any of the apparent
changes made during construc¬
tion.
We further advise that in our
opinion, wind conditions actually
had little to do with the failure of
this roofing assembly. All the fail¬
ure mechanisms were in place
prior to any significant wind
events, and, in fact, the assembly
had failed prior to any significant
wind event. The wet insulation
facer prevented any resistance to
wind uplift; and, given the eventu¬
al wind and the shape of the
building, flutter and failure were
inevitable.
The wind events that “proved”
the assembly failure were not that
significant. The wind events only
indicated that the failure had
taken place and additional or
more severe wind could then fur¬
ther damage the assembly and
building.
SUMMARY
Our opinions of the reasons
for the failure of this roof system
remained unchanged from our
preliminary review. The failure
mechanisms included poor or
improper workmanship of the
membrane assembly (primarily
the insulation and membrane
adhesive), improper installation of
the roof drains, coupled with fun¬
damental problems with the roof
and the building envelope design.
THE AFTERMATH
Subsequent to our report,
there was, predictably, a lot of fin¬
ger pointing. The manufacturer
declined warranty coverage due to
winds beyond the usual warranty
small print. We questioned the
wind information supplied by the
Proceedings of the RCI 23rd International Convention Wells – 193
manufacturer, but we were never
advised of the results. The manu¬
facturer offered to supply new
materials to the owner at a
reduced price, but assumed no
liability whatsoever. We used to
call this a “policy allowance,” in
my old days with a major manu¬
facturer. A “quit claim” always
accompanies this kind of offer.
Reminds me of my favorite
warranty expressions: “the
LARGE PRINT GIVETH and the
small print taketh away.” War¬
ranties aren’t printed on water¬
proof paper.
The developer and roofing
contractors are, to my knowledge,
in litigation. The insurance com¬
pany is attempting to subrogate.
Some months after our initial
involvement, the insurance com¬
panies’ lawyers asked that we
again visit the site to report on the
new roof system that was being
installed. We observed further
information about the initial fail¬
ure as the old roof was removed.
In its place, the roofer was
installing a new vapor retarder (2-
ply #15 felt in hot asphalt), new 3-
in isocyanurate mopped in hot
asphalt, a wood fiberboard over¬
lay, mopped and a 2-ply SBS
membrane with a mopped base
sheet.
We reported our observations,
and that was our last involvement
in the project.
We understand that the roofer
was denied a progress payment
on finishing the base sheet and
that subsequently, the roof sat
with just the base sheet installed
for nearly a year. I was recently
(October 2007) advised by anoth¬
er consultant that the cap sheet
had finally been installed a year
later. We need not say that this
kind of “phased” construction is
not usually considered acceptable
roofing practice.
Ah well, eveiy street we drive
down is a street of opportunity!
Wells – 194 Proceedings of the RCI 23rd International Convention