Skip to main content Skip to footer

Engineering Tomorrow’s Envelopes: Smart Blue Roofs Pioneering Sustainable Building Practices

January 16, 2026

By Jason Paulos, MBSc, LEED AP; Sal Alajek, RRO, PEng; and Sidney Picco, MSc and BASc

INTRODUCTION
Urbanization has altered the natural hydrological
cycle, leading to significant challenges in
managing stormwater in densely populated
areas. The reduction in green spaces has resulted
in increased surface runoff, higher solar radiation
absorption, and diminished evaporation rates, all
of which complicate water management in urban
settings.1 With climate change fueling more
frequent and severe storm events, traditional
stormwater systems are becoming increasingly
inadequate, resulting in localized flooding that
endangers public safety and property.2,3
To address these challenges, there is a growing
focus on blue roof technologies, which offer
opportunities for managing rooftop runoff. Blue roof
systems capture rainwater and store it temporarily,
allowing it to evaporate, be stored for reuse, or be
released over time to reduce the peak flow into the
municipal stormwater system.4 Additionally, blue
roofs enhance urban microclimates and conserve
water by storing rainwater for irrigation and toilet
flushing.1,3 They can also lower cooling demands
through evaporative cooling during hot weather.1
Research highlights the effectiveness of blue
roofs in reducing stormwater runoff, especially
in older urban areas with combined storm and
sanitary sewers, where the risk of sewer overflows is
particularly high.3
Given that low-slope roofs account for
approximately 28% of urban surfaces in North
America, according to satellite imagery studies,
they represent an opportunity for stormwater
management. This can mitigate environmental
impacts and promote sustainable urban
development amid ongoing urbanization and
climate change.4,5

TECHNOLOGY CLASSIFICATION
The concept of a blue roof has gained
prominence as an innovation for stormwater
management, setting it apart from traditional
vegetative roofs. Blue roofs can be categorized
based on their stormwater detention methods
into the following designs:
Roof-integrated design (RID) utilizes either
the entire roof or a portion thereof, with
modifications made to roof drainage inlets to
achieve a slower drainage rate into a leader pipe,
allowing water to accumulate on the roof surface,
as shown in Figure 1.6
RID systems can be passive or active. Passive
systems incorporate roof dams and checks or
drain inserts with an orifice that reduces flow
compared with conventional drains, as shown
in Figure 2. A check-dam system is constructed
with a series of partitions or weirs, each fitted
with openings at their lowest point. These
openings are strategically created to avert
the continuous water pooling and to facilitate
a steady flow of rainwater toward the roof’s
drainage point.1 On the other hand, active
systems feature remotely controlled valves
often governed by programming to manage
detention levels. These active systems may
also utilize algorithms and sensors to adapt to
varying weather conditions. By anticipating
and responding to weather patterns, active
RID systems optimize stormwater detention
and release, mitigating the risk of overflow
during intense rainfall events.4 Whether
passive or active, RID necessitates a roofing
system capable of performing under volumes
of ponded water for possibly extended periods
of time as compared to typical low-slope roof
system designs.
Modular tray design (MTD) incorporates
modular systems, such as tray-based systems,
which can be positioned on rooftops to store
and manage stormwater. These trays are
typically filled with porous media, enabling
controlled drainage through weep holes at the
base, complemented by various outlet drains
customizable to project requirements.4 The
flexibility of this design allows for selective
installation across diverse roof surfaces,
particularly in areas with structural loading
constraints or where rooftop equipment
must be accommodated.4 The trays can
either be freestanding, secured in place with
weighted materials, or attached directly to
the roof structure. MTD systems demand
less maintenance than other methods; they
can offer water detention capacity separated
from the roofing membrane, making them a
practical retrofit choice or an additional feature
without necessitating extensive roof assembly
modifications.4
“Blue-green” roofs integrate features of both
blue and vegetative roofs by incorporating
vegetation and growing medium layers above
ponded water. Blue-green roofs can either
utilize roof-integrated or modular designs. They
are designed like traditional vegetative roofs but
feature an expanded drainage layer, facilitating
enhanced evapotranspiration and enabling a
controlled, gradual release of stormwater.7,8
HISTORY AND MODERN
APPLICATIONS
Low-sloped roofs are defined by roofing
membrane systems installed on slopes of 25%
(1 in 4) or less.9 Flat roofs, a subset of low-sloped
roofs, have a minimum slope of 2% (1 in 50) to
ensure proper drainage.9 The historical use of low-sloped roofs can be traced back to ancient
civilizations in the Mediterranean, Africa, and
Asia, where the climate was conducive to such
architectural designs.10 In contrast, regions with
more severe weather conditions, characterized
by heavy rainfall, traditionally favoured pitched
roofs to prevent water accumulation and
potential structural damage.10
The 19th century saw an increase in lowsloped
roofs for residential buildings in urban
areas across Europe and North America.
Traditionally, these low-sloped roofs utilized
tar and gravel surfaces, which provided an
effective barrier against water as long as
proper drainage was maintained. This method
involved layering roofing felt, applying mastic,
and embedding silver-gray gravel into the
top layer to prevent the surface from drying
out.10 However, these materials were less
successful in colder climates, where ice dams
and sagging could impede water flow and
disrupt drainage.10 European construction laws
influenced low-sloped roof trends to maximize
building heights within city landscapes.10
Notable architects such as Le Corbusier and
Frank Lloyd Wright also popularized low-sloped
roofs in residential architecture during the early
20th century. Le Corbusier’s “Five Points of a
New Architecture,” published in 1926, promoted
low-sloped roofs’ functional and aesthetic
benefits, advocating for their use as gardens and
terraces to reclaim urban green spaces.11
The 1960s introduced bituminous felt roofing
sheets, offering a lightweight and cost-effective
alternative for roof coverage. Despite these
advantages, the material was prone to leaks and
had a limited lifespan.12,13 This was due to the
nature of the bituminous material, which could
become brittle and crack under extreme weather
conditions, leading to water ingress and damage.
In addition to bituminous felt, other roofing
systems, such as metal roofs and EPDM roofing
systems, were also being used.
In the 1970s, the roofing industry saw
the advent of vegetative roofs, which were
complemented by advanced waterproofing
and drainage systems, culminating in the
development of low-maintenance “extensive
vegetative roofs” by the decade’s end.14 In the
mid-2000s, many municipalities across North
America began encouraging vegetative roofs for
new public and private buildings, recognizing
the potential savings from reduced energy
consumption, mitigation of the urban heat-island
effect, and decreased stormwater infrastructure
costs.15 In 2009, Toronto became the first city
in North America to mandate vegetative roofs
for certain new developments, along with
stipulating minimum construction standards.16
In the 2010s, blue roofs emerged as an
approach to stormwater management. The
New York City Department of Environmental
Protection conducted several pilot studies in
2011 and 2012 to evaluate the effectiveness
of blue roofs. These studies involved the
installation of various modular tray systems and
check-dam systems at multiple sites to monitor
rainfall retention and detention rates. At one
location, four different tray systems were tested
at a community center to measure their outflow
rates and assess performance. Similarly, at a
storage facility on Metropolitan Avenue, the roof
was divided into sections to test various drain
inlet modifications and tray systems. These
pilot projects consistently demonstrated peak
flow reductions of 85% to 90%.17 However, the
study did not explore the impact of different
roof membrane types and their long-term
performance.
Subsequent research has broadened the
scope of blue roof studies. Campisano et al.18
conducted a full-scale pilot installation of a MTD
system on the University of Catania’s campus in
Catania, Italy. The study compared a section of
the roof equipped with the MTD system against
an unmodified section, observing an average
of 54% retention efficiency and 72% detention
efficiency for MTD system.18
Almaaitah et al.19 assessed a blue-green
roof’s hydrologic and thermal performance
during the 2021 growing season at the George
Vari Engineering and Computing Centre at the
Toronto Metropolitan University. The roof was
comprised of a 50 mm compost layer, a 250 mm
substrate, a filter sheet, a 50 mm drainage
layer, a root barrier, and a roofing membrane
arranged from top to bottom. The membrane
and drain system were not mentioned in the
study. The research highlighted the roof’s water
retention capability, with average rates between
85% and 88% and peak stormwater attenuation
of 82% to 85%.19 Temperature-wise, the study
observed a mean air temperature reduction
of 1.4°C to 2.5°C, varying with the type of
vegetation.19 Notably, the cooling effects were
more significant in the afternoon and evening,
while a warming trend was noted in the early
morning.19
While prototypes exist for tray systems, checkdammed
systems, and blue-green roofs, limited
research and case studies exist for RID systems,
flagging a potential area for further research
and development. This gap in research limits
practitioners’ understanding of RID systems and
their performance across various membrane types.
RELEVANT CANADIAN
CODES AND STANDARDS
While specific standards for blue roofs have yet to
be established within Canadian building codes
and standards, the principles for general roof
design remain pertinent. This section examines
how existing roofing codes and standards can be adapted to blue roof applications, ensuring their
functional and structural integrity.
The 2020 National Plumbing Code (NPC)
contains provisions for roof drainage relevant
to blue roofs. Section 2.4.10.4(1) determines
the maximum hydraulic load used to establish
the minimum leader size for the roof drain. For
roof drains with flow controls, the hydraulic
load is determined using a 25-year rainfall
intensity-duration-frequency curve provided by
Environment Canada.20 NPC clauses 2.4.10.4(2)
and (3) stipulate that water stored on the roof
should not remain for more than 24 hours and
have a maximum depth of 150 mm (6 in.).20
Additional clauses in the NBC 2015 specify the
location of drains, which must be no more than
15 m (49 ft) from the edge of the roof and no
more than 30 m (98 ft) from adjacent drains.20
Additionally, overflow scuppers must be installed
no more than 30 m (98 ft) apart along the
perimeter of the building to prevent structural
overloading of the roof if drains fail.20 However,
the NPC does not mandate specific roofing
membranes.
Many regionally specific codes, such as
the 2012 Ontario Building Code (OBC), share
requirements comparable to those of the
NPC drainage guidance. The distinction lies
in the sourcing of environmental data, where
references in the OBC must adhere to the
Ministry of Municipal Affairs and Housing
(MMAH) Supplementary Standard SB-1 instead
of NPC data.21
Different municipalities and regions may
also have specific stormwater management
and retention requirements. For example,
the Toronto Green Standard (TGS) Version 4
applies to new site plan applications for fourstory
or higher residential buildings and all
industrial, commercial, and institutional (ICI)
developments.22 Within the water quality and
efficiency prerequisite WQ1.1, Water Balance,
Quality & Quantity Control, there is a mandate
to retain 50% of the total average annual
rainfall volume, remove 80% of total suspended
solids, and control E. coli for discharges to Lake
Ontario or waterfront sites.22 Peak flow control
is also required; however, challenges arise in
implementing blue roofs under prerequisite
WQ1.3, On-site Green Infrastructure, due to
conflicting requirements, such as minimum
vegetative roof coverage, which can be
up to 80% of available roof space.22 These
requirements pose challenges in blue roof
implementation, with the standard specifications
supporting vegetative roof infrastructure.
Designers may consider implementing blue
roofs in the remaining available roof space or
installing a hybrid blue-green roof to meet the
Toronto bylaw requirements. The City of Toronto
also has a Wet Weather Flow Master Plan, which
sets wet-weather flow-management targets for
water balance, quality, and quantity. Table 1
in Section 2.2.1, Water Balance, lists examples
of on-site stormwater management practices
depending on the type of land use.23 For
example, commercial and industrial buildings
may implement vegetative roofs, rooftop
restrictors, and rainwater harvesting.
CSA A123.26:21, Performance Requirements
for Climate Resilience of Low Slope Membrane
Roofing Systems, lists even more stringent
recommendations related to drainage. The
standard outlines the requirements for lowsloped
membrane roofing systems to achieve
different ratings related to climate adaptation.
According to Clause 7.2.8, water should not run
more than 10.7 m. (35 ft) to a primary drain or
scupper to achieve a silver performance rating.24
For a gold performance rating, Clause 7.2.13
stipulates that water should not travel more than
6.1 m (20 ft) to a primary drain or scupper.24
CSA 478:19, Durability in Buildings, provides
minimum requirements to assist designers
in making design decisions, reviewing
construction, and performing building
maintenance in existing and new construction
projects.25 Blue roofs can influence the
lifespan and performance of a building due to
their unique construction and environment.
For example, Sections 4.3 and 4.4 of this
standard state that all foreseeable agents and
mechanisms that could impact durability and
performance must be considered and accounted
for during design, construction, repair, and
maintenance.25 Similarly, Section 8.3, clauses (b)
and (c), specify that the materials selected must
be appropriate for the structure’s environment,
design loads, and differential movements.25
Section 4.6.2 stipulates that a maintenance
and inspection plan should be developed for
building components, including repair and
replacement.25 This makes proper material
selection for the waterproofing membrane and a
thorough maintenance and repair plan essential
for blue roofs.
Leak detection is an important consideration
for blue roof systems. It can provide quality
assurance during construction and a mean of
leak diagnostics and monitoring for the life
cycle of the roof assembly. In considering leak
detection during design, the following standards
offer guidelines and requirements for electronicdetection
components: ASTM D7877, Standard
Guide for Electronic Methods for Detecting and
Locating Leaks in Waterproof Membranes, and
ASTM D823, Standard Practice for the Use of
a Low Voltage Electronic Scanning System for
Detecting and Locating Breaches in Roofing and
Waterproofing Membranes.26,27
Lastly, CSA B805:22/ICC 805:22, Rainwater
Harvesting Systems, provides comprehensive
guidelines for the design, materials, installation,
and operation of rainwater harvesting systems,
covering potable and non-potable applications
and water treatment.28 It can apply to blue roofs
if detained water is reused within the building for
potable or non-potable uses.
CASE STUDY
Building Description
The Credit Valley Conservation (CVC) Head
Office, located at 1255 Old Derry Road in
Mississauga, ON, consists of two buildings,
A and B, connected by a one-story corridor.
Constructed circa 2010, Building A is a four-story
steel-framed structure with a one-story garage
on the southeast elevation (Fig. 3 and 4). The
floors and roof slabs are supported by steel
beams connected to steel columns anchored to
cast-in-place footings. Building A has three roof
sections: the main roof (A-1), the garage roof
(A-2), and the elevator pit room (A-3), as shown
in Figure 5. Mechanical equipment on the west
side of roof A-1 sits within an open-air screen
enclosure. The approximate area of roof A-1 is
645 m2 (6943 ft2).
The main roof structure of Roof A-1 is a
250 mm (10 in.) thick hollow-core slab. On top
of the slab is a concrete topping that measures
230 mm (9 in.) at the perimeter, tapering to
50 mm (2 in.) at the center to facilitate drainage.
The existing roof assembly is a conventional
system that includes a self-adhered vapour
barrier, 125 mm (5 in.) of EPS insulation adhered
in place, and a 12.7 mm (1/2 in.) fibre board
adhered in place. The system is capped with
a single-ply fully adhered TPO membrane, as
depicted in Figure 6.
Roof A-1 does not have overflow scuppers.
The existing parapet height is 400 mm
(16 in.). Building A has seven drains. CVC
Head Office Building A was designed in
2008 by Montgomery Sisam Architects Inc.
Accordingly, the 2006 Ontario Building Code
was the applicable building code at the time
of design and permit issuance. Design loading
was in accordance with Part 4 of Division B.
Environmental loading data for Mississauga was
per Supplementary Standard SB-1.
FEASIBILITY STUDY
Project Background
In October 2017, the CVC authority began
exploring the feasibility of implementing an
RID blue-roof pilot project installation at their
office building. This pilot project was seen as an opportunity to test the effectiveness of
this emerging technology in managing storm
peak load, reducing energy consumption, and
determining the non-potable demand that could
be met by the existing rainwater harvesting
(RWH) system.10 Over the following months, CVC
engaged with internal and external stakeholders
to refine the project concept and secure funding.
Due to its size and relatively minimal mechanical
and conduit congestion, Roof A-1 was identified
as a candidate for the installation of the blue
roof system.
In light of the prevailing code regulations
in 2017, which allowed a maximum rainwater
drain-down time of 24 hours per day and a
maximum roof rainwater level of 150 mm (6 in.),
CVC entered pre-consultation and technical
discussions with the City of Mississauga Building
Department to determine the legislative
requirements for a blue roof. In addition to
complying with the general requirements of the
OBC, two alternative solutions were proposed
under OBC Division C to maximize the benefits of
a blue roof.
The first alternative, Solution A, proposed
extending the maximum allowable rainwater
drain-down time to six days. This extension
aimed to increase the amount of water stored
while also including provisions for reducing
the likelihood of mould or mildew growth and
the risk of illness from unsanitary conditions
caused by contaminated surfaces and vermin.29
This latter concern was particularly pertinent
in relation to Culex mosquitoes, whose larval
development cycle can be as early as five days
with favourable environmental conditions.30
Culex mosquitoes in this region are known to
carry the West Nile virus, and stagnant water
without treatment may lead to increased
larval development, potentially spreading the
disease.31 According to this alternative solution,
all accumulated rainwater must be treated every
two days per CSA B805 standards to control
bacteria and protozoa.28,29
The second alternative, Solution B, suggested
increasing the maximum allowable roof
rainwater level from 150 mm (6 in.) to 250 mm
(10 in.). The City of Mississauga requested a
detailed structural assessment and the inclusion
of additional overflow scuppers to manage
this increased capacity and alleviate the risk of
structural overloading on the existing structure.
Structural
The original structural deck was designed to
accommodate dead, live, variable, and wind
loads, according to OBC 2012, Table 4.1.2.1.A.
Dead loads include the self-weight of the structure, permanent construction materials,
roof assembly, overburden, rooftop equipment,
and architectural components. Live and
variable loads account for occupants, movable
equipment, and environmental factors such as
snow, ice, and rain. For most roof structures,
the variable snow or rain load is equal to or
greater than the dead load, with the dead
load calculated at 1.25 kPa (26 psf) and the
variable load at 1.5 kPa (31 psf), per OBC
Table 4.1.3.2.A.21
The rainwater storage capacity, integral
to blue roof technology, imposes a variable
load due to rain. Importantly, OBC Article
4.1.6.4.(3) specifies that snow and rain loads
do not coincide and should not be combined
in the same load calculation.21 Consequently,
the capacity of an existing roof to support a
rainwater storage capacity is equal to the design
snow or rain load. Based on the 2012 OBC and
regional precipitation data, hydraulic rain load
calculations indicate that snow load typically
governs design in Mississauga and Toronto, as
shown in Table 1.
It is common practice that an increase of up
to 5% in variable load is acceptable without
requiring structural reinforcement, translating
to increasing ponding from 130 mm (5 in.)
to 137 mm (5.4 in.) in Mississauga. However,
CVC’s requirement to store up to the maximum
allowable amount of water necessitated a
detailed assessment and potential roof structural
reinforcement. Design loads for the Roof A-1
were calculated, factoring a basic snow load
of 1.3 kPa, wind uplift of 1.3 kPa, and a basic
superimposed dead load (SDL) of 1.6 kPa.
Additionally, the average sloping topping
dead load was 4.7 kPa, varying from 2.8 kPa to
6.6 kPa, as shown in Figure 7.
Accordingly, it was determined that the
existing low-sloped roof can support basic
seasonal blue roof technology without additional
reinforcement, with a maximum snow load of
1.3 kPa plus 0.6 kPa in allowances or a maximum
ponding depth of 180 mm (7 in.). The blue roof
system drains should remain opened to avoid
ponding during the winter months.
Roof Assembly
Considering Roof A-1’s existing TPO roof
assembly condition and performance risks, full
roof replacement as part of the blue roof pilot
was contemplated. Roof cut tests completed by
CVC’s roofing contractor confirmed moisture
present below the existing TPO membrane
at several locations. Concerns were raised
regarding risks and the impact of future leaks
below the new blue roof, including building
operations disruption and hollow core structural
roof slab deterioration. CVC elected to replace
the full roof assembly as part of the blue roof
project. Considerations and factors reviewed in
making final new roof system design decisions
are presented below.
DESIGN
Overview
To implement the blue roof project on Roof A-1, a
separation was needed to isolate existing rooftop
building mechanical and weather monitoring
instrumentation systems installed on the west
section of the roof. Roof A-1 was divided by a
new segregation barrier into two distinct areas:
Zone 1 (the western third of the roof, which is
to remain a conventionally drained low-sloped
roof) and Zone 2 (the eastern remaining roof
area designated for blue roof water retention), as
depicted in Figure 8. Zone 3, the lower garage
roof (Roof A-2), falls outside this project’s scope.
Roof Assembly
The new replacement roof assembly at Zone 2
(the blue roof area), as a retrofit, was to at least
achieve the same thermal and condensation
resistance performance levels of the existing
TPO roof. Additional design decisions were
guided by four key objectives established by the
CVC. First was ensuring the new roof assembly
could allow for and perform under planned
maximum water storage volumes, above the
membrane, for prolonged periods outside of
winter conditions. The second objective was
maintaining the high reflectivity white roof
membrane surfacing design feature to reduce
solar heat gain and building cooling energy
loads. The third objective required that the roof
membrane not impact the stored water’s quality
and resist potential chlorine and algaecide water
treatment additives. Finally, the roof membrane
needed to withstand light foot traffic for
demonstration and maintenance purposes.
For the new roof membrane, the design team
considered fully adhered membranes with
redundant, multi-ply, and seamless applications
to improve leak resistance and roof durability. A
summary of the options reviewed is provided in
Table 2. All options included the same insulation
and vapour barrier details.

Given the following considerations, the
Option 3 roof assembly, including a PMMA
liquid-applied membrane system over a
1-ply modified-bitumen SBS base sheet, was
ultimately selected.
• The PMMA liquid-applied membrane is
installed in a seamless application and can
withstand the ponded water hydrostatic
pressure anticipated in the RID blue roof
pilot.32 Combined with a 1-ply modifiedbitumen
SBS base sheet below, Option
3’s membrane system is multi-ply and
redundant. The PMMA chemical structure
consists of polymer chains chemically
bonded with one another, resulting in
homogenous, seamless installation.32 It
also provides UV resistance and chemical
stability, including at chlorine levels above
expected treatment threshold of 1 mg/L
(8.35×10-6 lb/gal).32
• Option 1 was not selected, as the single-ply
TPO membrane includes seams not suitable
for prolonged periods of ponded water and
lacks the multi-ply redundancy desired. In
addition, TPO membranes tend to be more
slippery when wet as compared to the other
membranes considered, adding safety risk
associated with occasional foot traffic outside
designated walkways.
• Option 2, although a multi-ply and
redundant membrane system, also includes
seams. While there have not been specific
RID blue roof studies related to the impact
of ponding water on membrane seams, the
Canadian Roofing Contractors Association
(CRCA) advises against flood testing (i.e.,
ponding water) as a form of leak detection
due to ponded water’s hydrostatic pressure
impact on seam bond.33 In addition,
modified bitumen cap sheets rely on
embedded granules for UV protection. Under
sustained ponded water, granules may
become disturbed, reducing the membrane’s
UV protection.
• Conventional BUR and ballasted roof
assemblies were not considered, as the gravel/
ballast adds dead load, decreasing available
capacity for water storage.
Construction cost estimates were prepared for
the three options considered. Option 1 was the
least costly. Option 2 was ~20% and Option 3
was ~40% more costly than Option 1. All options
included a white membrane and EFVM leak
detection conductive medium.
The full new roof assembly is illustrated
in Figure 9. On top of new self-adhered
vapor barrier is an adhered in-place glassfaced
closed-cell polyisocyanurate foam core
insulation layer. Above the insulation is a leak
detection conductive medium, an adhered
in-place asphaltic overlay board layer composed
of a mineral-fortified asphaltic core formed
between two asphalt-saturated fiberglass mat
reinforcements. The roofing membrane system
includes a 1-ply torch-applied modified-bitumen
SBS membrane base sheet covered with the
two-component PMMA liquid membrane
with fleece fabric reinforcement. The PMMA
membrane system resin is pigmented to result
in designed high reflectively white finish.
At the parapets, above the PMMA membrane
upturn height, the roof membrane is comprised
of 1-ply torch-applied modified-bitumen SBS cap
sheet membrane installed over the modifiedbitumen
SBS base sheet. The parapets are then
protected with galvanized steel metal flashings.
Roof designated walkways within the blue roof
area are comprised of plastic bead and sand
particles embedded into the PMMA topcoat
during application.
All roof system components are specified
by the same roofing manufacturer to maintain
consistency and compatibility. As with all
considered assembly options, the final assembly
was designed to meet the calculated wind
uplift pressures and reviewed against relevant
standards, such as CSA A123.21:20, Standard Test
Method for the Dynamic Wind Uplift Resistance of
Membrane-Roofing Systems.34
Leak Detection
Leak detection and roof performance
monitoring was added as a design objective to
manage the risk associated with the planned
ponded water over the roof assembly. Electronic
leak detection (ELD) using an electric field
vector mapping (EFVM) system meant as a
diagnostics and monitoring tool, was integrated
into the new roof assembly by introducing an
electronic-detection-conductive medium. ASTM
Guide D7877 and ASTM Practice D8231 guided
the electronic-detection-conductive medium
selection and design.26,27 The conductive
medium sits between the polyisocyanurate
insulation and the asphaltic cover board,
comprised of welded stainless steel mesh.
In consultation with the roofing membrane
manufacturer, the conductive medium was
placed below the coverboard instead of directly
below the membrane system to protect the
liquid-applied membrane. The mesh grid,
spaced out at 50 mm by 50 mm (2 in. by 2 in.),
is connected through a contact plate and
cable to a connection box. During ELD testing,
a low-voltage charge is applied through the
connection box via a portable pulse generator.
Roof Drainage and Scuppers
The new replacement roof assembly included the
following drainage scope to accommodate the
blue roof mechanical system design. Figure 10
and Figure 11 illustrate the blue roof drains
connecting to the mechanical systems below the
roof deck.

• Upgrade the primary roof field drains, including
adding a field drain within the blue roof zone,
to tie-in the new roof assembly to the new blue
roof mechanical sensors, valves, and water
treatment/storage systems below the deck.
• Add new field overflow drains equipped
with extension pipes rising above the roof
membrane up to the maximum planned blue
roof water depth.
• Add new overflow scuppers through the
parapets set at the height of the maximum
planned blue roof water depth.
The primary roof field drains control flow and
pond water, and when the blue roof is inactive
(e.g., in the winter months), they provide primary
drainage to meet building design. These drains
were retrofitted to include vandal-proof cast
aluminum domes and hinged access gates,
pan-formed aluminum drain bodies, and cast
aluminum clamping rings. The retrofit drains
connected to the rainwater leaders below the
deck via mechanical coupling connections instead
of U-flow friction insert seals, as the pipes may
experience high flow rate and temporary backup
conditions during blue roof drain down.
The overflow field drains and scuppers
divert water, and meet the roof’s drainage
requirements, if the levels on the blue roof
reach maximum planned storage capacity. The
overflow scuppers cut into the parapets’ drain
through downspouts terminating at grade,
as illustrated in Figure 12. They were placed
along the roof edge to make scuppers easier to
inspect and were designed to complement the
architectural style of the building, integrating
with the overall design.
CONSTRUCTION
Construction commenced with removal
of the existing roof assembly, followed by
adjustments to existing roof anchors to extend
them above the maximum planned water
level. Surface preparation included cleaning
and priming of the existing concrete surface
for vapour barrier application, while insulation
was installed staggered and tightly butted.
ELD conductive medium mesh was installed
followed by coverboard and 1-ply modifiedbitumen
SBS base sheet. Surface cleaning
was carried out to remove any loose granules,
dust, or dirt prior to the liquid-applied PMMA
system application. PMMA system application
is sensitive to high temperatures, which
could lead to improper curing. Ambient and
substrate temperatures were closely monitored
throughout the process to verify application
conditions.
Uncovered concealed conditions during
construction, including original structural roof
deck precast panels construction tolerances,
required some modifications to overflow drain and scupper levels to meet planned blue roof
design water storage capacity loads. Multiple
methods to validate final installed new roof
membrane levels were employed. Based on
these actual site conditions, final blue roof water
storage volume and overflow drainage heights
were confirmed. Hand tape measurements, laser
levels, and total station surveys were completed
during several stages during new roof assembly
construction to confirm that the planned
maximum storage capacity water levels were
maintained.
After construction was completed and
installation was commissioned, blue roof water
flood testing was conducted to validate the roof
and flow control systems integrity. Mobile truck
pumped 16,000 L (4,200 gal.) of water onto the
roof, and a systematic monitoring program was
implemented to confirm the absence of leaks and
proper operations of the mechanical systems.
DISCUSSION
Implementing this blue roof pilot project at the
CVC Head Office in Mississauga is testing this
emerging and innovative approach to urban water
management and climate resilience. It provides
valuable insights into the feasibility and practicality
of blue roofs installations in municipal settings,
highlighting benefits and challenges encountered
during the design and construction phases.
The pilot project incorporated an ongoing
maintenance and monitoring program. The
mechanical system includes drain sensors
and control instruments to regulate flow.
These components are scheduled for regular
maintenance and monitoring to ensure proper
performance. The roof assembly’s embedded EFVM
conductive medium allows for regular testing for
moisture ingress and diagnostics in case of leaks.
Blue roofs, by design, increase the risk by
intentionally ponding water. Structural load
analysis, and incorporating redundancy and
fail-safe mechanisms to the design, manages
the risks. The design includes two separate
types of overflow drainage pathways (i.e.,
scuppers and drainpipes) to prevent water
accumulation beyond safe levels. The roof
membrane system and the drain sensors include
intentional redundancy to manage risks over
the life cycle of the design. Preliminary analysis
conducted by the CVC concluded that the blue
roof pilot, in conjunction with their existing
RWH, can harvest 8.84 m³/day (2,300 gal./day)
of non-potable water, surpassing their current
demand of 5.68 m³/day (1,500 gal./day).35 It is
also projected to save approximately 11.6 GJ
of energy annually, translating to 3,210 kWh of
electricity and a cost reduction of $302 annually
due to the cooling effects of ponding water.35
Accordingly, the system could reduce
greenhouse gas emissions by about 0.18 tonne
(0.2 ton) of CO2e annually.35 CVC has installed
monitoring equipment to gather data over the
next two years to confirm these projections.
Over the coming years, the CVC aims to
evaluate the total volume of stormwater diverted
from the storm sewer system, monitor roof
surface temperatures reduction due to the
blue roof, estimate annual water savings from
rainwater reuse, and calculate energy savings
from rooftop evaporative cooling.35 In addition,
TMU is researching this pilot project. Their
primary objective is to investigate the public
health hazards related to standing water on the
roof and consider strategies to mitigate such
risks.36 They will also assess the rationale of the
24-hour time limit for standing water described
in the Ontario Building Code.36 The authors of this
paper will continue to review and monitor the
roofing assembly and its long-term performance. CONCLUSION
Intentionally ponding water on building’s roofs
commands greater interrogation of each design
element. Designers need to reconsider some
of the conventional wisdom and accepted best
practices in managing water on roofs. Instead
of efficiently moving water off the deck, as most
roofs are designed, risk management is employed
to sustain ponded water for prolonged periods.
Blue roof systems can present a promising
mitigation strategy to the pressing challenges
of urban stormwater management, exacerbated
by urbanization and climate change. Through
comprehensive understanding of technology
classification, historical context, modern
applications, and case studies, the impact and
risks of this innovative approach on buildings can
be managed.
ACKNOWLEDGMENTS
The authors would like to sincerely thank Credit
Valley Conservation for their invaluable support
and collaboration throughout the implementation
of the blue roof project described in this paper. We
also acknowledge the support of Enviro-Stewards
and Trio Roofing Systems, who contributed to the
success of this endeavour.
REFERENCES
1. T. Almaaitah, J. Drake, and D. Joksimovic,
“Impact of design variables on hydrologic
and thermal performance of green, bluegreen
and blue roofs.” Blue-Green Systems,
vol. 4 (2), pp. 135-55, 2022.
2. C. Kloss, “Green infrastructure for urban
stormwater management.” In Low Impact
Development for Urban Ecosystem and
Habitat Protection (American Society of Civil
Engineers, 2008), pp. 1-7.
3. B. Surowiec, C. W. R. Hakimi, P. J. C.
Schembri, A. Bhatti, and K. Vander Linden,
Automated Real-time IoT Smart Blue
Roof Systems for the ICI Sector for Flood
and Drought Resilience and Adaptation:
Technical and Financial Feasibility Study,
2020.
4. Z. Jandaghian, J. S. Y. Zhu, H. Doshi, and
B. Baskaran, “Low-Sloped Rooftop Storm-
Water Detention Assembly to Mitigate
Urban Flooding,” Buildings, 2022.
5. M. Z. Jacobson and J. E. T. Hoeve, “Effects of
Urban Surfaces and White Roofs on Global
and Regional Climate,” Climate, vol. 25,
2012.
6. New Jersey Department of Environmental
Protection, “New Jersey Stormwater Best
Management Practices Manual,” 2021.
7. M. Shafique, R. Kim, and D. Lee, “The
potential of green-blue roof to manage
storm water in urban areas,” Nature
Environment and Pollution Technology,
vol. 15, no. 2, pp. 715-18, 2016.
8. D. Cirkel, B. Voortman, T. van Veen, and
Bartholomeus, Evaporation from (blue-)
green roofs: assessing the benefits of a
storage and capillary irrigation system
based on measurements and modeling,
vol. 10, no. 9, p. 1253, 2018.
9. Canadian Roofing Contractors Association,
“Canadian Roofing Reference Manual,”
20 November 2020 [Online]. Available:
https://roofingcanada.com/docs/
canadianroofing-reference-manual/.
10. J. Urbanik and A. Tomaszewicz, “Flat Roof—
Advantage or Disadvantage of Modern
Movement Buildings,” in Structural Analysis
of Historical Constructions, Mexico City,
Mexico, 2014.
11. L. Corbusier, Towards a new architecture.
London: The Architectural Press, 1927.
12. Ş. Vasiliu, “Evolution of Flat Roofs,” Bulletin
of the Polytechnic Institute of Jassy, vol. 55,
no. 4, pp. 71-80, 2009.
13. R. Johnson, “History and development of
modified bitumen,” in Roofing Technology,
National Roofing Contractors, Mannford,
1987.
14. C. Thuring and G. Grant, “The biodiversity of
temperate extensive green roofs—A review
of research and practice,” Israel Journal of
Ecology & Evolution, 2016.
15. L. Kosareo and R. Ries, “Comparative
environmental life cycle assessment of
green roofs,” Building and Environment,
vol. 42, no. 7, pp. 2606-13, 2007.
16. City of Toronto, “Toronto Municipal Code,
Chapter 492, Green Roofs,” in Toronto
Municipal Code, Toronto, Ontario, 2017.
17. New York City, “New York City Green
Infrastructure Plan. Green Infrastructure
Pilot Monitoring Report,” 2012.
18. A. Campisano, C. Modica, and A. Gullotta,
“Long-term experiments for the evaluation
of the potential for storm water control
of modular blue roofs in Mediterranean
climate,” Urban Water Journal, vol. 18,
no. 1, pp. 33-42, 20.
19. T. Almaaitah and D. Joksimovic, “Hydrologic
and Thermal Performance of a Full-Scale
Farmed Blue-Green Roof,” Water, vol. 14,
no. 11, 2022.
20. Codes, Canadian Commission on Building
and Fire, National Plumbing Code of
Canada: 2020, National Research Council of
Canada, 2022.
21. Ministry of Municipal Affairs and Housing,
2012 Ontario Building Code, Publications
Ontario, 2023.
22. City of Toronto, “Toronto Green Standard
Version 4” [Online]. Available: https://
www.toronto.ca/city-government/
planningdevelopment/officialplanguidelines/
toronto-green-standard/
toronto-green-standard-version-4/ [Accessed
21 August 2024].
23. City of Toronto, “The City’s Wet Weather
Flow Master Plan” [Online]. Available:
https://www.toronto.ca/services-payments/
waterenvironment/managing-rainmeltedsnow/
the-citys-wet-weatherflowmaster-
plan/#:~:text=Toronto’s%20
Wet%20Weather%20Flow%20
Master,and%20snow%20to%20be%20
absorbed [Accessed 21 August 2024].
24. Canadian Standards Association, CSA
A123.26:21, Performance Requirements for
Climate Resilience of Low Slope Membrane
Roofing Systems, 2021: CSA Group.
25. Canadian Standards Association, CSA 478:19,
Durability in Buildings, CSA Group, 2019.
26. ASTM International, “D7877-24 Standard
Guide for Electronic Methods for Detecting
and Locating Leaks in Waterproof
Membranes,” in Book of Standards,
vol. 04.04, West Conshohocken, ASTM
International, 2024.
27. ASTM International, “D8231-24 Standard
Practice for the Use of a Low-Voltage
Electronic Scanning System for Detecting
and Locating Breaches in Roofing and
Waterproofing Membranes,” in Book of
Standards, vol. 04.04, West Conshohocken,
ASTM International, 2024.
28. Canadian Standards Association, CSA
B805:22/ICC 805:2022 Rainwater harvesting
systems, CSA Group, 2022.
29. Enviro-Stewards Engineers, “Smart Blue
Roof & Rainwater Harvesting System
Optimization, Credit Valley Conservation
Authority, Engineering Design Brief,”
5 March 2022 [Online]. Available:
https://cvc.ca/document/smart-blueroof-
and-rainwaterharvesting-systemoptimizationengineering-
design-brief/.
30. Centers for Disease Control and Prevention,
“Life cycle of Culex mosquitoes,” 16 April
2024. [Online]. Available: https://www.cdc.
gov/mosquitoes/about/life-cycle-ofculexmosquitoes.
html. [Accessed 13 August 2024].
31. Wijayasri, Nelder, Russell, Johnson,
Badiani, and Sider, “West Nile virus
illness in Ontario, Canada: 2017,” Canada
Communicable Disease Report, vol. 44,
no. 1, pp. 32-37, 2017.
32. K. Goodrum, “The PMMA Revolution,” The
International Institute of Building Enclosure
Consultants (IIBEC), 5 November 2016.
33. CRCA National Technical Committee, “Flood
testing—Canadian Roofing Contractors
Association,” November 2009 [Online].
Available: https://roofingcanada.com/
bulletin/floodtesting/.
34. Canadian Standards Association, CSA
A123.21:20, Standard Test Method for
the Dynamic Wind Uplift Resistance
of Membrane-Roofing Systems.,
CSA Group, 2020.
35. Credit Valley Conservation, “Smart Blue
Roof,” 2024 [Online]. Available: https://
cvc.ca/project/smart-blueroof/ [Accessed
22 August 2024].
36. Toronto Metropolitan University, 8 March
2024 [Online]. Available: https://www.
torontomu.ca/water/events/2024/03/
you-are-now-inthe-main-content-areaassessingthe-
performance-a/ [Accessed
22 August 2024].
ABOUT THE AUTHORS
Jason Paulos is an
experienced project
manager at WSP, with
a strong background
in the construction
industry. With over
10 years of diverse
experience, he has
made significant
contributions in various
sectors, including
manufacturing,
contracting, and consulting. He has undertaken
projects in residential, institutional, commercial,
and transportation divisions. He actively
supports company-wide efforts to develop lowcarbon
solutions to enhance building envelope
performance. He also plays a key role in WSP’s
research and analysis of high-performance
glazing systems.
Sal Alajek is a
professional engineer
and project principal
at Sense Engineering.
With a focus on
existing building
rehabilitation, his
work encompasses
building enclosure,
structure, and
mechanical systems.
His expertise extends
to evaluating durability, energy performance,
and occupant comfort implications in design
and construction.
Sidney Picco has
experience across
multiple sectors of the
construction industry.
With over four years of
experience in building
sciences and restoration
in Canada, she has
been involved in
many roof restoration
projects. In 2024, Picco
moved to Scotland to
pursue an MSc. in fire engineering sciences at
the University of Edinburgh. She currently works
with a fire engineering consultancy in the United
Please address reader comments to
chamaker@iibec.org, including
“Letter to Editor” in the subject line, or
IIBEC, IIBEC Interface Journal,
434 Fayetteville St., Suite 2400,
Raleigh, NC 27601
JASON PAULOS, MBSC,
LEED AP
SAL ALAJEK, RRO,
PENG
SIDNEY PICCO, MSC
AND BASC
Kingdom, where she combines her passion for
building enclosure design with fire engineering
solutions.