Skip to main content Skip to footer

Case Study: Common Design and Workmanship Issues Related to Brick Veneer Masonry of a Modern Mid-rise Building

April 25, 2007

Doorways to the Future
PROCEEDINGS of the
RCI 22nd International
Convention & Trade Show
Orlando, Florida • March 1-6, 2007
© RCI, Inc.
1500 Sunday Drive, Suite 204 • Raleigh, NC 27607
Phone: 919-859-0742 • Fax: 919-859-1328 • www.rci-online.org
Proceedings of the RCI 22nd International Convention French – 39
Case Study: Common Design and Workmanship
Issues Related to Brick Veneer
Masonry of a Modern Mid-rise Building
Warren R. French, PE, RRC, RWC, FRCI, CMRS
French Engineering, Inc.
Houston, Texas
Doorways to the Future
ABSTRACT
At the time of our investigation, the 100,000-square-foot, 12-story, multi-family residential
building had been constructed for only about four years. It consisted of a
cast-in-place concrete structural frame and post-tensioned floor slabs, with coldformed
metal framing utilized as the wall in-fills. The metal studs had been covered
with a gypsum sheathing and a #15 felt weather barrier, utilizing a 2-inch air space
or cavity and nominal 4-inch-thick brick veneer. The fenestration included a complex
arrangement of four different colors of brick, as well as white cast stone elements at
copings and periodic masonry string courses. In addition, the building included a
three-story mansard composed of standing seam sheet metal roofing with a slight
radiused configuration. Additional architectural elements included vertical notches
and offsets, aluminum-and-glass curtain walls, and private balconies and terraces.
Terraces and balconies were provided with a fluid-applied deck coating as a waterproofing
application.
It is intended that this paper will present the results of observations made and testing
conducted at the site over a period of months. This paper will derive specific conclusions
related to the conditions encountered at this project and how these anomalies
detrimentally affected the cladding system’s performance. Recommendations
will be developed that could strengthen the original design and construction in order
that these failures may be avoided in the future.
SPEAKER
WARREN R. FRENCH,PE, RRC, RWC, CCS is president of French Engineering, Inc. in
Houston, Texas. Mr. French has over 30 years experience in design, engineering, and
construction of commercial, industrial, and institutional buildings for both domestic
and international projects. Special experience and abilities include analysis, design,
testing, and inspection of all types of construction assemblies intended to resist moisture
migration within buildings. Areas of expertise include all types of roofing systems,
below-grade and plaza-type waterproofing, building sealants, wall cladding systems,
plaster, EIFS, and all types of curtain walls.
Warren is a professional member of RCI, CSI, ASE, ASTM, the Post-Tensioning Institute,
and the International Concrete Repair Institute. He has been a speaker at
numerous conferences, symposiums, and national organization meetings, as well as
presenting several in-house seminars for major corporations and design firms,
including Hilton Hotels Corporation, Marriott Corporation, Trammel Crow, and HKS
Architects.
French – 40 Proceedings of the RCI 22nd International Convention
INTRODUCTION AND BACK –
GROUND
This paper will present the
findings of a forensic investigation
conducted on a 12-story, multifamily
residential building recently
constructed in New Orleans,
Louisiana. We were retained by
the owner’s representatives to
assist in determining a cause for
the interior water infiltration being
experienced, as well as to
develop a plan for cladding system
remediation and renovation.
BUILDING DESCRIPTION
General Building
At the time of our investigation,
the 100,000-sq-ft, 12-story,
multi-family residential building
that is the subject of this presentation
had been constructed for
only about four years. The building
contains 118 one-, two-, and
three-bedroom apartments and
30,000 sq ft of common areas
such as a library, craft room,
multi-purpose auditorium, an
exercise center, dining room, private
dining room, and business
center.
It consists of a cast-in-place
concrete structural frame and
post-tensioned floor slabs with
cold-formed metal framing utilized
as the wall in-fills. The metal
studs had been covered with gypsum
sheathing and a #15 felt
weather barrier, utilizing a 2-inch
air space or cavity and nominal 4-
inch-thick brick veneer. The fenestration
included a complex arrangement
of four different colors
of brick as well as white cast
stone elements at copings and
periodic masonry string courses.
In addition, the
building included a
three-story mansard
composed of
standing seam
sheet metal roofing
with a slight radiused
configuration.
Additional architectural
elements
included vertical
notches and offsets,
a lumi n um- a n d –
glass curtain walls,
and private balconies
and terraces.
Terraces and balconies
were provided
with a fluid-applied
deck coating
as a waterproofing
application.
The east and
west elevations are
comprised primarily
of brick veneer
cladding up to the
11th floor level with
one-, two-, and threepane
punched windows
installed approximately
two feet
below the top of slab
at each floor level.
The east and west
elevations have recessed rectangular
unit balconies and radiused
unit balconies that protrude outward
from the building between
the fifth and twelfth floor levels.
Storefront windows, arched storefront
windows, and glass block
windows are provided at the first
floor. A pre-finished metal mansard
with one- and two-pane bay
windows comprise the building
perimeter at the 11th and 12th
floor levels. A large open balcony
deck exists along the west elevation
at the second floor level.
A discontinuous building expansion
joint traverses the building
in the east-west direction near
the center of the building. The
north and south elevations are
clad with building finishes similar
to those described at the east and
west elevations. There is a gazebo
structure adjacent to the northeast
corner of the porte cochere
and there is another gazebo struc-
Proceedings of the RCI 22nd International Convention French – 41
Case Study: Common Design and Workmanship
Issues Related to Brick Veneer
Masonry of a Modern Mid-rise Building
Figure 1 – Typical elevation showing intricate
masonry.
ture on the south elevation at the
roof level. The north and south
elevations also have a curtain wall
that extends between the 5th- and
12th-floor levels. Pre-cast concrete
copings accent the perimeter
lower roof parapet walls, the balcony
terrace handrail walls, and
the handrail walls at the recessed
unit balconies and the radiused
unit balconies. Continuous painted
steel handrails mounted on
small masonry walls were provided
at all balcony areas.
Pre-cast concrete pavers were
installed over rigid insulation and
a concrete topping slab with a liquid-
applied waterproofing deck
coating at the unit balconies at
the fifth floor level located on the
north and south building elevations.
Concrete pavers were also
installed at the second floor balcony
deck that extends along a
portion of the west elevation. The
remaining exterior balconies have
a waterproofing deck coating applied
to a concrete topping slab
that slopes downward away from
the building.
Exterior Wall Cladding
Assemblies
Exterior wall cladding assemblies
were comprised of brick
masonry veneer installed on steel
shelf angles that were attached to
the underlying concrete slab at
each floor. Brick ties were designed
to be utilized at wall locations
to provide additional lateral
support. Elastomeric sealants
have been installed at horizontal
joints where shelf angles were
occurring, at vertical construction
joints of the brick veneer masonry
cladding, and at window perimeters.
Existing brick veneer masonry
cladding is the original cladding
system installed at this project.
The original brick masonry
veneer was an elaborate mixture
of four differently colored brick
with different shapes installed in
various bond patterns and brick
orientations, along
with pre-cast concrete
copings to
form corbels and
accent bands along
all building elevations.
The brick
masonry between
the first and eighth
floor levels was primarily
red and installed
in a running
bond pattern.
Wh i t e – c o l o r e d
brick and pre-cast
concrete copings
were used to form
a corbel accent
band at the second
floor level. Whitecolored
brick was
also used as an accent
band at the
ninth floor level.
White, pre-cast
concrete was used
to accent the edge
of all balconies.
Bricks of various
colors were installed
at the ninth
and tenth floors
levels in a vertical
stack bond pattern
with colors aligned
to form large running accent diamonds.
The brick veneer masonry
is typically supported by galvanized
shelf angles at each floor
level and galvanized steel lintels
were provided at window and door
heads.
Brief History
The property management for
this facility indicated the building
was completed and turned over to
them for occupancy in 1998. The
building envelope ostensibly
remained relatively dry until
Tropical Storm Bertha and Hurricane
Isidore passed through the
New Orleans, Louisiana, area in
August and September 2002, respectively.
The building owner
furnished our firm with markedup
floor plans that depict a total
of 22 locations between floor levels
one and 11 where water intrusion
problems were occurring and
have resulted in considerable
damage to the interior building
finishes. Moisture damage at ten
of these locations had required
mold remediation.
Since these storms, the water
intrusion had caused an on-going
operations problem and the building
owner notified the architect
and the general contractor to
investigate and correct these
problems. Initially, the general
contractor responded in a timely
manner and implemented certain
limited repair attempts. However,
the water intrusion continued
throughout the project due to
inadequate repairs, which as of
our involvement had not corrected
French – 42 Proceedings of the RCI 22nd International Convention
Figure 2 – Cracks in brick veneer at corner.
the building envelope anomalies. The building
owner made arrangements to repair the damaged
interior finishes at the individual living
units and at the common building areas; however,
the water intrusion continued to cause
damage to the building’s interior finishes.
INVESTIGATION AND EVALUATION
Brick Masonry Veneer
Our firm observed widespread efflorescence
stains on the face of masonry units
throughout each elevation of the building.
Efflorescence is normally attributed to faulty
design and construction practices. In addition,
our firm observed that the horizontal
joints in the masonry at the steel shelf angles
were approximately 3/8-in wide and there is
no space between the shelf angle and the
masonry veneer occurring below. This orientation
does not allow an effective means for
accommodating vertical movement due to
thermal expansion within the cladding assembly
or due to deflections and racking of the
structure. The horizontal masonry joint at the
steel shelf angle was completely filled in with
sealant and the through-wall flashing was not
visible. Above this masonry joint were hollow
plastic tubes for weeps. However, at several
locations, the weeps were spaced greater than
16 inches on center. Since the membrane
stops short of the exterior plane of the wall,
since the horizontal joints were filled with
sealant, and since excess mortar
droppings plug up the
weeps and/or dam water
between the weeps, restriction
of drainage from the wall cavity
occurs and eventually
results in water intrusion
inside the building.
Selective demolition and
construction performed along
all building elevations exposed
a typical steel shelf angle and
flashing assembly. Shelf
angles were galvanized and
constructed of bent steel plate
to form a 6-in by 6-in by 3/8-
in angle. At all shelf angle conditions,
the original membrane
through-wall flashing
did not extend out to the outer
plane of the brick wall and
was typically 1-1/2-in short.
Proceedings of the RCI 22nd International Convention French – 43
Figure 3 – Cracks in brick veneer above window.
Figure 4 – Efflorescence and water stains below
brick sill.
Through-wall flashing was
observed to be either a selfadhered
modified bitumen or PVC
membrane.
The self-adhering membrane
flashing at this project was not
lapped properly and the top edge
was detaching from the exterior
sheathing or the concrete structure.
At several locations, this
flashing was pulled down and out
by excess mortar droppings (at
least 4-in high) creating a source
for moisture intrusion into the
building interior. At all locations
where the PVC flashing membrane
was used, the flexible flashing
lap joint was not sealed with
mastic. We observed that the PVC
flashing material was also typically
set dry onto the steel lintel and
the lap joints were not sealed with
mastic. This condition would
cause water infiltration at the
shelf angle to be directed back
under the flashing to the brick
course below and eventually into
the building.
At a few locations, our firm
observed that the waterproofing
applications of the self-adhering
bituminous membranes, the PVC
flashing membranes,
as well as
the wall weather
barrier material
had been burned
or heat damaged
during or after
installation. We
suspect that the
flashing and
weather barrier
applications were
damaged when the
steel shelf angles
were being welded
onto the slab edge
embeds. Unfortunately,
no attempt
was made to repair
these critical waterproofing
materials
prior to erecting
the brick veneer.
At each of the
demolition locations
that were
adjacent to building
columns, CMU,
or concrete shear
walls, it was noted
that the felt weather
barrier was generally poorly
installed at the termination of the
stud wall. We observed terminations
of the weather barrier at
these locations that were
unsealed and were typically discontinuous
across the concrete or
CMU portion of the wall, leaving
exposed cut edges of the sheathing
without any protection against
water absorption from the brick
cavity.
At other selective demolition
locations, at the south end of the
east elevation, where CMU block
walls were erected at a stairwell,
we observed a separation between
the perpendicular CMU walls and
stud walls at inside corners. The
separation typically ranged from 1
to 2 inches wide. In some locations,
it appeared that a selfadhering
waterproofing membrane
was installed to bridge the
French – 44 Proceedings of the RCI 22nd International Convention
Figure 5 – Sealant installed with no backer rod.
Figure 6 – Sealants failing in compression:
masonry cracks.
void. However, in most cases,
adhesion of the waterproofing
membrane had failed, allowing
direct access for water infiltration
at the corners. At many other
locations, the CMU wall was not
installed up to the bottom of the
adjacent slab. In these locations,
there were spaces left between the
slab and CMU that were not
waterproofed. Water can enter
these spaces and traverse the bottom
of the slab by surface tension
to the interior of the building.
Selective demolition of the
pre-cast concrete coping was conducted
at a fifth-floor balcony
handrail parapet along the east
elevation of the building. Selfadhering
flashing membrane was
installed between the precast concrete
coping and the doublewythe
masonry wall, but it did not
extend over the edges of the masonry
wall. In addition, the voids
in the brick and CMU block were
not filled with mortar. The flashing
membrane was typically short
and only partially covered the
voids in the masonry brick and
CMU. This condition would cause
water on the flashing membrane
to infiltrate down to the brick
course below and eventually into
the building. Subsequent to our
initial survey, this assembly was
observed in several locations
along the east and north elevations.
In several locations, dry
sand was observed in the interstitial
spaces between the wythes of
brick, as well as within the brick
units.
Selective demolition of the
pre-cast concrete coping was also
conducted at the third floor roof
parapet and at the juncture
between the pre-finished metal
roofing system and the built-up
roofing system. At these locations,
we observed both design and construction
flaws.
Steel shelf angles and masonry
brick extend behind the curtain
wall at the north and south elevations
between floor levels five
through 12. Selective
demolition conducted along
the north elevation at
the fifth floor level exposed
a large void between
the shelf angle and
the curtain wall frame.
Visual observation made
through an inspection
hole cut at a kitchen wall
in one of the affected units
indicated this void occurs
at similar locations throughout
the height of the curtain
wall. This condition
would cause water infiltration
at the shelf angle
to be directed into the
building at these repetitive
locations.
The steel shelf angle in
the masonry wall below
the fifth floor terrace balcony
and above the windows
at the fourth floor
was exposed along the
east elevation of the building.
Masonry was also
removed at the inside corner
of the wall where it
intersects with the wall that continues
along the north elevation of
the building. Self-adhering flashing
membrane for through-wall
flashing was observed to be folded
and discontinuous, was not
lapped or sealed properly, and did
not extend over the wythe of the
masonry.
At a number of locations, steel
shelf angles were offset vertically
at locations below scuppers at
recessed balcony areas along the
east elevation. Selective demolition
performed at the fourth floor
below a balcony of one unit
revealed the through-wall flashing
to be discontinuous, not lapped
properly, and not extended over
the wythe of the masonry.
The masonry wall at the first
floor along the north elevation of
the building was constructed with
a steel shelf angle that continues
into the porte-cochere plenum
space above the lobby storefront
window system. Selective demolition
was conducted along this
masonry wall, as well as above the
porte-cochere where flashing for
the built-up roofing system was
surface-mounted on the masonry
wall.
In viewing the cavity space
below the masonry wall, we
observed that the steel shelf angle
continues into the porte-cochere
ceiling plenum space and the
through-wall flashing is turned
down. This condition would cause
water infiltration at the shelf
angle to be directed into the building
instead of being directed out
of the building.
Our firm observed stress
cracks within brick courses
directly below the steel shelf angle
at locations along the north and
east elevations of the building. At
the ninth floor level on the north
elevation, two vertical joints in the
brick veneer installed in a vertical
Proceedings of the RCI 22nd International Convention French – 45
Figure 7 – Adhesive sealant failure at
window jamb.
stack bond were repaired
with sealants due to an opening
in the mortar joint.
Additional stress cracks, similarly
repaired with sealant,
were also observed at the
south end of the east elevation,
on lower floors where
the brick is in a running
bond. This cracking and displacement
is normally
caused by excessive compressive
loads being imposed on
individual brick masonry
units without adequate joint
relief below the shelf angle or
due to the lack of a shelf
angle.
Brick Veneer Wall Ties
During the investigation
and renovation at this project,
we observed and documented
numerous anomalies
associated with the brick
veneer wall tie selection and installation. Brick ties
are intended to provide lateral support for masonry
veneer assemblies. Omitting or improperly installing
brick ties on high-rise buildings can be detrimental to
the structural integrity of the cladding system, especially
in areas affected by hurricane force winds.
During the renovation demolition, we observed
widespread periodic omission of specified wall ties or
improper installation of wall ties. In certain locations,
the original installation exhibits one or two missing
wall ties of the six to eight anchor locations visible,
while at other locations, the installation exhibits six
missing wall ties of the 12 anchor locations visible.
Accordingly, lateral support of the brick veneer in at
least some wall areas is completely absent, and in
other wall areas is questionable.
Specifically, our firm observed that wall ties were
regularly missing at and near the concrete columns.
Whereas typical metal stud fastening of the wall tie
anchors was generally adequate, there was generally
no attempt to fasten wall tie anchors into the concrete
columns. In select locations, our firm has observed
improper corrugated brick ties sparsely fastened to
portions of some of the concrete columns.
In addition, we observed that improper wall ties
were used in a number of locations. Generally, corrugated
wall ties are not utilized and are not compliant
with applicable codes for commercial buildings, such
as this facility. At a number of disparate locations
throughout this project, our firm observed corrugated
French – 46 Proceedings of the RCI 22nd International Convention
Figure 8 – Weather-resistive barrier not integrated with shelf angle;
missing wall ties.
Figure 9 – Weather-resistive barrier stops
short of column; not sealed at terminations.
wall ties utilized in lieu of the
specified two-piece wall ties. In
addition, several locations that do
utilize the two-piece wall ties have
the wrong type of tie inserted into
the anchor.
The most frequently observed
improper tie/anchor assembly
installed was a particular type of
adjustable tie installed into a selfdrilling
screw anchor base (incompatible
mating pieces). The
adjustable wall tie product specified
for use is designed for CMU or
double-wythe masonry applications
and utilizes a dual eyehook
anchor to secure the tie. In most
of the improperly installed locations,
a single prong of the tie was
inserted into the two-eyed anchor
base, which does not provide adequate
lateral support for the
masonry.
Steel Shelf Angels and Lintels
Our firm has observed numerous
anomalies associated with the
attachment and orientation of the
steel shelf angles as originally
installed at this project. The welding
of the shelf angles was in poor
condition considering the age of
the building. A number of broken
welds have been observed, as well
as severely corroded welds and
welds that projected more than
one-half inch away from the slab.
In addition, several
of the shelf
angles were so
poorly installed
that they fluctuate
in straightness,
elevation,
and plane over
relatively short
spans. These
anomalies directly
affect the structural
integrity of
the cladding system and made reinstallation
of the brick with proper
waterproofing nearly impossible.
Several lengths of shelf angle
have had to be removed and reinstalled
during the renovation,
as well as having numerous welds
repaired or replaced. In addition,
we observed numerous embeds
that have been skipped over. The
embeds in question were commonly
elevated or dropped below
where they were of practical use,
resulting in notched shelf angles.
The embeds were also commonly
covered in concrete and were not
readily visible.
At a few locations, our firm
observed originally installed shelf
angles at which the steel angle
had rotated downward due to
improper shimming and welding
of the shelf angle at the slab edge
embeds. Such configurations required
those angles to be returned
to their proper position, as well as
properly shimmed and secured to
the slab edge prior to re-installing
the brick cladding.
At a large percentage of the
areas opened up thus far, we
observed that the original shelf
angle was set hard against the
concrete slab edge and protruded
out too close to the front plane of
the brick veneer. This condition
was primarily caused by improper
erection tolerances of the concrete
and brick veneer. At many of
these locations, the current configuration
subjects the shelf angle
to moisture exposure and acceler-
Proceedings of the RCI 22nd International Convention French – 47
Figure 10 – Improper weatherresistive
barrier at corner.
Figure 11 – Missing wall ties at one section of wall.
ated corrosion. In addition, there was not adequate
space to install proposed metal flashings and
sealants. In numerous locations, it has been necessary
to cut the toe of the outstanding leg of the steel
angle, then apply a field corrosion inhibiting paint in
order to properly install the required flashings.
At a number of locations, we observed that the
original shelf angle was installed against the slab
edge where erection tolerances of the concrete and
brick have resulted in the shelf angle providing inadequate
support for the brick veneer (i.e., less than
the two-thirds brick width recommended by the
Brick Institute of America). At these locations, the
front plane of the brick veneer is too far away from
the concrete slab edge and the shelf angle should
have been either shimmed out from the slab embed
or else a shelf angle with larger horizontal leg dimension
should have been provided and installed.
At a few areas, we observed that coursing of the
brick veneer was not properly coordinated with
installation of the steel shelf angle such that, rather
than properly installing these cladding components,
the masonry subcontractor simply saw-cut the back
of each brick to allow the toe of the shelf angle to be
let-in to the back of the veneer. However, since the
shelf angle did not support the brick and there were
hard mortar joints above and below this brick
course, there was no proper relief of the brick expansion
and contraction at these shelf angle locations.
Building Sealants
During the initial investigation, we observed that
original building sealants installed at this facility
within expansion, construction, and perimeter joints
appeared to be failing at numerous locations. Our
firm observed several locations where
adhesion of the sealant along the
jambs and sills of the window frame
had failed, forming voids that were a
source for moisture intrusion.
In addition, we observed that
sealants installed at surface-mounted
counterflashings for base flashings
at the built-up roofing system
installed above the porte cochere
were failing. It was noted that there
were no provisions for expansion
within the counterflashing, and cohesive
failure of the sealant materials
was occurring. We also observed
adhesive sealant failure between the
French – 48 Proceedings of the RCI 22nd International Convention
Figure 12 (above) – Wall ties
improperly installed with one leg
engaged.
Figure 13 – Missing wall ties at one section of wall.
metal scupper and masonry at
several unit balcony locations.
Windows, Storefronts, and
End Wall Curtain Walls
Field leak testing performed
on punched windows along the
east and north elevation proved
inconclusive due to the fact that
no visual indication of water
intrusion through the window
assembly was observed on the
interior of the building. Prior to
leak testing, the juncture between
the window frame and the masonry
was taped-off to isolate the window
assembly. In our opinion, the
field leak testing results give evidence
to the fact that previous
leaks were more than likely associated
with sealant failures and
brick cladding deficiencies, such
as through-wall flashing, improper
steel shelf angles, and the lack
of end dam flashing at steel shelf
angles and lintels.
Our firm observed numerous
windows at all building elevations
where the sealant was failing and
a source for moisture intrusion.
AAMA 501.2 field leak testing performed
on a punched window at
the north elevation (where sealant
adhesive failure exists along the
window jambs and sill) resulted in
immediate water intrusion to the
interior. Selective demolition was
performed and revealed that the
flanged edge of the typical window
frame had not been provided with
sufficient thickness to leave an
adequate bonding surface for
sealants. We also observed that
the self-adhering window head
flashing was pulled down by mortar
droppings and there were no
end dams within that flashing as
recommended by BIA. The selfadhering
windowsill flashing was
folded up to form end dams, but
the length of flashing was not
turned up along the inside face of
the window frame to complete the
end dam. Also, the windowsill
flashing did not extend to the
outer plane of the brick veneer
and could divert water to the brick
below.
During the investigation of
problems, our firm observed that
the window frame extrusions do
not exhibit or provide an acceptable
sealant bond surface along
their perimeter edges. The configuration
of the typical window
frame extrusion provided significantly
less than the one-quarterinch-
wide bond surface typically
recommended by sealant manufacturers
and required by good
construction practice. Accordingly,
it was determined during
the design phase of the renovation
documents that a caulk stop
would be needed to provide an
adequate bonding surface for
sealants along the jambs and
head conditions of the window
frame. The renovation design provided
for appropriate substrates
necessary to apply proper
sealants at these critical junctures.
A spray rack leak test was performed
at an arched window head
at the first floor along the east elevation.
An inspection hole was cut
through the gypsum board
sheathing at the furred-out column
along the right jamb (as
viewed from inside) of this arched
window. We observed that the
metal stud framing at this column
furr-out was rusted due to chronic
water exposure. Selective demolition
of the brick veneer was also
performed at the window head-tocolumn
interface and revealed
that through-wall flashing did not
extend to the outer plane of the
brick veneer. In addition, the
flashing was installed dry and an
end dam was not provided to
divert water out and away from
the wall cavity.
A spray rack leak test was performed
on a storefront window at
the first floor along the west elevation
of the building at the north
end of Art Gallery 2. Our firm
observed that the elevation of the
stamped concrete at the patio was
higher than the windowsill and
water was ponding against the
windowsill during the leak test.
Water intrusion occurred along
this juncture and it appeared the
storefront windowsill was not
Proceedings of the RCI 22nd International Convention French – 49
Figure 14 – Shelf angle offset in elevation; no end dam at membrane
flashing.
installed with end dams, nor was
the windowsill properly sealed to
the concrete slab.
Based on selective demolition
and examination of the original
construction at several fifth floor
terrace locations associated with
the curtain wall systems, our firm
was able to discover the cause of
the chronic, relatively severe
water intrusion occurring at certain
living units.
At these locations, our firm
discovered that the PVC throughwall-
flashing installed at each
floor level terminated within the
brick veneer wall system without
an appropriate end dam or return
flashing. Accordingly, any water
infiltrating the brick wall and collected
on this through-wall-flashing
membrane would be capable
of dropping off the end into the
open wall cavity located adjacent
to these units on each floor. This
condition also allowed the collected
water infiltration to regularly
bypass the perimeter sealant at
the vertical jamb of the curtain
wall assembly.
Balcony Terrace Waterproofing
Selective demolition was performed
at the fifth floor level balcony
and at the second floor balcony
that extends along a portion
of the west elevation. These balcony
areas were originally constructed
with pre-cast concrete
pavers installed over rigid insulation
and a concrete slab having a
fluid-applied, waterproof deck
coating. Selective demolition at
these areas revealed numerous
deficiencies that were sources for
moisture intrusion to the building
interior. It was noted that waterproofing
membrane was applied
directly over the face of the CMU
masonry handrail wall, where several
surface irregularities and
cold joints were observed. In addition,
the base plates and anchor
bolts for the steel frame that support
the wood trellises were rusting
and causing the waterproofing
materials to fail. Adhesive failures
existed at the patch-type liquid
membrane repair made around
these base plates.
Brick removed at the interface
between the terrace deck and the
wall extending along the north
elevation of the building revealed
that self-adhering, through-wall
flashing was installed below the
topping slab and the lateral joints
were improperly adhered, allowing
openings. The top of the selfadhering
membrane was also
pulled down by excess mortar
droppings that were measured to
be ten inches high and plugging
up the plastic tube weeps.
Selective demolition at the second
floor terrace along the west
elevation revealed that the PVC
through-wall flashing material
was dry set onto the steel shelf
angle, the lap joints were not
sealed with mastic, and the flashing
did not extend to the outer
plane of the brick veneer. In addition,
the through-wall flashing
was not integrated with the waterproofing
membrane installed at
the juncture between the concrete
curb and the terrace deck. Mortar
droppings were also measured to
be eight inches high and plugging
the plastic weeps.
Our firm observed that the
waterproofing membrane applied
to the terrace deck exhibited several
blisters. A rubberized flashing
material was installed over the
French – 50 Proceedings of the RCI 22nd International Convention
Figure 15 – Shelf angle offset in elevation; no end dam at membrane flashing.
building expansion joint and integrated
into the deck’s waterproofing
membrane and applied directly
over the face of the concrete
curb.
The membrane flashing material
applied over the face of the
concrete curb was deteriorating
and peeling away from the curb
due to lack of a termination bar
and ultraviolet exposure. The rubberized
flashing material was also
looped downward, forming a gutter
along the length of the building’s
horizontal expansion joint.
This condition allowed the membrane
to retain water rather than
shedding it away from the building.
The precast concrete coping
along the perimeter of the second
floor terrace deck was most likely
installed similarly to the coping at
the fifth floor unit balcony terraces
on the north and south elevations.
The pre-cast concrete
coping had been constructed with
a continuous, welded, metal
handrail that spans across the
building expansion joint, but no
provisions were made for expansion
within the metal rails.
Our firm observed several
locations where stress cracking
existed within the mortar joints
between the pre-cast concrete
copings. In addition, the coping
was displaced at one location.
Scupper drains were observed to
be installed above the elevation of
the concrete slab and the flanges
were not sealed properly to prevent
the infiltration of water into
the brick wall cavity. A considerable
amount of efflorescence and
algae stains also exist on the surface
of brick finishes below the
pre-cast concrete coping. This
condition is indicative of chronic
water contact.
The waterproofing at recessed
and protruding radiused unit balconies
consists of a fluid-applied
waterproofing over a topping slab.
The topping slabs were sloped
towards the double-wythe masonry
handrail walls. Water stains on
the balcony deck indicate that
water is ponding along the masonry
handrail walls. Balcony
deck drain scuppers were provided
but were not flashed and
sealed properly, and were a
source for moisture intrusion into
the masonry parapet wall below.
During selective demolition,
we observed a number of locations
where reinforcing steel rods
for the masonry balcony parapets
penetrated through the self-ad-
Proceedings of the RCI 22nd International Convention French – 51
Figure 16 – PVC flashing lap set “dry.”
hering bituminous flashing membrane
installed at the shelf angle.
No apparent attempt had been
made to repair the flashing membrane
at these damaged locations.
In addition, we observed several
locations where reinforcing
steel required to vertically reinforce
the masonry balcony parapets
was totally missing. It was
noted that these locations
appeared to occur primarily at the
balconies with short parapets;
however, the masonry is completely
unreinforced and it is
questionable whether it meets
applicable design requirements.
Our firm observed several locations
where the CMU used to
support the cast stone was not
filled with grout. In apparently
random locations, the voids within
the CMU were
left empty. On the
fifth floor terrace
on the north elevation,
the CMU is
filled in at approximately
50% of the
locations, while at
the third floor on
the east elevation,
100% of the CMU
is unfilled. Unfilled
CMU has considerably
less structural
integrity than filled
concrete masonry
and may not provide
adequate structural
integrity for
these parapets.
During the renovation
process,
our firm produced
calculations that
indicate the original
fasteners utilized
to secure the
metal handrails to
the top surface of
the cast stone coping
stones were
inadequate for the
c o d e – r e q u i r e d
imposed loads.
Accordingly, renovation of the terrace
perimeters required comprehensive
removal and replacement
of the handrail baseplate fasteners
in order to alleviate this potentially
dangerous life safety issue.
Many of the inserts in question
were prematurely rusting and
deteriorating due to exposure to
weather conditions. Calculations
by our firm have shown that the
attachment of the handrails to the
cast stones is insufficient to support
the 50 lbs. per linear foot of
lateral force required to meet
building code.
Miscellaneous Anomalies
At the north elevation and at
the porte cochere roof level, surface-
mounted counterflashing
was installed at the juncture with
the double-wythe masonry wall.
Selective demolition at this condition
revealed that the throughwall
flashing was installed below
the counterflashing and there is
no method for extracting water
from the wall. This total lack of
coordination between the flashing
installations was evidence of inadequate
design and poor workmanship.
Along the west elevation at the
second floor level, the masonry
wall on the north side of the
building expansion joint is not
supported by a raised concrete
curb. Our firm was not able to
observe flashing at the juncture
between the masonry wall and the
terrace deck because there would
not be a method to temporarily
waterproof this assembly if selective
demolition were performed.
Blisters and tears in the balcony
deck waterproofing membrane
could allow water to infiltrate into
the building through the unsealed
flashings.
During our initial investigation,
ceiling tile of the suspended
ceiling system at the north end of
Art Gallery 2 was removed. This
allowed us to observe the structural
framing system along the
underside of the building expansion
joint. Our firm observed rusted
metal framing on the north
side of the expansion joint and
behind the masonry wall that is
not supported by a raised concrete
curb. We also observed
water seeping along the horizontal
offset portion of the building expansion
joint between the main
building and the second floor balcony
deck. Selective demolition
was conducted on a small portion
of the special expansion joint
material and revealed that the
expansion joint material was not
properly integrated into the waterproofing
membrane that is
installed behind the brick veneer.
Along the east elevation at the
third floor level, the building ex-
French – 52 Proceedings of the RCI 22nd International Convention
Figure 17 – Coordination error in shelf angle
placement; back of brick saw-cut.
pansion joint is horizontally offset
in the north-south direction between
the masonry wall and the
metal roofing system. Our firm
observed that no provisions for
expansion in either the longitudinal
or traverse directions were
designed or constructed for the
pre-finished metal roof system
that traverses the building expansion
joint along the east elevation
at the third floor level. The prefinished
metal roofing system was
observed to be oil canning and
was installed directly under the
pre-cast concrete coping. Our
firm observed water ponding on
the metal roof and along the
inside face of the pre-cast concrete
coping due to the lack of
adequate slope for positive drainage
towards scuppers. Also, thermal
expansion in the pre-finished
metal roofing system is causing
the seams to separate and buckle
at various locations.
Our firm observed several
scuppers at unit balconies that
were not installed and flashed
properly. Voids exist between the
flanges of the metal scupper and
masonry and were a point source
for moisture intrusion. A recessed
balcony condition that we viewed
at one of the units also exhibited
water ponding stains along the
length of the handrail parapet
wall due to the lack of adequate
slope towards the scupper.
We observed that the elevation
of stamped concrete at the patio
on the west side of the building
was higher than the building slab
at the storefront window system.
Water was ponding against the
storefront windowsill and infiltrating
the building.
There were numerous locations
where trash of various kinds
was found within the wall cavity,
including empty masonry cement
paper bags, Visqueen, and miscellaneous
construction debris. Although
not detrimental to the wall
cladding itself, these cellulose materials
will absorb and retain
water within the
wall, provide a food
source for termites,
and should
not have been
stashed behind the
veneer during the
original construction.
Each location
opened up during
the investigations
conducted near existing
dryer and
exhaust vents was
completely lacking
in proper closure
of the exterior
sheathing, repair
and integrity of the
weather barrier,
and installation of
proper waterproofing.
There were
numerous locations
where the
wire ties used during
construction
for scaffold tiebacks
had been
simply cut off at
the front plane of
the brick and either left unsealed
or else inadequately sealed, allowing
excessive amounts of water
into the masonry cavity.
Selective Demolition
Visual examination during the
initial selective demolition of the
building exterior was conducted
in 2003 and facilitated by the use
of ladders and two motorized
hydraulic telescoping boom platform
lifts. Five locations on the
north elevation, eight on the east
elevation, one on the west elevation,
and one at a particular balcony
(total of 15 locations) were
selectively demolished to expose
the condition of both the building
envelope assemblies and the
underlying (concealed) waterproofing
system. Many building
envelope locations that were demolished
were located immediately
above or immediately below
steel shelf angles that were installed
to support the brick masonry
veneer at that floor. It was
noted that several of these conditions
were observed to be occurring
on a consistent basis.
Subsequent to implementation
of the original scope renovation,
significant and severe conditions
not previously observed or
thought to be prevalent were encountered
during the initial selective
demolition for the planned
leg-and-leg renovation.
This situation prompted our
firm to recommend that additional
investigation of the exterior
cladding be made on a more widespread
basis to verify the conditions
observed. Once approved by
Proceedings of the RCI 22nd International Convention French – 53
Figure 18 – Flashings oozing; weep tube
clogged.
the building owner, we performed
limited selective demolition openings
at all elevations of the building
on an additional 49 locations
occurring at various floor levels.
These additional investigations
were facilitated by the use of
frame scaffolding and motorized
hydraulic telescoping boom platform
lifts. Documentation of the
conditions observed at those locations
was made by field notes,
sketches, and photographs.
In general, the conditions
revealed at these additional study
locations were repetitive and consistent
with the observations
made at the initial legand-
leg selective demolition
areas that
prompted the study.
Specifically, our firm
observed: 1) significant
and widespread wall
areas where appropriate
brick veneer ties
had been omitted or
improperly installed, 2)
unsealed penetrations
through the exterior
sheathing at the
drainage cavity, 3)
improper installation of
shelf angle flashing
membranes, 4) inconsistent
and discontinuous
shelf-angle flashing,
5) flexible electrical conduit
located within the brick veneer
drainage cavity, and 6) unsupported
or improperly supported
steel shelf angles.
An analysis of the results from
the initial selective demolition
related to the leg-and-leg renovation,
as well as the additional investigation
of these 49 locations,
ultimately led to a recommendation
by our firm that the entire
exterior brick cladding be completely
removed and replaced.
This recommendation was approved
by the building owner and
a change order was written to
increase the scope of work to a
c omp r e h e n s i v e
cladding renovation.
Additional materials
were ordered
and the comprehensive
cladding renovation
was begun in
earnest during December
of 2004.
Beginning with
the comprehensive
cladding renovation
scope of work that
was implemented in
late 2004 and continuing
until mid-
2006, our firm continued
services related to quality
assurance and documentation of
the conditions being uncovered on
an on-going basis by the renovation
contractor’s selective demolition.
This documentation has
been provided predominately in
the form of photographs, with a
log related to location, orientation,
and subject matter. In this manner,
our firm produced approximately
2,000 photographs taken
throughout the exposed cladding
areas since implementation of the
renovation work.
CONCLUSIONS
This paper is intended to enumerate
and discuss the cause of
numerous building envelope
anomalies observed at this
facility. Based on our initial
investigations, as well as
observations during selective
demolition activities of the
renovation, it is our opinion
that the design- and construction-
related problems
documented in this report
were systemic problems that
existed throughout the entire
building envelope.
Our firm conducted initial
investigations pertaining to
field leak testing of representative
windows, brick veneer
cladding, and precast concrete
copings. Field leak testing of
brick cladding and windows
revealed that selective demolition
was needed to inspect the installation
of shelf angles and flashing
materials. Based on our firm’s
observations of areas that were
leak tested and where selective
demolition was performed, the
primary sources of water intrusion
were due to insufficient
waterproofing design details and
poor workmanship. These types of
problems were observed to be
consistently occurring at the locations
that were tested.
In general, the building envelope
at this facility was, at the time
of our initial investigations, in fair-
French – 54 Proceedings of the RCI 22nd International Convention
Figure 19 – Mortar bridging at wall tie.
Figure 20 – Mortar bridging at wall tie.
ly poor condition
considering its age.
Specific examples
of this general
statement include
numerous and prevalent
defects within
the brick veneer
exterior cladding,
including efflorescence,
stress cracking,
the apparent
lack of appropriate
w a t e r p r o o f i n g
design details, deteriorated
building
materials, and hidden
defects related
to substandard workmanship.
Examples
of substandard workmanship
include
missing brick ties,
inadequate welds,
exposed flexible metal
conduit, and general
inattention to
detail at shelf angle
flashing locations.
Each of these defects
would require
comprehensive renovation,
including
complete removal
and replacement of
the cladding system.
In our opinion,
the extent of this
renovation program
was ultimately required and dictated
by the widespread, systemic,
and severe construction
defects found throughout the
exterior cladding systems of this
building, which were responsible
for the interior leakage experienced.
During the renovation process,
our firm produced calculations
that indicate the original
fasteners utilized to secure the
metal handrails to the top surface
of the cast stone coping stones
were inadequate for the coderequired
imposed loads. Accordingly,
renovation of the terrace
perimeters has required comprehensive
removal and replacement
of the handrail base plate fasteners
in order to alleviate this potentially
dangerous life safety issue.
Many of the inserts in question
were prematurely rusting and
deteriorating due to exposure to
weather conditions. Calculations
by our firm have shown that the
attachment of the handrails to the
cast stones is insufficient to support
the 50-lbs-per-linear-foot of
lateral force required to meet
building code.
Field leak testing was conducted
on one three-pane
punched window, four three-pane
punched windows, two storefront
windows, one arched store-front
window, brick
cladding at two steel
shelf angles, and at
one pre-cast concrete
coping along
the north, east, and
west elevations to
determine the waterproofing
integrity
of these assemblies,
as well as their potential
contribution
to previous and existing
wall cladding
deficiencies. At each
of these locations,
significant water intrusion
to the building
interior was experienced.
Exterior Wall
Cladding
Based upon our
visual survey of exterior
cladding systems,
it appears that
the waterproofing of
brick masonry veneer,
window openings,
balcony decks,
building expansion
joints, and pre-cast
concrete copings at
this project were performing
poorly,
resulting in significant,
widespread
water intrusion. This opinion was
based upon the prevalent occurrence
of efflorescent stains, the
reported water intrusion problems
that exist throughout the building
envelope, as well as the extent of
hidden waterproofing and building
cladding deficiencies that have
been exposed and documented by
our firm. These defects indicate a
general lack of adequate waterproofing
design details and poor
workmanship associated with the
waterproofing and masonry construction.
It is apparent that masonry
flashing at this project was not
installed in conformance to the
Brick Institute of America’s (BIA),
Proceedings of the RCI 22nd International Convention French – 55
Figure 21 – Excessive mortar droppings in drainage cavity.
Technical Note 7 (revised,
February 1985), “Water
Resistance of Brick Masonry
Design and Detailing Part I of
III.” Flashing installation
methods include the use of
end dams and indicate flashing
pieces should be lapped
at least six inches and the
laps sealed with mastic or an
adhesive compatible with the
flashing material.
The investigation performed
to date indicates that
improperly installed brick lintels
and shelf angles were allowing
the transfer of weight
from sections of brick veneer
wall cladding to underlying
sections of brick veneer wall
cladding, creating compressive
forces that unit brick
were not capable of resisting.
Brick “failure” is the result.
Conditions where the contractor
failed to provide adequate
clearance between
shelf angles and underlying sections
of brick veneer were allowing
transfer of the weight (load) from
one section of wall to the section
below. The accumulation of these
forces had caused the brick
veneer to crack, forming unsealed
openings in the cladding system
which, in turn, were contributing
to the water intrusion and the
eventual deterioration of the shelf
angles and masonry anchors.
Both primary and secondary
building components identified as
faulty within this paper were slated
for comprehensive corrective
work in order to alleviate the
design and construction defects
occurring during the original construction.
Particular areas of concern
include the widespread
amount of efflorescent stains,
poorly installed through-wall
flashing, improper type of masonry
weeps throughout the entire
building, inadequately designed
and installed shelf angle waterproofing
flashing, improperly
placed steel shelf angles and poorly
installed shelf angle welds, improper
brick tie spacing and
installation, omitted brick wall
ties, unsealed penetrations
through the sheathing caused by
installation of flexible metal conduit
within the drainage cavity of
the brick veneer, poorly installed
and designed handrail fasteners,
and sealants installed at horizontal
shelf angle joints, vertical
building joints, and window
perimeters.
Based on our observations
and testing, it was the recommendation
of our firm that each of the
design anomalies and construction
defects outlined above were
indicative of an interlacing network
of systemic and chronic construction
deficiencies that have
manifested numerous locations of
water intrusion occurring throughout
the cladding system of this
building under normal rain
events. These conditions have resulted
from a combination of improper
design details at specific
locations and an apparent lack of
concern on the part of the general
contractor and certain key subcontractors
regarding proper
workmanship, conformance with
code-stipulated construction criteria,
and compliance with general
industry practice.
The overwhelming magnitude
and severity of the combined
design and construction defects
within the cladding system at this
property left no alternative but to
recommend a comprehensive renovation
of the exterior cladding
system involving complete removal
and replacement of the brick
veneer and cast-stone coping elements,
correction of deteriorated
sheathing and improperly installed
weather barriers, implementation
of new flashing details
at shelf angles and penetrations
through the exterior sheathing,
correction and repair of the balcony
and terrace waterproofing
applications, and replacement of
failing and improperly installed
sealant applications.
In our opinion, there were a
number of significant and critical
French – 56 Proceedings of the RCI 22nd International Convention
Figure 22 – Improper weld between shelf angle and embed.
design details that were
either improperly executed
by the architect-of-record,
executed with insufficient
and incomplete (vague) information,
or else omitted
completely. In addition, our
firm discovered a number
of conditions that were
contrary to and not in compliance
with local building
codes. In our opinion,
these design deficiencies
have significantly contributed
to the construction
problems and water
intrusion issues that have
been so pervasive at this
property.
Specific examples of the
design deficiencies include,
but are not limited to,
improper through-wall
flashings at the cast stone
copings of the balcony and
terrace parapet walls, improper
through wall flashings at the terrace-
to-rising wall elevations,
improper design and assembly of
the metal roof perimeter at the
third floor, lack of forethought
regarding location and interference
of steel shelf angles with
other fenestration components,
poor selection and integration of
flashing membranes, omission of
specific detailing regarding flashing
end dams, and lack of specific
detailing for expansion relief within
the metal handrails of the second
and fifth floor terraces. In our
opinion, the vague, contradictory,
and omitted design details originally
provided by the architect for
this project were deficient and violated
the standard of care for projects
of this size and scope and
located in this geographic area.
In our opinion, the most pervasive
and damaging aspects of
the construction defects were the
widespread and prevalent examples
of poor workmanship realized
during the original construction,
particularly as they relate to the
assembly and integration of the
various components of the exterior
building envelope. Significant,
repetitive problems were observed
and documented throughout the
installation of the cladding system
with respect to steel shelf angles
(masonry structural support),
coordination of the brick veneer
with their support systems (as
well as other aspects of the fenestration),
integration and lateral
support of the brick veneer using
appropriate wall tie assemblies,
omitted wall ties, lack of continuity
and integration of membrane
flashing systems with wall components
and weather barriers, lack
of properly spaced weep holes,
omitted weep holes, lack of attention
to detail with respect to component
functionality, inconsistent
installations of wall components
with respect to elevation and continuity,
as well as “sloppy” workmanship
with respect to keeping
the brick drainage cavities clear of
debris and mortar droppings, and
application and tooling of sealants.
Each of these deficiencies
represents a direct violation of
building code requirements
and/or noncompliance with generally
recognized construction industry
standards.
Balcony and Terrace
Waterproofing
Balcony and terrace waterproofing
applications at this project
consisted of fluid-applied polyurethane
deck coating materials
that appeared to be adequately
applied, except with respect to the
lack of coordination with perimeter
masonry walls and parapets,
as well as other fenestration components
such as penetrations and
curtain walls. At a number of
locations, the original flashing
assemblies had no chance of
properly collecting water infiltration
and discharging it from the
wall due to inconsistent installations,
improper coordination of
flashing heights, and lack of weep
provisions. Once again, these
anomalies appeared to be the
result of both improper or omitted
detailing, as well as gross negligence
on the part of the trades
involved to properly install these
components in a workmanlike
manner. In our opinion, these
anomalies were the direct cause of
Proceedings of the RCI 22nd International Convention French – 57
Figure 23 – Broken weld at shelf angle attachment.
a certain percentage of
leakage occurring at these
locations (and below), and
required comprehensive
renovation of the terrace
perimeter flashings and
cast stone copings.
Roofing Systems
Our firm was not provided
with any information
of deficiencies within the
main roof system of this
building during our initial
investigation, and therefore
did not conduct a
thorough evaluation of the
gravel-surfaced, built-up
roof assembly at this level.
However, a cursory assessment
indicated that the
main roof level installation
is serving its intended purpose,
and a non-destructive
roof moisture survey
conducted in early 2006
(after Hurricane Katrina)
indicated continued
acceptable performance with only
minor, isolated exceptions. However,
although the main roof level
had been designed and constructed
with fixed internal drains for
the primary drainage, this facility
had not been provided with emergency
overflow drains, which was
a violation of the Standard Building
Code (SBC) at the time of construction.
In addition, we observed significant
design and constructionrelated
problems with the lowslope,
sheet metal roof installed at
the third floor of the east elevation,
including single scuppers
used as primary drains, direct termination
and contact of the metal
panels against the cast stone coping
joint, chronic water retention
against the coping mortar joint,
and lack of coordination with the
height of the roof and the height of
the adjacent windowsills. In our
opinion, the combination of these
deficiencies was significant and
severe enough to warrant complete
removal and replacement of
this roof system.
At the porte cochere roof, our
firm observed that the height of
this roof was not properly terminated
against the main portion of
the building and the through-wall
flashing had been inconsistently
installed with end dams omitted.
Based on our investigations, these
conditions were responsible for a
majority of the past water leakage
occurring at the main entry
vestibule and storefront. In our
opinion, it was necessary and
prudent to provide for the renovation
of the flashing and expansion
joint assemblies in this area.
Miscellaneous
During the investigation of
problems at this project, our firm
observed that the window frame
extrusions provided for this project
do not exhibit or provide an
acceptable sealant bond surface
along their perimeter edges. Configuration
of the window frame
extrusion provides significantly
less than the one-quarter-inchwide
bond surface typically recommended
by sealant manufacturers
and required by good construction
practice. In order to alleviate
this condition and avoid premature
sealant failures, it is our
opinion that the renovation design
had to provide for appropriate
substrates (caulk stops),
which were required to retrofit the
existing windows so that sealants
can be properly applied with adequate
bond surface.
French – 58 Proceedings of the RCI 22nd International Convention
Figure 24 – Extent of scaffolding during renovation for occupied building.