Skip to main content Skip to footer

Net-Zero/Carbon-Neutral Retrofits, 140 Kendrick St. Case Study: Tactics, Tradeoffs, and Takeaways

April 9, 2026

By Christopher Grey, RRC, REWC, PEng, and
Samira Ahmadi, BEMP, LEED AP, WELL AP
This paper was presented at the 2025 IIBEC
International Convention and Trade Show.

INTRODUCTION
140 Kendrick St. is a 2000s-era, 440,000 ft2
(40,877 m2) workplace campus in Needham,
Massachusetts, developed, owned, and
managed by Boston Properties (BXP). The
campus consists of several buildings, all
interconnected, including Buildings A, B, and C;
a mixed amenities center that connects Buildings
A and B; an elevated bridge that connects
Buildings A and C; and a parking garage with
elevated bridges connecting to Buildings B and
C (Fig. 1).
This case study will focus on 140 Kendrick
St., Building A, a 106,000 ft2 (9,850 m2) office
building that has undergone a retrofit focused
on improving overall operational efficiency
and occupant comfort. Building A is the first
net-zero, carbon-neutral office repositioning of
this scale in Massachusetts, meaning that it is a
highly energy-efficient building that produces
renewable energy on site to meet building
operations’ energy consumption annually.
The project was completed in partnership
with BXP’s lessee, which leased the building
in 2021. The scope of the renovation project
included full electrification (i.e., no fossil
fuel burning systems), building enclosure
improvements, advanced energy recovery
systems, mechanical system modernization,
and the addition of on-site renewable energy
generation. The project is expected to achieve
LEED v4 Gold Certification (pending) and
is pursuing LEED Zero Carbon certification
(pending), which will make this building the
first large-scale office to achieve this rating in
Massachusetts.
The project team consisted of the following:
• Building owner and developer: BXP
• Architect of record: Stantec Architecture
• Sustainability consultant: enviENERGY
Studio (EES)
• Building enclosure and structural engineer:
Simpson Gumpertz & Heger Inc. (SGH)
By Christopher Grey, RRC, REWC, PEng, and
Samira Ahmadi, BEMP, LEED AP, WELL AP
This paper was presented at the 2025 IIBEC
International Convention and Trade Show.
This paper will explain the process for
achieving net-zero energy and carbon neutrality
with an existing building for this project. It
will also address challenges associated with
achieving those goals and general takeaways
that other project teams should consider in the
future when reviewing existing buildings, with a
focus on specific challenges encountered during
the Building A retrofit.
Project Achievements
The key driver for the Building A retrofit was
the alignment of energy savings goals of
both BXP and their lessee. When redesigning
the building, BXP presented the lessee with
three retrofit scenarios with differing levels of
sustainability ambition. The lessee selected
the most ambitious option in line with LEED v4
Gold Certification and LEED Zero Carbon project
targets. According to BXP, the primary goal was
to create a “state-of-the-art, efficient, LEED Zero
Carbon building that provides its clients with a
safe, comfortable, and productive environment.”
The project ultimately met the following metrics:
• 40% reduction in energy use intensity (EUI)
• 1.4 MW on-site solar energy production and
storage
• 1.3M kWh annual production of renewable
energy
• 23.4 kg CO2e/ft2 (254.4 kg CO2e/m2)
embodied carbon savings
• 90% building heat recovered
• 38% reduction in indoor water use

NET-ZERO ENERGY AND
CARBON PATHWAY
Massachusetts has set carbon neutrality goals
for 2050, aligning with broader efforts to reduce
greenhouse gas emissions. Meanwhile, BXP
aims to reach carbon-neutral operation by 2025,
requiring strategic interventions to decarbonize
the built environment. Decarbonization,
the process of reducing carbon emissions
from buildings, is closely tied to both energy
efficiency improvements (i.e., upgrading
building assemblies and systems to reduce
operational energy) and electrification (i.e.,
converting building systems to rely solely on
electricity, preferably sourced from renewable
energy rather than fossil fuels). Decarbonizing
existing buildings can be a multiphase process,
where the proposed carbon reduction measures
(CRMs) can be ranked and prioritized based
on their complexity and overall impact. The
building enclosure enhancement measures
are often (and should be) prioritized over the
electrification measures as they directly impact
the heating, ventilation, and air conditioning
(HVAC) equipment sizing and overall energy
demand and cost. Given that electricity is
often more expensive than gas in many states,
including Massachusetts, upgrading the
building enclosure should be prioritized. This
includes measures such as improving insulation
and airtightness to reduce heating and cooling
loads prior to electrification, which helps avoid
increased operation costs.
In addition to enhancing energy efficiency, it is
equally important to prioritize materials with low
embodied carbon (that is, the life-cycle carbon
emissions arising from the manufacturing,
transportation, installation, and disposal of the
material). Selecting products that contribute less
embodied carbon ensures that both operational
and embodied carbon are minimized, creating a
more sustainable building in line with the goal of
carbon neutrality.
In decarbonization projects, building energy
modeling software plays a significant role; it
is utilized as a critical decision-making tool to
assess various CRMs. A critical component in the
analysis included creating an energy model that
was calibrated with utility and metered data to
represent the existing building conditions (Fig. 2).
The calibrated model was used as a baseline
for evaluating the impact of multiple CRMs,
focusing on improving the building enclosure
and upgrading the HVAC system to support the
project’s decarbonization goals. Conducting
parametric energy modeling allowed for
exploration of the most effective ways to reduce the
building’s carbon footprint, particularly in terms
of air infiltration/exfiltration and heat loss, while
modernizing systems to achieve carbon neutrality.
An early goal for the project was to achieve
a targeted EUI of 35 kBTU/ft2 (380.4 kBTU/m2)
and operational carbon neutrality with on-site
renewable energy generation. This involved
comprehensive renovations, including improving
airtightness, adding insulation to the exterior
walls and roof, and electrifying the HVAC system.
The building enclosure plays a vital role
in energy efficiency and carbon reduction,
particularly in office buildings. Air leakage through
the building’s enclosure can significantly affect
energy consumption (Fig. 3). Parametric modeling
of three sets of enclosure upgrades was reviewed,
including adding insulation to the exterior
walls and roof and improving the enclosure’s
airtightness. Each enclosure upgrade’s impact
was evaluated first on the building’s existing
mechanical systems and then in combination
with an all-electric system. This approach helped

us identify the optimal balance between energy
savings and carbon reduction to achieve the best
outcome for the building’s future (Fig. 4).
EXISTING BUILDING
CONSTRUCTION CHALLENGES
A core focus of the Building A retrofit was
improving the building’s energy performance,
primarily driven by the mechanical and enclosure
systems. The main driver for compliance was to
improve the mechanical system’s performance
by incorporating energy recovery and electrifying
the building’s HVAC system. While the
mechanical systems constitute a large percentage
of the overall building performance, the enclosure
thermal and air infiltration performance
also needed to be improved to reduce EUI,
as demonstrated in the parametric analysis
performed at the onset of the project (Fig. 3).
The original 140 Kendrick St. complex was
designed by Tsoi/Kobus & Associates Architects
and constructed in 2000. The three main
buildings were generally constructed around the
same period and used similar enclosures and
mechanical systems.
Mechanical
To decarbonize an existing building, it was crucial
to electrify both the HVAC and service water
heating systems while simultaneously upgrading
the building enclosure. At 140 Kendrick St.,
the original mechanical system consists of
gas-furnace and direct expansion (DX)-cooling
rooftop units. These units were modernized
to energy recovery units with high-efficiency
variable refrigerant flow heating and DX cooling.
The zone-level conditioning remained largely
intact, with series fan-powered terminal boxes
featuring electric reheat in the perimeter zones
and standard variable air volume boxes in the
core zones. Additionally, the new ERUs are
equipped with a high-efficiency Superblock
heat recovery system, designed to operate at an
impressive 90% effectiveness, further reducing
energy consumption and improving overall
sustainability.
Enclosure Systems
In order to meet net-zero requirements, it
was critical to make upgrades to the building
enclosure without major modifications to the
fenestration and opaque wall cladding systems.
While the building was only in service for
approximately 20 years prior to the retrofit project
and the enclosure systems generally appeared
to be in good condition, the original construction
created challenges that required review
throughout the design and construction phases.
The primary goals included improving thermal
and whole-building airtightness performance
as much as possible. The enclosure systems
for the building primarily included low-slope
membrane roofing, brick masonry veneer exterior
walls with horizontal cast stone trim elements,
and aluminum-framed fenestration systems.
The project team evaluated several potential
improvement scenarios for each of the systems,
with some being easier to upgrade than others.
Roofing Systems
The existing roofing systems were original to
construction, about 20 years old, and included
about 3 in. of polyisocyanurate insulation
equating to R-17. Although the goal was to
reuse the existing systems, upgrading the
thermal performance of the roof was a critical
need to improve energy efficiency, as the roof
constitutes a relatively large percentage of the
enclosure for this building’s geometry. Through
the parametric energy modeling process, the
design team established a goal of achieving
R-30 (code minimum) R-40 (enhanced) with
the new roof assembly. Additionally, since the
project scope included adding a solar panel array
across the Building A roof with a mechanical
system replacement, replacing the roof was
recommended so that the service lives of the
systems aligned more closely. For example, the
project team did not want to install a solar array
with a 25- to 30-year lifespan on a 20-year-old
roof and then need to remove and reinstall the
solar array when the roof needed replacement in
approximately 10 years.

The scope of work included removing the
existing roofs and replacing them with new
single-ply membrane systems, including cover
board, insulation, drainage boards, and pedestal
paver amenity deck systems, where applicable.
The project team evaluated two primary options:
R-30 and R-40, which both involved increasing
insulation thickness compared to the original
construction: approximately 5 in. thick insulation
for R-30 and 7 in. for R-40. There were several
challenges associated with increasing insulation
thickness across the roof, including drainage
modifications, increased structural loading,
and increased insulation heights at interface/
flashing conditions. The existing structural metal
deck was sloped at 1/8 in. per ft. (10.4 mm/m),
and although there was a desire to improve
drainage to ¼ in. per ft. (20.8 mm/m), adding
additional tapered insulation quadrupled the
amount of insulation at the high points located
at the building perimeter (Fig. 5). This would
have triggered replacement of rising wall and
mechanical interface flashings and would
have significantly impacted the aesthetics of
the parapet edges and exterior wall cladding
elements that were not in the project’s intended
scope of work. Furthermore, loads on the roof
would be increased due to the additional dead
load of the tapered insulation and the solar array
and increased ponding loads during clogged
drain events due to the increased slope to high
points. The increased loads triggered a structural
analysis of the existing roof framing to confirm
that the existing structure could support the
new loading conditions. The roof structure
was framed with metal deck and intermittent
structural framing members and had limited
reserve capacity. The International Existing
Building Code (IEBC) allows existing roof slopes
to remain if positive drainage is provided, which
the existing roof did even at 1/8 in. per ft. Due to
the dimensional and structural limitations, the
project team decided to maintain the original
roof slope of 1/8 in. per ft. with only tapered
insulation where required to divert water laterally
between roof drains, around obstructions, and as
needed to maintain positive drainage. Although
the lower slope system was selected, the team
maintained the new R-40 roof insulation.
Opaque Wall Systems
The exterior walls include existing brick masonry
veneer, mechanically attached water-resistive
barrier, and exterior sheathing over light-gauge
framing with batt insulation between studs
(Fig. 6). While the opaque wall systems were
generally in good condition and included a
water-resistive barrier behind the brick masonry,
the system lacked a dedicated air barrier, and
the walls were insulated on the interior. Both
components needed to be addressed by the
design team as part of the retrofit to meet
the project goals of improving airtightness
performance and achieving approximately R-30
in the opaque walls. Given the project’s climate
conditions, both design aspects could not be
reviewed independently, and a decision in one
component may have had a negative impact on
the other component.
The existing construction included fiberglass
insulation between 6 in. (152.4 mm) deep
light-gauge metal-framed studs. The upper
floors included an additional uninsulated 2½ in.
(63.5 mm) deep interior light-gauge metal-framed
stud wall furred off approximately 1 in. (25.4 mm)
from the exterior light-gauge metal-framed stud
wall. We suspect that this additional wall was
added by a previous lessee as it is not shown
on the existing building drawings. Including
thermal bridging of the studs, the existing wall
assembly provided approximately U-0.0143
Btu/h·ft2·F (0.812 W/m2·K), (R-7), with the intended
retrofit goal to be U-0.033 Btu/h·ft2·F (0.187 W/
m2·K), (R-30). As the team evaluated several
options, regardless of what insulation product
was selected, a driving factor for the design was
to keep the existing wall depth the same so that
rentable square footage did not decrease.
During the initial parametric study, the
project team investigated several other
options for insulating the walls and ultimately
decided to use closed-cell spray foam. The
project team selected closed-cell spray foam

because it satisfied several design issues for
the project, including providing a high thermal
performance per inch thickness, vapor barrier,
and air barrier integral with the product in a
single layer. Fiberglass and mineral wool were
also evaluated as well as a combination of
closed-cell spray foam with those products, all
of which were viable options, but would require
thicker wall assemblies to meet the project
goal of U-0.033 Btu/h·ft2·F (0.187 W/m2·K),
(R-30). Also, using fiberglass or mineral wool
products required dedicated vapor barriers in
the insulation, which the closed-cell spray foam
did not require.
Using THERM, which is a two-dimensional
heat transfer model used to assess the thermal
performance of building components and
connections between building components, we
calculated effective wall assembly U-factors.
Using closed-cell spray foam for a depth of
7½ in. (190.5 mm), an effective R-value of
U-0.032 Btu/h·ft2·F (0.182 W/m2·K), (R-31), was
calculated for the clear field wall, which met
the project goals. In addition to the thermal
and vapor performance, the closed-cell spray
foam provided a dedicated air barrier across
the wall assembly with an air permeance of
0.004 cfm/ft2 (1.23 L*m/m2), compared to the
existing building paper, which offered some
resistance to moisture but generally lacked
the continuous, durable properties needed
to prevent air infiltration. The environmental
impact of spray foam insulation was also
considered, and a UL Greenguard Gold Certified
product with ultra-low global warming potential
was specified.
The existing 2½ in. (63.5 mm) interior stud
wall was generally constructed offset from the
main exterior stud wall, which reduced the
assembly as we were able to insulate both stud
cavities (Fig. 7). Although thermal bridging
within the field of the wall was reduced with
the offsetting walls, there was existing building
geometry, such as an inaccessible soffit, and
other conditions that could not be improved
without more significant reconstruction. During
the design phase, thermal derating calculations
were performed to determine an effective
overall opaque wall U-0.050 (R-20), including
the impacts due to these larger thermal
bridges, for evaluation in the parametric
energy modeling.
Fenestration Systems
The existing fenestration systems consisted
of aluminum thermally broken storefront
systems. The intended project scope was for
all existing fenestrations to remain except for
localized removal and replacement at a new
Figure 7. Opaque wall thermal analysis: retrofit wall construction and thermal bridging model
(top); typical retrofit wall construction (bottom left); typical existing-to-remain thermal bridge
(bottom right). Figure credit: Simpson Gumpertz & Heger Inc.
entrance to an amenity deck level. Replacing or
even retrofitting triple-glazed insulated glass
units into the existing systems was a financial
non-starter for the project; therefore, the project
team was tasked with addressing the air leakage
breaches and analyzing the existing system
to accurately estimate the as-built thermal
performance for the energy model. Based
on the original project documentation, the
estimated thermal performance of the existing
system was determined to be U-0.45 using the
manufacturer’s readily available literature.
From an airtightness standpoint, the
fenestration systems were generally in good
condition; however, several issues were
observed upon demolition of the existing
interior finishes that represented significant
breaches in the air barrier system and needed
to be addressed as part of the retrofit. These
issues included a lack of interior perimeter
backer rod and sealant joints between the
fenestration system and the rough opening
(Fig. 8), missing perimeter flashings and a lack
of integration with the adjacent brick masonry
walls in localized areas, and discontinuities in
the fenestration system components (Fig. 9).
The project documents required new perimeter
backer rod and sealant joints and newly
constructed perimeter flashings installed from
the interior at localized areas. Additionally,
there was a provision that the contractor field
survey the existing fenestrations with design
team oversight and replace any missing
or dislodged components and adjust any
dislocated insulated glass units.
Whole-Building Airtightness
As part of our work, an initial partial-building
air leakage test was performed (e.g., blower
door testing) to identify a baseline enclosure
air leakage rate to be used in the energy
model. The overall enclosure airtightness is
typically reported as the air leakage per unit
of building enclosure surface area at 75 Pa
(0.3 in. water column) pressure difference.
Although Building A was fully unoccupied

and not that large relative to the rest of the
complex, executing a whole-building air
leakage test was difficult. Interior partitions
and mechanical systems from the previous
tenant remained in situ. Levels 1 and 2 are
connected by a two-story lobby with open
stairs on the north elevation. Level 2 is
connected to the adjacent buildings via a
bridge at the northeast corner and a hallway
with locker rooms on the west elevation.
Because these spaces are all interconnected,
Levels 1 and 2 were difficult to isolate from
the adjacent buildings. Therefore, the project
team decided to isolate Level 3 and perform
partial-building air testing on only the third
floor. Building A contains centralized HVAC
systems, as well as mechanical shafts,
staircases, and elevators that connect
Levels 1, 2, and 3. During testing, Level 3
was isolated by temporarily sealing elevator
doors, all supply and exhaust air diffusers on
the third floor, and the return air plenum at
the shaft wall assembly (Fig. 10). Because
supply vents were temporarily sealed, Level
3 was not conditioned to normal setpoints
during testing.
Our initial partial-building air leakage testing
showed that the average air leakage rate for
Level 3 was 0.61 cfm/ft2 (187.77 L*m/m2) at
75 Pa of differential pressure across the building
enclosure. Note that this was measured with
the HVAC building enclosure penetrations
temporarily sealed. It was impossible to seal
all imperfections in the shaft wall construction,
HVAC ductwork and some diffusers, or other
miscellaneous conditions concealed by interior
finishes to fully isolate Level 3 from the rest of
Building A.
For reference, multiple current building
codes and industry standards provide
requirements and/or guidelines for
whole-building airtightness of new buildings,
typically reported as the air leakage per unit of
building enclosure surface area at 75 Pa (0.3 in.
water column) pressure difference, including
the following:
• 0.40 cfm/ft2 (123 L*m/m2) from American
Society of Heating, Refrigerating, and
Air-Conditioning Engineers (ASHRAE)
Standard 90.1, Energy Standard for Sites
and Buildings Except Low-Rise Residential
Buildings (optional test). The Air Barrier
Association of America (ABAA) often cites
this airtightness level as the maximum
recommended air leakage rate.
• AHSRAE Handbook—Fundamentals references
a 1976 study that indicates the typical
leakage values for US office buildings as
0.10 cfm/ft2 (30.78 L*m/m2) for tight walls,
0.30 cfm/ft2 (92.34 L*m/m2) for average
walls, and 0.60 cfm/ft2 (184.70 L*m/m2) for
leaky walls.
• 0.25 cfm/ft2 (76.96 L*m/m2) from the US
Army Corps of Engineers, International Green
Construction Code/ASHRAE Standard 189.1
and GSA PBS-P100 Tier 1.
• 0.10 cfm/ft2 (30.78 L*m/m2) for GSA PBS-P100
Tier 3 and State of Utah High Performance
Structures.

It is important to note that these reference
standards are intended for new buildings, not
necessarily existing buildings. As buildings age
and are subjected to weather, seals and other
items contributing to airtightness may begin to
deteriorate, causing increased air leakage over
time. In addition, this building was designed
and constructed before air barriers became
a prescriptive building code requirement in
Massachusetts circa 2001; the existing exterior
wall system does not include a dedicated air
barrier layer as is now required by code. Despite
the lack of a dedicated air barrier, the measured
leakage rate falls within the range of what we
would expect for a typical office building at
the time of original construction. In the design
phase energy modeling, the project team
conservatively assumed the measured value
of 0.61 cfm/ft2 (187.77 L*m/m2) in the existing
condition and utility and metered calibrated
models. In the final proposed case, an
improved value of 0.40 cfm/ft2 (123.13 L*m/m2)
(approximately a 35% reduction) was assumed,
which aligns with the ASHRAE Standard 90.1
values. The project team felt that this would
be a conservative and improved rate since a
dedicated air barrier was being added as part
of this work. Due to the issues encountered and
lack of confidence in the measured air leakage
during the initial partial test, the project team
opted to exclude retesting post-retrofit. The
use of the closed-cell spray foam, installation
of window perimeter flashing and seals, and
repair of voids in the exterior wall construction
all contributed to significantly reducing air
leakage, likely beyond the assumed 0.40 cfm/
ft2 (123.13 L*m/m2) value.
EARLY GOALS AND
FINAL DECISIONS
Setting early goals is critical for decarbonization
and net-zero carbon projects as it establishes
a clear vision and roadmap for achieving
sustainability targets. It also allows project teams
to align on objectives such as EUI targets, carbon
reduction strategies, and key performance
indicators. An early goal for the 140 Kendrick St.
project was to achieve a targeted EUI of 35 kBTU/
ft2 (380 kBTU/m2) and to achieve an operational
carbon neutrality with on-site renewable energy
generation. This involved comprehensive
renovations, including building enclosure
upgrades and electrification of the HVAC system.
To achieve these goals, an early energy
modeling and parametric analysis were
integrated in the design process and used
a tool to help the project team with making
informed choices, optimizing building systems,
and avoiding costly retrofits or redesigns later
in the project. It also helped with stakeholder
engagement, as early goals provide a clear
framework for discussions with tenants and
investors, ensuring all parties are aligned with
the project’s sustainability objectives from
day one.
During the decision-making phase, the
project team performed an iterative energy
modeling strategy and assessed the impact
of several CRMs on the existing and improved
conditions. The outcome of these analyses
was that all proposed CRMs were necessary
for achieving the building carbon neutrality
goals with the exception of the window
replacement measure. The energy audit and
analyses showed that the existing windows
were in good condition and replacing them
with code-compliant windows would not
have had a significant impact on the building
operation. 140 Kendrick St. has been occupied
and operational for almost a year and has been
going through a retro commissioning process.
The on-site renewable energy production
exceeds the project energy consumption, and
therefore, the project is on track to achieve its
carbon neutrality goals.
CONCLUSIONS
The 140 Kendrick St., Building A, project
was a renovation of an existing building to
a net-zero-energy and carbon-neutral office

located in Needham, Massachusetts. The
energy retrofit included full electrification,
building enclosure improvements, and HVAC
modernization including advanced heat
recovery system and on-site renewable energy
generation.
The project team conducted a series of energy
modeling runs and investigated pathways for
the project to achieve net-zero-energy and
carbon-neutrality status. The impact of several
energy conservation measures on the building’s
overall energy use, cost, and GHG emissions
was evaluated and presented to the design
team during the schematic design and design
development phases. This project, like all
decarbonization studies conducted by our teams,
highlights the importance of early involvement
and goal setting, and utilizing energy
modeling as a decision-making tool. Engaging
stakeholders early on allows for a clear definition
of objectives, while setting ambitious yet
achievable goals provide a strategic framework
for the project. Early iterative energy modeling
was essential for evaluating various scenarios,
optimizing system performance, and ensuring
that each decision contributed to reducing
the building’s carbon footprint efficiently and
cost-effectively.
REFERENCE
Boston Properties Case Study Archives (2024). Pioneering
Net-Zero Redevelopment of an Existing Building, Boston
Properties website, https://www.bxp.com/wp-content/
uploads/2023/08/140-Kendrick_BXP_Final_08.16.23.pdf.
ABOUT THE AUTHORS
Christopher Grey is an
Associate Principal in
Simpson Gumpertz &
Heger Inc.’s (SGH) Building
Technology Division in
Boston, Massachusetts.
He is experienced
in investigating,
rehabilitating, and
designing a wide range
of building enclosure
systems, from historic
structures to contemporary high-rise buildings.
His practice focuses on enclosure consulting for
new construction and existing building retrofits
specializing in energy performance analysis,
performance testing, and the design and coordination
of unitized curtainwall and prefabricated megapanel
enclosure systems. Grey holds a Bachelor of Science
in civil engineering and a Master of Science in civil
engineering, structural focus, from Virginia Tech.
He is a certified sUAS Level I Thermographer and a
contributing member of the FGIA/AAMA, serving on
several industry-standard task groups.

Samira Ahmadi is the
Founding Principal of
enviENERGY Studio
LLC and has more than
14 years of experience
in energy modeling
and sustainability
consulting. Her
practice focuses on
sustainability and
energy performance
analyses for new
construction and
existing building retrofit projects that aim for
sustainability certifications, energy upgrades,
decarbonization, enhanced occupant health
and comfort, and post-occupancy evaluation,
measurement, and verification. Ahmadi holds a
Master of Science in building performance and
diagnostics from Carnegie Mellon University, a
Bachelor of Science in architectural engineering,
and a Master of Architecture from the University
of Texas at San Antonio. She is a member of the
BAC Board of Trustees and has previously served
on the US Green Building Council Massachusetts
Chapter Board of Directors.