Skip to main content Skip to footer

From Roofing to Waterproofing: How Components in the Building Enclosure Connect

September 19, 2022

March 2022 IIBEC Interface • 11
Diagnosing issues (specifically
leaks) is always exciting
because every problem in
every building is distinctive,
and determining the causes
of these problems can be
tricky. That is why learning the fundamentals
of waterproofing is essential. To successfully
diagnose hard-to-solve leaks, the consultant or
contractor must understand how the parts of
the building connect, as well as Kubal’s “90 to
1” rule, which states that 90% of all leaks occur
from 1% of the building’s surface: terminations,
transitions, and penetrations.1
I learned about waterproofing in conjunction
with roofing, and the experience was eye
opening. There were times in the beginning
when I thought a wall was just that—a wall.
Now, however, I understand that it is an intricate
facade assembly that experiences a wide
variety of issues based on design, material, and
installation. To address these issues, we need to
grasp the distinctive characteristics of materials
such as thermoplastic olefin (TPO) membrane
and modified bitumen. Similarly, solutions for
the exterior insulation and finish system or for
masonry have their own sets of nuances.
The most crucial lesson I’ve learned is that
the “construction industry has yet to adopt the
principle that the entire exterior facade must
be treated as a single cohesive unit, an enclosure
in which all individual components are
transitioned into one another in completely
waterproof detailing.”1 Furthermore, to achieve
this principle, industry professionals must have
a high level of knowledge about waterproofing
(below grade and above grade), roofing, flashing,
and damp-proofing, and they need to apply
this knowledge precisely. Unfortunately, not
all contractors have the necessary knowledge
or skills—and when industry professionals do
not understand the principles of waterproofing,
building owners and managers are left out to
dry (pun intended).
Where I work, 99.9% of our business is
negotiated commercial work, where we work
closely with management teams, facility engineers,
and owners. I help pinpoint problems
and design solutions, and sometimes I must
have uncomfortable conversations to tell someone
that the solution’s scope and magnitude are
greater than they expected.
For example, I was recently called to investigate
a leak on a two-story commercial office
building with a TPO roof, an acrylic-coated
brick masonry facade retrofitted with a galvanized
continuous metal wall panel around the
interstitial space between the second floor and
roofline, and additional horizontal metal panels
between the first- and second-story window
bands (Fig. 1). The problem was that the interior
drywall in an office space on the northern
face of the building was extremely wet after a
heavy rain. The building engineer cut into the
wall to repair the drywall, and he said the experience
was like cutting through butter, which
then led him to cut out the entire wall.
When I arrived to investigate the area, a few
Figure 1. This masonry facade was retrofitted with continuous metal panels at the interstitial
space between the roofline and the second-story ceiling.
12 • IIBEC Interface March 2022
things stood out to me. The first was that
the through-wall flashing at the base of the
vertical panels was extremely short and did
not sufficiently cover the masonry (Fig. 2).
The flashing also appeared to lack a waterproofing
membrane, and it sloped backward
toward the building (Fig. 3). Continuous metal
panels constantly expand and contract, and
when water enters the system, capillary action
occurs; the inadequate metal flashing was a
compromising detail. The silicone gaskets
around the windows at this location were for
the most part sound; however, the culmination
point occurred where the sealant stopped at
the frame-to-substrate joint, and the mortar
in the area was cracked (Fig. 4). As a result,
the gypsum sheathing (with no water-resistive
Figure 2. Inadequate throughwall
flashing without proper
waterproofing beneath.
Figure 4. Evidence of water intrusion
(rust) at the transition of the
through-wall flashing, metal panel,
and window (1) with failed masonry
joints down the wall (2).
My journey into the roofing and waterproofing industry started in 2016.
I was an active-duty captain in the United States Marine Corps, serving as
executive officer for Region 5, Marine Corps Embassy Security Group. My wife,
Allison, and I knew that we planned to transition from active duty to the civilian
sector, and we planned to start our own venture. Allison had successfully
completed her master’s in business and communication, and I was about to
complete my MBA. Owning a business seemed like a perfect fit. However, when
Allan Rodger offered me a position with the family business at Zenith Roofing &
Waterproofing, I realized it was an offer I couldn’t refuse.
When I moved into the industry, I instantly fell in love. The work was fastpaced
and dynamic, and although Dallas–Fort Worth is a major metroplex, the
area and industry within has the same small-community feel that the Marine
Corps does. As an officer, I was always challenged to find creative solutions to
problems on the go. Those skills transferred over perfectly into commercial
roofing. I consistently tell people that the reason I exist is to help solve
problems, which is why I find roofing, and especially
repair and maintenance, so interesting.
Figure 3.
Through-wall
flashing sloped
toward the
building.
Leak area
No waterproofing barrier
Failed mortar joint
Through-wall flashing is
sloped back toward
building
March 2022 IIBEC Interface • 13
barrier) in this area of the building was crumbling and infested with
organic substance (Fig. 5–7). Upon further inspection of the interior,
my team found noticeable water damage throughout the building
around the windows. The building was leaking, and when we cut
open the abscess, we could see the infection—but how far did it go?
The next steps were to inform ownership about my findings
and offer recommendations for remediating the problems. I wrote
a report and documented everything. My final recommendation
was to remove the brick at that single location so that the gypsum
sheathing could be replaced with new sheathing and waterproofing
material. At that time, we could assess the metal through-wall flashing
and reseal the joints properly within the area.
My client explained that they wanted to get a second opinion,
and I encouraged them to do so. Obviously, they had a big decision
to make. I re-emphasized the importance of treating the organic
substance within the wall cavity for the overall health and reputation
of the building. The bottom line: I advised them to take care of
the problems the right way, before people could post complaints on
social media or tenants could break their leases.
My client contacted me later to provide a bid for sealing all the
Figure 5. The interior of the leak area with
organic growth on the weather barrier.
Figure 6. The weather barrier
easily crumbled due to
excessive moisture saturation.
Figure 7. Exterior view of the leak area.
Interior of brick wall
14 • IIBEC Interface March 2022
metal joints on the northern face of the building
until they decided on how they wanted to
proceed. He explained that he was reluctant
to de-clad the facade in the area (roughly 70
ft2 [7 m2]), and that a restoration company had
suggested sealing the entire building. A mentor
of mine, David Leslie, RWC, once told me, “If
it doesn’t get wet, it doesn’t leak.” Well, I don’t
think that this is what he meant.
I explained to my client that by completing
that scope of work, we would be treating a symptom
of the problem, and that the sheathing issue
was going to go unaddressed, which concerned
me. I’m used to objections and losing deals from
time to time, but when I see someone making a
mistake by choosing the wrong solution, that’s
always a tough pill to swallow. I explained that
the panels were not meant to be sealed and that
they needed to weep properly, and I stressed
that sealant was only a temporary fix and would
become a maintenance issue.
Here was my primary conundrum: I knew
the right way to solve the issue but was being
invited to bid on the wrong specifications.
Another issue was that the project might not
commence for six months. During that time, the
building would experience moisture intrusion
on 80% of the facade through winter and spring.
What would the long-term effects of this be?
We all know and have seen what trapped
water in a wall will do. And what would happen
if the sealant failed, or the roof leaked at the
wall? There would be nowhere for the moisture
to go. I don’t know what my competitor told my
client, but I do know that the other firm agreed
to seal the entire building. I couldn’t do that, so
I bid my own specifications that would ensure
the system wept properly.
There is a delicate balance and fine line
between being right and doing what’s right. My
relationship with my client is one that I respect
and cherish. I would never insult them by
refusing their invitation to bid an opportunity.
However, I was clear in my proposal that we
would take specific measures to create adequate
drainage. If we lose the opportunity because the
monetary cost is too high, then I am okay with
that, but my client will know that I don’t take
shortcuts and ultimately have their best interest
in mind.
If we as an industry don’t take the time to
understand the second- and third-order effects
of designed solutions, we can leave the buildings
we work on, and their owners, in a worse situation
than they faced before we intervened. As I
reflect on what I could have done better in this
situation, I wish I had proposed that the owner
host an on-site walk with all bidders during
which we could discuss our observations and
create a scope of work that made the most sense
for the project. I would have loved the opportunity
to talk with everyone who was involved
in making decisions about the project scope.
Sometimes this strategy works—if you can get
the parties together. However, in many cases,
owners just want you to “give them a bid.” It’s best
practice to resist this pressure. To ensure everyone’s
success, we have to take our time to evaluate
the situation, determine the potential causes
and effects of the problems we identify, and
understand the long-term effects of the work.
As industry professionals, we have an obligation
to our companies and to our clients to
understand how components in the building
enclosure connect. If we shortchange investigation
and simply suggest “obvious” or “quick-fix”
specifications, we shortchange the industry and
our peers. Over time, we will discover improved
ways to apply lessons from past experiences to
the present, and these improvements will shape
our future decision-making processes.
As information becomes more readily available,
people will be able to see the history behind
the decisions we make, and they will assess the
judgment that underlies those decisions. If we
fail our clients by allowing them to make poor
decisions with their money, our industry will
suffer. Owners and contractors who face the
consequences of those poor decisions are at
serious risk of concluding that our industry is
only interested in making money and does so
by treating symptoms instead of doing the hard
work to solve the underlying issues.
Here’s an analogy: A patient with an injured
ankle goes to the doctor. The doctor explains
that the patient needs to immobilize the ankle,
and further recommends rest, compression,
and elevation for a week, with some minimal
stretching, to solve the problem. However, the
patient rejects the treatment plan as being too
slow and too complicated, and says, “Just give
me some medicine to take away my pain.” The
doctor does what the patient wishes, without
disclosing the possible risks or side effects.
While the ankle may feel better, the pain medication
doesn’t heal the injury. Furthermore,
the patient experiences a range of adverse drug
effects, such as chronic dry skin, halitosis, and
nausea. Even worse, when the patient is without
her medication, the pain is intolerable, and
she becomes dependent on the medication.
Is this really the way that we want to treat
our “patients”? As professionals, we owe it to
everyone to identify the problem correctly and
provide the best solutions.
If we are to make the industry better, we
must understand and uphold Kubal’s principle.
By ensuring that our employees and others
throughout the construction industry are better
educated, we help owners make better decisions
from the start and throughout the lives of
their buildings. More specifically, contractors,
consultants, and those who maintain the building
own a piece of the effort. Ideally, problems
can be prevented from the very beginning;
read Leslie’s article in the September 2018 issue
of RCI Interface.2 However, we need to keep
buildings in our current inventory from entering
what I call “the fatal funnel.” We know that
our community can create more sustainable
buildings with healthy spaces for the tenants,
and we can help owners make choices to avoid
costly repairs in the future. If everyone in our
industry makes a concerted effort to truly educate
owners and colleagues about how components
of the exterior facade components or
assemblies must work in unison, we will all be
better off. Understanding how the components
of the building enclosure connect and interact
has been an absolute blessing, and, as time goes
on, I am positive I will have fewer stories like
this one to share. Until then, I will do my best
to learn, educate, and pay it forward.
REFERENCES
1. Kubal, M. T. 1992. Waterproofing the
Building Envelope. New York, NY:
McGraw-Hill Professional.
2. Leslie, D. 2018 “The Building
Maker.” RCI Interface, September. pp.
21–24. http://iibec.org/wp-content/
uploads/2018-09-leslie.pdf.
Please address reader comments to
chamaker@iibec.org, including “Letter to
Editor” in the subject line, or IIBEC, IIBEC
Interface Journal, 434 Fayetteville St., Suite
2400, Raleigh, NC 27601.
Blaine Sibby, MBA,
is the vice president
of building forensics
at Zenith Roofing &
Waterproofing in Fort
Worth, Texas. His
experience includes
project management,
estimating, and sales.
Sibby is formally
trained in thermography
and is a licensed
drone pilot. His dedication
to solving leak issues led him to recently
file a patent application to resolve industrywide
complications. Sibby is an eight-year veteran of
the United States Marine Corps. He was deployed
to Afghanistan in 2012–2013.
Blaine Sibby, MBA