Skip to main content Skip to footer

Interface Detail for New Construction

May 14, 2005

Introduction
One of the most common call-backs for “leaky roofs” may not have anything to
do with the roof at all, but rather an improperly detailed and constructed interface
between the roof and wall. This article discusses how to properly design and build
a roof-to-masonry cavity wall interface detail (Figure 1).
Early Decisions
Successful roof-to-wall interface details begin with the designer. First, it is critical
for the producer of construction documents to realize that this detail needs to
be developed, drawn (ideally at a scale of 3″ = 1′-0″), and referenced by building section.
Too often this protocol is overlooked and construction decisions are delegated
to “others” to figure out in the field.
Project specifications should reference this critical detail and suggest coordination
between related trades in a preconstruction meeting. For example, when a roof
terminates at a masonry cavity wall, the mason and the roof installer need to coordinate
an appropriate elevation for masonry through-wall flashing, to provide clear-
Figure 2 – Detail represents proper connection of
roof termination and two-piece stainless steel
flashing to create a continuous water-resistive
barrier.
20 • I N T E R FA C E MAY 2005
Figure 1 – Typical roof-to-wall scenario.
ance for tapered insulation systems, flashing
steps, ballast thickness, and snow
(Figure 2).
Roofing industry standards recommend
wall flashing to be an absolute minimum of
six inches above the finished roof membrane,
preferably eight to 12 inches.
Construction Issues
Once this detail has been discussed in a
preconstruction meeting, the next step in
building a successful roof-to-wall
interface detail is to schedule and
conduct proper installation inspection.
The project superintendent,
quality control representative, masonry
foreman, lead roofer, and other
related parties should oversee installation.
Key observation points include:
• Masonry wall flashing set at
correct elevation.
• Use of durable and properly
installed masonry flashing
materials.
• Provisions for, and connection
of, wall flashing and roof
termination (Figure 3).
Moisture Management Basics
Exterior wall systems may take
on water from both external and
internal sources. Wind-driven rain
will attack wall systems from the
outside, while air leakage from the
building interior may contribute
moisture inside wall assemblies in
the form of vapor condensation
(depending
on geography).
Therefore,
walls need to have
the ability to dissipate
moisture, either by drainage
or evaporation, before it becomes
problematic.
With increased understanding of moisture
management dynamics for exterior wall
systems, superior walls today are built to
both drain and breathe; masonry cavity
walls lead the way.
Masonry Cavity Walls
Masonry cavity walls are designed to
have two wythes separated by an air space.
This wall technology has an integral
drainage plane behind the veneer wythe,
allowing an opportunity for air to circulate
behind the veneer to dry the wall from the
inside out, via natural convection.
Through-wall flashing is a key component
for successful moisture management
of masonry cavity walls. Depending on wall
design, through-wall flashing should be
located at the above-grade foundation wall,
under wall caps and copings, under masonry
sills, and anywhere the vertical drainage
plane is interrupted by a wall element or
roof.
It is important to understand that the
roof-to-wall interface is an interruption in
the vertical drainage plane. If this detail
fails, building occupants will know about it
because the leak is above their heads and
likely will be expressed in the form of water
entry into the building interior.
Masonry Flashing Systems
Properly installed through-wall flashing
systems for masonry walls should follow
project specifications and details. These
construction documents should meet or
exceed applicable model, local building
codes, and approved industry standards.
Industry standards for through-wall
masonry flashing include:
• 8-inch minimum vertical flashing
rise between masonry wythes.
• Flashing top edge securely fastened
Figure 3 – Connected
roof termination
to through-wall
flashing.
Figure 4 – Sagging initial through-wall flashing (under new metal flashing) creates an internal
gutter that leaked.
MAY 2005 I N T E R FA C E • 2 1
so it does not pull away or delaminate
over time.
• Flashing support (when needed) so
it does not sag when spanning the
air space separating the masonry
wythes (Figure 4).
• 6-inch minimum flashing laps,
sealed with compatible
sealant, even when
using adhesive flashing.
• Horizontal leg of flashing
minimally level;
ideally, positively
pitched to the outside.
• Not allowing flashing to
terminate within the
wall (Figure 5).
• End dams at interruptions
of horizontal
flashing to contain
water.
• Weep holes adequately
spaced with durable
and breathable weep
hole inserts.
It is important to note that craftworkers
are required to build details as presented in
the construction documents and not by
assumed “industry standards.” All deviations
from construction documents need
approval through a proper sequence of communication
along contractual lines; i.e.,
masonry contractors submit requests for
information (RFI) to their contract holder
(construction manager, general contractor,
etc.), and not typically to the designer.
Flashing Selection
Flashing is available in many different
materials, such as stainless steel, copper,
copper composites, adhesive rubberized
asphalt membranes, and EPDM. Note that
PVC flashing has been omitted from this
list. Some light-gauge PVC flashings are not
UV-stable and have been discovered brittle
and fractured inside walls.
Flashing materials have many
characteristics. However, the three
most important through-wall
flashing attributes for
roof-to-wall interfaces
are: durability, fewest
laps possible (laps are
leakers), and ability to
resist sagging.
If the flashing on the
project does not have the
above positive attributes for
the roof-to-wall interface detail,
consider switching material
to minimize risk. In all likelihood,
there are few lineal feet of this detail
on the project. Return on investment
is significant when factoring
in the likelihood and cost of future
repairs (Figure 6).
EPDM Through-Wall Flashing
Some builders prefer to use approved
alternate materials at the roof level, regardless
of what flashing may be specified for
the rest of the project. Better flashing materials
for this critical detail include throughwall
stainless steel or 40-
mil (1.0 mm) flexible
EPDM membrane flashing.
To facilitate efficient
installation, some manufacturers
are now marketing
flexible EPDM
through-wall masonry
flashing systems in
appropriately sized roll
widths to meet specified
dimensions. This material
is thinner and more workable
than typical roofing
membrane stock at 45-
mil (1.12 mm) or 60-mil
(1.5 mm).
EPDM has the advantage
of being durable during
construction, UV-stable,
and will not ooze out
of the wall. Furthermore,
EPDM has far fewer laps
compared to any other
flashing material, such as
most adhesive flashings
(Figure 7).
Figure 5 – Water runs around end of concealed flashing.
Figure 6 – Costly through-wall flashing repair four months after initial installation.
22 • I N T E R FA C E MAY 2005
A typical piece of stainless steel flashing
is 10 feet long, while EPDM comes in 50-
foot rolls and is workable in long lengths,
unlike adhesive flashings. It also conforms
to irregularities in building construction,
unlike metal.
When using EPDM
flashing, remember to
secure the top and
bond the bottom
edges securely to
a rigid drip edge
with chemically
c o m p a t i b l e
accessories such
as sealant or tape.
It is this metal drip
edge that will ultimately
connect to the
roof termination.
Conclusion
It is critically important for
all members of the design and construction
team to understand the potential
pitfalls of roof-to-wall interface details and
the headaches they may cause. The next
time a call comes in for a leaky roof at the
intersection of the classroom wing and the
taller gymnasium wall, check out both the
roof and wall system details.
MAY 2005 I N T E R FA C E • 2 3
Figure 7 – Adhesive rubberized
flashing oozing out of wall.
Shipments of low-slope roofing membranes by members of SPRI,
the national organization representing sheet membrane and component
suppliers to the commercial roofing industry, ended 2004 on a high
note. Most materials saw double-digit increases over 2003. TPO thermoplastic
shipments were up 18% in 2004. Thermoset shipments, up
17%; and APP modified bitumens, up 20%. No year-to-year comparison
was available for “other thermoplastic” shipments, while SBS modifieds
“also posted gains,” according to SPRI.
Patrick J. Conway, AIA, is the International Masonry
Institute’s (IMI’s) director of technical services in Wisconsin.
He is a nationally published author and presenter on topics
such as flashing and moisture control, masonry movement
joints, new masonry technologies, air barriers, and job-site
troubleshooting. Conway is a member of both the American
Institute of Architects (AIA) and the Construction
Specification Institute (CSI), and can be reached via e-mail at
pconway@imiweb.org.
Patrick J. Conway,AIA
SPRI REPORTS INCREASED SHIPMENTS
trustfibertite.com
I N T E L L I G E N T R O O F I N G S O L U T I O N S
YEARS OF PROVEN
PERFORMANCE
fiberspective.
25/55 — What does it mean for you?
It’s a major step forward in fiber
membrane technology that started
55 years ago. A technology that’s
produced North America’s leading
architectural membrane. And the
world’s most durable geomembrane
liners for hazardous waste.
Not to mention 25 years of
harsh winters and blistering
summers on roofs all over
the world. Get the facts
about Intelligent Roofing
SolutionsTM in our free “fiberspective”
brochure by calling toll-free
800-927-8578, ext. 1335.