Skip to main content Skip to footer

High-Performance Buildings: Integrating the Wall and Roof Air Barriers

November 23, 2017

High-Performance Buildings:
Integrating the Wall and Roof Air Barriers
Bill Waterston, RRC, AIA
Wiss, Janney, Elstner Associates, Inc.
311 Summer Street, Ste. 300, Boston, MA, 02210
Phone: 617-946-3400 • E-mail: wwaterston@wje.com
B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7 Wa te r st o n • 9 3
Abstract
Controlling unintentional air leakage (infiltration and exfiltration) across building enclosures
is a key factor for achieving high-performing buildings. Continuity between air barrier
materials and assemblies is essential to controlling air leakage. This presentation will provide
practical answers to the question: “What does it take to construct a high-performance
building that maintains air barrier continuity across the full enclosure?” Quality assurance
and quality control measures, including whole-building air leakage testing and building
enclosure commissioning, will be discussed, with examples showing the challenges, equipment,
and coordination involved in achieving these measures. Case studies will be presented
to highlight project-specific examples.
Speaker
Bill Waterston, RRC, AIA — Wiss, Janney, Elstner Associates, Inc.
Bill Waterston , RRC, AIA, is a registered architect and a
Registered Roof Consultant. He has broad-based architectural experience
in both waterproofing and roofing systems, which provides him
with a unique perspective for solving building enclosure challenges
for new and existing buildings. Waterston provides building enclosure
assessments and building commissioning services and performs
building enclosure testing of components and completed buildings. He
has authored several articles on roofing material choices and roofing
practices. Waterston has presented at ABX, RCI, and Construction
Specification Institute meetings and symposia.
Nonpresenting Coauthors
Ben Lueck, RA — Wiss, Janney, Elstner Associates
Wei Lam, PE — Wiss, Janney, Elstner Associates
9 4 • Wa te r st o n B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7
Introduction
Controlling unintentional air leakage
(infiltration and exfiltration) across building
enclosures is a key factor in achieving
high levels of performance in buildings.
Continuity between various air barrier
materials and assemblies is essential to
controlling air leakage. Adhesive compatibility,
chemical compatibility, and construction
sequence are just some of the factors
that need to be considered. Roof-to-wall
transitions can present some specific challenges
in this regard.
This paper provides a general explanation
of air barriers and discuss their performance.
We will review various materials,
systems, and whole-building requirements
and provide definitions and examples of
each. The reader will be exposed to examples
of air barriers at roof-to-wall transitions
that are not continuous. The paper and presentation
will also identify important considerations
with respect to integrating air
barriers between wall and roof assemblies.
Additionally, common details and methods
will be presented.
Air Barriers Defined
Air barriers control air leakage into and
out of the building envelope. A further definition
of a continuous air barrier would be:
the combination of interconnected materials,
assemblies, and flexible sealed joints
and components of the building envelope
that provide airtightness to a specified permeability.
Air Barrier Continuity
Continuity is a code requirement for the
air barrier. Care should be taken in detailing
and construction, whether the building
is simple or complex, a few stories or many.
To quote from an article in Construction
Specifier:
Discontinuity is one of the most
common mistakes designers and
contractor make. On the drawings,
the air barrier should be “traceable”
with a finger around the entire envelope,
with no discontinuities. One
typical problem area involves the
membrane installation. The membrane
should be installed flat against
the substrate without wrinkles or
tunnels to control air transfer.
Other locations of concern are
the transitions between the wall
and roof air barriers, which should
overlap each other. However, interference
from the roof deck or parapet
can make this difficult to achieve. In
some cases, the air barrier may need
to extend beneath the parapet framing
to achieve continuity, or the edge
of deck may need to move inward
to allow continuity of the barrier
behind the wall veneer. If the area is
improperly detailed or constructed,
severe damage can result, including
condensation and damage/corrosion
to concealed construction.1
An interesting benefit to including an
air barrier within a roof assembly was
noted in a paper from 2009. The National
Research Council of Canada (NRCC) performed
research on a variety of fully bonded
single-ply roofing assemblies and determined
the impact of air intrusion on wind
uplift resistance and the benefit of including
an air barrier in the roofing assembly.
The paper states that air intrusion can
significantly alter the wind uplift behavior
of the roofing assembly. The research concludes
that, “Wind uplift performance is
improved on assemblies with (air) barrier[s].
An improvement of about 50% can be measured
in the wind uplift rating for the tested
assemblies.”2
Air Barrier Products
Air barrier products may take several
forms:
• Mechanically attached membranes,
also known as house-wraps—usually
a polyethylene-fiber or spunbonded
polyolefin, such as Tyvek—
generally accepted as moisture and
air barriers (ASTM E2178)
• Self-adhered membranes, which are
typically also water-resistant and
vapor barriers
• Fluid-applied membranes, such as
heavy-bodied paints or coatings,
including polymeric-based and
asphaltic-based materials
• Closed-cell, medium-density, sprayapplied
polyurethane foam, which
typically provides insulation as well
• Some open-cell, spray-applied polyurethane
foams that are of high
density
• Board stock, which includes 12-mm
plywood or oriented strand board
(OSB), 25-mm extruded polystyrene,
etc., and those with taped seams
Air Barrier Systems
A complete air barrier system is composed
of the following hierarchy: Air barrier
materials and air barrier accessories
are combined into air barrier components;
those are combined into air barrier assemblies;
and together, they become air barrier
systems.
Air barrier materials – Building materials
that are designed and constructed
to provide the principal plane of airtightness
through an environmental separator,
which has an air permeance rate no greater
than 0.02 L/(s•m²) at a pressure difference
of 75 Pa when tested in accordance
with ASTM E2178. Air barrier materials
meet the requirements of the CAN/ULC
S741 Air Barrier Material Specification.
The air barrier materials are typically the
“big” pieces of material used in an air barrier
assembly.
Air barrier accessories – Products designated
to maintain airtightness between
air barrier materials, assemblies, and components,
to fasten them to the structure of
the building, or both (e.g., sealants, tapes,
backer rods, transition membranes, nails/
washers, ties, clips, staples, strapping,
primers), and which have an air permeance
rate no greater than 0.02 L/(s•m²) at
a pressure difference of 75 Pa when tested
in accordance with ASTM E2178. Air barrier
components are used to connect and
seal air barrier materials and/or air barrier
assemblies together.
High-Performance Buildings:
Integrating the Wall and Roof Air Barriers
B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7 Wa te r st o n • 9 5
Air barrier components – Premanufactured
elements, such as windows,
doors, and service elements that are
installed in the environmental separator
and sealed by air barrier accessories and
that have an air leakage rate no greater
than 0.20 L/(s•m²) at a pressure difference
of 75 Pa when tested in accordance with
ASTM E2357.
Air barrier assemblies – Combinations
of air barrier materials and air barrier accessories
that are designated and designed
within the environmental separator to act
as continuous barriers to the movement of
air through the environmental separator
and that have an air leakage rate no greater
than 0.20 L/(s•m²) at a pressure difference
of 75 Pa when tested in accordance with
ASTM E2357.
Air barrier systems – Combinations
of air barrier assemblies and air barrier
components, connected by air barrier
accessories, that are designed to provide a
continuous barrier to the movement of air
through an environmental separator, which
has an air leakage rate no greater than
2.00 L/(s•m²) at a pressure difference of 75
Pa when tested in accordance with ASTM
E779 or CAN/CGSB 149.10 or CAN/CGSB
149.15.
Marketplace Challenges
As designers, consultants, manufacturers,
and installers, we have many challenges
in today’s construction environment,
including design complexity, increasing
material and system options, varying project
delivery, contracting and procurement
methods, and both national and local code
performance requirements.
Requirements
The U.S. Army Corps of Engineers
(USACE) set a requirement (ECB 29-2009)
that all new buildings and buildings undergoing
major renovation shall pass an air
leakage test where the results are less than
or equal to 0.25 CFM per square foot of
exterior envelope at 0.3 inch of water gage
(75 Pa) pressure difference.
Since the introduction of air barrier
requirements and maximum
allowable air leakage rate in 2009,
more than 250 newly constructed
and renovated buildings have been
tested to meet or significantly exceed
these requirements. Some of them
were proven to have an air leakage
rate between 0.005 and 0.25 CFM/
sq. ft. at a pressure difference of 75
Pa during the first test. This experience
has proven that when buildings
are designed and constructed with
attention to details, US Army requirement
to air tightness can be met with
minimal cost increase (primarily for
development of architectural details
and testing).3
Since this was published in 2011, it is
expected that the USACE continues to experience
similar results.
Within ASHRAE Standard 189.1 – 2014,
Standard for the Design of High Performance
Green Buildings, there is a requirement that
the air barrier be continuous and the completed
building air leakage rate of the building
envelope must be less than or equal to
0.25 cubic feet per minute per square foot of
envelope area (0.25 CFM75/ft2).
Mandatory requirements of ASHRAE
90.1 – 2016, Section 5.4.3, Air Leakage,
include:
• Continuous air barrier design
• Continuous air barrier installation
• Testing, acceptable materials,
assemblies
• Fenestration and doors
• L oading-dock weather seals
• Vestibules
In Section 5.4.3.1.1, Continuous Air
Barrier Design, requirements are:
• Air barrier components of each
building envelope assembly clearly
identified or noted on construction
documents
• Joints, interconnections, and penetrations
of continuous air barrier
components detailed or noted
• Continuous air barrier shall extend
over all surfaces of the building
envelope
• Continuous air barrier shall be
designed to resist positive and negative
pressures from driving forces
In Section 5.4.3.1.2, Continuous Air
Barrier Installation, they are:
• Joints around fenestration and door
frames
• Junctions between walls and floors,
between walls at building corners,
and between walls and roofs or ceilings
• Penetrations through the continuous
air barrier in building envelope
roofs, walls, and floors
• Joints, seams, connections between
planes, and other changes in continuous
air barrier materials
General Design of the
Building Enclosure
Let’s step back and look at the various
functions of the building enclosure. The
building enclosure must:
• Control rain penetration
• Control airflow
• Control vapor flow
• Control heat flow
• Control light, solar, and other radiation
• Control noise
• Control fire
• Be durable
• Provide strength and rigidity
• Be aesthetically pleasing
• Be economical
• Require little or no maintenance
For the purposes of this paper, we are
only discussing controlling airflow. Issues
with air leakage include the following:
• L ife safety: fire and smoke containment,
frozen sprinkler pipes
• Durability: condensation, corrosion,
decay, and biological growth
• Roof membrane uplift forces
• Occupant comfort and health:
indoor air quality, temperature control,
noise, moisture, odor transmission
• Elevator and manual or automatic
door operation
• Insect and pest control
• Operating costs: energy consumption,
maintenance
Air Leakage
For air leakage to occur, there must be
a pathway or opening and a driving force
or difference in pressure. The pathway
can be an orifice, a channel, or diffuse or
microscopic openings that allow airflow
directly through a material. Leakage paths
in buildings are from exterior to interior,
as well as interior to interior, and include
shafts, stairs, elevators, and duct work. The
direction of flow is always from high pressure
to low. Differential pressure can come
from wind, stack effect, or be mechanically
driven.
9 6 • Wa te r st o n B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7
Whole -Building Air
Leakage Testing
Whole-building air leakage testing is
generally performed following the test method
described in ASTM E779, Standard Test
Method for Determining Air Leakage Rate
by Fan Pressurization. This test method is
intended to quantify the airtightness of a
building envelope. This test method consists
of mechanical pressurization or depressurization
of a building and measurements of
the resulting airflow rates at given indooroutdoor
static pressure differences. From
the relationship between the airflow rates
and pressure differences, the air leakage
characteristics of a building envelope are
determined.
Generally, fans are installed in door
openings, and relative pressure differences
are measured between indoor and outdoor
conditions. The amount of airflow is measured.
These tests are performed during
mild temperatures and low-wind conditions
to minimize the impact of those external
factors.
To perform whole-building air leakage
testing, the building must be essentially
completely constructed. If the building does
not meet the performance requirements,
repairs to the air barrier are difficult or
impossible without deconstructing building
envelope components. Testing of components,
portions of the building, or individual
systems, such as curtainwall assemblies
or opaque wall systems before the cladding
is installed, is recommended while
the building is under construction. This
will help determine the air leakage rates of
components to confirm the
materials and installation
are in alignment with the
whole-building leakage criteria.
By performing testing
early, remediation efforts
can more easily be performed.
Air leakage testing
of the whole building can
then be performed as a confirmation
that the building
enclosure systems meet the
overall requirements.
In an effort to determine
average whole-building air
leakage rates for more modern
buildings in the United
States, ASHRAE developed
a research project, designated
ASHRAE 1478 – RP.
Sixteen mid- and high-rise commercial
buildings constructed since 2000 were tested
from 2010 to 2012 for airtightness as a
research project for ASHRAE. The enclosure
of each was tested to determine its overall
air leakage compared to other buildings
in the group and previous investigations
and compared to design standards. The
International Energy Conservation Code
(IECC) 2012 (0.40 CFM75/ft2), U.S. Army
Corps of Engineers (USACE) (0.25 cfm75/
ft2), and ASHRAE Standard 189.1, Design
of High Performance Green Buildings (0.25
CFM75/ft2), were used as benchmarks.
Each of the standards relies on the same
testing procedures; only the maximum
allowable air leakage values vary.
Three-quarters of the buildings met the
IECC requirement of 0.40 cfm75/ft2.
Of the sixteen, six were designed with
an enclosure consultant and quality assurance
program. All buildings with such special
attention paid to airtightness met the
USACE 0.25 CFM75/ft2 standard.4
Project Example – Example 1
The reality in some projects is interesting
and instructive. The following section
and detail depict a roof-to-wall intersection
at a scupper (Figure 1). The details
and shop drawing development illustrate
the limited information provided by the
construction documents and the interpretation
of the design in the shop drawings.
The constructability of the air barrier and
the sequencing of construction are not
addressed well in the curtainwall contractor’s
drawings.
The detail was further modified in the
shop drawing process (Figure 2). Some of
B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7 Wa te r st o n • 9 7
Figure 1 – Section provided in the documents of roof edge and curtainwall
intersection.
Figure 2 – Detail provided for the scupper within the drawings.
the work required for a fully integrated air
barrier was indicated to be performed “by
others.”
This shop drawing detail did not consider
the sequencing of the roofing installation
and the fastening of the curtainwall
supports (Figure 3).
Other cases are caught after construction
and then need to be modified, such
as this example of exhaust ducts located
on the roof plan, without adequate distance
between penetrations and intake
and exhaust (Figure 4 and Figure 5). This
was a roofing issue and an air barrier
issue, because at this point, both terminated
at the same point. Ultimately,
the stacks were reconfigured to create a
greater separation between intake and
exhaust airflow.
Specifying Air Barriers and
Quality Assurance
When specifying air barriers, each of the
following must be addressed:
• Performance
• Warranty
• Submittals
• Quality assurance
• Products
• Execution
• Field quality control
All of these are included in the technical
sections for the products, but it is also
advised to include a Division 01 specification
that outlines the coordination necessary
between the application of air barriers
and the systems and products that they
attach to, overlap, or otherwise interact
with. Within the Division 01 specification,
the performance testing for the completed
work, mock-ups required, and those shop
drawings that include transitions—i.e.,
between wall and roof air barrier system—
must all be defined.
When specifying air barrier submittals,
require product data, test reports,
product certificates, shop drawings, and
installer qualifications. This documentation
is required in order to ensure that
the product or products submitted meet
the performance requirements. Review of
these documents will assist with proper
sequencing, confirm proper coordination,
ensure compatibility, identify manufacturers’
requirements, and confirm that the
installer is qualified for the installation.
Many times, installers resist the detailing of
the integration of their system with adjacent
systems. However, it should be required
9 8 • Wa te r st o n B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7
Figure 3 – Detail by curtainwall contractor.
that the shop drawings be coordinated and
that details indicate the continuity of the
air barrier to ensure proper integration and
understanding of sequencing.
When specifying the products, the air
barriers should be strong enough to resist
building pressures and be suitable for the
climate (i.e., high-temperature-resistant).
This also applies to auxiliary and accessory
materials. Indicate the location on the drawings
of the air barrier in relation to other
materials, and review the constructability
of the assembly in which it will be installed.
In your product review and comparison
between products, assure that materials
are available and that there are skilled
and trained installers in the location of the
project.
Compatibility of products within the
assembly and adjacent materials is vitally
important. We often see materials intended
to bond to silicone sealant or silicone
sheet. Nothing bonds well to silicone except
silicone. So the order of construction and
the selection of sealants and mechanical
attachment are all important in order to
ensure that materials intended to be bonded
together stay attached.
Quality assurance steps to specify
include the third-party assessment and
testing of the air barrier by trained inspectors.
One group that trains installers and
inspectors is the Air Barrier Association
of America (ABAA). Full-scale mock-ups
at an offsite laboratory, as well as on-site
mock-ups, can be used to illustrate and
review details and conditions found in the
overall project. This allows the installing
contractor the opportunity to review the
assembly, sequencing, coordination, and
constructability of the various components.
Pre-installation meetings are important to
include not only the installing contractors
for the air barrier, but include the contractors
installing the neighboring or overlying
components. Insist on a meeting where the
wall air barrier contractor and the roofing
contractor, as well as the waterproofing
contractor, discuss edge conditions and the
overlapping of materials, the potential time
delays between the installation of materials,
and other coordination issues to ensure a
continuous air barrier.
When the product and systems are
being installed, specify that the contractor
examine the substrate assembly and
adjacent materials, the surface preparation
for the air barrier, and the treatment
of joints between the products.
Specify flashing materials and their support.
Specify transition materials such as
silicone sheets to bridge the gap between
window assemblies and roofing or walls.
B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7 Wa te r st o n • 9 9
Figures 4 (left) and 5 (below) –
Images of intake and exhaust
stacks with inadequate separation
between stacks to provide space to
secure and seal the air barrier and
roofing to the stacks.
Include specifications for the
repair of damage or deficient
air barriers and substrate conditions.
Stress continuity and
the coordination with other
trades.
Field quality control can
take the form of inspections
by ABAA inspectors, field tests
to determine if penetrations or
ties are sealed and airtight,
partial system testing, and
other specific tests such as
adhesion tests for the membranes.
Remember not to rely
on whole-building air leakage
testing as quality control,
because it requires that the
building be essentially complete
before any testing can be
performed. Rely on testing of
materials, systems, and joints
between systems to be air and
watertight. Test as you build,
rather than testing after it’s all
built because by then, it may
be too late to go back and fix
something broken.
Whole -Building Air
Leakage Testing
Whole-building air leakage
testing can be performed using
ASTM E779-10, Determining Airtightness of
Buildings’ Air Leakage Rate by Single-Zone
Air Pressurization or the U.S. Army Corps
of Engineers’ Air Leakage Test Protocol for
Building Envelopes, 2012. All of these test
methods collect data to determine the building
airtightness. It should be noted that
whole-building testing is not a simple or
inexpensive undertaking. This testing can
be disruptive and will require a coordinated
effort by a variety of personnel. It should
include those familiar with the operation
of the heating and cooling of the building,
the ventilation and exhaust stacks, and the
stair and elevator operations.
Reviewing Air Barrier Designs
or Drawing Air Barriers
When reviewing or designing air barriers,
take the time to look at the building
overall. Determine where the plane of the
air barrier will be within each component
or system. Consider floor edges, vestibules,
loading docks, mechanical spaces,
balconies, terraces, roof edges, soffits,
1 0 0 • Wa te r st o n B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7
Figure 7 – An isometric view of the entire building with various areas and
functions highlighted. Green area is conditioned space air barrier; yellow area is
conditioned space under negative pressure (interior and exterior air barrier); red
area is unconditioned space with interior air barrier.
Figure 6 – Section view of the overall building, with the outline of the air barrier location.
and all other transitions and terminations. Wallto-
foundation and roof-to-wall intersections are
important. How is the barrier intended to bridge
across those joints? Examine the transition from
walls to windows and walls to curtainwalls, and
determine where the air barrier is to join the window
or curtainwall. Determine if the connection is
durable, or is it relying on a single line of sealant
to create the connection? Expansion joints should
be reviewed closely. Make sure the air barrier
extends across the joint and can move with the
other materials.
Look at the building and determine what
spaces are conditioned, as well as those that are
under positive or negative pressure. Hospitals and
laboratories use pressurization to control contaminates,
and those areas should be understood and
detailed. Here is an example of an overall section
with the location of the air barrier highlighted and
an overall depiction of the building with the different
spaces and their relationships (Figure 6 and
Figure 7).
Examples of Air Barriers at the
Roof and Wall
Example 2
As an example, let’s look at the roof-to-wall intersection.
Where is the air barrier going to be installed? It
can be at the roof slab and transition to the wall. It can
also extend up the parapet, over the parapet, under the
blocking, and tie again into the wall air barrier.
B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7 Wa te r st o n • 1 0 1
Figure 10 – Section detail at steep-sloped roof and low-sloped roof
intersection.
Figure 8 – Detail section of roof and wall intersection with
potential air barrier location over the parapet.
Figure 9 – Detail section of roof and wall intersection with wall
barrier meeting roof barrier at slab edge.
Here are two roof edge conditions with
two different air barrier locations. Figure
8 brings the air barrier up the parapet,
under the coping, and ties the air barrier in
under the blocking. Consider the sequencing
required and the coordination needed
among trades to build a continuous air
barrier. Figure 9 is a much simpler and
straightforward approach where the wall
and roof air barrier meet at the slab edge.
This will require the air barrier from the wall
to extend past the roof deck so the roof air
barrier can bond to the wall barrier.
Example 3
Here is an example where a sloped
roof wall, parapet, and roof edge condition
created a location where air leaked into
the parapet (Figure 10). The warm, moist
air entered the cooler parapet and caused
condensation that lead to water in the
roofing system and corrosion of the metal
components.
The sequence of construction did not
allow the installation of the air barrier as
a continuous membrane (Figure 11). The
metal stud wall supporting the parapet was
installed on the metal
deck with a membrane
between the stud track
and the deck. When the
substrate board for the
air barrier for the lowsloped
roof or the steepsloped
roof was installed,
the membrane under the
stud track did not transition
and did not join the
wall or roof air barriers.
There was now a direct
path from the interior up
into the parapet and into
the roofing systems.
Example 4
Figure 12 shows a
detail of an expansion
joint that fails to coordinate
the air barrier and
creates open paths for air
infiltration.
This is a condition
where a third-floor wall
meets a third-floor roof,
and an expansion joint
separates the two. The
opening is watertight, and
it has a cover that can
move as the joint opens
and closes. The expansion
joint seal is positioned
at the floor level
and seals on one side
against the floor slab. The
air barrier from the rising
wall can extend down
to the slab, under the
exterior wall framing, and
continue across the seal.
Where the seal meets the
roof, a light-gauge metal
stud curb with insulation
rises above the roof deck. The air barrier
from the roof deck is applied to the sheathing
on the curb and extends up to the top of the
curb under the expansion joint cover. The
detail misses the connection of the air barrier
from the top of the curb to the roof side of the
expansion joint seal. There is no sheathing
on this side, and air can easily move from the
interior up through the insulation and stud
curb, under the cover, up the exterior wall
assembly, and out the flashing for the wall.
1 0 2 • Wa te r st o n B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7
Figure 11 – Section detail at steep-sloped roof and low-sloped roof intersection. Red dashed line
illustrates the air barrier location. The blue line is the path for warm, moist air that escaped into
the roofing and parapet because of openings in the air barrier at the roof deck.
Conclusions
During the design and
project reviews, identify
challenging transitions and
terminations with respect to
achieving air barrier system
continuity. Document the
conditions and communicate
clearly the intent.
Specify for performance,
continuity, and trade coordination,
and consider constructability
and compatibility
of the air barrier, its
components, and the transitions
between systems and
materials.
Observe installations
and validate performance
with mock-ups and quality
control testing.
References
1. J. Kelly, J. Ceruti.
“Continuing Problems
With Air Barrier
Systems.” Construction
Specifier,
pp. 62-72, December
2011.
2. B.A. Baskaran, S.
Molleti, and M. Sexton.
“Impact of Air
Intrusion on the Wind
Uplift Performance of
Fully Bonded Roofing Assemblies.”
Construction and Building Materials,
23, (2), pp. 889-901, February 01,
2009 (NRCC-49721).
3. A. Zhivov and D. Herron. “Improvement
of Air Tightness in U. S.
Army Buildings.” Journal of Building
Enclosure Design, 2011-07-01, p.
11-13.
4. T. Brennan et al. “ASHRAE 1478-
RP: Measuring Airtightness of Midand
High-Rise Non-Residential
Buildings.” Proceedings of the
Thermal Performance of the Exterior
of Whole Buildings XII International
Conference. May 13, 2014.
B u i l d i n g E n v e l o p e T e c h n o l o g y S y m p o s i u m • No v e m be r 1 3 – 1 4 , 2 0 1 7 Wa te r st o n • 1 0 3
Figure 12 – Section detail of expansion joint.