Skip to main content Skip to footer

Pros and Cons of Various Thermal Clips in Building Envelope Remediations Using Continuous Exterior Insulation

August 5, 2016

With an increased focus
on careful stewardship
of resources and rapidly
rising energy costs, it is
now mandatory for new
and remediated buildings
to be more energy efficient. For buildings
under remediation, this is often easier
said than done. There are a number of
challenges that a design team must address
during the design and construction phases
of such a project.
One of the main challenges
the building envelope industry
currently faces is the design
of exterior wall assemblies
that address thermal bridging,
with lower-conductivity
components ideally located
outboard of the sheathing.
Standards and building code
requirements are trending in
this direction. To meet the
requirements of ASHRAE 90.1,
Energy Standard for Buildings
Except Low-Rise Residential
Buildings, using the prescriptive
method (required by some
building codes), one can either
demonstrate low overall heat
loss for an assembly, or incorporate
a continuous layer of
insulation in the exterior wall
design (Figure 1).
Recently, several thermal
clips have been introduced to
the construction industry to
facilitate the construction of
exterior walls with insulation located outboard
of the wall sheathing (Figures 2
and 3). Several types of thermal clips are
available; however, they are not all created
equal. Each clip has its advantages
and disadvantages, ranging from thermal
properties to the user-friendly aspects of its
installation.
WSP Canada has been involved in projects
in which these thermal clips have been
used. Three case studies with three different
thermal clips will be presented while
some of the advantages and disadvantages
of each clip, such as thermal effectiveness,
adjustability, cost, and design considerations,
will be discussed.
Even with these new thermal clips,
exterior insulated wall designs can be
quite challenging during building envelope
remediation projects, as existing buildings
are often constructed using the traditional
method of insulating between the wall
studs. During these types of projects, it
is crucial to properly design the new wall
assemblies so that the air barriers
and vapor retarders are at
the correct locations to prevent
potential condensation problems.
Besides exterior insulated
finish systems (EIFS)—wall
assemblies that are adhered to
the wall sheathing and structure—
most exterior walls have
framing components that can
bridge the insulation layer. The
impact of these components
on the thermal performance of
the exterior walls is significant.
There are numerous strategies
and wall-cladding assemblies
available to reduce thermal
bridging through an exterior
insulation layer.
As previously mentioned,
there are significant design
and construction challenges
with exterior insulated wall
assemblies. These challenges
should not be taken lightly,
1 4 • I n t e r f a c e A u g u s t 2 0 1 6
Figure 1 – Plan view of an exterior insulated wall assembly.
as they could
become problematic
and, in some
cases, possibly
c a t a s t r o p h i c .
Design solutions
for these assemblies
need to perform
thermally,
but also in accordance
with good
moisture management
practices.
Moisture
m a n a g e m e n t
should be considered
in all exterior
wall designs,
but it is of primary importance in the coastal
climate of British Columbia, where the
author of this article practices engineering.
Current versions of ASHRAE 90.1 do not
explicitly state its importance (as earlier versions
did), but the standard’s primary focus
is energy-efficient design. As insulation levels
increase and walls become more airtight,
it becomes increasingly difficult for the
assembly to dry out, which makes it even
more important to make sure the assembly
doesn’t get wet in the first place. So reduced
heat loss is important, as is proper management
of wind-driven rain, air leakage,
capillary action (pressure), and water-vapor
diffusion. A wall or roof design that doesn’t
consider or account for these
can be subject to potential
leaks or condensation within
the assemblies.
These exterior wall assemblies
must also perform structurally
and economically; in
other words, they need to be
relatively cost-effective and not overly difficult
to construct.
Following are some case studies using
these thermal clips.
CASE STUDY ONE
Recently, our engineering design team
was faced with a challenging building envelope
remediation project
in a healthcare facility.
This structure had a history
of building envelope
failures due to air and water leakage. It
was originally constructed with insulation
between the steel framing. To increase the
thermal performance of the exterior walls
and to enhance the airtightness of the
building, the design team decided to have
the air barrier/vapor retarder (also the
weather barrier layer) and the insulation
layer outside of the sheathing.
During the demolition phase, it was recognized
that the deterioration to the existing
steel framing and the interior components
A u g u s t 2 0 1 6 I n t e r f a c e • 1 5
Figures 2 and 3 – Examples of
thermal clips used for exterior
insulated wall assemblies.
Figure 4 – A layer of exterior insulation behind the
Z-girts was secured to the fiberglass thermal clips of
the building in Case Study One.
Figure 5 – The new wall claddings
after completion of Case Study One.
was worse than expected. Due to the
extent of deterioration to the existing
sheathing, studs, and interior wall
components, it was necessary to
remove all wall components down to
the framing. Another challenge was
to properly scaffold and weatherprotect
the building during demolition,
as this is a hospital setting.
Since the building was required to
remain operational during construction,
it was necessary that strict
infection-control procedures be
established to safeguard patients
and staff. The exterior walls and
scaffolding area were fully enclosed,
and the interior of the building was
pressurized to prevent any contamination
of the occupied space. The
pressure was monitored at all times,
and air quality testing was performed
before, during, and after construction.
The new wall design incorporated
specialized engineered wall cladding
assemblies to allow for drying and
drainage, while reducing thermal
bridging with fiberglass clips to reduce heat transfer. The new
wall assembly consisted of a fiberglass-faced gypsum sheathing
installed over the steel framing, a new self-adhered air barrier/
vapor retarder (also the weather barrier layer) membrane installed
onto the sheathing, and new fiberglass thermal clips connecting
the cladding to the sheathing to reduce thermal bridging through
the semi-rigid insulation layer. The cladding types utilized for
this remediation project were fiber-cement panels and horizontal
corrugated metal panels (Figures 4 and 5).
Challenges during the design and construction included
providing proper structural support at all the joints in the new
fiber-cement panels, and at transitions between wall cladding
types. This required careful planning prior to installation of the
fiberglass thermal clips and Z-girts. One of the disadvantages of
this particular thermal clip is the lack of possible adjustment
both laterally (side to side) and front to back, to allow for construction
tolerances. Therefore, the clip must be shimmed if the
exterior wall sheathing is not plumb.
CASE STUDY TWO
WSP Canada is also currently involved in a project that is
using galvanized steel clips with a “thermal break” incorporated
at the back of the clip (Figure 6). This project is the construction
of a new healthcare building. The exterior wall construction is
similar to Case Study One, with a self-adhered air barrier/vapor
retarder (also the weather barrier layer) outside of the sheathing
and semi-rigid exterior insulation. Some advantages were noted
with regards to the design of these clips, the first being that they
have a slot to allow for the installation of horizontal and vertical
girts outboard of the clip. This allows the girt to be easily adjusted
if the substrate is out of plane. It allows for the installation of
both vertical and horizontal girts, if needed.
1 6 • I n t e r f a c e A u g u s t 2 0 1 6
Figure 6 – Installation of the thermal clip used in Case Study Two over self-adhered membrane.
Figures 7 – Clip used in Case Study Three with aerogel insulation.
A couple of disadvantages were noted
as well. Due to the material and its design,
this clip doesn’t provide the thermal effectiveness
that other clips can provide. The
design team may want to model the clip
using a thermal transfer software and/or
use thermal transfer equations to determine
and confi rm its thermal effectiveness.
Several factors can infl uence the thermal
effectiveness of the clip and exterior wall
assembly. A small change in the exterior
wall assembly’s effective R-value could have
a signifi cant impact on the building energy
model. While other clips come in multiple
sizes, the “T-Clip” used on this project is
only available in a depth of 4 inches.
CASE STUDY THREE
Our team is also currently using a
third type of thermal clip on a project on
Vancouver Island. These particular clips are
made of stainless steel and are paired with
an aerogel product that can be placed on
either end or both ends of each clip (Figure
7). Each aerogel layer has an R-4 value, and
multiple layers can be used.
An advantage with this clip (similar to
the previously discussed thermal clip in
Case Study Two) is the fact that it is adjustable.
This gives installers the ability to
adjust the clip to account for imperfections
in the walls. These imperfections are common
in renovated buildings with concrete,
brick, and steel studs that are non-parallel
or inconsistent with one another.
One of the disadvantages of this clip
is its cost, as the materials used are fairly
expensive.
CONCLUSION
As stated, there are a variety of thermal
clips from which to choose, but they are not
necessarily created equal. It is up to the
design and project team to research, test,
and model the various types to determine
which thermal clip is best for its upcoming
project.
These types of wall assemblies, whether
in new construction or building envelope
remediation projects, will become more
prevalent as the industry moves towards
more energy-effi cient buildings. These projects
are challenging, but with careful planning,
design, and proper review during
the construction processes, can be accomplished
with great success.
a u g u s t 2 0 1 6 I n t e r f a c e • 1 7
PROTECT THE INTEGRITY OF YOUR ROOFING ASSEMBLY
Fry Reglet’s “Reglet & Springlok™ Flashing System” provides the ultimate in roof protection
from moisture intrusion and wind uplift.
(Per ASTM D3161 Class F 110MPH Test)
For stucco finishes, our “STX Reglet” with a 3 1/2” attachment flange provides the perfect
amount of space for WRB’s without additional accessories.
1/2”
7/8”
3 1/2”
“STX” REGLET
FLASHING
ARCHITECTURAL METALS + ENGINEERED PRODUCT SYSTEMS | 800-237-9773 | www.fryreglet.com SPRINGLOK FLASHING SYSTEM
Specify Fry Reglet Today.
Guillaume Vadeboncoeur,
PEng,
LEED AP, is a professional
engineer
with over 11 years
of experience in
the fi eld. He is the
building science
group leader for the
Fraser Valley and
Southern Interior in
British Columbia,
Canada, for WSP
Canada Ltd. He
has managed several
building science projects that include
building envelope remediations, condition
assessments, roof replacement projects, and
wall monitoring. Vadeboncoeur attended
Laval University and graduated with a diploma
in mechanical engineering. He is president
of the Western Canada RCI Chapter
and the vice-chair of the ACECBC Building
Engineering Committee.
Guillaume
Vadeboncoeur,
PEng, LEED® AP