Skip to main content Skip to footer

Full-Scale Stand-Alone Blindside Waterproofing Mock-Up and the Lessons Learned

August 10, 2019

INTRODUCTION
The construction of buildings is a team
effort involving numerous stakeholders. It
takes multiple people from various disciplines
to bring a building to fruition for
the owner. For the project to be successful,
collaboration is critical. Three key elements
are required for effective collaboration: a
singular goal, alignment of expectations,
and a common language. One way to solidify
these points is through the process of
constructing a stand-alone site mock-up.
This article will discuss our unique example
of constructing a full-scale mock-up of
pre-applied blindside waterproofing for a
structural shotcrete wall, and the lessons
learned through the process.
STAKEHOLDERS AND EXPECTATIONS:
A successful project has three traits:
the finished building is delivered on time,
is within budget, and performs as intended.
However, diverse stakeholders may perceive
a project from different vantage points. With
various people and disciplines involved in
the construction, it is only natural that
there may be a range of expectations. It is
important to define the stakeholders and to
highlight their key expectations. The following
are examples of expectations the various
stakeholders may bring to the project.
• Owner’s Core Expectation –
Performance and budget: Owners
expect the building to perform to
meet their requirements and that
the people constructing it are professional
and capable of accomplishing
the task within their available budget.
• Designer’s Core Expectation –
Reputation and performance: Designers
expect that the people selected
and the products installed will
meet the intent of their design and
performance requirements.
• Contractor’s Core Expectation –
Time and budget: Contractors expect
that the design, people, and products
selected will meet the designated
timeframe of their proposal and
meet the project budget.
• Subcontractor’s Core Expectation
– Workmanship and quality:
Subcontractors expect that the
design and products selected, along
with the logistics and coordination
managed by the contractor during
construction, will meet the framework
of their bid.
• Manufacturer’s Core Expectation –
Connections: Manufacturers expect
that the design correctly utilizes and
specifies materials for the projectspecific
conditions and that the contractors
properly install them as a
system.
KEY POINTS
The process of constructing a full-scale
mock-up provides the opportunity to establish
the key points by defining a singular
goal, aligning expectations, and creating a
common language before issues develop on
the actual building. These points are critical
to a successful project, but in some cases
can be difficult to achieve.
We must first understand that all new
construction projects are unique. They are
often a new design, on a new site, and
constructed by a new team. Considering
the various vantage points from the stakeholders
and their highlighted core expectations,
it is easy to understand how the construction
process can sometimes become
contentious. Compounding the situation
are the varying communication styles often
used by the various stakeholders. Designers
typically communicate with drawings and
written words. Manufacturers communicate
with numbers that describe physical
properties of their materials and diagrams
that illustrate step-by-step instructions for
installation. Contractors communicate with
hands-on physical objects. Add these different
aspects together, and it is not hard to
understand how issues can arise during the
construction process.
Before going much further, it is important
to capture the thought process that
not only went into the construction of the
A u g u s t 2 0 1 9 I I B E C I n t e r f a ce • 1 9
project-specific mock-up that we will describe
in this article, but also into its writing.
During the processes of both, there
was a continuous exchange of insights—the
sharing of expectations, observations, and
ideas. To capture a sense of our interactions,
the remainder of the article has been
formatted to reflect those conversations.
Jerry Carter represents the designer
stakeholder and is a member of SmithGroup’s
Building Technology Studio with a specialization
in the building enclosure, and for this
project, he focused on the design of belowgrade
waterproofing systems.
David Leslie represents the manufacturer
stakeholder. He is the director for
technical services and product management
at Polyguard Products. For this project he
focused on the design and training of installers
for below-grade waterproofing systems.
PROJECT HISTORY
Jerry Carter:
SmithGroup, an architectural engineering
firm, partnered with a design–build
contractor to develop a new university laboratory
building. The building included two
stories of below-grade construction and is
at the corner of the project site close to the
intersection of two streets. The placement
of the building created a situation with tight
site constraints, which required an earth
retention system and a blindside waterproofing
application. The contractor recommended
the use of Polyguard’s Underseal®
Blindside™ Membrane as they have had a
history of working with their products on
several other successful projects.
Pre-applied waterproofing applications
create a difficult scenario in that designers,
manufacturers, and contractors are unsure
how well the waterproofing system will
perform, as one cannot review or inspect it
after the concrete is installed. This application
method is also called “blindside” and is
typically the result of zero-lot-line sites or
limited-area sites for excavation.
The characteristics that SmithGroup
expects for blindside waterproofing membrane
systems include a history of successful
projects demonstrating durability and
longevity of the membrane systems, trained
and certified installers, and fully adhered
membranes that mitigate lateral migration of
water between the membrane and the concrete
substrate. At SmithGroup’s request,
these expectations led to Polyguard providing
them with a list of successful projects using
their product, holding discussions with their
technical staff regarding installation and
quality control procedures, inviting them to
tour their manufacturing facility, and providing
large product samples for in-house
evaluation. All of this culminated in further
evaluation on a full-scale, stand-alone project
mock-up (Figure 1). To our knowledge,
a stand-alone blindside mock-up had never
been produced before with this product.
After the mock-up was completed and the
shotcrete was installed and cured, the formwork
was removed to allow an opportunity to
evaluate the membrane from the backside.
David Leslie:
The process of evaluating the products,
collaboratively designing the systems, and
validating the assembly through the trial
run of a mock-up is what every manufacturer
wishes would occur on all projects. It
Building enclosure material manufacturers
do not produce the finished product or
system. Manufacturers make components
that must be designed into the building by
one group and assembled on the building
by another. This being the case, having
a design firm take the time to visit our
facilities, to study the composition of the
products, and learn the physics behind the
design theory of the system is invaluable
and greatly appreciated.
Bringing together design, material, and
installation into a successful project must
2 0 • I I B E C I n t e r f a ce A u g u s t 2 0 1 9
Figure 1 – The stand-alone blindside mock-up shortly after the shotcrete was placed.
start with a common understanding of the
core function of the various systems and
how to achieve that function. With preapplied
waterproofing, the core function
is to prevent water intrusion, and that is
achieved by the system being installed
watertight and remaining watertight through
completion of the building. A critical phase
of the construction is the concrete foundation,
because pre-applied waterproofing is
not complete until the concrete is placed.
The process of assembling the concrete
structure is an arduous endeavor
requiring the meshing of multiple trades.
There is site preparation, soil stabilization,
concrete forming, setting of the structural
steel, concrete placement, concrete finishing,
and waterproofing. Each element builds
upon the other. Constructing a building
on a zero-lot line site adds another level
of complexity because the perimeter of the
excavation functions as the outside form
and will never be exposed again. So, every
component of the perimeter shoring/form
must withstand the rigors of constructing
the wall (i.e., rebar setting and concrete
placement), including the waterproofing.
This is especially true regarding structural
shotcrete, which will be shot at 90 mph
directly onto the waterproofing membrane.
Therefore, durability and longevity are vital
components of the pre-applied waterproofing
system in order to remain watertight
throughout construction.
Well-consolidated concrete, by nature,
has water resistance. For liquid water to
pass through concrete, there needs to be a
hole, a crack, a cold joint, or a void. The process
of casting concrete typically produces
well-consolidated concrete. Unfortunately,
it is much more difficult to consistently
consolidate shotcrete, which significantly
increases the opportunity for areas of
porous concrete. In the presence of water,
there are three components needed for
lateral water migration to occur: a breach
in the waterproof membrane, an interface
between a water-resistant substrate and
the waterproof membrane, and a pressure
differential caused by a hole, a crack, or
cold joints in the substrate. In the case of
shotcrete, the areas of porous concrete do
not provide an interface of a water-resistant
substrate. So, the theories of lateral water
migration for structural concrete are less
applicable with shotcrete and an important
reason for the system to remain watertight
throughout construction.
It is from these vantage points, and the
fundamental understanding of pre-applied
waterproofing with a structural shotcrete
wall, that the lessons learned were applied
to establish the anchor points for a successful
project.
LESSONS LEARNED
1. Other trades’ impact on waterproofing
(Figure 2)
Jerry: In a pre-applied waterproofing
application, the waterproofing installer is
the first trade that installs a product after
excavation. Every trade will follow them
and have direct access to the waterproofing
membrane, leaving the installer’s work vulnerable.
Educating other trades that follow
the waterproofing installer is a key for success
to waterproofing a space below grade.
Learning this lesson on a stand-alone mockup
allows for mistakes to be made without
impacting the built project.
David: There is nothing more frustrating
than revisiting a project after a final inspec-
YOU CALL ME RAIN
HYDROTECH CALLS
ME OPPORTUNITY
A u g u s t 2 0 1 9 I I B E C I n t e r f a ce • 2 1
Figure 2 – Following the waterproofing
installation onto the earth retention system,
additional striker pins were observed after
the waterproofing installers completed their
work.
tion, only to find the system completely
destroyed, and then to be asked if it is warrantable.
The answer can be yes, but it will
take more time and money that was not in
the schedule or budget. Sorting things out
during the mock-up saved significant time
and money.
2. Seeing is believing (Figure 3)
Jerry: Every project has quality control
measures to ensure that the end goal
is communicated across the project team.
Designers often will include pre-installation
meetings as a requirement in the
specifications. Some of these meetings will
include members of the trades that follow
the waterproofing installer. Discussion will
outline the importance of other trades’ work
and that damaging other’s work should be
avoided. No trade plans to damage someone
else’s work, but it happens. During a
stand-alone mock-up, which includes the
entire below-grade wall, every trade gets to
finish their work. Though they were warned
not to, and though they didn’t think it
would happen, damage to the waterproofing
membrane occurred prior to the shotcrete
application. Issues between the trades were
resolved prior to work on the actual building.
David: Having everyone in one place at
the same time is so powerful. Being able to
see it, then touch it, and then discuss it, gave
everyone the ability to communicate and
understand how to work together in a way
that could never happen without a mock-up.
3. Striker pin (or rebar tie-back anchor)
detail (Figure 4)
Jerry: To achieve a well-consolidated
shotcrete wall, limiting the movement of the
reinforcing steel is required. Based on the
floor-to-floor height at the new university
laboratory building, tie-back anchors were
used to restrict reverberations of the reinforcing
steel during placement of the shotcrete.
The initial anchor, coined “striker pin”
for this project, was observed during the
stand-alone mock-up. The type of anchor
was selected by the subcontractor installing
the reinforcing steel. During the stand-alone
mock-up, the striker pins demonstrated a
difficult detail to successfully waterproof
repeatedly. As a result of several discussions
amongst all parties, the design–builder
revised the striker pin to a stainless-steel hex
bolt, providing a stable anchor and depth
adequate to detail waterproofing onto. The
stand-alone mock-up provided a platform
to discover and discuss a critical detail that
would occur hundreds of times below grade.
David: Intentionally penetrating a
waterproofing membrane is not a good idea,
but sometimes it can’t be avoided. The striker
pins were required for the project, but we
did not realize that standard pins are unstable
and could not be made watertight. It
wasn’t until we saw the pins in use that we
could understand that different pins were
required and how to make them watertight.
4. Overspray of shotcrete (Figure 5)
Jerry: A stand-alone mock-up provided
access to the backside of the wall that would
not be accessible on the building itself. After
removal of the lagging boards and drainage
panels, the waterproofing membrane was
exposed for observation. Areas of disbonded
membrane were observed approximately the
same height as the first lift of shotcrete.
After destructive removal of the waterproofing
membrane, it was discovered that the
disbonded areas were covered in a thin layer
of shotcrete as a result of overspray from the
first lift of shotcrete, creating a bond-breaker
for the second lift. The overspray was well
bonded to the waterproofing membrane,
while the shotcrete did not bond at all to the
oversprayed shotcrete. Without destructive
2 2 • I I B E C I n t e r f a ce A u g u s t 2 0 1 9
Figure 3 – During placement of shotcrete, installation of an additional striker pin was
observed, which created penetrations in the waterproofing membrane that could not be
detailed by the waterproofing installer.
Figure 4 – Striker pin installed and detailed with waterproofing was observed to be
inadequate, demonstrating a difficult detail to achieve repeatedly in the field.
observation to the backside of the standalone
mock-up, this would not have been
discovered.
David: Considering we were working
with a structural shotcrete wall, reduction
of lateral water migration was not the driving
factor for a good bond to the wall; the
driving factor was durability. An intimate
bond of the membrane to the substrate
increased the overall durability of the system.
Seeing a fresh lift of shotcrete fail to
stick to old shotcrete overspray was astonishing
and something we needed to address.
5. Impact of shotcrete (Figure 6)
Jerry: The process of installing shotcrete
applies significant force upon impact,
and having the project team (owner representatives,
architects, engineers, design–
builders, subcontractors, and manufacturer
representatives) observe this force made
an impression on the importance of durable
details that have been proven to work
for similar installations. Every pre-applied
waterproofing system is different, and each
manufacturer tackles the impact of shotcrete
differently.
David: Until you have seen concrete
shot out of a hose at 90 mph, you cannot
fathom the forces involved. Yes, the impact
of the aggregate hitting the wall is intense,
but the forces on the membrane are no joke.
It is amazing how much load is put on the
laps.
ORDINARY ROOFS
WASTE ME
HYDROTECH ROOFS
LEVERAGE MY
POTENTIAL
A u g u s t 2 0 1 9 I I B E C I n t e r f a ce • 2 3
Figure 6 – Observations of the placement of shotcrete.
Figure 5 – Observations from the backside of the mock-up showed the membrane did not
bond in the oversprayed shotcrete areas (see arrow).
6. Detensioning of tie-backs (Figure 7)
Jerry: Stand-alone mock-ups provide
an opportunity to validate construction
sequencing at difficult details. Detensioning
of tie-backs occurs after the shotcrete is
placed and when the wall has strength to
resist the imposed load from the soils. An
example of this process was used on the
mock-up, and it demonstrated accessibility
to this condition after the infill forms were
removed.
David: Ninety percent of leaks happen
at terminations, transitions, and penetrations—
basically, where there is a lack of
continuity. Constructing the mock-up gave
us the ability to create continuity in the
team communications and, thus, the ability
to address these critical areas.
7. Securement of waterproofing at end of
pour/shooting of shotcrete (Figure 8)
Jerry: The mock-up demonstrated what
could happen when a membrane is not
completely secured to its substrate. As an
incidental occurrence, and since this was
a stand-alone mock-up, the waterproofing
installers did not take the care to secure the
membrane at the edge of the mock-up wall.
The finished shotcrete did not cover all the
installed waterproofing area for the standalone
mock-up. This created about a twofoot-
wide area at both ends of the mockup.
After the completion of the installed
shotcrete, overspray was observed on the
exposed membrane. By not being secured to
the substrate, the membrane could conform
to the sprayed shotcrete and did not remain
flat against the lagging wall. The membrane
curled at the edge of the shotcrete, creating
areas that did not bond to the shotcrete.
David: Other than the configuration,
this is the same situation as the pockets for
detensioning the tie-backs. The continuity
with the team creates continuity with the
system and goes a long way to addressing
the majority of potential leaks.
8. Bond of waterproofing demonstrated
by destructive testing
(Figure 9)
Jerry: As one of SmithGroup’s expectations
for installed waterproofing membranes,
the bond that is achieved between the membrane
and the shotcrete was important. In
addition to the stand-alone mock-up wall,
a smaller mock-up—approximately 4 x 4
ft.—was constructed. The intention of this
mock-up was to perform a pull test in the
field similar to what is done as a lab test
for ASTM D903. The smaller mock-up was
2 4 • I I B E C I n t e r f a ce A u g u s t 2 0 1 9
Figure 7 – Earth retention tie-back observed after form work was removed prior to the
application of waterproofing detailing.
Figure 8 – View looking up and towards the
edge of the shotcrete mock-up wall. Figure 9 – Pull test of the waterproofing membrane by hand on a smaller 4- x 4-ft. mock-up.
the result of a concern that destructive
removal of the lagging boards and drainage
board on the stand-alone mock-up could
jeopardize the integrity of the waterproofing
membrane’s bond to the shotcrete. With the
understanding that field tests and lab tests
are not replicas, a performance value published
on the product data was used as a
benchmark for the field test. Unfortunately,
the field version of the pull test was never
performed. The significant force needed to
pull the membrane away from the substrate
by hand was observed to be difficult and
demonstrated a successful bond.
David: No matter what numbers you
put on a data sheet or lab test that you run,
there is nothing like the empirical “data”
from trying to yank something off the wall.
PROJECT ANCHOR POINTS
The three anchor points established
during the construction and deconstruction
of the mock-up were:
• The goal: Make a building that does
not leak.
• The expectation: Everyone is responsible
for making a watertight system.
• The common language: Teamwork.
CONCLUSION
Any mock-up should provide lessons
learned within the construction processes,
but this mock-up revealed far more. Our
stand-alone blindside waterproofing mockup
provided a rare look behind the wall (literally)
and gave us an understanding of how
the project-specific materials functioned.
There were three surprising observations
that would not have been possible without
deconstructing the lagging wall:
• How significantly the shotcrete overspray
affected the bond between lifts
of the assembly
• How large the areas of moderately
consolidated shotcrete were
observed in the mock-up
• How tenaciously the blindside membrane
bonded to the areas of wellconsolidated
shotcrete
Given the uncertain efficacy of blindside
waterproofing installations and the uncovering
of these surprise observations found
in the mock-up, we understand the significant
demand placed upon the waterproofing
system. The use of a stand-alone mock-up
not only gave us insights into improving the
processes on this project, but it gave us a
better understanding of the obstacles inherent
in most structural shotcrete blindside
waterproofing.
As an industry we all agree that mockups
are an important tool in the production
of a successful project, but this mock-up
revealed insights into blind-side waterproofing
that were previously inaccessible. The
lessons learned and the subsequent application
to the stakeholders’ expectations
were well worth the significant time and
expense committed to constructing this
full-size stand-alone mock-up, let alone the
importance of future projects.
THE GARDEN ROOF®
ASSEMBLY
INTRODUCED OVER
20 YEARS AGO,
PROVIDING:
stormwater management solutions
reduce
retain
delay
extended roof longevity
additional usable space
full assembly warranty
Learn more today at
hydrotechusa.com/power-of-rain
HELPING YOU
HARNESS THE
POWER OF RAIN™
© 2019 Garden Roof is a registered trademark of American Hydrotech, Inc.
Harness the Power of Rain is a trademark of American Hydrotech, Inc.
A u g u s t 2 0 1 9 I I B E C I n t e r f a ce • 2 5
David Leslie, RWC,
is director of technical
services and
product management
for Polyguard
Products. His three
decades of industry
experience include
product development,
contracting,
and consulting.
He is a
published author,
public speaker, expert witness, and
holder of multiple patent applications.
Leslie is an active member of IIBEC, a
Licensed Field Auditor with ABAA,
and a member of SWRI. His core belief is that
there is no good reason for a building to leak,
and he has committed his career to keeping
people dry.
David Leslie, RWC
Jerry Carter has
been a member
of SmithGroup’s
Building Technology
Studio
for 11 years. He
specializes in the
design and restoration
of plazas
and garden roofs,
conventional roofing,
and belowgrade
waterproofing.
He also plays a key role in developing
and maintaining SmithGroup’s master specifications
related to the exterior enclosure.
Carter received his bachelor’s and master’s
degrees in architecture from Lawrence
Technological University. He is currently vicechair
for the local chapter of the Building
Enclosure Council.
Jerry Carter